aech chapter 11

Upload: car-alv

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 AECH Chapter 11

    1/28

    Section III Covered and Insulated Aluminum Wire and Cable

    Chapter 11

    Installation Practices*

    Aluminum was first used on an overhead transmissionline more than 85 years ago. Today virtually all overheadtransmission lines have conductors of aluminum or aluminum reinforced with steel (ACSR).The performance record of aluminum on overheadtransmission lines led to its use in conductors of othertypes so that today most overhead distribution, servicedrop, and service entrance cables are aluminum. Morerecently, insulated aluminum cable has corne into widespread use in underground distribution and building wireapplications.Aluminum building wire installation procedures arebasically the same as those for copper. However, becausealuminum is a different metal "ith different properties,several differences in installation practices must be followed. Connectors tested and approved for aluminumconductors must be employed and equipment to whichaluminum conductors are to be connected must haveterminals intended for use with aluminum conductors.

    Aluminum wire and cable are available in sizes to meetall needs and with the same types of insulation as copper(See Table lI-l). Connectors for all types and sizes ofaluminum conductors and equipment with suitable terminals are available. Such equipment, UL-listed anddesignated for use with aluminum or copper conductor(ALlCU), and connectors designated "AL7CU" or"AL9CU" are available as stock merchandise in leadingsupply houses.The types and electrical properties of wires and cablesused in secondary distribution and interior wiring circuitsare listed in previous chapters. However, the dimensionsfor a wide range of sizes and various types of insulationare listed, for convenience, in Table 11-1. The method of

    '" FOr further infonnation On the installation of aJuminum buildingwire see the AA bookIet "Aluminum Building Wire Instailation Manualand Design Guide."

    connecting** a single wire or cable (or the individualconductors of a multi-conductor cable) to other conductors or to switch-gear depends on the size of the conductor, the type of connector, and whether the components to be joined are both aluminum or one is of anothermetal such as copper.

    Aluminum Conductor Connectioll$The electrical conductor has no functional value untilit has been properly connected to complete the electricalcircuit. Experience indicates that, apart from damage dueto faulty installation or operation, most of the problemsencountered in the field are at connections. Therefore, itis apparent that care taken in making a proper termination

    or splice is time well spent.A similar record can be attained with insulated aluminum conductors if there is proper attention to theconnecting methods. The basic function of extending theconducting path is the same whether the conductor isbare or insulated, overhead or underground, inside building walls, Or in cable trays or conduit.In the joining process, the oxide film on the contactsurface of the aluminum must be ruptured to expose basemetal. This fissured contact surface must be entrappedand collapsed against the adjoining contact member toestablish metal-to-metal conducting areas. In addition,the joining process must protect these conducting areasagainst the degrading effects of service. In this respectthe use of joint compound is most important. Its mainfunction is to prevent the entry of moisture. Electricalconnections are particularly vulnerable to this when the

    $>/I For purposes oftbis discussion, splicing and terminating will referto conductors in circuits above 1000 volts which require not onlyconnecting the separate conductor elements. but also the restorationof sometimes complex installation systems over tbe splice or terminaland, under some circumstances, application of added protection,Splicing and terminating are described separately. page 11-11 et. seq.,,-,

  • 7/30/2019 AECH Chapter 11

    2/28

    covered and insulated aluminum Wire and cableTABLE 11-1Nominal Dimensions and Areas, Aluminum Building Wire (Taken From 1987 NEe)

    Bare Conductor*" TypeTHW TypeTHHN TypeXHHWSize

    AWGorKCMILSize Number

    AWGor ofKCMIL Strands Oiam.InchesApprox.Oiam.Inches

    Approx. Approx.Area Oiam.Sq. In. InchesApprox.AreaSq. In.

    Approx.I

    Approx.Diam. AreaInches Sq. In.8 7 .134 .255 .0510 - - .224 .0394 86 7 .169 .290 .0660 .240 .0452 .260 .0530 64 7 .213 .335 .0881 .305 .0730 .305 .0730 42 7 .268 .390 .1194 .360 .1017 .360 .1017 21 19 .299 .465 .1698 .415 .1352 .415 .1352 1

    110 19 .336 .500 .1963 .450 .1590 .450 .1590 liD2/0 19 .376 .545 .2332 .495 .1924 .490 .1885 2103/0 19 .423 .590 .2733 .540 .2290 .540 .2290 310410 19 .475 .645 .3267 .595 .2780 .590 .2733 4/0250 37 .520 .725 .4128 .670 .3525 .660 .3421 250300 37 .570 .775 .4717 .720 .4071 .715 .4015 300350 37 .616 .820 .5281 .770 .4656 .760 .4536 350400 37 .659 .865 .5876 .815 .5216 .800 .5026 400500600

    3761

    .736 .940

    .613 1.050.6939.8659

    .685

    .985.6151 I .860.7620 .960 .6082 600.7542 600700 61 .877 1.110 .9676 1.050 .8659 1.050 .6859 700750 61 .908 1.150 1.0386 1.075 .9076 1.060 .9331 7501000 61 1.060 1.285 1.2968 1.255 1.2370 1.230 1.1682 1000

    'Ou'l'lensioos are from industry $OUrces uCompact conductor per ASTM B 400, Artide 310-14 of the 1987 NEe calls for AA 8000 series electfical grade aluminum aHoy conductor material.

    power is off and the conductors are cool. To the extentthese are accomplished, the connection will have lowand stable contact resistance during its service life. (Formore information on electrical contact theory, the readeris referred to the bibliography at the end of Chapter 13.)In this, as in preceding chapters, we will first considerconductors for secondary circuits (0 to 1000 volts) andthe installation practices associates with them.

    Building Wire ConnectorsOnly pressure-type connectors marked AL7CU orAL9CU to indicate they have been tested and are listedby UL for aluminum, copper, or aluminum to copperconnections interchangeably should be used. The connectors are usually plated to avoid the formation of oxide

    and to resist corrosion.Pressure connectors are of two basic types--mechanical screw type and compression type applied with a tooland die.Both types are designed to apply sufficient pressure toshatter the brittle aluminum oxide from the strand surfaces and provide low resistance metal to metal eontact.Both basic types are suitable for usc with aluminum,although many contractors believe that compression connectors are less susceptible to installation error.

    UL Slandard 486, covering connectors for use withaluminum wire, has been revised. A numberof connectorhave already been tested under the more stringent requirements of the new standard, UL 486B. and arcurrently available.Installers are cautioned to avoid mechanical pressurconnectors with too wide a range of wire sizes becausthe screw may not adequately engage the strands of thsmaller conductors. Installers are also advised to contacconductor manufacturers for recommendations concerning specific connectors for use with their products.

    Connectors for every conceivable need are availableSome typical connectors are shown in Fig. 11-1. Whichever type you use, follow the mannfacturer's instructioncarefully.Compression Connectors

    Aluminum conductors are particularly suitable for connecting to each other or to an equipment terminal by usof solderless compression type sleeves because the conductor strands tend to weld together as a result of highcompression pressure.

    Compression connectors similar to those used for bareconductors (see Chapter 5) arc widely used for connecting insulated conductors (Fig. 11-1). Various styleare available, along with special tools, representing the"system" of a particular manufacturer. Depending on11-2

  • 7/30/2019 AECH Chapter 11

    3/28

    Compression Connectorsr!Es

    SPLICE

    MECHANICAL COHHCTOR$

    TfES

    CROSSOVER, TEEOF! PARALLEL TAP

    TAPS

    Fig. 11-1 Connectors have been de-signed and manufactured for everyconceivable contingency. Make sureconnector is UL listed for alumi-num.

    the size of the conductors, compression is obtained byuse of hand tools Or from hydraulic pressure.Mechanical ConnectorsPressure connectors of the setscrew or bolted mechanical type. Fig. 11-2, also provide a rapid means of makingconnections particularly where space is limited and wheremany taps are taken from a main as in panel boards orjunction boxes. Aluminum connector bodies are machined from extruded high-strength aluminum, such as6061-T6. The setscrews are of the Allen head type andtightening of screws or bolts by wrench compresses thealuminum conductor strands against the side wall of the

    installation practicesrecess, causing the strands to intermingle, Fig. 11-l.Mechanical connectors should be tightened to manufacturer's recommended torque levels. In the absence ofmanufacturer's recommended torque levels, values inTable JI-2 should be followed.Connector Plating

    UL standards require that connectors for use withaluminum conductors be plated with tin or some othersuitable contact metal and the face of any pad or lug thatis plated should not be scratch-brushed but merely cleanedwith a suitable solvent cleaner. Scratching the platedsurface is likely to remove the plating. It should be notedthat zinc plated connectors have an adverse effect onaluminum and should never be used on systems wherealuminum wire is used.

