alley 111- rfi-0171 - placing boom blockout [ skanska 4212049 … · 2015-12-04 · the proposed...
TRANSCRIPT
1
Smith, Andrea
From: Bill Henshaw <[email protected]>Sent: Tuesday, October 21, 2014 9:59 AMTo: Smith, AndreaSubject: Re: Alley 111 - 50' Pogo Weight - Placing Boom
Andrea. I just talked with swing America and they said that the in operation and out of operation chart is based on the
longest mast they have which is a 59 footer. So you are good to go.
Bill Henshaw
On Oct 20, 2014, at 5:38 PM, "Smith, Andrea" <[email protected]> wrote:
Hi Bill,
How does the 50’ pogo change the in-operation and out of operation weights and forces?
We were previously provided and in operation weight of 46,300 pounds, and an out-of-operation weight
of 36,400 pounds.
Thanks-
Andrea Smith Senior Project Engineer
Skanska USA Building Operations usa.skanska.com 929 109th Ave NE Bellevue, WA 98004, United States
Mobile +1 206 327 2765 Fax +1 877 884 6119
Connect With Us: Blog | Facebook | Twitter | LinkedIn | Instagram | YouTube
Think twice before you press "print." This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy or deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you.
1
Smith, Andrea
From: Smith, AndreaSent: Thursday, September 04, 2014 11:39 AMTo: '[email protected]' ([email protected])Cc: [email protected]; Smith, Dale ([email protected])Subject: FW: Alley 111 - Placing Boom and Pour Strip - Blockout SizeErrorandShoringAttachments: FSK-2 - Placing Boom Shoring.pdf
For your records, see below.
Susan- thank you for your time this morning. I really appreciate it.
From: Mike Braun [mailto:[email protected]] Sent: Thursday, September 04, 2014 11:14 AM To: Smith, Andrea Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout SizeErrorandShoring
Andrea
No exceptions taken to proposed shoring.
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 1420 Fifth Ave, Suite 425 Seattle, WA 98101-4019 206-343-3000 phone 206-948-5974 mobile 206-343-3013 fax [email protected]
From: Smith, Andrea [mailto:[email protected]] Sent: Thursday, September 04, 2014 11:04 AM To: Mike Braun Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout SizeErrorandShoring
Hi Mike,
The attached appears to meet all of your criteria, and we are proceeding to install from SOG (P4) and up.
Let me know if you have any concerns.
Thanks-
From: Mike Braun [mailto:[email protected]] Sent: Thursday, September 04, 2014 10:01 AM To: Smith, Andrea Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout SizeErrorand Shoring
Andrea
The slab supporting the placing boom should be shored down to the slab-on-grade.
2
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 206-343-3000 phone 206-948-5974 mobile 206-343-3013 fax [email protected]
From: Smith, Andrea [mailto:[email protected]] Sent: Thursday, September 04, 2014 9:56 AM To: Mike Braun Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout SizeErrorand Shoring
Just a heads up, they are installing the placing boom today, and utilizing it to pour the level 3 deck.
From: Mike Braun [mailto:[email protected]] Sent: Thursday, September 04, 2014 9:52 AM To: Smith, Andrea Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout Size Errorand Shoring
Andrea
This email is to confirm our phone conversation regarding shoring for the concrete placing boom. The required shoring
capacity is 46,300 lbs “in-operation” (36,400 lbs “out-of-operation”) according to the product information you sent on
2/6/14. The number of shoring posts required depends on the capacity of each post. Round up to an even number and
place equal number each side of the pour strip. The posts should run down to the slab-on-grade as the concrete floor
slabs do not have enough capacity even when summed. Align the posts vertically. Do not offset them more than 4”,
say, to prevent punching through the slab.
I just saw your email to Ceco Concrete and agree with the information provided. It is my understanding that you will not
install the placing boom until you reach the 4th
Floor.
Please contact me if you have additional questions.
