Bi-Weekly Progress Update No. 18 September 1, 2020 – September 15, 2020
Project Status:
ATAS Building – Task #2
Completed pouring the concrete southeast retaining wall.
Completed excavating and forming the building footprint.
Continued investigating the existing site utilities and points of connection for new site utilities.
Started importing and filling engineered soil for the building foundations.
Connector Road and Parking Lot 5B – Task #5
Completed relocation of High Voltage electrical line.
Continued safing off, demolishing, and removing existing site utilities.
Continued grading operation.
Continued installing storm drain utility infrastructure.
ATAS Building – Building Footprint Excavation, North Wings and Main Lobby
ATAS Building – Building Footprint Excavation, South Wing
ATAS Building – The Southeast Retaining Wall
ATAS Building – Import and Fill Operation of Engineered Soil, North Wing
ATAS Building – Import and Fill Operation of Engineered Soil, South Wing
Connector Road and Parking Lot 5B – Storm Drain Infrastructure Installation
Connector Road and Parking Lot 5B – Grading Operation from Baseball Stands
Connector Road and Parking Lot 5B – Storm Drain Piping
Upcoming Activities:
ATAS Building – Task #2
Complete import and fill operation.
Continue site utilities investigations.
Begin excavating foundations and footings for the building.
Begin site utilities installation.
Begin pouring concrete foundations and footings for the building.
Connector Road and Parking Lot 5B – Task #5
Continue the grading operation.
Continue site utilities installation.