ae to... · 2019. 4. 22. · requesting an effective date of “12/31/9998”2 for the tariff...
TRANSCRIPT
April 22, 2019
The Honorable Kimberly D. Bose
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426
Re: Southwest Power Pool, Inc., Docket No. ER19-____
Submission of Tariff Revisions to Allow Dispatchable Variable Energy
Resources to Utilize Control Statuses to Indicate the Resource is not Currently
Capable of Following a Dispatch Instruction
Dear Secretary Bose:
Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d,
and Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”)
Regulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. ("SPP"), as authorized by
its independent Board of Directors, submits revisions to Section 4.1.2.4 of Attachment
AE of the SPP Open Access Transmission Tariff (“Tariff”)1 to allow Dispatchable
Variable Energy Resources (“DVER”) to utilize control statuses to indicate the
Resource is not currently capable of following a Dispatch Instruction.
SPP is requesting that the Commission issue an order in this docket as soon as
practicable, but not later than July 1, 2019. SPP is also requesting an open effective
date. In light of the facts that the exact date of Commission action on this filing is
unclear at this time and that SPP will need a number of months to build, test, and
implement the necessary software on top of SPP’s new Settlement Management System
(“SMS”) currently scheduled to be implemented in the first quarter of 2020, SPP is
requesting an effective date of “12/31/9998”2 for the Tariff Records submitted in this
filing. SPP commits to submit a filing with the Commission specifying a precise
1 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised
Volume No. 1. References in this filing to "Tariff" refer to the version of SPP’s
Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the
revisions proposed in this filing. All capitalized terms not otherwise defined in
this filing shall have the definitions assigned by the Tariff.
2 See, e.g., Implementation Guide for Electronic Filing of Parts 35, 154, 284, 300,
and 341 Tariff Filings at 10 (Nov. 14, 2016) (“If the effective date is not known
at the time of the filing, such as the effective date is contingent on FERC
approval . . . the date of 12/31/9998 must be used.”).
The Honorable Kimberly D. Bose
April 22, 2019
Page 2
effective date not later than 30 days prior to implementation. Upon Commission
acceptance of SPP’s filing and the completion of the SMS, SPP will work as quickly
as practicable to technologically implement the proposed changes with a target
completion date in the second quarter of 2020.
SPP respectfully requests waiver of the Commission’s timing requirements to
allow these tariff revisions to be effective more than 120 days after the date of filing.
I. BACKGROUND
A. SPP
SPP is a Commission-approved Regional Transmission Organization
(“RTO”).3 It is an Arkansas non-profit corporation with its principal place of business
in Little Rock, Arkansas. SPP currently has 97 members, including 16 investor-owned
utilities, 14 municipal systems, 20 generation and transmission cooperatives, 8 state
agencies, 14 independent power producers, 12 power marketers, 11 independent
transmission companies, 1 federal agency, and 1 large retail customer. As an RTO,
SPP: (1) administers, across the facilities of SPP's Transmission Owners, open access
transmission service over approximately 66,500 miles of transmission lines covering
portions of Arkansas, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana,
Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas, and
Wyoming; and (2) administers the Integrated Marketplace, a centralized day-ahead and
real-time Energy and Operating Reserve market with locational marginal pricing and
market-based congestion management.4
B. Stakeholder Approval
The proposed revisions were reviewed and approved through the SPP
stakeholder process, including: (1) a meeting of the Market Working Group ("MWG")
on September 11, 2018;5 (2) a meeting of the Regional Tariff Working Group
3 Sw. Power Pool, Inc., 109 FERC ¶ 61,009 (2004), order on reh’g, 110 FERC ¶
61,137 (2005).
4 Sw. Power Pool, Inc., 146 FERC ¶ 61,130 (2014) (order approving the start-up
and operation of the Integrated Marketplace effective March 1, 2014).
5 See MWG Minutes dated September 11-12, 2018, at Agenda Item 9 posted at:
https://www.spp.org/documents/58661/mwg%20minutes%20&%20attachmen
ts%2020180911%2012.pdf. The MWG is responsible for the development and
coordination of the changes necessary to support any SPP administered
wholesale market(s), including energy, congestion management, and market
monitoring, consistent with direction from the SPP Board of Directors.
The Honorable Kimberly D. Bose
April 22, 2019
Page 3
("RTWG") on September 27, 2018;6 and (3) a meeting of the Markets and Operations
Policy Committee on October 16, 2018.7 The revisions were approved for filing with
the Commission at a meeting of the SPP Members Committee8 and Board of Directors
on October 30, 2018.9 While SPP recognizes that stakeholder approval does not by
itself cause a filing to be just and reasonable, SPP requests that the Commission extend
appropriate deference to the wishes of SPP’s stakeholders, consistent with Commission
precedent.10
6 See RTWG Minutes dated September 27, 2018, at Agenda Item 11(a) posted at:
https://spp.org/documents/58757/rtwg%20september%2027%202018%20min
utes.pdf. The RTWG is responsible for development, recommendation, overall
implementation, and oversight of SPP’s Tariff. The RTWG also advises SPP
staff on regulatory and implementation issues not specifically covered by the
Tariff or issues where there may be conflicts or differing interpretations of the
Tariff.
7 See MOPC Minutes dated October 16-17, 2018, at Agenda Item 5 posted at:
https://www.spp.org/documents/58860/mopc%20minutes%20and%20attachm
ents%2020181016-17%20revised%2010-25-2018.pdf. The MOPC consists of
a representative officer or employee from each SPP Member and reports to the
SPP Board of Directors. Its responsibilities include recommending
modifications to the SPP Tariff. See Southwest Power Pool, Inc., Bylaws, First
Revised Volume No. 4 ("Bylaws") at Section 6.1.
8 The Members Committee currently consists of up to 24 representatives of the
Transmission Owning Member and Transmission Using Member sectors of
SPP’s Membership. This committee provides input to and assists the SPP
Board of Directors with the management and direction of the general business
of SPP. See Bylaws at Section 5.1.
9 See Board of Directors/Members Committee Meeting Minutes No. 181, dated
October 30, 2018, at Agenda Item 3 posted at:
https://www.spp.org/documents/58979/bod-
mc%20minutes%2020181030.pdf.