    Building Wire TerminationsUL-listed terminal lugs marked AL7CU or AL9CU areused to connect aluminum conductors to transformers,switches, bus bar, motors and other equipment. Aluminum terminals are usually plated and plated connectorsshould not be scratch-brushed or abraided.Like connectors, they are of two basic types-mechanical screw type and compression type applied bytool and die. Some typical terminal lugs are shown inFig. 11-2. They are applied to the conductor ends in thesame manner as described under "Connectors."All equipment should be furnished with CL-listed, allaluminum terminals. Mechanical terminal lugs that arecopper bodied and tin plated should not be used with

    aluminum conductors larger than #6 unless they havepassed the 500-cycle requirements of new UL Standard486B.Care should be taken that the conductor temperatureand ampacity ratings are compatible with the terminalsand equipment to which they are to be connected.When all components are aluminum (bus, sluds, lugs)only aluminum bolts should be used to make the connections.The following procedures should be used:

    I. Aluminum bolts should be anodized alloy 2024-T4 andconform to ANSI BI8.2.1 specifications and to ASTMB 211 or B 221 chemical and mechanical propertylimits.2. Nuts should be aluminum alloy 606I-T6 or 6262-T9and conform to ANSI B 18.2.2.3. Washers should be fiat aluminum alloy Alclad 2024T4, Type A plain, standard wide series conforming toANSI B27.2 SAE or narrow series washers shouldnot be used.4. Hardware should be assembled as shown in Fig.IJ-3.

    11-3

  • 7/30/2019 AECH Chapter 11

    4/28

    --

    covered and insulated aluminum wire and cableTerminals

    SCREWTVPE: TERMINAL LUGS

    ! ;e~ COMPRESSION TERMINAL L.UGSc"1f? p .~ ~ ~ ~

    iaMond eire um1erefltl a: He/ll;;gofl;L Inder"lted CompreSSIOI ' I VersaCrirnp

    Fig. 11-2. Typical plated aluminum terminal lugs corne in variety of styles.TABLE 11-2 STANDARD PRESSURE-CONNECTOR TORQUE TABLES

    Tightening Torque For Scrsws.Toraue, Pound-lnehe$

    Slotted Head No. 1Qand Lar98rb Hexagonal HeadSlot Width-Inches External DriveSocket WrenchTo 3164 Over 3/64 Split-Bolt Othsrf o ~ l e n g t h - I n c h e sTo 1 4 Over 1/4 Connectors Connect

    Torque Fo r Slotted Head Screws.Smatter Than No. 10 For Use With Torque ForNo 10 AWG or Smaller Conductol"$ Socket Head Screws'"Torque-Lblnches

    Screw- Screww$lot Wklth-lnche5SlotLongth- Less MoreInchesc Than 3164 Than 3/64To 513251323116713211491329/32 +

    7 97 127 127 129 12- 15- 20

    SocketSize Across Torque.F l a t s ~ Pound-Inchesnehss

    4551321/8 1003/16 1207132 150114 2002753185116 375112 5009/16 600

    a. Clamping screws with mu!tiple tightening means: for example,for a slotted hexagonal head screw, use the highest torQuevalue associated with the different tightening means.b. For values of slot width or length other than those specified,select the largest torque value associated with conductor size,c. For slot lengths of intermediate values, select torQues p e r t a j n ~ing to next shorter slot length.

    20 35 60810 AWG 40 60 25 45 1655 45 165 - 275 50 27560 275 50 385/0 50 385010 50- 50010 50- 50010 - 650050 komi!30035040050050070075060090010001250150017502000

    6500- 50 65 050- 62550 6251000050 100050- 100011000- 11000-: 1100110050- 1100- 11001100- -

    7575110110150150150160160250250325325325325375375375375500500500500600600600

    Note: The torque :ab!es presented here are taken from UL Standard 4868, but are representative ofIhose pL.bllshed in other UL Standards, in NEMA equipment installation instruction publications. andIn the Canadian Electrical Code. The same values apply to pressure connectors tor both copper(UL Standard 486A) and aluminum conductors.

    11-4

  • 7/30/2019 AECH Chapter 11

    5/28

    1 AlumInum Bolt2 Alummum Washer3 Aluminum Bu s4 A!ommum tu g5. AlumllHJm Wbshel6 Alumit'lum Nu t

    installation practicesTABLE 11-3

    Lug Bolting Torque,'Bolt Diameter

    'nthTightening Torque

    PoundFeet1/4 or less5/1631871161125/8 or more

    61119304055Fig. 11-3. When all components arealuminum. aluminum hardwareshould be used and installed asabove.

    5. All hardware should be suitably lubricated beforetightening.6. Bolts securing lugs should be tightened to the manufacturer-s recommended torque. In the absence ofsuch recommendations, torque values listed in UL486 Standards should be used. (See Table 1I-3)

    If adding to an existing installation containing copperbus or studs or if it is impossible to obtain the requiredequipment with aluminum terminations. then a steel boltshould be used with a Belleville spring washer to allowfor the differing rates of thermal expansion of the materials. The following procedures should be used:1. The steel bolt should be plated or galvanized. mediumcarbon steel heat treated, quenched and tempered

    equal to ASTM A 325 or SAE grade 5.

    'FromUt 4S6 Standards.HOTE: Ii bOilS are nOllubricaled with sUiton spray Cfclner suitable lubricant. torques may 'fary widely atldresu!! ,I> high (lon-tacl resistance

  • 7/30/2019 AECH Chapter 11

    6/28

    covered and insulated aluminum wire and cable

    Fig. 11-5. Belleville washer is usedto make an aluminum-ta-copper orsteel joint. Note: Crown of Belleville washer should be under thenut.

    With equipment having terminals that will accommo aluminum bolts and nuts are used, only the heavy washerdate only copper conductors. a "gutter splice" may be bearing on the aluminum lug, is necessary.used to connect the aluminum conductor. The aluminum Figures 11-7 to 11-12 show some typical connectionconductor is spliced to a short length of copperconductor, of aluminum conductors to equipment terminals.and the copper conductor stub is then connected to the Because of the differing rates of thermal expansion oequipment terminal (Fig. 11-4). An AL7CU or AL9CU aluminum and other conducting or support metals, it icompression type connector is used to make the splice. preferable to have all parts of the circuit, including studInstead of a gutter splice, onc of the many UL-listed and clamp bolts, of aluminum. The aluminum bolts shoulAL7CU or AL9CU adaptor fittings specifically designed be of alloy 2024-T4 and the nuts compatible, thougfor this purpose may be used (Fig. 11-6). preferably not of identical alloy and temper. Bolts anFor connecting large aluminum conduc tors (500 kcmil nuts should be of heavy series design to reduce stresand up) to heavy equipment having copper terminal studs beneath the head. NC (coarse) threads are preferred foand/or pads, large compression type lugs, preferably with the 2024-T4 aluminum bolts. Components should btwo holes, should be used in making such a connection assembled as shown in Fig, 11-9. More information abou(Fig. 5-2). With other than aluminum bolts, Belleville aluminum bolted connections will be found in Chaptespring washers and heavy flat washers in consecutive 13.arrangement as shO\m in Fig. 11-5 must be used. If

    Fig. 11-7. Where possible, currenttransformer terminals should be re-placed with compression type (B).If not possible /0 remove, sectionof copper cable should be splicedto aluminum (AJ.

    Fig. 11-8. Power transformer ter-:minals, ifcopper, must employ shortcopper stub spliced to aluminum L___~ ~ ~ ~ ~ : . : : : ! : = - _ Jcable.

    Fig. JI-4. Gutter splice is used whenterminal lugs are not removableand are approved for copper cableconnection only.

    ~ l O @ @ ~ t 2 3 .. fi\

    \CrownFacu"ut

    t. Aluminum IY BlI$ (or stud)2 Sfe1'l:1 or CQPper St"";3. AI"minvM Lug4. S t ~ i J l Flat Washef5. Steel Selleville6, Sleel Nut

    Fig. 11-6. There are a number oUL-listed adaptor jittings availablefor use with terminals not suitablefor direct connection of aluminumconductors.

    11-6

  • 7/30/2019 AECH Chapter 11

    7/28

    installation practices

    Fig. 11-9. When connecting aluminum conductors to a unit substalion with copper bus, usecompression type aluminum lugsattached with a steel bolt, a fiatwasher, and a Belleville washer (A).Copper primary leads on transformer are connected to aluminumfeeders in aluminum connectors andbolted back-to-back using a steelbolt, a fiat washer, and a Bellevillewasher (B).