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 206-343-3000 phone 206-948-5974 mobile 206-343-3013 fax [email protected]
From: Smith, Andrea [mailto:[email protected]] Sent: Thursday, September 04, 2014 8:51 AM To: Mike Braun Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout Size Errorand Shoring Importance: High
Sorry for the communication overload, but I just found out we need this shoring layout by noon. So it’s a little hotter
than I thought.
From: Smith, Andrea Sent: Thursday, September 04, 2014 8:41 AM To: 'Mike Braun' Cc: Smith, Dale ([email protected]) Subject: RE: Alley 111 - Placing Boom and Pour Strip - Blockout Size Error and Shoring
3
Hi Mike,
I left a voicemail on your cell this AM. We had a couple of issues with the placing boom I was hoping to get some help
with:
1. The Placing Boom opening was supposed to 41”x41” versus 3’-6”x3’-6”. I had not noticed this previously when
reviewing the drawing, and right now we don’t need anything regarding this item. Just for an FYI.
2. We had some correspondence over the phone back in March about reshoring requirements for the placing
boom. Can you send me the reshoring comments in email, so I can pass along to Ceco?
Thanks-
From: Mike Braun [mailto:[email protected]] Sent: Thursday, March 20, 2014 11:51 AM To: Smith, Andrea Cc: Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip
Andrea
Preliminary sketches for the concrete placing boom openings are attached. Please review and let me know if you have
any questions or comments. If everything is OK, I will sign/seal.
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 206-343-3000 phone 206-948-5974 mobile [email protected]
From: Smith, Andrea [mailto:[email protected]] Sent: Wednesday, March 19, 2014 2:56 PM To: Mike Braun Subject: RE: Alley 111 - Placing Boom and Pour Strip
Hi Mike-
Any chance to review?
From: Mike Braun [mailto:[email protected]] Sent: Wednesday, March 12, 2014 8:35 AM To: Smith, Andrea Subject: RE: Alley 111 - Placing Boom and Pour Strip
Andrea
Ok, I’ll take a look at it.
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 206-343-3000 phone 206-948-5974 mobile
From: Smith, Andrea [mailto:[email protected]] Sent: Wednesday, March 12, 2014 8:14 AM To: Mike Braun Subject: FW: Alley 111 - Placing Boom and Pour Strip
4
Hi Mike-
Finally swinging back to this-
See Schwing responses below in red about the placing boom and let me know how this impacts the design.
The slab edges are currently being designed via RFI to be self-supporting cantilevers. We do not yet have the response,
but they will just be made to support the live loads they would carry per S1.0a.
Thanks-
From: Bill Henshaw [mailto:[email protected]] Sent: Wednesday, February 12, 2014 4:58 PM To: Smith, Andrea Cc: 'Brett Young' Subject: FW: Alley 111 - Placing Boom and Pour Strip
Andrea, Did you see the response from Schwing below?
Bill Henshaw
Brundage-Bone Concrete Pumping Inc.
1055 4th
AVE N.
Kent, WA. 98032
253-859-4444
206-510-3299 (cell)
From: Mehl, Jason [mailto:[email protected]]
Sent: Tuesday, February 11, 2014 2:28 PM
To: Bill Henshaw
Cc: 'Brett Young'
Subject: RE: Alley 111 - Placing Boom and Pour Strip
Hi Bill,
My red colored comments to the yellow highlighted items are stated below.
Have a good night.
Jason Mehl, IIW IWE
Structural Engineering Manager
SCHWING America, Inc.
Subsidiary of SCHWING GmbH
St. Paul, Minnesota | USA
+1.888.724.9464 | www.schwing.com
From: Bill Henshaw [mailto:[email protected]] Sent: Tuesday, February 11, 2014 12:52 PM To: Mehl, Jason Cc: 'Brett Young' Subject: FW: Alley 111 - Placing Boom and Pour Strip
5
Jason,
Please take a look at the questions BBCP has been asked Regarding putting a Placing Boom in a pour strip of a upcoming
job. Could you please respond ASAP with your thoughts?