10 The Commission has previously recognized that provisions approved through
RTO stakeholder processes are due deference. See Sw. Power Pool, Inc., 127
FERC ¶ 61,283, at P 33 (2009) (noting that the Commission "accord[s] an
appropriate degree of deference to RTO stakeholder processes"); New Eng.
Power Pool, 105 FERC ¶ 61,300, at P 34 (2003) (Commission approval of
transmission cost allocation proposal based upon an extensive and thorough
stakeholder process); Policy Statement Regarding Regional Transmission
Groups, 1991-1996 FERC Stats. & Regs., Preambles ¶ 30,976, at 30,872 (1993)
(the Commission will afford the appropriate degree of deference to the
stakeholder approval process). The Commission’s deference to RTO
The Honorable Kimberly D. Bose
April 22, 2019
Page 4
II. PURPOSE AND JUSTIFICATION FOR PROPOSED TARIFF
REVISIONS
SPP’s proposed revisions to Section 4.1.2.4 of Attachment AE of the Tariff to
remove the phrase “even if the Market Participant has indicated that the Resource is
not dispatchable” will allow DVERs to use a Control Status, as other Resources do, to
indicate that a DVER is currently unable to follow Dispatch Instructions.
Control Status is a value telemetered to SPP via the Inter-Control Center
Communications Protocol (ICCP). Control Status is used by SPP and its systems to
determine, in real time, the ability of a Resource to respond to specific dispatch
instructions issued by the RTO. The Market Participant can indicate that a Resource is:
(A) “Off-line (Control Status 0) – This Control Status indicates that the Resource
is off-line and not available to the [Real-Time Balancing Market (“RTBM”)].
This status is reserved for Resources which are generating 0 MWs. This
includes Resources which are disconnected from the grid for an approved
outage and Resources lacking a current commitment or start instruction.
(B) Non-Regulating (Control Status 1) – This Control Status indicates that the
Resource is on-line and capable of following a Dispatch Instruction and/or
Contingency Reserve Deployment Instruction. Resources in Control Status of
Non-Regulating will not be eligible to clear Regulation-Up Service and/or
Regulation-Down Service.
(C) Regulating (Control Status 2) – This Control Status indicates that the
Resource is on-line and capable of following a Dispatch Instruction,
Contingency Reserve Deployment Instruction, and/or Regulation Deployment.
(D) Manual (Control Status 3) – This Control Status indicates that the Resource
is on-line but not capable of following a Dispatch Instruction. This status is
reserved for generating Resources operating under the following conditions:
(1) Start-up
(2) Shut-down
(3) Testing
(4) Experiencing, or recovering from, a unit trip
(5) Generating at an output to which the Resource is not capable of
responding to a Dispatch Instruction
(6) Condensing
stakeholder processes has been upheld by the courts. See Pub. Serv. Comm’n of
Wis. v. FERC, 545 F.3d 1058, 1062-63 (D.C. Cir. 2008) (noting the
Commission often gives weight to RTO proposals that reflect the position of
the majority of the RTO’s stakeholders) (quoting Am. Elec. Power Serv. Corp.
v. Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,083, at P
172 (2008)).
The Honorable Kimberly D. Bose
April 22, 2019
Page 5
(7) Experiencing environmental, control or mechanical issues
(8) Qualifying Facility exercising its rights under PURPA to deliver its net
output to its host utility.”11
Currently, for the RTBM, DVER Dispatch Instructions are calculated assuming
the DVER is dispatchable regardless of its ability to control output as communicated
in its submitted Control Status. This creates a condition where a DVER is unable to
follow a Dispatch Instruction for a legitimate reason and has tried to communicate the
condition through the use of Control Status 3, yet could still receive a Dispatch
Instruction with an expectation to perform.
Ignoring a Control Status indicating that a DVER is currently unable to follow
a Dispatch Instruction can lead to discrepancies between the RTBM software and actual
system conditions. The differences could include (1) RTBM expects the DVER to
follow the Dispatch Instruction despite its inability to do so leading to increased
Regulation Deployment; and (2) congestion management inefficiencies due to
RTBM’s expectation that a DVER could relieve loading on a flowgate through dispatch
of that DVER when that DVER cannot actually respond resulting in unresolved
flowgate congestion.
Additionally, under the current Tariff language, when a DVER receives a
Dispatch Instruction to change its output despite its inability to follow that instruction,
the DVER is exposed to Uninstructed Resource Deviation (“URD”) under Section 6.4.1
of Attachment AE of the Tariff. Allowing DVERs to utilize Control Statuses to
indicate a current inability to follow Dispatch Instructions will indicate to the market
to set the Dispatch Instruction equal to the current output of the DVER thus removing
the exposure to URD.
DVERs can use Control Status 2 under the current Tariff language to indicate
to SPP that the DVER is capable of regulating. Any other Control Status is ignored
and the DVER is assumed dispatchable. The issues raised above exist specifically
because DVERs cannot currently use Control Status 3. In the initial design and filings
for the Integrated Marketplace, based on feedback from stakeholders and other RTOs,
SPP chose to ignore Control Modes other than 2 for DVERs. At that time, SPP and the
stakeholders believed that the usage of control mode 3 could be used to circumvent
being dispatched down by SPP. Additionally, it was assumed that, technically, a wind
powered DVER was dispatchable downwards at all times.
11 SPP Integrated Marketplace Market Protocols (“Market Protocols”) at Section
4.4.2.2.3. The Market Protocols are posted on SPP’s website at:
https://www.spp.org/spp-documents-filings/?id=18162.
The Honorable Kimberly D. Bose
April 22, 2019
Page 6
Five years of experience in the Integrated Marketplace have shown that those
original assumptions were not entirely correct. Real-Time operational experience has
shown that instances exist where a DVER is not dispatchable in the downwards
direction. In these instances, SPP is forced to manually direct and communicate with
the DVER due to systems, under the current Tariff language, ignoring Control Status 3
from DVERs. This creates a burden on SPP’s Real-Time operators, requiring valuable
time to be spent on this issue that could be spent in other areas. As SPP’s experience in
the Integrated Marketplace has grown, both the membership and SPP are more
comfortable in the ability to monitor for situations where the appropriateness of Control
Status 3 needs to be evaluated.