    Basic Installation Techniques

    Fig. 11-10. Three methods of making motor connections are shownin detail A. All terminals are preferably aluminum. Where bolt is steelor copper, Belleville washer is necessary (B).

    Fig. 11-12. Copper lug connectionson switchgear are rep/aced withequivalent aluminum connectors.Belleville washer is used with copper or steel studs.

    1. Stripping InsulationNever use a knife or pliers to ring a conductor whenstripping insulation. One way to avoid this is to pencilor whittle the insulation (Fig. 11-13).Another method is to skin the insulation back from thecut end of the conductor and then cut outward (Fig.11-14).Several types of insulation stripper are available forquick, easy removal of insulation. One of these, usefulfor small size conductors, is shown in Fig. 11-15.

    2. Making ConnectionsPreparation of aluminum conductors for connection toan equipment terminal or another conductor requiresstripping of the insulation and rupture and dispersal ofthe nonconducting oxide film that appears quickly on afresh aluminum surface exposed to air. Care must betaken not to nick the wires when removing insulation inorder to avoid broken strands in installation or service.Sevel".tl types of insulation stripper are available forquick, easy penciling or square-cut removal of insulation.One type is shov,n in Fig. 11-16.Abrading the conductor strands with a wire brush orother appropriate tool will serve to clean the conductor

    and disperse the oxide coating prior to application ofjoint compound.The conductor end is then inserted into a compressionsleeve of adequate thickness or a suitable mechanicaltype pressure connector. I f the connector does not comefactory-filled with an acceptable joint compound, suchpaste should be applied to the conductor end beforeinsertion into the connector. (Some manufacturers' connectors may not require the use of compound but itshould be used in the absence of specific instructions tothe contrary.) The compression sleeve should then becompressed with a hydraulic compression device, or thesetscrew of a mechanical connector tightened, in a mannerprescribed by the connector manufacturer. Excess compound should be removed from the conductor insulation,

    but not from the joint itself where it will serve to preventair from entering.Solid aluminum wires are prepared in a similar manner,and the smaller sizes may be fastened under a bindinghead screw* (without joint compound) after looping in aclockwise direction.

    * Note: The ALiCU or AL9CU marking is not required on equipmentconnectors. However the equipment in which they are installed mustindicate suitability for use with aluminum and connector tighteningtorques.

    11-7

    http:///reader/full/Sevel%22.tlhttp:///reader/full/Sevel%22.tl
  • 7/30/2019 AECH Chapter 11

    8/28

    covered and insulated aluminum wire and cable

    Fig. 1113. Never ring a cable-itmay lead to a break. Insulationshould be removed as one wouldsharpen a pencil.

    Fig. 11-14. Another safe way ofremoving insulation from conduc-tor is to peel the insulation backand then cut outward.

    Fig. 11-15. Use wire stripper forremoving insulation from smallerwire sizes. Match stripper notch towire size.

    Fig. 11-16. Penciling tool for removal of insulationbevel configuration by rotation. Several sizes are avaable. which by proper selection ofbushing are applicabto all usual sizes of cables. This tool is particularsuitable for primary cables, which have comparativethick insulation.

    In making connections, first strip the insulation instructed heretofore. Then apply joint compound i f itnot already contained in the connector.If the connector is a mechanical screw type, appJy tmanufacturer's recommended torque (Fig. 11-17).

    absence of specific torque recommendations, use U468B torque values shown in Table II-I. Ifacompressiotype, crimp it as recommended by the manufacturer (Fi11-18). Be sure to select the correct size die and clothe tool completely for full compression. Wipe off anexcess compound. Then tape the joint as instructed undSection BZ Or apply the inSUlating enclosure that comwith some types of connectors.

    3. Pulling Conductors in Conduit orElectrical TubingThe following procedures are applicable to conduitall types including aluminum:

    a. Run a "fish" line through the conduit. This maydone by attaching the line to a piston-type deviwhich is propelled through the conduit by compressair. Another method is to push a round flexibspeedometer type steel wire through the conduPolyethylene fish tapes may be used for shorter runup to about 100 feet.

    b. Attach a clean-out brush to the fish line and behindattach the pull line, then pull both through the conduby means of the fish line.c. Attach the pull line to the conductor or conductoA basket grip over the insulation may be used for thpurpose (Fig. 11-19).

    11-8

  • 7/30/2019 AECH Chapter 11

    9/28

    installation practices

    Fig. 11-18. Crimping tool must befully closed. Failure to close crimping 1001 will lead to an unsatisfactory and weak joint.Fig. 11-17. Proper torque is important-over-tightening may sever the Fig. 11-19. Basket grip.wires Or break the filling; undertightening may lead to overheatingand failure. (See Table 11-2.)

    d. Where conductors are pulled with a rope, stagger j. When conductor ends are prepared for pUlling, be sUrethe conductor ends and anchor in position with tape, not to nick the stranded aluminum conductor duringto provide maximum lIexibility around bends (Fig. insulation removal, Damaged strands can reduce the11-20). pulling tension capabilities of the conductor. To avoidthis, pencil the insulation for removal, as describedabove; do not ring cut the insulation.k. Follow all NEC requirements,

    Fora detailed description ofcalculating pulling tensions,see the example given on page 11-11 on undergroundinstallations. See Chapter 17 for a complete treatment ofaluminum conductors in conduit.Fig. 11-20. When a rope pull hasto be used, skin the cable ends andstagger them after locking with tape. 4. Installation of Cables in TraysThis will hold tie to a minimum Where aluminum cable is to be pulled in trays or cablecross section. racks, take the following precautions, plus those applicable to conduit:e. Try to feed conductors into conduit end closest to the a. Where pulling attachments are used on the conductors,sharpest bend, to reduce pulling tension. cover them with rubber-like or plastic tapes to prevent

    . Have pulling equipment with adequate power available scoring of the trays and installation sheaves during ato make a steady pull on the cables without "jerks" conductor pull.during the pulling operations. b. Use large-radius sheaves around bends and smallerg. Use pulling compound compatible with the conductor sheaves on the straight sections of cable support traysinsulation as the conductors are fed into the conduit, to facilitate cable installations, to reduce the required, to reduce coefficient of friction and required pulling pulling tensions and to prevent damage to strandedtension. conductors or insulations,h. For single conductors on a reel, stagger reels, one c. Where cables are anchored on trays, be sure strapsbehind the other, while feeding in conduit, to maintain or other cable anchoring devices do not cut into theequal pulling tensions and prevent conductors from insulation."crossing over" and jamming in the conduit. d. Cables installed in trays should follow the requireI. Wherever possible, pull conductors in a downward ments of NEC Article 318 for the aUowable numberdirection, to allow gravity to assist in pulling with of cables permitted in trays and their respectivereduced tension. ampacities.

    119

  • 7/30/2019 AECH Chapter 11

    10/28

    covered and insulated aluminum wire and cablee. Straight cable tray runs may often be installed bysimply laying thelightweight aluminum cables in place.f. Be sure tray supports are capable of handling maximum weight of conductors and planned conductoradditions in the future.

    5. Minimum Training RadiiWhere permanent bends are made at terminations usingaluminum building wire, Table 11-5 indicates the minimum bending radius as a multiple of the overall cablediameter. Such bends should be made before the terminalis applied to minimize electrical contact distortion.

    6. Conductors in Vertical RacewaysThe NEC under section 3()()"19 stipulates that conductors in vertical raceways shall be supported. As a generalrule one cable support shall be provided at the top of thevertical raceway or as close to the top as is practical plusan additional support for each interval of spacing as

    shown in Table 11-6. An exception to this rule is that ifthe vertical riser is less than 25% of the spacing listed inthe Table, nO cable support shall be required.

    Installing Cable in Conduit or DuctTheprocedures forinsertinga "fish" lineor tape througa conduit or duct, followed by a pull line andlor cable required for the pull, are well known and established field practice and do not need extensive description herAluminum conductors may be attached to pull linecable by means of a factory-installed pulling eye,

    placing a basket grip around the conductors' insulatio(Fig. 11-21), or by tying the line to a loop in the uninsulatpart of the conductor (Fig. 11-20). Steel pull cables usto pull conductors around bends in aluminum conduruns may damage the conduit at the bend. This is oftavoided by using steel elbows with aluminum conduit by use of a pull line that will not damage aluminuelbows.Pulls should be accomplished with steady tension apulling speeds not exceeding 50 feet per minute. Hapulls can be eased if the reel if hand controlled and slaccable is guided into the conduit.Pulling tensions may be reduced by lubricating t

    cable surface. However, SOme lubricating materials habeen found to adversely affect cable insulations or outjackets. In addition to cable pulling compounds, th

    TABLE 11-5 TRAINING RADII

    For 600 V Cable Not in Conduit, on Sheaves or While Under TensionPOWER CABLES WITHOUT METALLIC SHIELDING ON ARMOR.The minimum recommended bending radii as muHiplies of 1I1e overall cablediameter given in the following tabulation are for both single and multi-conductorcable with or without lead sheath and without metallic shielding or armor.

