Air Pollution Control Source Testing. Source Testing (Stack Sampling). why? methods of determining ER source testing sampling train process of sampling (PM) location of sampler, probe calculating ER is it isokinetic?. Why Sample Stack?. need ER. Methods of Determining ER. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Air Pollution Control Source Testing

Air Pollution ControlSource Testing

Page 2: Air Pollution Control Source Testing

Source Testing (Stack Sampling)

• why?

• methods of determining ER

• source testing– sampling train– process of sampling (PM)

• location of sampler, probe• calculating ER• is it isokinetic?

Page 3: Air Pollution Control Source Testing

Why Sample Stack?

• need ER

Page 4: Air Pollution Control Source Testing

Methods of Determining ER

1. Mass Balance/ Engineering Calculations• if (mass in) > (mass out)

then mass loss → • evaporation rate, chemical kinetics

Page 5: Air Pollution Control Source Testing
Page 6: Air Pollution Control Source Testing

Methods of Determining ER

2. Emission Factors (in kg/Mg lime produced)

Page 7: Air Pollution Control Source Testing

Methods of Determining ER

3. Source Testing– quantify process η – C of A– test APCD– calibrate CEM

• Ontario Source Testing Code• MOE Procedure A-1-1

Page 8: Air Pollution Control Source Testing

Source Testing (PM)

• sampling train

Page 9: Air Pollution Control Source Testing

Source Testing (PM)

Page 10: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process

3. visit the site

4. preliminary test

5. source sampling

6. analysis, result

Page 11: Air Pollution Control Source Testing

Process of Sampling

1. define the problem– what to sample?– why?

2. understand the process

3. visit the site

4. preliminary test

5. source sampling

6. analysis, result

Page 12: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process– feed rate, production rate, APC– T. RH, estimate of PM conc., loading, gas

composition

3. visit the site

4. preliminary test

5. source sampling

6. analysis, result

Page 13: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process

3. visit the site– accessibility, port location– services (power, water, lab.)

4. preliminary test

5. source sampling

6. analysis, result

Page 14: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process

3. visit the site

4. preliminary test– gas velocity, temperature– gas composition, moisture content

5. source sampling

6. analysis, result

Page 15: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process

3. visit the site

4. preliminary test

5. source sampling– do sampling– lab analysis– check isokineticity

6. analysis, result

Page 16: Air Pollution Control Source Testing

Process of Sampling

1. define the problem

2. understand the process

3. visit the site

4. preliminary test

5. source sampling

6. analysis, result– calculate ER– report

Page 17: Air Pollution Control Source Testing

3. Visit Site

• port location– 8 dia. downstream, 2 dia. upstream of

disturbance

• probe location– 2 perpendicular traverses– divide cross section into equal areas– sample at “centre” of area– different charts for rectangular ducts

Page 18: Air Pollution Control Source Testing

Probe Location

Page 19: Air Pollution Control Source Testing

Probe Location

Page 20: Air Pollution Control Source Testing

• determine port height

• determine number and location of sampling points

Page 21: Air Pollution Control Source Testing

5. Source Sampling

Page 22: Air Pollution Control Source Testing
Page 23: Air Pollution Control Source Testing
Page 24: Air Pollution Control Source Testing
Page 25: Air Pollution Control Source Testing
Page 26: Air Pollution Control Source Testing

Problem

• calculate ERp , given:

Us(avg) = 40 ft/s

Vm(ref) = 1.40 m3

Mp = 17,200 mg

Ts(avg) = 386 K

Ww = 56.6 g

Ps = 101.5 kPa

stack dia. = 7.0 ft

Page 27: Air Pollution Control Source Testing

• check if sampling was isokinetic

Page 28: Air Pollution Control Source Testing
Page 29: Air Pollution Control Source Testing

Source Testing