Additionally, the language proposed allows the use of the Control Status 3
under the same rules as other Resources. Specifically, the use of Control Status 3 is
restricted to circumstances where the Resource is truly beyond the ability to respond.
As with other Resources, use of Control Status 3 is subject to review by the SPP Market
Monitoring Unit under the Market Monitoring Plan for improper utilization.
Accordingly, SPP respectfully requests that the Commission accept the Tariff
revisions proposed herein as just and reasonable.
These changes are contingent upon and cannot be implemented until the SMS
goes live. The changes will take several months to implement once the SMS has gone
live and SPP has received an order on these changes from the Commission. At this
point, SPP expects that the software changes will be completed between two and four
months after the SMS goes live. Shortly after the SMS goes live, SPP will have a much
clearer picture of when the software will be completed.
SPP is requesting that the Commission issue an order in this docket as soon as
practicable, but not later than July 1, 2019. SPP is also requesting an open effective
date. In light of the facts that the exact date of Commission action on this filing is
unclear at this time and that SPP will need a number of months to build, test, and
implement the necessary software on top of the SMS, SPP is requesting an effective
date of “12/31/9998”12 for the Tariff Records submitted in this filing. SPP commits to
submit a filing with the Commission specifying a precise effective date at a later time.
Upon Commission acceptance of SPP’s filing and the completion of the SMS, SPP will
work as quickly as practicable to technologically implement the proposed changes with
a target completion date in the second quarter of 2020.
12 Supra n. 2.
The Honorable Kimberly D. Bose
April 22, 2019
Page 7
III. DESCRIPTION OF TARIFF REVISIONS
A. Section 4.1.2.4 of Attachment AE (Dispatchable Variable Energy
Resource)
The revisions to current Tariff language in Section 4.1.2.4 of Attachment AE
remove the phrase “even if the Market Participant has indicated that the Resource is
not dispatchable[.]”
The purpose of the revision is to allow DVERs to utilize Control Statuses to
indicate the Resource is not currently capable of following a Dispatch Instruction. As
stated above this will enable RTBM to have more accurate information for reliably and
economically dispatching Resources to meet obligation and manage congestion.
IV. EFFECTIVE DATE AND REQUEST FOR WAIVER
SPP is requesting an effective date of “12/31/9998” for the Tariff Records
included with this filing. The expected effective date of the Tariff revisions included
herein is within the second quarter of 2020, which is more than 120 days after filing.
Therefore, SPP requests waiver of the Commission’s notice requirements.13 Good
cause exists for the proposed revisions to be effective in the second quarter of 2020 in
accordance with the Commission’s waiver of notice requirement codified in Section
35.11 of the Commission’s regulations14 because SPP will need a number of months to
build, test, and implement the necessary software on top of SPP’s new SMS currently
scheduled to be implemented in the first quarter of 2020. SPP requests the Commission
issue an order by July 1, 2019 to allow SPP sufficient time to make the necessary
software changes.
13 18 C.F.R. § 35.3(a)(1).
14 18 C.F.R. § 35.11.
The Honorable Kimberly D. Bose
April 22, 2019
Page 8
V. ADDITIONAL INFORMATION
A. Information Provided Per Commission Regulations15
1. Documents submitted with this filing:
In addition to this Transmittal Letter, Clean and Redlined Tariff
revisions under the Sixth Revised Volume No. 1.
2. Service:
SPP has electronically served a copy of this filing on all its
Members, Transmission Customers and Market Participants. A
complete copy of this filing will be posted on the SPP web site,
www.spp.org, and is also being served on all affected state
commissions.
3. Requisite agreements:
Not applicable.
B. Communications
Correspondence and communications with respect to this filing should be sent
to, and SPP requests the Secretary to include on the official service list, the
following:
Nicole Wagner
Manager, Regulatory Policy
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 688-1642
Fax: (501) 482-2022
Christopher M. Nolen
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2394
Fax: (501) 482-2022
15 Because the revisions to the Tariff submitted herein do not involve any changes
in rates, the use of the abbreviated filing procedures as set forth in 18 C.F.R. §
35.13(a)(2)(iii) is appropriate.
The Honorable Kimberly D. Bose
April 22, 2019
Page 9
VI. CONCLUSION
For all of the foregoing reasons, SPP respectfully requests that the Commission
issue an order accepting the Tariff revisions proposed herein as soon as practicable.
SPP will submit a filing with the Commission specifying a precise effective date not
later than 30 days prior to implementation.
Respectfully submitted,
/s/ Christopher M. Nolen
Christopher M. Nolen
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
501.482.2394
Attorney for
Southwest Power Pool, Inc.
4.1.2 Additional Provisions for Non-Traditional Resources
4.1.2.1 Demand Response Resources
(1) Dispatchable Demand Response Resource - A Dispatchable Demand Response
Resource is modeled in the Commercial Model the same as any other Resource,
except that the Settlement Location associated with the Dispatchable Demand
Response Resource must contain the Price Node, or aggregated Price Node as
described in Section 2.2(2) of this Attachment AE, associated with the Demand
Response Load. The Market Participant must submit the Real-Time value of the
Demand Response Load to the Transmission Provider via telemetering that meets
the technical requirements specified in the Market Protocols. A Dispatchable
Demand Response Resource shall submit Energy Offer Curves based on the
criteria in Section 3.2(F) of Attachment AF of this Tariff. For purposes of these
Resources, the short-run marginal cost may equal opportunity cost. A
Dispatchable Demand Response Resource may select one of two options for
reporting of the actual Dispatchable Demand Response Resource output:
(a) Submitted Resource production option:
The Dispatchable Demand Response Resource output is sent directly to
the Transmission Provider by the Market Participant via telemetering for
Real-Time operational purposes and the Meter Agent submits either five
(5) minute or hourly actual output values to the Transmission Provider for
use in settlements. The submitted Resource production option is only
allowed for Demand Response Resources that are: (1) utilizing strictly
Behind-The-Meter Generation to provide the response and are utilizing
Real-Time metering capable of reporting both the Behind-The-Meter
Generation output and the load; (2) Demand Response Resources where
the Market Participant is offering the Resource under a retail tariff
provision that includes near Real-Time measurement and verification
terms that are compliant with the Business Practices for Measurement and
Verification of Wholesale Electricity Demand Response of the North
American Energy Standards Board, incorporated by reference in the
Commission’s Regulations, 18 C.F.R. § 38.2(a)(12); or (3) Demand
Response Load utilizing near Real-Time measurement and verification
capability that is compliant with the Business Practices for Measurement
and Verification of Wholesale Electricity Demand Response of the North
American Energy Standards Board, incorporated by reference in the
Commission’s Regulations, 18 C.F.R. § 38.2(a)(12).
