advantage of usc technology in power generation_l
TRANSCRIPT
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
1/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Advantages of Ultra SuperCritical Technology in
Power Generation
by
Hans H. Poulsen
Burmeister & Wain Energy A/S
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
2/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Burmeister & Wain Energy A/S (I):
Company founded in 1843
First steam boiler supplied1852.
First Benson once-throughboiler supplied in 1952
World record - above 47% in efficiency for acoal fired utility boiler 1999
Part of the Italian STF S.p.A. Group (2002)
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
3/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Burmeister & Wain Energy A/S (II):
Advanced Ultra Super Critical steam boilers
FGD Flue Gas Desulphurization plants
Low-NOx firing systems
Regenerative Gas-Gas Heaters
Upgrading of existing boilers to improvedperformance
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
4/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Clean Coal technology:
IGCC processes
PFBC processes
USC power cycles
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
5/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
1950 19701960 19901980 20202000 2010
30
32
34
36
38
40
42
44
46
48
52
50
54
56
58
60
%
Net Efficiency (LHV)
Commissioning Year
Esbjerg 3Nordjyllandsvrket
Avedre 2
Fynsv. 7
250 MW
Studstrup 3/4Ensted 3
Line of Steel
Line of Super Alloys
Efficiency Increase in DK
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
6/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
BENSON once-through boiler system
Supplied on a licens from Siemens
since 1952
IP1.1
IP2.1
IP2.2
HP2
HP1
ECO
IP1.2
Asnsvrket #2
150MWe, 1958
Asnsvrket #3
250MWe, 1962
Fynsvrket #7
350MWe, 1991
Nordjyllandsvrket #3
415MWe, 1998
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
7/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Conventional 2-pass design:
Fynvrket Unit 7 (FV-7):
350MWe
2-Pass Benson boiler, Single Reheat
Tangential firing system
Furnace dimensions
Height of Boiler 66m
Problems related to this design:
Flue gas changes flow direction through the boiler.Flue gas flow direction not perpendicular to the first
heating surfaces
Cracks can appear in the connections between themembrane walls of the first and second pass.
Flue gas flow in the second pass are not uniformcausing problems of erosion as well as thermal
unbalance
Uneven distribution of loads on the top frame
Pressure part not fully drainable
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
8/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Tower design (I):
IP1.1
IP2.1
IP2.2
HP2
HP1
ECO
IP1.2
Nordjyllandsvrket Unit 3 (NVV-3):
400MWe
Tower type Benson boiler, Double Reheat
Tangential firing system
Furnace dimensions: 12.2512.25m
Height of Boiler 80m
Problems solved by this design:
The flue gas flows in one direction through theboiler.
Even distribution of loads on the top frame
The main direction of the flue gas is perpendicular tothe tubes in all heating surfaces
The flue gas flow through the convention pass seemsto be uniform. Problems of erosion are not reported.
Heat pick-up are uniform
Pressure part fully drainable
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
9/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Tower design (II):
Compared to 2-pass boilers
15-20% additional height
App. 10% reduction ofmaterial consumption
Penthouse not necessary
Ideal for T-firing
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
10/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
First
tower type
boilersupplied
to STEAGin 1987
Walsum #9
400MWe
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
11/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Ultra Super Critical Installations of the World
Power station Cap. Steam parameters Fuel Year of Eff. Boiler/steam Turbine
MW Comm. % line materials materials
Matsuura 2 1000 255bar/598C/596C PC 1997 Super304HP91 TMK1
Skrbk 3 400 290bar/580C/580C/580 NG 1997 49 TP347FG/P91 COST 501 F
Haramachi 2 1000 259bar/604C/602C PC 1998 Super304H/P91 HR1100
Nordjylland 3 400 290bar/580C/580C/580 PC 1998 47 TP347FG/P91 COST 501 F
Nanaoota 2 700 255bar/593C/593C PC 1998 P91 Toshiba 12Cr
Misumi 1 1000 259bar/604C/602C PC 1998 Super304H/P91 TMK2/TMK1
Lippendorf 934 267bar/554C/583C Lignite 1999 42.3 1.4910/P91 COST 501 E
Boxberg 915 267bar/555C/578C Lignite 2000 41.7 1.4910/P91 COST 501 E
Tsuruga 2 700 255bar/597C/597C PC 2000 Super304H/P122 Toshiba 12Cr
Tachibanawan 2 1050 260bar/605C/613C PC 2001 Super304H/P122/P92 TMK2/TMK1
Avedre 2 400 300bar/580C/600C NG 2001 49.7 TP347FG/P92 COST 501 E
Niederaussen 975 265bar/565C/600C Lignite 2002 >43 1.4910/E911 COST 501 E
Isogo 1 600 250bar/600C/610C Coal 2002 Super304/P122 COST 501 E
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
12/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
400
800
1200
1600
2000
2400
2800
3200
3600
4000
0 50 100 150 200 250 300 350 400
Pressure [bar]
Enthalpy[kJ/kg]
100C
150C
200C
250C
300C
350C
400C
450C
500C
550C
600C
650C
700C
750C
Ultra Super Critical ??