Bill Henshaw
Brundage-Bone Concrete Pumping Inc.
1055 4th
AVE N.
Kent, WA. 98032
253-859-4444
206-510-3299 (cell)
From: Bill Henshaw [mailto:[email protected]]
Sent: Tuesday, February 11, 2014 10:26 AM
To: 'Smith, Andrea'
Cc: 'Brett Young'
Subject: RE: Alley 111 - Placing Boom and Pour Strip
Hello Andrea,
I do know that the floor frames must be supported by all four sides. The other statement that the upper support only
accounts for horizontal HO only, I have to defer that to the Manufacture engineers. My first thought is no, taking into
consideration what the term Moment means. I do believe moment is more than just a horizontal force. I will run this by
Schwing and get back to you.
Bill Henshaw
Brundage-Bone Concrete Pumping Inc.
1055 4th
AVE N.
Kent, WA. 98032
253-859-4444
206-510-3299 (cell)
From: Smith, Andrea [mailto:[email protected]]
Sent: Monday, February 10, 2014 4:59 PM
To: Bill Henshaw ([email protected])
Subject: FW: Alley 111 - Placing Boom and Pour Strip
Hi Bill,
Can you look at the two highlighted items below and respond?
Thanks-
From: Mike Braun [mailto:[email protected]] Sent: Monday, February 10, 2014 2:12 PM To: Smith, Andrea Cc: Smith, Dale; Martin, Albert; Bradford, Jim; Howard Burton Subject: RE: Alley 111 - Placing Boom and Pour Strip
Andrea
6
This email is to summarize our recent phone conversations.
The proposed concrete placing boom location is dead center between Grids G-H/4-5. The total in-operation weight of
the equipment, concrete, and impact is 46,300 lbs according to the information you sent. It is my understanding that
the vertical load, the skewing torsion, and horizontal force Hu is supported at the lower floor frame. The upper floor
frame supports the horizontal force Ho only. Please confirm this with Brundage-Bone. True, plus wind [W] at the upper
floor frame. Summary: Ho & W loads on upper floor frame; Hu, V, & Md loads on lower floor frame.
The floor slabs must be shored to support the concrete placing boom. The worst case scenario is that the slabs are
shored all the way down to Level P4. You mentioned that Swenson Say Faget said the slab adjacent to the pour strip
was not designed as a cantilever to support construction loading. If the slab is reinforced with rebar so it can support
load as a cantilever, the number of levels of shoring could be reduced.
We envision shoring posts with a total capacity of 48,000 lbs at each level. The shoring posts must be aligned vertically
so they do not punch through the slab.
A preliminary sketch is attached showing the concrete placing boom floor frame supported by the slab edges of the pour
strip. The floor frame shown is not supported in the pour strip. We could add a steel beam on these 2 sides. Please ask
Brundage-Bone whether the floor frame may be supported on 2 sides only. I strongly advise 4 sides are constrained for
the floor frames. Independent of the project pour plan, the SPB operator could slew the boom in any 360° slewing
position.
Mike Braun, P.E., S.E. Seattle Structural PS Inc. 1420 Fifth Ave, Suite 425 Seattle, WA 98101-4019 206-343-3000 phone 206-948-5974 mobile 206-343-3013 fax [email protected]
From: Smith, Andrea [mailto:[email protected]] Sent: Thursday, February 06, 2014 8:18 PM To: Mike Braun Cc: Smith, Dale; Martin, Albert; Bradford, Jim Subject: Alley 111 - Placing Boom and Pour Strip
Hi Mike,
We are ready to start getting some engineering and design for our placing boom supports and penetrations. Below is a
description of what we are thinking about doing.
A placing boom will be utilized to pour from Level 2 through the roof deck. The placing boom weighs 18,500 lbs (see
attached Placing Boom Specifications), it imposes loads on the surrounding floor slabs per the attached Load Table, and
it requires a 41"x41" opening per the attached Floor Frame Diagram. The attached Floor Frame Diagram also shows a
10"x10" pipe line hole within 16" of the placing boom opening.