(b) Calculated Resource production option:
(i) For each Dispatch Interval in each hour in which the Demand
Response Resource has been committed, the Demand Response
Resource output for Real-Time operational purposes is calculated
by the Transmission Provider as the greater of zero (0) or the
difference between:
The lesser of the Real-Time consumption of the Demand
Response Load associated with the Demand Response
Resource in the Dispatch Interval immediately preceding
initial commitment of the Demand Response Resource or
the hourly baseline as described in (3) below for the hour,
and
The actual value of the associated Demand Response Load
received via telemetering.
(ii) For each Dispatch Interval in each hour in which the Demand
Response Resource has been committed, the Demand Response
Resource output for settlement purposes is calculated by the
Transmission Provider as the maximum of zero (0) or the
difference between:
The lesser of the Real-Time consumption of the Demand
Response Load associated with the Demand Response
Resource in the Dispatch Interval immediately preceding
initial commitment of the Demand Response Resource or
the hourly baseline as described in (3) below for the hour,
and
The actual value of the associated Demand Response Load
received from the Meter Agent either on a five (5) minute
basis or an hourly basis.
(2) Block Demand Response Resource – A Block Demand Response Resource is
modeled in the Commercial Model the same as any other Resource except that the
Settlement Location associated with the Block Demand Response Resource must
contain the Price Node, or aggregated Price Node as described in Section 2.2(2)
of this Attachment AE, associated with the Demand Response Load. The Market
Participant must submit the Real-Time value of the Demand Response Load to the
Transmission Provider via telemetering that meets the technical requirements
specified in the Market Protocols. All Block Demand Response Resources will
use the calculated Resource production option, described in Section 4.1.2.1(1)(b)
above, to determine the amount of Real-Time Resource production and actual
Resource production.
(a) If the Block Demand Response Resource is committed and dispatched in
the Day-Ahead Market, Day-Ahead RUC or Intra-Day RUC, the Block
Demand Response Resource’s Minimum Economic Capacity Operating
Limit will be increased in the RTBM to match the dispatched amount.
Spinning Reserve or Supplemental Reserve will be allowed to clear above
minimum output if the Block Demand Response Resource is a Spin
Qualified Resource and Supplemental Reserve will be allowed to clear
above minimum output if the Block Demand Response Resource is a
Supplemental Qualified Resource.
(b) Spinning Reserve and/or Supplemental Reserve clearing will be based
upon submitted ramp rates for the Block Demand Response Resource, the
submitted Spinning Reserve Offer, the Supplemental Reserve Offer and
the Block Demand Response Resource’s Maximum Economic Capacity
Operating Limit.
(3) Hourly Baseline
(a) The Market Participant must submit an hourly baseline for the Demand
Response Load indicating the level of energy consumption expected at
that location in MWh if the Demand Response Resource is not dispatched.
The baseline must cover, at a minimum, all hours the Resource is
submitting Offers for in the Energy and Operating Reserve Markets. This
baseline must be submitted by 1100 hours on the day prior to the
Operating Day and may be updated up to thirty (30) minutes in advance of
the operating hour. The baseline should be based on the average of the
hourly integrated Demand Response Load for the same hours in the last 30
calendar days when the Resource was not dispatched, adjusted by the
Market Participant as necessary to account for changes in the expected
level of energy consumption by the Demand Response Load.
(b) If there have been deviations in hourly integrated metered load from the
hourly baseline during periods when the Resource was not dispatched the
hourly baseline will be adjusted as follows by the Transmission Provider
prior to the calculation of the Demand Response Load. If the average of
the hourly deviation between integrated metered load and submitted
hourly baseline for the hours in the last thirty (30) calendar days when the
Resource was not dispatched is more than five percent (5%) below the
hourly baseline, the hourly baseline will be adjusted by the average
deviation. The Transmission Provider will perform this assessment each
day and notify the Market Participant of any adjustment.
(c) If the hourly baseline has not been submitted, the Transmission Provider
shall set the hourly baseline equal to the Real-Time consumption of the
Demand Response Load associated with the Demand Response Resource
in the Dispatch Interval immediately preceding initial commitment of the
Demand Response Resource.
4.1.2.2 Combined Cycle Resource
Market Participants shall select from one of the four following options
regarding submitting Resource Offers for their registered combined cycle
Resources, which will be declared during asset registration as described under
Sections 2.2 and 2.9 of this Attachment AE:
(1) A Resource Offer may be submitted for a single aggregate combined cycle
Resource, where the aggregate will represent a Market Participant selected
operating configuration of combustion turbines and steam turbines. Under
this option, the combined cycle Resource will be committed, dispatched
and settled the same as any other Resource; or
(2) A Resource Offer may be submitted for each combined cycle Resource
combustion turbine and/or steam turbine and each component will be
committed and dispatched independently and settled the same as any other
single Resource; or
(3) A Resource Offer may be submitted for each pseudo combined cycle
Resource, where each pseudo combined cycle Resource will represent the
combination of one combustion turbine and a portion of the steam turbine.