    Minimum Training RadiusThickness of as multiple of cable diameterConductor Insulation Overall Diameter of CAble-Inchesmils 1.000 and Less 1.001 to 2.000 2.001 and over155 and less 4 5 6170 to 310 5 6 7325 and over 7 8 I

    POWER CABLES WITH METALLIC SHIELDING OR ARMOR(a) Interlocked Armored CablesThe minimum recommended bending radius for all interlockedarmored cables is in accordance with table above but not less than 7 timesthe overall diameter of the cable, except as noted below (c) for tape shieldedcable.(b) Flat Tape and Wire Armored CablesThe minimum recommended bending radius for all flat tape armored and allwire armored cables is 12 times the overall diameter of cable.(c) Tape Chielded CablesFor ali cables having metallic shielding tapes the minimum recommendedbending radius is 12 times 1I1e overall diameter of the completed cable.(d) Wire Shielded CablesWire Shielded Cables should have the same bending radius as power cableswithout metallic shielding tape.Aepfi:'lted loon ICEA 5-66-524, NWA WC-7

    11-10

  • 7/30/2019 AECH Chapter 11

    11/28

    instollation practicesTABLE 11-6

    SUPPORTING CONDUCTORS IN VERTICAL RACEWAYSFrom 1987 NEe Table 30019 (a)

    ConduelorsAluminum Copper

    No. 18 to No. B No t greater than 100 feet 100 feetNO.6 to No 0 No t greater than 200 feel 100 feelNo. 00 to No. 0000 Not greater than 180 feel 80 feet211.6 kernil to 350 kernil No t greater than 135 feet 60 feet350 kernil to 500 kernil No t greater than 120 feet 50 feet500 kernil to 750 kernil Not greater than 95 feet 40 feetAbove 750 kernil Not greater than 85 feet 35 feet

    applies to potting and joint compounds, adhesives, tapes,etc. I f in doubt, compatibility of materials foreign to theinsulation should be cleared through the cable manufacturer.A number of proprietary wire puUing lubricants andcompounds are UL-listed and labeled to indicate thecompound's compatibility with conductor coverings. Inall cases, the manufacturers' instructions should be observed.

    Allowable Pulling TensionThe following formulas can be used to calculate themaximum allowable tension that should be applied to the

    cables. Note that these allowable tensions assume the pulling eye is attached to the conductor. Where the pulling lineis attached to a basket grip that surrounds the insulation,the pulling tension should not exceed 1000 100. It should bekept in mind that tension developed for straight runs perunit length is less than that for the portion of the cable inbends.

    L The maximum a J ~ o w a b l e pulling tension, if the pulling eye isaHached to the conductor

    (Eq. H l )where Pm Maximum allowable tension, lb

    N Number of conductors being pulled simultaneouslyA :::; Circular mil area of each conductor

    ( I f conductors are of various sizes, add the individual NA values)

    K = Conductor stress factor2. The maximum allowable pulling tension (Pm) cannot exceed1000 Ib where cables are pulled with a basket grip; however,the tension per Eqs. 11-1 or 1t-2 should nOL be exceeded,3. The ma;t;imum allowable pulling tension for cable in conduit

    or duct bends (to prevent cable damage becallse of rubbingon sides of bend) must not exceed the following:I'b = 100 r (Eq. H2)

    where Pt> = Maximum allowable bend tension. Ibr = Radius of curvature of the conduit or duct bend, ft

    Note: The maximum aIIowable tension determined from Eqs. 11-1or 1 l ~ 2 should not be exceeded.4. For straight section of conduit or duct, the pulling tension (lb) likelyto be developed can be determined as follows:

    P!,!=L w t (Eq. H3)where = Pulling tension in straight section. Ib

    L Length of conduit or duct straight section, ft'1' = Weight of cable (o r cables), lb per ftt = Coefficient of frictionNote: Fo r a wen constructed conduit or duct with a lubricatedcable, "f" approximates 0.5, Fo r less favorable conditionsor with considerable curvature, " f" may approximate 0.75.

    5. For curved sections of conduit or duct. the pulling tension (lb) likelyto be developed can be determined as follows:I'c =1'. + 1', eta; CEq. 1l-4)

    where Pc = Total pulling tension, IbP::s = Tension for straight section at pulling end, IbPI =:: Tension fo r straight section at feeding end, Ib'" = Angle of bend in radians ( I radian = 57.3 deg)e = Base of Naperian logarithms (2,718)f = Coefficient of friction

    Example: Determine the maximum pulling tension required toinstall three single-conductor cables in a duct. according to thearrangement in Fig, 11-22. The cable specifications are:Three single conductor #4/0 AWG 600-volt aluminum cableswith cross-linked PE insulationWeight, 3 @ 290 Ib/M It = 0.87 Ib per ftCable diameter, ea ch 0.690 in.Coefficietlt of friction=O.5; K value::::.Q.OOS

    K 0.008 for hard aluminum conductors. or 0.004 for Y2 or J.4.;:II hard aluminum.

    iI' ';>\iFf.!:R" . . ~ " \ o ""'5 11-11

  • 7/30/2019 AECH Chapter 11

    12/28

    covered and insulated aluminum wire and cable

    A. C o n d t . t j ~ or Doct Ckan,.,/)Ot BrushB. Kellems GripC. "Job Famianed"' Pulling BlUk'et

    Fig. 1121. Pulling cable in duct. Pulling cable between junction boxes of conduit installations is similar.

    Using a single pulling eye attached to the three conductors and applying Eq. 1 1 ~ 1 . the maximum allowable pulling tension isPm =0.008 X 3 X 211,600=5078 Ib per Sq. II I

    For the entire run from pull-box (I) to pull box (6), the tensionincrements are as follows:Sq.113: At box (2 ) p, == L,., X w X t == 100 X 0.87 X 0.5 == 43.5Ib

    f 0: 05 X 1.S7111-4: At box (3) p, == P. X e = 43.5 X e43.5 x 2.194=95,4113: At box (4) P. = 95.4 + (4 . X w X tJ == 95.4 + (SO X0.87 X 0.5) = )J 7,2 Ib 0,$ X 1.571 114: At box (5) p, == 117.2 = 117,2 X 2,194 =257,llb113: At box (6) P. 257.1 + ( 4 . X w X f) = 257.1 + (15 X0,87 X 0.5) = 263,7 Ib

    The total puning tension of 254 lb is far below the 5080Ib limitation, and the tension at each bend is far below the11-12

    recommendation per Eq. 11-2 of 100 x 10, or 1000 lb.Study of such examples shows that there is an advantage inpuning cables from the pull box or manhole closest to thefirst bend. This aids in reducing tension on the installedcable. In this instance, if the pull started at box (6), thefinal tension would be about half the above-found value.For a more complete treatment of cable puning in conduit, the reader is referred to R.C. Rifenberg, AlEE Transactions, Dec. 1953.

    Installing Directly Buried Power Cables'I f cable placement can be started Defore sidewalks andother obstructions are installed, the plowing-in methodusually is the most economical method of burying powercable. If soil conditions are unsuitable for plowing, the

    *See also Aluminum Underground Distribution Reference Book.

  • 7/30/2019 AECH Chapter 11

    13/28

    PULL BOX

    50'

    PULL BOXFig. 11-22. Diagram o/circui t layout to illustrate methodof computing pulling tension.

    use of trenchers, back hoes, Or manual digging is customary. If the soil is rocky, it should be screened to preventcable damage. In t is not sufficiently fine to closely coverthe cable surface, a four-inch thickness of sandy loamplaced under and over the cable will improve the heatradiating quality of the soil.Duct Or conduit also should be used under streets orwhere access by digging to a buried cable is not practicable.Sufficient cable slack should be provided at risers and

    terminals to permit earth movement that may occurbecause of conductor thermal expansion, frost, and also asan allowance for future repair.Boards or slabs placed over the cable for mechanicalprotection should not be directly in contact with the cablebut should be laid on an earth fill over the cable.Depth of burial ranges from about 30 to 48 inches forprimary cable and from about 24 to 42 inches for secondary cable when buried separately. On many systems,both primary and secondary cables are buried in the sametrench with no separation. In many areas. the trenchesare shared jointly with other utilities, notably communi

    cations-both telephone and television cables. Joint useof trenches requires close collaboration on installationschedules but offers substantial economies to the sharingutilities.

