alexis flooring method statement - rev 11.05
TRANSCRIPT
Method Statement
Work Activity: FLOOR PREPARATION & INSTALLATION OF FLOOR COVERINGS
Project: TBC Address TBC
Revision: 002
Project Description
Contract Period; July 2019 – September 2020
Communication; Senior Contracts Manager – TBA
Contracts Manager – TBA
Site Supervisor – TBA
Director of Sales – TBA
Travelling to work under Covid 19 conditions
• Where possible travel to site alone in your own vehicle. Avoid public transport if possible. • If transport has to be shared;
- Journeys should be shared with the same individuals and numbers minimised - Keep good ventilation (windows open) and face away from each other in the vehicle - Vehicle should be cleaned regularly with emphasis on areas touched
• Use alternative means of transport if possible – Cycling, walking etc.
TT.05.105.1 © Copyright 2011 4See Risk Management of 1 6
Method Statement
Coronavirus (Covid-19) – Site Rules
• In all scenarios, including queing, transiting around site and within offices, a two metre social distance rule must be adhered to
• 2 metre social distancing must also be maintained on entry to site as well as within all Welfare and Working areas
• Minimise the number of key personnel on site to avoid overcrowding work areas • All physical contact must be strictly avoided e.g. shaking of hands, high fives etc • Operatives to adhere to the site specific signage, traffic routes and site rules set out by
the Main Contractor • Alexis Supervisor to monitor compliance with the Safe System of Work (SSoW) and also
monitor compliance with social distancing control measures • Where social distancing cannot be complied with whilst undertaking specific task or
activity, the activity must be risk assessed and additional control measures deployed • On entering site for the day, NO RE-ENTRY will be permitted in the same day if an
operative leaves the site (1 day = 1 visit) • Material Hoists to be used for moving materials between floors with no personnel (except
the operator) to travel in the hoist • The canteen is limited to 1 person per 1 table, staggered break times will be advised
• ALEXIS FLOORING REQUEST THAT ALL OPERATIVES WEAR A SUITABLE FACE MASK WHEN NOT IN THEIR DESIGNATED WORK AREA
Site Specific Arrangements
Working hours: Monday to Friday – TBC Saturday – TBC
Induction carried out daily at TBC.
Site access and egress will be monitored and operatives temperature taken. ID must be shown
Site arrival and departure times will be staggered to avoid congestion.
2 metre social distancing must all be maintained on entry to site as well as within all Welfare and Working areas.
On entering site for the day, NO RE-ENTRY will be permitted in the same day if an operative leaves site (1 day = 1 visit).
Canteen eating times will also be staggered to avoid overcrowding.
Handwashing facilities are available at the Entrance/Exit to site and should be utilised by all operatives on entry/exit, ensuring hands are cleaned for a minimum of 20 seconds.
All operatives to complete a site induction prior to commencement on site. The induction will provide up to date information on the site procedures and H&S elements.
Access and Egress to site is through the Site Entrance. Operatives are required to enter through this entrance and will need to produce a name/number card as ID for the Telford Homes Gateman to sign you in.
Accessing work areas within different Blocks is via the Pedestrian walkway system put in place by (Developer). Access is as (Developer) (this is subject to change but regular updates will be
TT.05.105.1 © Copyright 2011 4See Risk Management of 2 6
Method Statement
Emergency Procedures
Should an accident, incident or near miss arise on site, it must be reported immediately to the Alexis flooring Supervisor and to the relevant site manager.
The accident will be recorded in the accident book located in the site office. A record will also be logged in the Alexis Flooring accident book kept at the office. HSE notification will be made as required.
First Aid facilities will be provided by site.
The site specific emergency procedures will be explained to all operatives at the site induction.