Under this option, each pseudo combined cycle Resource must be capable
of being committed and dispatched independently the same as any other
Resource and each pseudo combined cycle Resource will be settled the
same as any other Resource; or
(4) A Resource Offer may be submitted for each registered combined cycle
configuration, where each configuration represents an operating state of
the combined cycle Resource with a distinct set of physical operating
characteristics, as dictated by the physical attributes of the combined cycle
Resource. The Transmission Provider will determine the most economic
commitment configuration, if requested to do so by the Market Participant
as part of the submitted Resource Offer, and once committed, the most
economic configuration to transition to for use in both the Day-Ahead
Market and Real-Time Balancing Market. Settlement for a combined
cycle Resource submitting offers in this manner will occur in the same
manner as any other Resource except for Contingency Reserve during
transitions as described under Section 8.5.9 of this Attachment AE and
adjustments for Operating Reserves during transitions as described under
Section 8.6.5 of this Attachment AE. Under this option, Market
Participants must define during asset registration the:
(a) Valid configurations, one of which must represent the
maximum capacity of the combined cycle Resource;
(b) Valid transitions between configurations as defined in the
Market Protocols; and
(c) One or more sets of physical units that can participate in a
configuration.
4.1.2.3 Jointly Owned Unit
Under the individual Jointly Owned Unit Resource option, each Market
Participant may submit Resource Offers for its share of the Jointly Owned Unit as
specified in the Market Protocols. Offer parameters must meet the following
criteria in order to be accepted as valid Offers, otherwise the last submitted valid
offer shall apply:
(1) The sum of the Maximum Emergency Capacity Operating Limits of all
shares of the Jointly Owned Unit must be less than or equal to the Jointly
Owned Unit maximum physical capacity operating limit.
Commitment of individual Jointly Owned Unit shares that have registered under
the individual Resource option will be evaluated by security constrained unit
commitment (“SCUC”) based on the individually submitted Offers for each
Jointly Owned Unit share.
4.1.2.4 Dispatchable Variable Energy Resource
Each Market Participant may submit Resource Offers for Dispatchable
Variable Energy Resources using the same Offer parameters available to any
other Resource, except that:
(1) The minimum operating limits specified in the Resource Offer must be
equal to zero;
(2) The maximum operating limits for use in the Day-Ahead RUC and the
Intra-Day RUC shall be calculated by the Transmission Provider as equal
to the lesser of the maximum operating limits submitted in the Resource
Offer or the Transmission Provider’s output forecast for that Resource to
the extent that such output forecast is available;
a) Dispatchable Variable Energy Resources for which the
Transmission Provider is calculating an output forecast are not
eligible to receive RUC make whole payments as described under
Section 8.6.5 of this Attachment AE.
(3) For the purposes of issuing Dispatch Instructions to Resources as
described under Section 4.1.2.4(6) of this Attachment AE, Dispatchable
Variable Energy Resources with a maximum capability of less than two-
hundred (200) MWs, submitted ramp rates multiplied by five (5) cannot
exceed forty (40) MWs;
(4) For the purposes of issuing Dispatch Instructions to Resources as
described under Section 4.1.2.4(6) of this Attachment AE, Dispatchable
Variable Energy Resources with a maximum capability of greater than or
equal to two-hundred (200) MWs, submitted ramp rates multiplied by five
(5) cannot exceed twenty percent (20%) of the maximum capability;
(5) For the RTBM, during times when the Transmission Provider issues a
Dispatch Instruction to a Dispatchable Variable Energy Resource to
reduce output, the Resource’s Setpoint Instruction shall be equal to the
sum of the Resource’s Dispatch Instruction and any Regulation-Down
deployment;
(6) For the RTBM, during times when the Transmission Provider issues a
Dispatch Instruction to a Dispatchable Variable Energy Resource to
increase output in Dispatch Intervals immediately following a Dispatch
Interval in which a Dispatch Instruction was issued to reduce output as
described in Section 4.1.2.4(5) of this Attachment AE, the Transmission
Provider shall calculate the Resource maximum operating limit to be equal
to:
(a) The lesser of the maximum operating limits submitted in the
Resource Offer or the Transmission Provider’s Dispatchable
Variable Energy Resource output forecast for that Resource to the
extent the such forecast is available, except that, the Transmission
Provider’s output forecast for the Resource shall be used for the
maximum operating limits when: (i) maximum operating limits
have not been submitted; (ii) the maximum operating limits
submitted in the Resource Offer were not updated during the
Operating Hour prior to the Operating Hour in which the Resource
limit would apply but before the lead time described in Section 4.1
of this Attachment AE; or (iii) the maximum operating limits
submitted in the Resource Offer exceed the maximum physical
rating of the Resource as stated during market registration; or
(b) The maximum operating limits submitted in the Resource Offer if
the Transmission Provider’s Dispatchable Variable Energy
Resource output forecast for that Resource is not available.
The Transmission Provider shall continue to calculate such maximum
operating limits for each subsequent Dispatch Interval until the maximum
operating limit is equal to the lesser of the Transmission Provider’s
Dispatchable Variable Energy Resource output forecast for that Resource
or the maximum operating limit submitted in the Resource Offer, after
which, the Dispatchable Variable Energy Resource’s maximum operating
limit shall be calculated as described in Section 4.1.2.4(7) of this
Attachment AE.
(7) For the RTBM, during times other than those times described under
Section 4.1.2.4(6) of this Attachment AE, the Resource’s maximum
operating limit for use in the current Dispatch Interval shall be equal to the
Resource’s actual output at the start of the Dispatch Interval and the
ramping restrictions described under Sections 4.1.2.4(3) and (4) of this
Attachment AE shall not apply.
(8) Dispatchable Variable Energy Resources may also receive an OOME
according to the rules in Section 6.2.4 of this Attachment AE.