    Initially, a separation of one foot was required betweenprimary power and communication cables and many companies still require this separation. An amendment to theNESC, however, permits random-lay (no deliberateseparation) installation of communication and powercables in the same trenches with grounded wye powersystems operating at voltages not in excess of 22 leV to

    installation practicesground ordelta systems operating at voltages not in excessof 5.3 kV phase to phase, under certain conditions described in NESC Section 35, Article 354. However, joint usewith very long single-phase primary circuits is not recommended because of the inductive pickUp of harmonics bythe communication cables from the power cables.

    Care exercised in handling the cable during installationwill help to avoid trouble later, for damage sustained bythe cable during installation has proved to be a majorcause of subsequent cable failure.

    Many of these precautions have to do with making surethere is no insulation damage. The cable is not susceptibleto corrosion failure when insulation is unbroken, evenwhere moisture has gained entry into the conductor is somemanner; this fact has been determined in cable manufacturer laboratory tests and from research by utilities. Migration of moisture through damaged insulation in thepresence of ac potential concentrates ions and promotesac electrolysis.Cable transitions between overhead and underground

    usually employ the conventional factory-molded pothead,of which special types are available for use in URDsystems. A termination is not reqnired, however, if theinsulated aerial cable is also suitable for direct burial.Such a cable can be carried directly down the pole. Risershields or conduit should be used to protect the cable onthe riser pole to a point at least eight feet above groundlevel, and should extend at least 12 inches below ground.The riser shield must be solidly grounded to the systemneutral, and bonded to the lightning arrester to avoidtransient potentials.Many other practices relating to buried cables and theirconnection to transformers, to service entrances, and tap

    connections in junction boxes and vaults are described inindustry manuals.' Practice is gradually becoming standardized in the direction of increasing reliability and lowering installation and maintenance costs in this most im-portant segment of power distribution.The following suggestions will help to avoid failuresfrom this cause; they apply equally to cable and cable inpipe:

    1. Make sure that end seals are intact both while thecable is stored and installed to avoid entrance ofwater into the strands.2. If plowing is not used, cables, if at all possible, should

    be payed out along the side of the trench from movingreels, or carefully laid in the trench from stationaryreels.3. The trench should not be dug before final grading isdetermined, so cable will not be exposed or be tooclose to the surface.

    See also IEEE Conference Record 31C35 Specia.l TechnicalConference on Underground Distribution. Sept. 2 7 ~ 2 9 , 1966.

    11-13

  • 7/30/2019 AECH Chapter 11

    14/28

    covered and insulated aluminum wire and cableTABLE 117

    I ICEA MINIMUM BENDING RADII' FOR POWER CABLESWlTHOtIT METAlliC SHIELDING'I Minimum Bendine RHii as aMultiple of Cable DiameterI cabl. DO, Inch

    Tlllcimess of 1.000 1.001 2.001i

    Insulation, Inch I and less tD 2.000 and OYer0.156 and Ie. . 4 5 6

    I0.157 to 0.312 5

    i6

    !

    70.313 and over - 7 S Only applicable for cable training; bearing pressure limitation may require larger bending radii forcable tension.

    ** Data apply to single and multiple conductor cable; also to wire-shielded cable, Minimum bendingradius for cables with metallic shielding tape is 12 Urnes the completed cable 00. The National Elec-trical Code Section 300-34 requires 8 times fot non-Shielded and 12 times for shielded mediumvoltage cable bending radiI.

    4. In rocky soil areas, use screened backfill Or sand toprotect direct buried cable. A 2-inch bedding issufficient below; but there should be a minimumcover of about 4 inches. (The bedding and cover canbe omitted when duct in conduit is used).5. If boards, concrete slabs, etc., are used above thecable for mechanical protection, they should not bein direct contact, to avoid shearing action when the

    soil settles. Make sure boards are treated with preservatives that will not harm the cable's insulation.6. Check the cable visually for damage before burial orinstallation in duct.7. When primaries are pulled into ducts or open trenches,the use of a pulling grip over the cable is commonrather than a pulling eye or other attachment connected directly to the conductor. Duct should becarefully cleaned by pulling a plug through it toremove all burrs and obstructions. To keep the cablepulling tension within safe limits, a lubricant approvedfor use with the specific insulation and insulationshield should be used.8. When doing permanent training make sure that theminimum bending radii are observed (see Table11-7). Make every effor t to provide more radius thanthese values at reel payout, risers, plow guides, ductbend, etc.9. Make sure splices and other connections are madein accordance with manufacturers' recommendations.

    10. Double check to make sure proper backfilling is done.Rock fill should be kept away from the cables to

    prevent damage. Compacting should be carefullydone, and air spaces minimized.11. Proof test the cable after installation to insure integrity of insulation and splices. (See Table 11-8).12. Don't overfuse the cable. Because of the paucity offailures, many utilities prefer to use one-shot fuses

    as an added protective measure for the cable.Many of these precautions have to do with makingsure there is nO insulation damage. The conductor in 600volt cables is not susceptible to corrosion failure wheninsulation is unbroken and moisture has not gained entryinto the conductor. When moisture enters a break ininsulation, however, ac electrolysis begins.

    Splicing and Terminating in Underground SystemsThe revolution in underground distribution systemdesign has included the devices and methods used formaking splices, connections, and terminations. The objective here has been to reduce the amount of skill and

    time required in the field so as to reduce the installationcosts. More prefabrication is being done under factorycontrolled conditions, and the need for heating andpouring of insulating compounds or extensive taping inthe field has been greatly reduced.Aluminum connectors and terminating devices should

    be used with aluminum conductors so as to avoid differential thermal expansion and contraction upon heatingand cooling that could result from the use of connectorsof dissimilar metals. Compression type connectors andlugs applied with a tool and die are widely used. It is11-14

  • 7/30/2019 AECH Chapter 11

    15/28

    insto/lation practicesTABLE 118

    ICEA RECOMMENDED de PRooFTEST VOLTAGES(15 Minute Test)Polyethylene or CrossLinked Polyethylene Insulat.d cables

    : ProofTestRated Insulation Voltage 1mCircuit Thicllnm ,Mils)oltage Installationi

    255001 8000 1152001 5000 : 90

    35800115000 175 5515001 25000 8025001 28000

    2608580: 28001 35000 345 100

    important in installing these devices that a die of thecorrect size be used and full pressure be applied in orderto obtain permanently sound connections.600 Voll Secondary Clrcuils

    In this regard connector manufacturers have madeimportant advances in the design of connection devicesfor secondary circuits. There are far too many types todescribe them all in this handbook. However, a coupleof examples are given below to indicate the types of premolded splices and terminations that are currently available for this type of service.(a) Underground Direct Burial Splice 600 volt insulated

    cable splices are available for conductor sizes #6 AWGstranded through 1000 kcmil and can be completelyinstalled and sealed without taping or compound filling.Typical installation procedure is (Fig. 1123) as follows:Step A

    Lubricate both insulating splice caps by applying asmall amount of the supplied lubricant to the insidediameter of the cap at both the housing end and alsoto the inside diameter at the conductor hole end. Foreasier assembly of the insulating caps to the conductor, jt is recommended that the insulation at theend of the conductor be penciled before stripping.Then place the proper caps over each conductorend.

    Step BStrip correct length of conductor insulation for thesplice connector being used. Place splice housingover end of conductor and assemble one cap tohousing. Large end of cap should cover the knurledline of the housing body.

    Step CWire brush exposed cable ends and then immediately

    insert cables into connector. Start crimping spliceonto conductor as per manufacturer's instructions,Continue crimping to ends of splice, overlappingcrimps 118 inch minimum. Wipe away all excessoxide inhibitor,Step DPlace housing with the assembled cap over spliceconnection and snap remaining cap in place onhousing to complete the sealed splice. When capsare correctly installed, the large ends should coverthe knurled lines on both ends of the housing body.