Sub Critical
Super Critical
Ultra Super Critical
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
13/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Sub-, Super- and Ultra Super Critical Boilers
0
500
1000
1500
2000
2500
3000
3500
4000
0 50 100 150 200 250 300 350
Pressure [Bara]
ENTHALPY,
H
[kJ/kg]
100C
200C
400C
600C
NVV 3FV 7ASV 5
HT
IP1IP2
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
14/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Increasing live steam parameters(temperature and pressure)
Reducing the condenser pressure by
means of a cold and effective cooling
media preferably sea water
Using reheat and maybe double reheat
Optimizing the feed water temperature
Selecting the single train mono
component solution for the air/flue gas
path and thereby reduce aux. power
Increasing boiler efficiency
Increasing Plant Efficiency
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
15/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Reducing flue gas exit temperature bymeans of an effective air preheater
reducing Unburned Carbon (UBC) in the
fly ash by effective and improved
combustion
Reducing air excess and thereby areduced flue gas loss
Reducing leakage in the air prehaeter
Reducing pressure loss of the
water/steam cycle
Increasing Boiler Efficiency
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
16/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Ultra
Super
Critical
SuperCritical Sub
Critical
Nordjyllandsvrket (I):
3 Generations of Power Plants:
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
17/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Unit 3: State of the art Clean Coal Technology
Nordjyllandsvrket (II):
More than 50.000 h of
operational hours has
proven:
Plant efficiency >47%
Availability > 98%
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
18/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Generator output 411 MW
Aux. Power consumption incl. DeNOx- and DeSOx plant 26 MW
Aux. Power consumption excl. DeNOx- and DeSOx plant 23 MW
400 kV output to grid, incl. DeNOx- and DeSOx plants 385 MW400 kV output to grid, excl. DeNOx- and DeSOx plants 388 MW
Turbogenerator, heat rate, based on gen. output 6.736,6 kJ/kWh
Boiler efficiency 94,2 %
Power plant, heat rate, based on gen. output 7.151,4 kJ/kWh
Gross calorific value of coal 26 MJ/kg
Specific coal consumption, based on gen. output 275 g/kWh
Specific coal consumption, based on 400 kV output to grid 293 g/kwh
Thermal efficiency, based on 400 kV output to grid 47,2 %
NVV B3 operationdata, Cond. mode
Operational data, power production only100% load, condensing mode, 10 c cooling water.
Operational results: Power production only
Nordjyllandsvrket (III):
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
19/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Generator output 339,5 MW
Aux. Power consumption incl. DeNOx- and DeSOx plant 26,5 MW
Aux. Power consumption excl. DeNOx- and DeSOx plant 23,5 MW
400 kV output to grid, incl. DeNOx- and DeSOx plants 313 MW
400 kV output to grid, excl. DeNOx- and DeSOx plants 316 MWDistrict heating output 422 Mj/s
Turbogenerator, heat rate, based on gen. output 8150,3 kJ/kWh
Boiler efficiency 94,2 %
Power plant, heat rate, based on gen. output 8652,1 kJ/kWh
Gross calorific value of coal 26 MJ/kgSpecific coal consumption, based on gen. output + DH output 148 g/kWh
Specific coal consumption, 400 kV output to grid + DH output 154 g/kwh
Thermal efficiency, 400 kV output to grid +DH output 90 %
NVV B3 op CHP mode
Operational data, combined heat and power production100% load, back pressure mode, 4 c cooling water..
Operational results: Combined Heat and Power production:
Nordjyllandsvrket (IV):
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
20/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
0
50
100
150
200
250
300
0 100 200 300 400 500 600 700
Temperature [C]
Allowablestress
[N/mm
2]
13CrMo4-5
SA-213 T23
7CrMoVTiB10-10
HCM12
Materials for membrane walls:
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
21/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Materials for super heaters:
0
50
100
150
200
250
0 100 200 300 400 500 600 700
Temperature [C]
Allowablestre
ss
[N/mm
2]
HR3C
Super304HTP347HFG
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
22/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
1950 19701960 19901980 20202000 2010
30
32
3436
38
40
42
44
46
48
52
50
54
56
58
60
%
Net Efficiency (LHV)
Commissioning Year
Esbjerg 3Nordjyllandsvrket
Avedre 2
Fynsv. 7
250 MW
Studstrup 3/4Ensted 3
Line of Steel
Line of Super Alloys
Future efficiencies
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
23/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
NVV B3 op CHP mode
The USC Power Cycle :
Conclusion:
is the current development edge of theconventional Rankine power cycle
has demonstrated high efficiency and has apotential for further efficiency increase
has proved to have high and satisfactoryavailability
-
7/29/2019 ADVANTAGE of USC Technology in Power Generation_L
24/24
Clean Coal Technology, Sardinia May 2005
Group
Burmeister & Wain Energy A/S J gersborg All 164 DK-2820 Gentofte Denmark Tel/fax +45 39 45 20 00/+45 39 45 20 05 [email protected]
Visit us on the web www.bwe.dk