4.1.2.5 Non-Dispatchable Variable Energy Resource
Each Market Participant may submit Resource Offers for Non-
Dispatchable Variable Energy Resources using the same Offer parameters
available to any other Resource, except that
(1) The minimum operating limits specified in the Resource Offer must be
equal to zero;
(2) For the RTBM, the Resource’s Energy Offer Curve shall not apply;
(3) For the RTBM, the Resource’s Dispatch Instruction shall be equal to the
Resource’s actual output at the start of the Dispatch Interval and the
Resources must operate as non-dispatchable;
(4) Resource Energy Offer Curve prices shall be assumed equal to zero (0) for
the purposes of calculating production costs relating to RUC make whole
payments and cost allocation thereof under Sections 8.6.5 and 8.6.7 of this
Attachment AE;
(5) An OOME may be issued to a Non-Dispatchable Variable Energy
Resource. In addition, the Transmission Provider will issue the dispatch
instruction to the Resource in accordance with Section 6.2.4 of this
Attachment AE; and
(6) The maximum operating limits for use in the Day-Ahead RUC and the
Intra-Day RUC shall be calculated by the Transmission Provider as equal
to the lesser of the maximum operating limits submitted in the Resource
Offer or the Transmission Provider’s output forecast for that Resource to
the extent that such output forecast is available, otherwise the maximum
operating limits shall be equal to those submitted in the Resource Offer;
(a) Non-Dispatchable Variable Energy Resources for which the
Transmission Provider is calculating an output forecast are not
eligible to receive RUC make whole payments as described under
Section 8.6.5 of this Attachment AE.
4.1.2.6 External Dynamic Resource
Each Market Participant may submit Resource Offers for External
Dynamic Resources (“EDR”) using the same Offer parameters available to any
other Resource, except that:
(1) A Market Participant may only submit a commitment status as defined in
Section 4.1(10)(a) or (d) of this Attachment AE;
(2) For an EDR in the Eastern Interconnection, a Market Participant must
submit a dispatch status indicating that the EDR is not available for energy
dispatch as described under Section 4.1(11)(a) of this Attachment AE;
(3) For an EDR in the Eastern Interconnection, Resource Offer parameters are
limited to: Regulation-Up and Regulation-Down Offers, Spinning and
Supplemental Reserve Offers, Regulation Ramp Rate, Contingency
Reserve Ramp Rate and Resource Status. All other Resource Offer
parameters as listed in Section 4.1(9) of this Attachment AE shall not
apply to EDRs in the Eastern Interconnection.
(4) For an EDR that is not in the Eastern Interconnection, Resource Offer
parameters are limited to: Energy Offer Curve, Ramp-Rate-Up, Ramp-
Rate-Down, Regulation-Up and Regulation-Down Offers, Spinning and
Supplemental Reserve Offers, Regulation Ramp Rate, Contingency
Reserve Ramp Rate and Resource Status. All other Resource Offer
parameters as listed in Section 4.1(9) of this Attachment AE shall not
apply to EDRs that are not in the Eastern Interconnection.
4.1.2 Additional Provisions for Non-Traditional Resources
4.1.2.1 Demand Response Resources
(1) Dispatchable Demand Response Resource - A Dispatchable Demand Response
Resource is modeled in the Commercial Model the same as any other Resource,
except that the Settlement Location associated with the Dispatchable Demand
Response Resource must contain the Price Node, or aggregated Price Node as
described in Section 2.2(2) of this Attachment AE, associated with the Demand
Response Load. The Market Participant must submit the Real-Time value of the
Demand Response Load to the Transmission Provider via telemetering that meets
the technical requirements specified in the Market Protocols. A Dispatchable
Demand Response Resource shall submit Energy Offer Curves based on the
criteria in Section 3.2(F) of Attachment AF of this Tariff. For purposes of these
Resources, the short-run marginal cost may equal opportunity cost. A
Dispatchable Demand Response Resource may select one of two options for
reporting of the actual Dispatchable Demand Response Resource output:
(a) Submitted Resource production option:
The Dispatchable Demand Response Resource output is sent directly to
the Transmission Provider by the Market Participant via telemetering for
Real-Time operational purposes and the Meter Agent submits either five
(5) minute or hourly actual output values to the Transmission Provider for
use in settlements. The submitted Resource production option is only
allowed for Demand Response Resources that are: (1) utilizing strictly
Behind-The-Meter Generation to provide the response and are utilizing
Real-Time metering capable of reporting both the Behind-The-Meter
Generation output and the load; (2) Demand Response Resources where
the Market Participant is offering the Resource under a retail tariff
provision that includes near Real-Time measurement and verification
terms that are compliant with the Business Practices for Measurement and
Verification of Wholesale Electricity Demand Response of the North
American Energy Standards Board, incorporated by reference in the
Commission’s Regulations, 18 C.F.R. § 38.2(a)(12); or (3) Demand
Response Load utilizing near Real-Time measurement and verification
capability that is compliant with the Business Practices for Measurement
and Verification of Wholesale Electricity Demand Response of the North
American Energy Standards Board, incorporated by reference in the
Commission’s Regulations, 18 C.F.R. § 38.2(a)(12).
(b) Calculated Resource production option:
(i) For each Dispatch Interval in each hour in which the Demand
Response Resource has been committed, the Demand Response
Resource output for Real-Time operational purposes is calculated
by the Transmission Provider as the greater of zero (0) or the
difference between:
The lesser of the Real-Time consumption of the Demand
Response Load associated with the Demand Response
Resource in the Dispatch Interval immediately preceding
initial commitment of the Demand Response Resource or
the hourly baseline as described in (3) below for the hour,
and
The actual value of the associated Demand Response Load
received via telemetering.
(ii) For each Dispatch Interval in each hour in which the Demand
Response Resource has been committed, the Demand Response
Resource output for settlement purposes is calculated by the
Transmission Provider as the maximum of zero (0) or the
difference between:
The lesser of the Real-Time consumption of the Demand
Response Load associated with the Demand Response
Resource in the Dispatch Interval immediately preceding
initial commitment of the Demand Response Resource or
the hourly baseline as described in (3) below for the hour,
and
The actual value of the associated Demand Response Load
received from the Meter Agent either on a five (5) minute
basis or an hourly basis.
(2) Block Demand Response Resource – A Block Demand Response Resource is
modeled in the Commercial Model the same as any other Resource except that the
Settlement Location associated with the Block Demand Response Resource must
contain the Price Node, or aggregated Price Node as described in Section 2.2(2)
of this Attachment AE, associated with the Demand Response Load. The Market
Participant must submit the Real-Time value of the Demand Response Load to the
Transmission Provider via telemetering that meets the technical requirements
specified in the Market Protocols. All Block Demand Response Resources will
use the calculated Resource production option, described in Section 4.1.2.1(1)(b)
above, to determine the amount of Real-Time Resource production and actual
Resource production.
