Board Meeting May 2015 Construction Update for the Stadium Repairs
ALLEN INDEPENDENT SCHOOL DISTRICT
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Summary of Stadium Repairs Phase Description of Work of Work Phase 1 Scoreboard Complete Phase 2 Low Rise Lateral Complete Phase 3 Retaining Walls Complete Phase 4 Press Box Repairs Complete Phase 5 Exp. Joints, Complete
One-Story Gravity Phase 6 Concourse Structure Complete at
Home side/In Progress Phase 7 Traffic Topping In Progress
-
Stadium Repairs Scoreboard Phase 1 - Complete
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 2 One Story Lateral Load Buildings on Concourse Level. The structural repairs are complete Concession Stands complete Entry towers are reconstructed Beams over gate ramps are complete
-
Allen ISD Eagle Stadium Concession Repairs 5-2015
-
Allen ISD Eagle Stadium Towers at Ramp Entries 5-2015
-
Allen ISD Eagle Stadium Ramped Entry at D 4-2015
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 3 Retaining Wall Repairs Shotcrete complete Geo-foam complete Rock Anchors complete
-
Eagle Stadium Shotcrete on Retaining Wall Phase 3
-
Eagle Stadium Retaining Wall Soil Nails Phase 3
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 4 Press Box Repairs Structural Steel Repairs complete from the Press box
to the foundation Press box repairs are complete
-
Allen ISD Eagle Stadium Press box repairs complete
-
Allen ISD Eagle Stadium Press box repairs complete
-
Allen ISD Eagle Stadium Press box repairs
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 5 Expansion Joints, Transfer Girders, and One Story Gravity Repairs Structural Steel Repairs complete Water shed metal roof is complete
-
Allen ISD Eagle Stadium Phase 5
-
Allen ISD Eagle Stadium Phase 5
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 6 Concourse Structural Repairs Installation of FRP Composite System to concrete
joists on-going Home side joists and beams has been wrapped and
installation is underway on the visitor side
-
Concrete Joists repaired with FRP Application
-
ALLEN INDEPENDENT SCHOOL DISTRICT
Stadium Repairs Phase 7 Traffic Topping Installation of a coating over the concrete concourse
walking surface Installation has started and we are waiting on a break
in the weather
-
Traffic Topping Installed at home side of Stadium
-
Traffic Topping Installed at the visitor side of Stadium
-
ALLEN INDEPENDENT SCHOOL DISTRICT