    (b) Secondary 600 V Underground Terminations. Thereare several different designs of connector products whichare approved for use in underground 600 V electric powersystems, They supply the needs of connectors requiredfor residential or commercial use; direct burial, belowgrade vaults; pedestal or pad mounted equipment; boltedor compression fittings, and in any combination,

    Fig. 11-24 shows a representative group of these fittingswhich are designed to accommodate a wide range ofconductors, Their installation is straightforward and requires no field cutting or hand taping for insulation orenvironmental sealing. The threaded stud connector fortransformers is such that the connector can be detachedfrom the transformer without disconnecting the conductors.

    Primary CircuitsTermination of primary underground cables requiressome type of stress relief. Initially, these were made upby taping a stress cone, which proved to be one of themost tedious and time-consuming jobs for the field man.Today most utilities use some form of preshaped Orprefabricated stress cone, which can be installed in afraction of the time.

    11-15

  • 7/30/2019 AECH Chapter 11

    16/28

    -----------

    covered and insulated aluminum wire and coble

    B. IN4fSUI.ATlNGAP rNO PENCILING__ ( REQUIRED

    .:- . -f --, - IL

    c. -. ._-D.

    STRIP :oslENGTH

    INSU!..ATIN;:i CAPKNURLED LINES

    - - - - -H,HH+~SPUCE HOUSING

    ~ ~ ~ - " ~ ~ ' . ~ - "PUCE CONNECTOR INSULATING CAP ----- E--- .KNURLEO :;;LINES

    l__________________________________________________________ ~ c ~ o u _ n _ e ~ ~ . 8 ~ l a ~ O k ~ b _ r i a ~ n ~ . C ~ O ~ _ J Fig. 1123. Secondary 600 V Underground Splice Kit showing sequence of assembly steps.

    Typical terminations for primary cables indicate thatmolded, precut tape, and porcelain types are used indoorswhile porcelain units are most often used outdoors. Oneof the most significant developments in primary cableterminations has been the introduction of plugin connectors for joining the cables to equipment or othercables. With these devices it is almost as easy to connccta primary cable as to plug in or remove an appliancecord from a convenience outlet.1116

    The concept of premolded stress relief takes the fabrication of a stress relief COre away from the field aninto the factory with its controlled environment, leavinjust the assembly to the field installer. Elastomeric connections form a very convenient, inexpensive, and reliabmethod of connecting or terminating high voltage cablePower cable loadbreak elbows in the 35 kV class werintroduced to the industry in 1983, with designs for 15 kand 25 kV following in 1985.

  • 7/30/2019 AECH Chapter 11

    17/28

    installation practices

    CAPfo r porcelain bushings

    Se t screw s In s eu connector are light -ened do w n on flat side 01 Adapter :pressure deforms Adapter to lo ck

    A d ~ p t e r and seu conneCtor tothreaded stud : un screws can be-ofl Adapter an d se u conn eCto rremoved from transformer withoutremo ving conductor from connector .

    Thr eaded Stud Secondary Bush ingl \ Adapter Scr6W5 on threaded, tud of bllshing : "'Iat" side01 Adapter mUSt be orientedto receive se l Ic rews

    seu connector slips o verAdapUlr : Al l Adapters have ~0-ring5 In Sealing Ce p sam e 0 .0 , all seu co n -seal aro"nd Bushing neclors h.o ve seme AdepterNe ck and seu connector cavity 1.0 .

    Fig . //-24. Some typical 600 V underground termination fillings.

    Through the combined efforts of the connector and Some typical applications of premolded products areapparatus manufacturers and the utilities, there is avail at pulling or junction boxes, cable to equipment connecabte today an array of premolded products that exhibit a tons, and cable to cable connections. All of these comhigh degree of safety , reliability, and flexibility.' ponents are designed and tested to be in compliance withANSUIEEE Standard 386-1985 Separable InsulatedSee James W . Fitzhugh's paper. "Exploring the Application of Connectors for Power Distribution Systems above 600Premolded Products for High Voltage Power Systems:' Volts .

    11-17

  • 7/30/2019 AECH Chapter 11

    18/28

    covered and insulated aluminum WIre and cable

    Prlo(o counesy 01 ELASTIMQFig. / /-25 . Power cable joint for use af 15 k V or 25 kV.

    Primal'( Voltage CircuitsA cutaway view of an up-to-date power cable j0int isshown in Fig. 11-25 . The cloverleaf design allows thejoint to operate at lower temperature s.While installation of premolded devices are si milar,conditions may vary depending on the device , the cable,and the manufacturer of the splice or termination. In all

    cases, full instructions will be provided and should befollowed . Additional typical designs are shown in Fig.11-26.Development work in splicing, connecting, and terminating devices is still proceeding. Use rs thus areadvised to keep posted on the latest designs being offeredby the connector manufacturers in order to achievegreatest economies in making cable splices, connections,and terminations.Though recent trends have been toward th e use ofpremolded splicing and terminating devices, it is stillnecessary or desirable in so me circumstances to makehand-taped joints by traditional methods. Because of thisthe details of making a hand-taped , concentric neutral,st raight splice are given below. Details of the joint areshown in Fig. 11 -27.The following are the inst ruction s to be generally basedin making the joint illustrated in Fig 11-27. They are fora typical hand-taped primary cable splice . All splices andterminations should be made by a qualified cable splicerin accordance with the manufacturer's instructions andrecommendations.

    I. Study splice drawing and instructions:2. Train cables into final position and overlap for 18inches to afford enough excess concentric wire forfinal jointing.

    11-18

    3. Temporarily wrap a number of turn s of tape over theouter concentric wires at least 18 inches from thecenterline of the splice.

    4. Carefully unwrap outer concent ric wires and temporarily remove them out of the splice area, beingsure not to damage or kink them.

    TABLE " -9 Recommending Taping Dimensions

    Inlull-Ok. . A B C 0 KThk:k.. .u

    15KV175P On e- /'Iall '" Connector Z 4%" 2A oj.- 1 4 ' ~ 3/8".220" lenglh

    25KVOne-tlall.2so" Connecl0r 2W 5\14" 2A + 11\12" 7/16'length

    35KVOne-hall345" 7"onnector 2A + 22"length '"

    5. Cut off excess cable at splice centerine.6. Remove outer semiconducting jacket for a di stanceof (A + I + B + C) inches from each cab le , makingsure t h ~ t the insulation is not damaged during theremoval operation. All traces of the semiconducting

    jacket must be removed by a nonconductive abrasiveor rasp.

    7. Remove the insulation from each conductor for adistance of (A + I) inches, making su re that theconducto r is no t nicked during the removal operation,

  • 7/30/2019 AECH Chapter 11

    19/28

    installation practices

    Assembly of Tee Splice and Tap Devices

    : :Straight Line SpliceDisconnectible Straight Line Splice

    LoadbreakElbowConnectors

    "'.

    Modular CableTerminator

    Fig. 11-26. Some typical primary voltage premolded splicing and terminating devices.11-19

  • 7/30/2019 AECH Chapter 11

    20/28

    covered and insulated aluminum wire and cableSplicing*-15kV-25kV-35kV Primary Cables-Hand Taped SpliceSingle conductor with concentriC neutral, straight splice (conventional or crosslinked polyethylene insulated, solid or stranded) for grounded neutral service.

    Concentric WiresTwiSled & Splicedin ConnectorOne H,lflapped Laye, Friction Tape Halflapped layerSemlConducting SelfFusing Tape Self-Vulcanizing TapeOne Halflapped layer 10 "K" Thickn. ..Tinned Copper Mesh Braid

    Two Half-Lapped layersSelf-Fusing A = OneHalf Connector lengthRubber-Like TapeFig. 1127. Details ofa taped primary cable joint.

    Penciling tools will remove the insulation, as well asprovide smooth penciled surface.8. Apply the required compression connector on eachcable, following the connector manufacturer's recommended procedure. Note: It is recommended thata smooth surface type connector be used--not anindented type. I f an indented type is used, fill theindents with a pliable insulation putty.9. Remove all sharp edges from compressed connector,using a file Or heavy abrasive cloth.

    10. Pencil the ends of the polyethylene insulation for adistance of (B) inches. Be sure not to cut into theinsulation or damage the conductor during the penciling procedure. Buff the insulation pencils if theyare not smooth with a nonconductive abrasive orrasp. This step would be completed with a pencilingtool. (See Step 7 above.)II. Clean all exposed surfaces with a nontoxic andnonflammable solvent and allow to dry. Care mustbe taken in wiping the black conductingjackets, sincethis may smear over the insulation surface.