(a) If the Block Demand Response Resource is committed and dispatched in
the Day-Ahead Market, Day-Ahead RUC or Intra-Day RUC, the Block
Demand Response Resource’s Minimum Economic Capacity Operating
Limit will be increased in the RTBM to match the dispatched amount.
Spinning Reserve or Supplemental Reserve will be allowed to clear above
minimum output if the Block Demand Response Resource is a Spin
Qualified Resource and Supplemental Reserve will be allowed to clear
above minimum output if the Block Demand Response Resource is a
Supplemental Qualified Resource.
(b) Spinning Reserve and/or Supplemental Reserve clearing will be based
upon submitted ramp rates for the Block Demand Response Resource, the
submitted Spinning Reserve Offer, the Supplemental Reserve Offer and
the Block Demand Response Resource’s Maximum Economic Capacity
Operating Limit.
(3) Hourly Baseline
(a) The Market Participant must submit an hourly baseline for the Demand
Response Load indicating the level of energy consumption expected at
that location in MWh if the Demand Response Resource is not dispatched.
The baseline must cover, at a minimum, all hours the Resource is
submitting Offers for in the Energy and Operating Reserve Markets. This
baseline must be submitted by 1100 hours on the day prior to the
Operating Day and may be updated up to thirty (30) minutes in advance of
the operating hour. The baseline should be based on the average of the
hourly integrated Demand Response Load for the same hours in the last 30
calendar days when the Resource was not dispatched, adjusted by the
Market Participant as necessary to account for changes in the expected
level of energy consumption by the Demand Response Load.
(b) If there have been deviations in hourly integrated metered load from the
hourly baseline during periods when the Resource was not dispatched the
hourly baseline will be adjusted as follows by the Transmission Provider
prior to the calculation of the Demand Response Load. If the average of
the hourly deviation between integrated metered load and submitted
hourly baseline for the hours in the last thirty (30) calendar days when the
Resource was not dispatched is more than five percent (5%) below the
hourly baseline, the hourly baseline will be adjusted by the average
deviation. The Transmission Provider will perform this assessment each
day and notify the Market Participant of any adjustment.
(c) If the hourly baseline has not been submitted, the Transmission Provider
shall set the hourly baseline equal to the Real-Time consumption of the
Demand Response Load associated with the Demand Response Resource
in the Dispatch Interval immediately preceding initial commitment of the
Demand Response Resource.
4.1.2.2 Combined Cycle Resource
Market Participants shall select from one of the four following options
regarding submitting Resource Offers for their registered combined cycle
Resources, which will be declared during asset registration as described under
Sections 2.2 and 2.9 of this Attachment AE:
(1) A Resource Offer may be submitted for a single aggregate combined cycle
Resource, where the aggregate will represent a Market Participant selected
operating configuration of combustion turbines and steam turbines. Under
this option, the combined cycle Resource will be committed, dispatched
and settled the same as any other Resource; or
(2) A Resource Offer may be submitted for each combined cycle Resource
combustion turbine and/or steam turbine and each component will be
committed and dispatched independently and settled the same as any other
single Resource; or
(3) A Resource Offer may be submitted for each pseudo combined cycle
Resource, where each pseudo combined cycle Resource will represent the
combination of one combustion turbine and a portion of the steam turbine.
Under this option, each pseudo combined cycle Resource must be capable
of being committed and dispatched independently the same as any other
Resource and each pseudo combined cycle Resource will be settled the
same as any other Resource; or
(4) A Resource Offer may be submitted for each registered combined cycle
configuration, where each configuration represents an operating state of
the combined cycle Resource with a distinct set of physical operating
characteristics, as dictated by the physical attributes of the combined cycle
Resource. The Transmission Provider will determine the most economic
commitment configuration, if requested to do so by the Market Participant
as part of the submitted Resource Offer, and once committed, the most
economic configuration to transition to for use in both the Day-Ahead
Market and Real-Time Balancing Market. Settlement for a combined
cycle Resource submitting offers in this manner will occur in the same
manner as any other Resource except for Contingency Reserve during
transitions as described under Section 8.5.9 of this Attachment AE and
adjustments for Operating Reserves during transitions as described under
Section 8.6.5 of this Attachment AE. Under this option, Market
Participants must define during asset registration the:
(a) Valid configurations, one of which must represent the
maximum capacity of the combined cycle Resource;
(b) Valid transitions between configurations as defined in the
Market Protocols; and
(c) One or more sets of physical units that can participate in a
configuration.
4.1.2.3 Jointly Owned Unit
Under the individual Jointly Owned Unit Resource option, each Market
Participant may submit Resource Offers for its share of the Jointly Owned Unit as
specified in the Market Protocols. Offer parameters must meet the following
criteria in order to be accepted as valid Offers, otherwise the last submitted valid
offer shall apply:
(1) The sum of the Maximum Emergency Capacity Operating Limits of all
shares of the Jointly Owned Unit must be less than or equal to the Jointly
Owned Unit maximum physical capacity operating limit.
Commitment of individual Jointly Owned Unit shares that have registered under
the individual Resource option will be evaluated by security constrained unit
commitment (“SCUC”) based on the individually submitted Offers for each
Jointly Owned Unit share.
4.1.2.4 Dispatchable Variable Energy Resource
Each Market Participant may submit Resource Offers for Dispatchable
Variable Energy Resources using the same Offer parameters available to any
other Resource, except that:
(1) The minimum operating limits specified in the Resource Offer must be
equal to zero;
(2) The maximum operating limits for use in the Day-Ahead RUC and the
Intra-Day RUC shall be calculated by the Transmission Provider as equal
to the lesser of the maximum operating limits submitted in the Resource
Offer or the Transmission Provider’s output forecast for that Resource to
the extent that such output forecast is available;
a) Dispatchable Variable Energy Resources for which the
Transmission Provider is calculating an output forecast are not
eligible to receive RUC make whole payments as described under
Section 8.6.5 of this Attachment AE.
