agile conference2010 upstream-kanban_at_ctct
DESCRIPTION
Transformation of the Website Team at Constant Contact through the use of KanbanTRANSCRIPT
![Page 1: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/1.jpg)
Upstream KanbanProcess Evolution in the Constant Contact Website Team
Rick Simmons – Mike Fitterman
This work is licensed under the Creative Commons Attribution-NonCommercial-ShareAlike 3.0 Unported License.
![Page 2: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/2.jpg)
Mike
Engineering Mgr, Web Team
20 years in dev leadership Tried many processes: “All can
work” Interested in process beyond
utilization and deadlines
[email protected] @cutshot
Rick
Director, Agile Practices
22 years in dev/ops leadership Tried many processes: “Some
work better than others” Interested in change and
maturity at organizationlevel
[email protected] @simmons3k
Now Directorof Engineering
Now Agile Coach
![Page 3: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/3.jpg)
![Page 4: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/4.jpg)
Kanban:quantitative
workflow management
Kanban flow
Your roles, competencies,
processes,etc.
R
![Page 5: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/5.jpg)
Map the “value stream”
Put it on the wall
Pick some WIP limits
Pull work through
Measure
Watch, tackle, improve
How do you Kanban?
Cycle Time
5 2 2 4
R
![Page 6: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/6.jpg)
• Convert visitors to trialers
Constant Contact Website:
Login portal
R
![Page 7: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/7.jpg)
EngineeringProduct Strategy
Organization Before
PRODUCT DELIVERY
Product Mgt Dev Ops
Design
190 ppl
Web
team: 15
R
![Page 8: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/8.jpg)
Upstream?
Web Team:
Service
Organization
StakeholdersMarketing
R
![Page 9: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/9.jpg)
Milestones
6/09 4/1011/09
Launch
Policies
Team reorganization
Metrics
Upstream board
Upstream WIP limits
R
![Page 10: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/10.jpg)
Team Makeup and Process, 2009
Engineering4 Java/J2EE Developers+ Manager
Design4 Design/Web Developers+ Manager
SharedPOs, QA
Scrum• Weekly Releases• HTML/JSP/CSS only changes• 1 ½ days testing to ship
• Monthly Releases• Delivered “hard” changes – Java code, integrations, etc.• Week-long Regression to ship
6/09 4/1011/09
Launch
M
![Page 11: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/11.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change
from retros
Reputation for slow delivery
Redundancy
ChallengesM
![Page 12: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/12.jpg)
Initial Goals
Smooth out delivery flow
Function as one team
Gain back some time
Iterate fast and make change as we go
• Have teams work together• Release more things more often
• Eliminate Developer and QA problems from 2 teams working on code base• Coordinated planning meetings
• Eliminate PO/Scrum Master/QA time split• Shorter planning meetings, but more often
M
![Page 13: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/13.jpg)
First Board
Swim lanes WIP limits Verify col.
R
![Page 14: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/14.jpg)
Week 2: overloaded, hidden work
Verify column over limit
Blocked Items
Work not on board
R
![Page 15: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/15.jpg)
Week 4: Board mods and policies
6/09 4/1011/09
Policies
Wait states Less columns Team adding policies
R
![Page 16: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/16.jpg)
Policies on wiki page…
…but no one ever went there
:(
Eventually we put them on the board
M
![Page 17: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/17.jpg)
Week 5: Broke down code queue
Items Tasks
M
![Page 18: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/18.jpg)
A few days later….
Deploy states
No work not on board
M
![Page 19: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/19.jpg)
Engineering
Product Strategy
Marketing
Large-scale Reorganization
“Kaikaku”
R
![Page 20: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/20.jpg)
EngineeringProduct Strategy
Before re-org
Rest of org
Marketing
Web Design Web Eng
PO PO
PM
R
![Page 21: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/21.jpg)
Product Strategy
Web Team
After re-org
Rest of org
Marketing
Delivery team
Engineering
Engineering
Design
K
a
n
b
a
n
GM
POs
R
![Page 22: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/22.jpg)
Strategy aligned with Execution
Eliminated redundant functions
Made team made self sufficient
– Approve own work, remove wait states
Reorganization
6/09 4/1011/09
Team reorganization
R
![Page 23: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/23.jpg)
2 teams, 1 board: single flowM
![Page 24: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/24.jpg)
Month 5: Metrics & Mike’s lesson
■ Ability to watch and tune
■ From intuition to quantitative management
6/09 4/1011/09
Metrics
M
![Page 25: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/25.jpg)
What the metrics showed
■ QA is many times overloaded
■ Needed to get them below their limits
■ Worked on “constant” delivery
■ Delivering late causes overload and quality problems
M
![Page 26: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/26.jpg)
How We Smoothed Out Flow
Work on separate dev branches
Test in parallel on other QA Environments
Earlier testing, less work at end
More policies
Automation/unit testing; add known bugs to tests
Increase functional testing; added Cubic Test
Unit Testingto constant
improvement
Metrics are the KEY
M
![Page 27: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/27.jpg)
6 Months
Explicit policies, but no WIP limit
New Class of Service: Bugs & “Footprints”
M
![Page 28: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/28.jpg)
Visibility up 200%, extends up to GM
Eliminated redundant Excel data
Collaborative prioritization
Upstream board to marketing
6/09 4/1011/09
Upstream Board
PO’sidea!