    12. Apply one half-lapped layer of semiconducting tap(Bishop Tape No. 17 or equivalent) over the exposeconductor and connector. Tape should just contacthe edge of the cable insulation and be applied witenough tension to conform to the connector.13. Apply half.lapped layer of high voltage, selffusintape with manufacturer's recommended tensionstarting at connector centerline and building up tthe level of !be connector in areas between insulatiopencil and connector by evenly wrapping tape bacand forth across the connector. Apply splice tapbuildup to a thickness of "K" inches over th

    connector and for a longitudinal distance of "Dinches, tapering at the ends.14. Apply one hulf-Iapped layer of selffusing semiconducting tape over insulating tape buildup, extendinI inch beyond insulating tape onto !be semiconductinjacket on each side of splice. The semiconductintape should be applied with adequate tension.15. Apply one half-lapped layer of tinned copper mesbraid over the semiconducting tape and extend I incat each end of splice. The tinned copper mesh brai

    11-20

  • 7/30/2019 AECH Chapter 11

    21/28

    Insulating TopeFflction TapeRain Shield

    r - , . h ~ / . b j : ; ; ; ; ; ; ; ; : - - I n s u l a l i n g TopeMelol Grounding Strap

    installation practicesshould be wrapped as tight as possible, and tapingshould be started at the centerline of tbe splice, usingtwo portions of tinned copper mesh braid.

    16. Apply two solder lines 180 degrees apart for the fulllength of the mesh braid, making sure that the heatdoes not remian in one spot too long to damage thecable insulation or tapes.17. Tie the concentric outer wires in place using wrapsof No. 14 AW G tinned or bare copper wire and tacksolder in place.18. Apply two half-lapped layers of a self-fusing highvoltage tape OVer the outer braid with minimumtension.19. Apply one half-lapped layer of jacket tape over tbemesb braid to the edge of the concentric wires ateach end of the splice.20. Twist the concentric wires together and cut off excesslength. Place the formed wires into the proper sizedmechanical (or compression) connector and splice inplace to form low resistance joint, following the

    connector manufacturer's recommended procedure.

    oInsuloling Tope - - I O ! ' ~ "

    Conduclor - -+. .0

    Coble Insulo'lion - - 1 ~

    Insuloling TopeFriclion Tope

    Rain S ~ i e l d

    Bios-CuiInsuloting TopeMesh Shielding Braid

    Friction Tope1t1,--Stress-Re ie , Cone

    Coble Shielding Tope --Hi:!c1--\J

    Jacket

    A. Single conductor outdoor termination

    Terminal Lug

    Mesh Shielding Braid

    + - - - - J a c k e l

    B. 3-Conductor outdoor termination

    Terminating DetailThe construction details of secondary or primary cableterminations depend on whether the termination is outdoor, indoor. or from underground and wbether it ishorizontal for connection to an equipment terminal or vertical for connection to another conductor. Trifurcatingassemblies are also used for terminating a three-conductorcable so the urunsulated terminals are well separated (Fig.11-28).Terminations usually are either of the pothead type orthe built-up stress-relief type. Both types provide extrainsulation close to the actual termination of the conductorto provide protection against the extra voltage at theselocations.Primarily. potheads of plastic insulating materials areused with primary and secondary URD systems, altboughporcelain potheads and semi-assembled. built-ut, s',essrelief cones (or kits that facilitate tbeir qllick assemt:) _.estill used for this application. (Fig. ll-16)Stress-relief cones are also required in cable splices

    Terminal Lugo oIlir":--Conductor

    It-lt.-Insula;;ngTope

    Fig. 11-28. Typical terminations S-lSkV.11-21

  • 7/30/2019 AECH Chapter 11

    22/28

    covered and insulated aluminum WIre and cablewhere there is a change of conductor size; the variation ofcurrent density in the adjacent conductors creates dielectricstress variations that occur when a cable is terminated.

    The detailed methods of terminating shielded and nonshielded cables closely resemble those used for splicing.except that the termination process requires the inclusionof a stress-relief cone or a pothead, and if the installationis outdoor and vertical the addition of a rain shield to shedwater from the cable insulation is customary. Descriptivedetails are supplied by cable and accessory manufacturerswith dimensions for various sizes and voltages. The accompanying illustrations list the successive operations. Theprecautionary recommendations mentioned in relation tocable splicing also apply to terminating procedure, subject

    1. TERMINAL CONNECTORThe universal rod connector attaches to thepower source.

    2. MOLDED RUBBER CAPPresses over top of tenninator with an interference fit to provide complete wstersealtegrity.

    3, RETAINING WASHERMechanically prevents any cable slippage withinterminator.4. TERMINATOR HOUSINGMolded of special EPDM compounds lor functional reliability and long life. Actual creepdistance is 18" (45,7 em).5. CABLE INSULATIONPrimary insulation is provided since cableinsulation carries through the terminator.6. INTERFERENCE FITMolded insulating EPDM exerts unffonn concentric pressure on insulation of cable toprovide required creeppatl1 length and waterseat7. MOLDED STRESS RELIEFFactory-tested molded stress relief assuresproper stress relief for terminating cable. Apatented Elastimold feature.8. GROUND STRAP

    Provides a convenient point to connet a groundwire to the molded conductive shield andplaces the molded shield at ground potential.Courtesy Amerace Corp., Elastimold Div,

    to such changes as appear in manufacturer's instructionamanuals.The cross-section of a molded terminal connector ishown in Fig. 11-29, illustrating the component part ofconnector designed for conductors up to 25 kV. I t isuitable for uSe on solid dielectric cables and can bapplied directly on cables with extruded semi-conductivshields including full neutral concentric. I t will accommodate aluminum conductors in the range of No, 6 t410 AWG with an insulation thickness of 0,495 to 1.115"Mter proper cable preparation, the terminal connectois slid down over the bared cable insulation until ibottoms On the cable shield. No special tools or pottincompounds are required for the assembly of this type ofitting.

    Fig. 11-29. Typical single conductor molded pothead for cable termination.11-22

  • 7/30/2019 AECH Chapter 11

    23/28

    Installing Aerial Insulated CablesSingle insulated or covered overhead primary aluminumconductors suspended from insulators sometimes are usedin tree areas or similar locations. Their installation is similar to that of bare conductors, as described in Chapter 5.The span lengths usually are moderate so that sag andtension values generally are obtained from tables. However, for unusual spans, sag-tension charts can be com

    puted or are available from conductor suppliers. Foraluminum 1350 conductors or less than hard tempers,adjustment must be made for reduction of strength.For economic reasons, however, most overhead spansof insulated power conductors are in the form of preassembled or field-assembled multi-conductor cables suspended from a bare messenger. Insulator support is notrequired and space is saved by using a single-multi-conductor cable. The conductors may be spiraled around themessenger or arranged paraliel to it, as described 10Chapter 7. Messenger supported cables are in two groups:Preassembled aerial cables (to 35 kV)Aerial cable assemblies (0 to 600 volts).

    Primary Aerial CablesThe messenger size for primary cables is determined bythe required strength, except that for single-phase primary circuits (No. 2 AWG or smaller) where the messenger also serves as a neutral conductor, the conductanceof the messenger must equal that of the insulated conductor. Bare messengers not used as neutral conductorsare often used also as a part of relaying circuits, as a partof the grounding circuit for the insulation shielding, andas an auxiliary to a common-neutral. For these reasons

    specifications for multi-conductor primary cables with baremessengers usually specify the ohmic resistance of themessenger. The combination of strength and moderateelectrical resistance requirements of such non-neutral messengers has led to wide acceptance of composites ofaluminum and of steel (Alumoweld) for the make-up ofthe messenger.Messenger sizes are such that the normal initial saggingtension at 60'F will not exceed 30% of its rated strength,and its maximum tension will not exceed 50% of its ratedstrength at the fully loaded condition. Physical details ofthe cables used for the messengers listed in Tables 11-10and II-II can be found in Tables 4-5 (1350-Hl9). 4-12(6201-T81) and 4-14 (ACSR). These messenger sizesconform to the ICBA recommendation that the initial sag

    be such that the final sag be not less than 1.667% of thespan length.Stringing sag and tension charts are supplied by cablemanufacturers as an aid to circuit design for light. medium,or heavy loading conditions (NESC, see Table 5-1) foruse as described in Chapter 5. However, in most instancesthe spans are of moderate length so suitable sag-tensionvalues may be obtained directly or interpolated from manu

    installation practicesfaeturer-supplied tables that Jist initial and final valuesfor 100, 125, and 150 ft spans.

