ahcal mechanics and test beam setups

21
AHCAL Mechanics and test beam setups status report Karsten Gadow AHCAL Main Meeting DESY, 09.12.2013

Upload: palmer-graves

Post on 03-Jan-2016

54 views

Category:

Documents


0 download

DESCRIPTION

AHCAL Mechanics and test beam setups. status report. Karsten Gadow AHCAL Main Meeting DESY, 09.12.2013. Outline AHCAL Status Report Mechanics and test beam setups. DESY II test beam setup PS/SPS AHCAL test beam setup PS/SPS AHCAL Tungsten test beam setup AHCAL cabling and cooling setup - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: AHCAL Mechanics and test beam setups

AHCALMechanics and test beam setups

status report

Karsten GadowAHCAL Main MeetingDESY, 09.12.2013

Page 2: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 2

Outline AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 3: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 3

AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 4: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 4

AHCAL DESY II test beam setup

15 pieces 1xHBU housings are produced at DESY

15 HBU´s with CIB´s has to be mounted and commissioned

all 15 layers will be tested with air stack

Page 5: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 5

AHCAL DESY II test beam setup

DESYII TB22

1 t Stage

Air Stack

Absorber stack with 5 layers

Page 6: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 6

Task list (Summary):

> Test beam setup position inside the TB 22 allows parasitic measurements up to KW10 2014

test beam schedule fixed KW1+2 2014

supply and read out hardware ongoing

15 layer absorber structure installed

1 t DESY II Stage installed

15 layer air stack ready

>Detector layer production production of 15 pieces 1xHBU housings ready

production of 15 HBU´s and install tiles 6 done

commission and beam test in air ongoing

AHCAL DESY II test beam setup

Page 7: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 7

AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 8: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 8

AHCALPS/SPS AHCAL test beam setup

Movable Stage with 2 x absorber stack

Air stack

2 x absorber stack stand alone

Tungsten setup layers

Movable stage with 1 x absorber stack

Page 9: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 9

Task list (Summary):

> Test beam setup position inside PS/SPS ?

test beam schedule ?

supply, read out and cooling scheme ongoing

install absorber structure self standing or with Movable Stage ?

install new GUI for Movable Stage controlongoing

>Detector layer production production of 2 x 50 x 2xHBU-extended housings (MPI) ongoing

production of 2 x 48 x 2 HBU´s and install tiles ?

production of 10 x HBU dummy's ?

commission and test ?

AHCALPS/SPS AHCAL test beam setup

Page 10: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 10

AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 11: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 11

AHCALPS/SPS AHCAL Tungsten test beam setup

aluminum frame with 2 x 1 mm FR4 cover to center the housing

tungsten area

Al frame parts produced at MPI

Page 12: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 12

AHCALPS/SPS AHCAL Tungsten test beam setup

housing with SIB

housing with CIB

SIB

CIB

production of 0,5 mm thin stainless steel housings by MPI

Page 13: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 13

AHCALPS/SPS AHCAL Tungsten test beam setup

special configuration with extender board

4 HBU´s per layer

Page 14: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 14

AHCALPS/SPS AHCAL Tungsten test beam setup

50 frames

frame with housings

closed housings

removed cover plate

Page 15: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 15

AHCALPS/SPS AHCAL Tungsten test beam setup

40 tungsten absorber plates are installed

Install Tail catcher ?

Tail Catcher Instrumentation?

add 8 tungsten absorber plates ?

Page 16: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 16

AHCALPS/SPS AHCAL Tungsten test beam setup

Modification of the tungsten absorber structure ?

Page 17: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 17

Task list (Summary):

> Test beam setup configuration 48 layers ?

test beam schedule ?

supply, read out and cooling preparation ongoing

modify tungsten absorber structure ?

Tail Catcher installation ?

>Detector layer production production of 50 frame parts (MPI) and mounting with facing (DESY) ready

production of 2 x 50 x 2xHBU-extended housings (MPI) ongoing

production of 2 x 48 x 2 HBU´s and install tiles ?

commission and test ?

AHCALPS/SPS AHCAL Tungsten test beam setup

Page 18: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 18

AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 19: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 19

AHCAL cabling and cooling setup

power distribution

Power cabling for 1 x submodul

LDA

Page 20: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 20

AHCAL Status Report Mechanics and test beam setups

1. DESY II test beam setup

2. PS/SPS AHCAL test beam setup

3. PS/SPS AHCAL Tungsten test beam setup

4. AHCAL cabling and cooling setup

5. AHCAL absorber structure modification (earth quake)

Page 21: AHCAL Mechanics and test beam setups

Karsten Gadow | AHCAL main meeting | 09.12.2013 | Page 21

AHCALabsorber structure modification (earth quake)

Simulation for AHCAL barrel and end cap structure must be done soon!

ILD workshop, Cracow, 24-26 September 2013