Daily updates will be communicated by Managers/Supervisors following updates from site
Covid 19 Procedures if someone falls ill on site
Any operative who either has a high temperature or a new persistent cough at work should: • Ensure their manager or supervisor is informed • Return home immediately • Avoid touching anything • Cough or sneeze into a tissue and put into a bin, or if they do not have tissues, cough and
sneeze into the crook of their elbow • They must then follow Government guidelines on self-isolation and not return to work
until their period of self-isolation has been completed
Significant Risks Coronavirus (Covid 19)
TT.05.105.1 © Copyright 2011 4See Risk Management of 3 6
Method Statement
Hazardous Materials Dust Sharp Objects Power Tools Live Services Lighting Levels Access/Egress Manual Handling Moving Plant
PPE
Type Mandatory Task Specific Safety Helmet √ High Visibility Vest √ Safety Boots √
Safety Glasses √ Gloves √
Dust Mask (FFP3) √ Ear Defenders √
TT.05.105.1 © Copyright 2011 4See Risk Management of 4 6
Method Statement
Method of Work
Prior to work Commencing;
1. Operatives will arrive to site and sign in at the gatehouse. 2. Operatives will receive a site induction at 8.15a.m. in the Induction Room. 3. Following Induction finger print recognition will be set up at the gate house allowing
access and egress to site via the turnstiles. New temporary entry systems will be in place during Social distancing procedures.
4. Operatives will adhere to the three-point PPE site rules that are in place.
The Working Process;
1. The Supervisor will assess the Plot to ensure it is clear and all works have been completed by other trades to allow flooring works to commence.
2. Barriers/Signage will be erected to minimise access to the work area. 3. Other trades will be restricted from the work area. 4. Uzin PE360 penetrating primer will be applied to the subfloor using a long pile roller.
This will achieve a key for the smoothing compound. 5. Uzin NC105 Smoothing Compound will be mixed in a bucket. The smoothing
compound will then be applied to the primed subbase with a screed rake or trowel at a nominal thickness of 3mm.
6. The smoothing compound will be treated with a spikey roller immediately after application. This will remove any air bubbles in the mix and any imperfection in the finish.
7. Once the smoothing compound has fully cured (generally the next day), the Tarkett Safetread Vinyl will be installed to the surface using Uzin KE2000S Adhesive.
8. The area will then be assessed and a suitable starting line will be set out on the floor. 9. The Safetread installation will commence from the set-out line. Installation will be as
the Manufacturers guidelines. 10. On completion, the installation will be inspected by the Alexis manager and QA sheet
completed and presented to the relevant Telford Homes floor manager. 11. Protection will then be installed. 12. Installation of the bedroom carpets will then proceed with concrete pin gripper being
installed to perimeter of the bedrooms. 13. A door bar will be installed to bedroom doorways. 14. Roma underlay will be installed directly to the subfloor. 15. The relevant carpet will be laid out in the bedroom, stretched onto the gripper, cut into
the perimeter and then tucked around perimeter and into the door bar. 16. On completion, the installation will be inspected by the Alexis manager and QA sheet
completed and presented to the relevant Telford Homes floor manager. 17. The carpet will be swept/vacuumed off and carpet protection applied. 18. All material waste will be put in bins supplied by Telford Homes.
Prepared By: Tom Tarrant Date: 11th May 2020
TT.05.105.1 © Copyright 2011 4See Risk Management of 5 6
Method Statement
Note: Employees must be briefed on the content of this Method Statement and Risk Assessments referred to in order that a Safe System of Work is adopted by them. Signatures are to be entered on RA/MS briefing Sheets.
Received/Reviewed at Site By:
Date:
General
• Sharp items such as gripper rods and door bars should be transported into the property boxed and only removed immediately prior to installation.
• Sharp hand tools such as cutting knives should be kept in their holsters, or have the blades retracted whenever these are not in use.
• Adhesives and tackifiers will be kept in their original containers; lids will be replaced as soon as work is complete.
• Waste materials will be removed in accordance with site requirements. • The gripper rods and door bars will be installed and secured prior to the installation of the
flooring itself. • Upon completion of the works the Plot will be locked off. • All operatives to sign out at the completion of each working day.
Welfare Facilities
• Breaks times for the canteen will be allocated with no more than 18 no at one time. Due to the coronavirus.
Changes Prepared By: Tom Tarrant Date: 11th May 2020
Changes Received/ Agreed at Site By: Date:
TT.05.105.1 © Copyright 2011 4See Risk Management of 6 6