    For the installer of the cable the most useful tabularvalues are those for initial sag and tension, usually for60F. but a correction factor is applied if the installationtemperature differs from 60'F. The final sag and tensionvalues for the various NESC loading districts then willmeet requirements as to the percent that messenger tensionbears to its ultimate breaking strength, and the manufacturer's table will confirm this if required. The messengersfor preassembled primary cables are not neutral conductors, but high conductance is useful for grounding or signalpurposes, hence the equivalent conductor rating is usuallylisted for the messenger. For this reason various combinations of steel, 1350 aluminum, and high-strength alloyaluminum are often used for primary aerial messengers.

    Table 11-10 is extracted from more complete tables inorder to show the form in which such tables are supplied.Although this table shows use of a combination messengermade of 1350 aluminum strands assembled with strands ofaluminum-clad steel, other messengers are similarly usedof high strength ACSR, as well as combinations of 6201aluminum with steel reinforcement (AACSR).

    Fig. 11-30 depicts several kinds of fittings and accessories used when installing messengers and preassembledaerial cables, some of which also apply to preassembledsecondary and service-drop cables.

    Neutral-Supported Secondaryand Service-Drop Cables

    Preassembled aluminum insulated multi-conductorcables supported by bare neutral messenger conductorshave practically become standard for secondary aerial circuits and service drops. Subject to the NEC limitation of300 volts to ground for bare neutrals, the triplex form(two insulated conductors preassembled with a bare neutral) supplies the usual single-phase three-wire circuits.Similar quadruplex cables (three insulated conductors) ifconneeted to a three-phase Y source supplies low-voltagethree-phase loads.The neutral messengers of such cables are selected onbasis of strength and conductivity; either with conductivity equal to that ofa phase conductoror as a "reduced"neutral having conductivity not less than one-half that of

    a phase conductor, depending on service requirements.Tables in Chapter 4 show, as mentioned above, dataregarding bare neutral messengers for such cables. Chapte r 10 describes various types of cables. Fig. 11-31 depictsinstallation details for usual conditions of installation ofthe secondary cable and the service-drop taps extendingfrom it. Initial sag-and-tension data for preassembledtriplex aluminum cables with full- and reduced-size neutrals are in Table 11-11 for the various NESC loadingsfor 125 ft spans.

    11-23

  • 7/30/2019 AECH Chapter 11

    24/28

    3 Bolt Guy Clamp

    2 Bott Uni"rsal GUY CHp

    Split Bolt Connector

    covered and insulated aluminum wire and cable

    :3 Bolt GUY Clamp

    Oval Eye Bolt

    Vise Type Connectors:

    The notation on Table 1I-1I with regard to initial sagvalues for other spans than 125 ft is based on Eq. 5-2,but it is only approximate; hence it is available to obtaincorrect values from the cable manufacturer.The sag-tension values of Table 11-11 are for initial unloaded conditions at 60'F. The sag eventually will increase to the final value and the tension correspondingly

    will decrease as a result of long-time creep. When fullyloaded according to NESC values the sag and tension bothwill increase, and as temperature drops to OCF underHeavy-Loading conditions the sag decreases and tension

    F

    2 Bolt Universal GUY Clip

    B

    E

    Strand Connector

    i n c r e a s e ~ . Thus. for 2/0-2/0 cable with aluminum-alloy6201 me. ,:nger, the initial stringing sag-tension of 13 in. -865 Ib becomes 24 in.-1955 Ib (see Chapter 5) .The sag-tension values under conditions of maximumNESC loading are useful for circuit design because theyindicate minimum clearances under the cable, and alsoverify that there is the specified margin between actual

    tension and the rated breaking strength of the messenger.However, tables .imilar to Table H-ll for initial stringingconditions are u s ~ d as a basis for installation, which isthe subject considered in this chapter.

    oc

    Fig. 11-30. Typical details for supporting and dead-ending cables, messengers, and guy wires on poles.11-24

  • 7/30/2019 AECH Chapter 11

    25/28

    installation praclices

    APrelcftl'lel!

    .A !: ""V. ' vv"

    Insulated Clev!s

    ToPIt

    oDe

  • 7/30/2019 AECH Chapter 11

    26/28

    covered and insulated aluminum wire and cable

    TABLE 11-10Representative Values extracted from Tables Supplied byCable Manufacturer for Initial Sag-and-Tension Values at

    60'F, suitable for Light or Heavy NESC District>For Preassembled Primary AerialSI/C Cables with AWAC Messenger

    Conductor I Cal>l. Span Length in FeetI IizeAWG orKcmi!

    !

    I;

    MesseIize

    ngerRated

    Strength: Assembly (2)

    Diam.in.

    Weight 100 125 : 150Ibl t t ! Sa!tinches (3)

    100 i 125 I 150Tensionlb (11

    5000 Volt Unshielded (Class B concentric stranded aluminum, cross-linked polyethylene insulation)6 #3-3/41

    2/0 "4/0 "350500 #32/5750 #2215

    1000 # 1/0-2/5

    UbI7700

    113001350019500

    ;1.251: 0.421 ! 191.5751.7702.0072.3742.6933.2153.695

    0.645 I"0.8271.100 191.6002.1583.076 "4.053 "

    23"23

    ""

    28 337 428 509516 78055" 662 840 1000

    27 1118 1364801280 1626 1983

    2193726 26752461 i 3126 38133242 I 4119 5024

    15.()(J(} Volt Shielded, Grounded Neutral (Class B concentric stranded aluminum; semi-con tape;strand shield; 0.175 in. XLPE insulation; extruded semicon PE, No. 22 AWG copperconcentric; Mylar tape; PVC jacket)

    2 #3-3/4110 "4/0 #32/5350 #1/0-215500 "750 556,50()j30!7)

    1000

    7700

    113001950026900

    2.459' 1.379 192.618 1.6063.006 2.215 "3.504 3.0753.789 3.696 ."4.575 5,039 "5_079 6.390 "

    23 2728"272831

    1122 11418 17391306 1645 20241801 2269 26792500 3151 37203005 3787 46594032 5040 . 60485031 J 4 ( ) ( ) ~

    1. Initial tension lS such that the final temiion will not exceed 25 percent of rated strength at 60F forlight or Heavy NESC loading districts.

    2. Includes weight of messenger and binder tape.3. Initial sag is such that final sag approximately conforms to ICEA recommendation of 1.667 percent of span

    length.

    11-26

  • 7/30/2019 AECH Chapter 11

    27/28

    instollation practicesTABLE 11-11

    Typical Initial Stringing Sag and Tension Values for Three-Conductor Sell-Supported Polyethylene Service-Drop and

    Secondary Cable (Triplexl, lor 125 f t span at 60F lo r Various NESC Loading Districts (see Table 5-1'*

    For roughly approximate value. for spans of 100 ft and 150 ft , multiply the initial sag values for 125 ft span by 0.64 for l00.ftspan and by 1.45 for 150-ft span, retaining the initial tension values for 125 ft span. These approximations are less accurate forthe Heavy Loading District. More accu rate values for spans other than for 125 ft, are obtainable from cable manufacturer.;.

    I NeutralMessenger I NESCLight-Loading

    N:i:SCMedium-Loading

    NESCHeavy-loading

    Con- I Oistrict District Districtductor Size Rated

    Size AWG Initial Inital Initial Initial Initial Initialtrellgth rAWG (or EquivJ Ib Sag Tension Sag Tension Sag TensionALUMINUM ALLOY 6201 NEUTRAL MESSENGER

    421/02/0

    42

    I/O2/0

    1760280044605390

    8888

    467750

    11951415

    10108

    10

    410680

    10601255

    16121 I

    13

    250553875865

    ACSR NEUTRAL MESSENGER6 1190 10 290 10 3054 1860 10 445 8 4152 2 11 575850 10 6604380/O/0 10 1005 12 8652/0 5310/0 10 1255 12 1070

    REDUCED ACSR NEUTRAL MESSENGER12 350

    24 6 1190 12 295

    4 13 445 13 435110 2

    18602850 13 670 14 600

    2/0 3550 13 835 16 730I IALUMINUM NEUTRAL MESSENGER (Aluminum 1350)

    54 4419 19519 29523 410

    6 6 5604 4 8812 2 13501/0 110 1990

    26 9119 19517 38519 485

    29 9811 3751 I 60012 84013 975

    34171314

    104724940

    105330655755

    2353

    115230

    .,. These jnitial sag-tension values are based on NESC loading limits for REA systems; that is, loaded tension is not to exceed 500/0 of messenger ratedstrength; final stringing tension is not to exceed 25%1 Of rated strength: and initial stringing tension is not to exceed 3 3 ~ 1 ! 3 % Of rated strength.

    11-27

  • 7/30/2019 AECH Chapter 11

    28/28