(3) For the purposes of issuing Dispatch Instructions to Resources as
described under Section 4.1.2.4(6) of this Attachment AE, Dispatchable
Variable Energy Resources with a maximum capability of less than two-
hundred (200) MWs, submitted ramp rates multiplied by five (5) cannot
exceed forty (40) MWs;
(4) For the purposes of issuing Dispatch Instructions to Resources as
described under Section 4.1.2.4(6) of this Attachment AE, Dispatchable
Variable Energy Resources with a maximum capability of greater than or
equal to two-hundred (200) MWs, submitted ramp rates multiplied by five
(5) cannot exceed twenty percent (20%) of the maximum capability;
(5) For the RTBM, during times when the Transmission Provider issues a
Dispatch Instruction to a Dispatchable Variable Energy Resource to
reduce output, the Resource’s Setpoint Instruction shall be equal to the
sum of the Resource’s Dispatch Instruction and any Regulation-Down
deployment, even if the Market Participant has indicated that the Resource
is not dispatchable;
(6) For the RTBM, during times when the Transmission Provider issues a
Dispatch Instruction to a Dispatchable Variable Energy Resource to
increase output in Dispatch Intervals immediately following a Dispatch
Interval in which a Dispatch Instruction was issued to reduce output as
described in Section 4.1.2.4(5) of this Attachment AE, the Transmission
Provider shall calculate the Resource maximum operating limit to be equal
to:
(a) The lesser of the maximum operating limits submitted in the
Resource Offer or the Transmission Provider’s Dispatchable
Variable Energy Resource output forecast for that Resource to the
extent the such forecast is available, except that, the Transmission
Provider’s output forecast for the Resource shall be used for the
maximum operating limits when: (i) maximum operating limits
have not been submitted; (ii) the maximum operating limits
submitted in the Resource Offer were not updated during the
Operating Hour prior to the Operating Hour in which the Resource
limit would apply but before the lead time described in Section 4.1
of this Attachment AE; or (iii) the maximum operating limits
submitted in the Resource Offer exceed the maximum physical
rating of the Resource as stated during market registration; or
(b) The maximum operating limits submitted in the Resource Offer if
the Transmission Provider’s Dispatchable Variable Energy
Resource output forecast for that Resource is not available.
The Transmission Provider shall continue to calculate such maximum
operating limits for each subsequent Dispatch Interval until the maximum
operating limit is equal to the lesser of the Transmission Provider’s
Dispatchable Variable Energy Resource output forecast for that Resource
or the maximum operating limit submitted in the Resource Offer, after
which, the Dispatchable Variable Energy Resource’s maximum operating
limit shall be calculated as described in Section 4.1.2.4(7) of this
Attachment AE.
(7) For the RTBM, during times other than those times described under
Section 4.1.2.4(6) of this Attachment AE, the Resource’s maximum
operating limit for use in the current Dispatch Interval shall be equal to the
Resource’s actual output at the start of the Dispatch Interval and the
ramping restrictions described under Sections 4.1.2.4(3) and (4) of this
Attachment AE shall not apply.
(8) Dispatchable Variable Energy Resources may also receive an OOME
according to the rules in Section 6.2.4 of this Attachment AE.
4.1.2.5 Non-Dispatchable Variable Energy Resource
Each Market Participant may submit Resource Offers for Non-
Dispatchable Variable Energy Resources using the same Offer parameters
available to any other Resource, except that
(1) The minimum operating limits specified in the Resource Offer must be
equal to zero;
(2) For the RTBM, the Resource’s Energy Offer Curve shall not apply;
(3) For the RTBM, the Resource’s Dispatch Instruction shall be equal to the
Resource’s actual output at the start of the Dispatch Interval and the
Resources must operate as non-dispatchable;
(4) Resource Energy Offer Curve prices shall be assumed equal to zero (0) for
the purposes of calculating production costs relating to RUC make whole
payments and cost allocation thereof under Sections 8.6.5 and 8.6.7 of this
Attachment AE;
(5) An OOME may be issued to a Non-Dispatchable Variable Energy
Resource. In addition, the Transmission Provider will issue the dispatch
instruction to the Resource in accordance with Section 6.2.4 of this
Attachment AE; and
(6) The maximum operating limits for use in the Day-Ahead RUC and the
Intra-Day RUC shall be calculated by the Transmission Provider as equal
to the lesser of the maximum operating limits submitted in the Resource
Offer or the Transmission Provider’s output forecast for that Resource to
the extent that such output forecast is available, otherwise the maximum
operating limits shall be equal to those submitted in the Resource Offer;
(a) Non-Dispatchable Variable Energy Resources for which the
Transmission Provider is calculating an output forecast are not
eligible to receive RUC make whole payments as described under
Section 8.6.5 of this Attachment AE.
4.1.2.6 External Dynamic Resource
Each Market Participant may submit Resource Offers for External
Dynamic Resources (“EDR”) using the same Offer parameters available to any
other Resource, except that:
(1) A Market Participant may only submit a commitment status as defined in
Section 4.1(10)(a) or (d) of this Attachment AE;
(2) For an EDR in the Eastern Interconnection, a Market Participant must
submit a dispatch status indicating that the EDR is not available for energy
dispatch as described under Section 4.1(11)(a) of this Attachment AE;
(3) For an EDR in the Eastern Interconnection, Resource Offer parameters are
limited to: Regulation-Up and Regulation-Down Offers, Spinning and
Supplemental Reserve Offers, Regulation Ramp Rate, Contingency
Reserve Ramp Rate and Resource Status. All other Resource Offer
parameters as listed in Section 4.1(9) of this Attachment AE shall not
apply to EDRs in the Eastern Interconnection.
(4) For an EDR that is not in the Eastern Interconnection, Resource Offer
parameters are limited to: Energy Offer Curve, Ramp-Rate-Up, Ramp-
Rate-Down, Regulation-Up and Regulation-Down Offers, Spinning and
Supplemental Reserve Offers, Regulation Ramp Rate, Contingency
Reserve Ramp Rate and Resource Status. All other Resource Offer
parameters as listed in Section 4.1(9) of this Attachment AE shall not
apply to EDRs that are not in the Eastern Interconnection.