M
![Page 29: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/29.jpg)
9 Months: Too much stuff
Downstream capacity:5 to 7 items per week
4X capacity upstream…Need to limit upstream WIP
M
![Page 30: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/30.jpg)
10 Months: WIP Limits on PO BoardCurrent Board
6/09 4/1011/09
Upstream WIPLs
Old Board
M
![Page 31: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/31.jpg)
Month 10: Single queue
Produce
Todo
Item and task type by color
WIPL = 6 full items
Bugs & Footprints on board
Visible policies
M
![Page 32: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/32.jpg)
Improvement just from the visualizing flow
Manager is responsible to make improvement happen
– Not the Team, although they are empowered to
Change should be based on metrics
Value in measuring change
– Know that it was a “good change”
– Show effectiveness to team
– Show improvement to organization
Kanban… “It’s really aboutmanagement” –Mike
M
![Page 33: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/33.jpg)
“It’s really about
improvement”
–Rick
Kanban…R
![Page 34: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/34.jpg)
Business Value Metrics (Sticky Color)
Managers care about bugs
PO/PMs care about where time is going overall
M
![Page 35: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/35.jpg)
Throughput metrics
Possible inverse correlation between items and bugs?
M
![Page 36: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/36.jpg)
Cycle TimesClass of Service
SLA to Production
Footprint 7 Calendar Days
Bug 12 Calendar Days
Small 15 Calendar Days
Medium 56 Calendar Days
Large Class of Service: unpredictable… eliminated
Cycle Time is an SLA is for the Product Mgt Team
Will extend to “Lead Time”, a Stakeholder SLA
M
![Page 37: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/37.jpg)
11 Items
Interim Adjustment Example - CFD
8 Items
Bugs increased after an increase in WIP
M
![Page 38: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/38.jpg)
Control Chart - Smalls
This is perfect!
Just what we would expect… very predictable
M
![Page 39: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/39.jpg)
Control Chart - Mediums
Just enough to start being significant
Erratic scatter – more likely to miss SLA
Experimenting with breaking Mediums into Smalls
M
![Page 40: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/40.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change from
retros
Reputation for slow deliveryRedundancy
Challenges -> benefits
Replaced with design & code
reviews, JIT tasking
Meeting waste reduced by 51
person-hrs
Kaizen has
taken root
in the
whole team
M
![Page 41: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/41.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change from
retros
Reputation for slow deliveryRedundancy
Challenges -> benefits
Design: less wait statesEngineering: 4X pace of delivery
Increased pace of delivery for
both teams
Collaboration
is way up
M
![Page 42: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/42.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change from
retros
Reputation for slow deliveryRedundancy
Challenges -> benefits
WIPLs transformed upstream prioritizing
& approval cycles
Collapsed redundant
marketing functions
M
![Page 43: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/43.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change from
retros
Reputation for slow deliveryRedundancy
Challenges -> benefits
• Goal team with realmetrics
• See issues as they happen rather than long after
• Understand why they happened rather than intuit it
Reputation transformed
Managing by metrics
M
![Page 44: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/44.jpg)
Organizational Change andRick’s lesson…
Value from small change
influences big change
R
![Page 45: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/45.jpg)
EngineeringProduct Strategy
PRODUCT DELIVERY
Product Mgt Dev Ops
Organization After Rest of org
3 teams trying
5 teams thinking
5 teams LIVE
R
![Page 46: Agile conference2010 upstream-kanban_at_ctct](https://reader033.vdocument.in/reader033/viewer/2022052911/559e33761a28abe25d8b45d8/html5/thumbnails/46.jpg)
Silo development
Disjoint cycles
Split QAlower quality
Upstream dependencies
Plan/retro time12-24 hr/mo per
member
Small change from
retros
Reputation for slow deliveryRedundancy
The best thing about success… influencing change
Thanks for coming!