Agenda. Introductions. Morning: Proposals (5). lunch. Afternoon: proposals (4). Discussion/wrap-up. HiRadMat - Status. Adrian Fabich HiRadMat Scientific Board CERN , 14th March 2014. Overview. Report from HiRadMat experiments in 2012 Shut-down work Summary of 2014 proposals. - PowerPoint PPT PresentationTRANSCRIPT
A. Fabich 1
Agenda
14/3/2014
Introductions
Morning: Proposals (5)
Afternoon: proposals (4)
lunch
Discussion/wrap-up
A. Fabich 3
Overview
• Report from HiRadMat experiments in 2012
• Shut-down work
• Summary of 2014 proposals
14/3/2014
A. Fabich 4
2012 experiments
• 9 experiments completed• On average 4 weeks between 2 experiment– Partially grouped
14/3/2014
A. Fabich 5
2012 - Protons to HiRadMat
• Total: 1.4*1016 protons• About 48 hours of SPS cycling for HiRadMat
– Preparation, waiting and extractions– Similar time span in 2011 for commissioning
14/3/2014
A. Fabich 6
Experiments in 2012
• RIB target R&D • LHC transfer collimator (2x)• BLM validation• RP benchmarking• Crystal collimation
PhDs completed:Juan Blanco, Nov. 2013
Nikos Charitonidis, March 201403/04/2013
Beam tunneling(HRMT12)
TE/MPER. Schmidt et al.
Powder target(HRMT10)C. Densham et al.
A. Fabich 8
Shut-down work
• Installation of additional cabling– Mainly for vacuum and HQ signal
• Removal of experiments from – Remainders in TNC:
• LPROT (HRMT12): follow-up required• TISD (HRMT01): removal delayed by availability of class-A lab• TPSG4 (HRMT06) on target location: removal in April 2014
• Removal of WNAF collimator blocks– Minimum advancement– lengthy preparations for and discussions with authorities
14/3/2014
A. Fabich 9
Proposals
• 12 applications– Named 14xx (year 2014 + running number)– Running number in the order of reception
• 9 invited for presentation/discussion
• 3 proposals to be discussed “offline”“placing them on the radar screen”– TPGS4 (1402): repetition with slightly higher intensity– Supra Magnet (1406): later availability– Microphone (1411): purely parasitic
14/3/2014
A. Fabich 11
Time frame
• One experiment interested in ion operation• Half the user groups are interested in TA (Transnational Access)
14/3/2014
A. Fabich 12
Aim of Today
Review the proposals• Primarily based on the scientific value
But also • in view of schedule• Technical feasibility– Note: 3e13 p/pulse is the limit until spring 2015– at a later stage might reach 5e13 p/pulse
Follow-up: Written report on the view by the Board14/3/2014