We want to put the placing boom in the pour strip between GL-G and H in the center of the building. It would require
the pour strip to be widened at the location of the mast. We would also want to keep the 10”x10” pipe line blockout out
of the pour strip.
Once you have a chance to get oriented, give me a call and let’s go through before you start designing. I would like to get
this design 100% dialed in by 2/19 so we can get it incorporated in the shop drawings for reinforcing steel and deck
formwork. Let me know how this target works for you.
7
Thanks,
Andrea Smith Senior Project Engineer
Skanska USA Building Operations usa.skanska.com 929 109th Ave NE Bellevue, WA 98004, United States Mobile +1 206 327 2765 Fax +1 877 884 6119 Connect With Us: Blog | Facebook | Twitter | LinkedIn | Instagram | YouTube
Think twice before you press "print." This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy or deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you.
No virus found in this message.
Checked by AVG - www.avg.com
Version: 2014.0.4765 / Virus Database: 4015/8145 - Release Date: 09/02/14
No virus found in this message.
Checked by AVG - www.avg.com
Version: 2014.0.4765 / Virus Database: 4015/8145 - Release Date: 09/02/14
No virus found in this message.
Checked by AVG - www.avg.com
Version: 2014.0.4765 / Virus Database: 4015/8145 - Release Date: 09/02/14
G H
4
53"
2' -
6"
2' -
6"
3"
8" 3' - 6" 8"
1' - 4"
6 EACH EFCO L2 SHORES(CAPACITY 8500# EA.)PER LEVEL AS SHOWNALIGNED VERTICALLYTHROUGH STRUCTUREFROM LVL P4 UP
6' - 1"6' - 1"6' -
0 1
/2"
6' -
0 1
/2"
CECO CONCRETE
CONSTRUCTION, LLC
CONTRACT NUMBER:
SCALE:DRAWN BY: DATE:
SHEET:
1/4" = 1'-0"Alley 111
50-69-14041 Placing Boom ShoringFSK-2
09/04/14SRT
1/4" = 1'-0"1
Placing Boom Shoring Plan
From: Sean Williams <[email protected]>
Sent: Friday, May 09, 2014 4:59 PM
To: al titus; Martin, Albert; Smith, Andrea; Andy Rasmussen; Antonio Corona;
Bhaumik Shah; Cammy Hunter; Cara Hattrick; Smith, Dale; Daniel McCartt;
Dennis Elbert; Eric Mittet; Gary Byrne; Gregg Robinson; Harold Paulson;
James Johnston; Jenae Goldfinch; Smith, Jenny; Bradford, Jim; Joe
Chevalier; Joe Goldfinch; Jon Bryant; Josh Dickerson; Justin Schmidt; Kalin
Wate; Louis Mark; Mark Glidewell; Mark Rosas; Santeford, Matt; Randy
Dana; Rene Fabros; Rod Imamura; Rod Rippin; Samantha Wallish; Scot
Love; Sean Setterberg; Williams, Sean; Ssuan Timmons; Steve Murphy;
Steve Otis; Steve Vaaga; Leptich, Tom; trevor Miller
Subject: Alley 111- RFI-0171 - Placing Boom Blockout [ Skanska 4212049-000 -
Alley 111 Apartments]
Attachments: RFI-171 Placing Boom Blockout.pdf; Alley 111 Conc Placing Boom
SKETCHES 2014-04-18.pdf; RFI 0171.pdf; Transmittal.pdf; PMATH1.txt
****** Request For Information: 0171 - Placing Boom Blockout ****** RFI ID:
112577
Number:
0171
Subject:
Placing Boom Blockout
Is Official:
1
Is Closed:
1
Date Created:
5/6/2014
Date Required:
5/13/2014
Date Responded:
5/9/2014
Question:
Reference: "Sketches for Placing Boom Blockout", S2.5-S2.13
Please see the attached "Sketches for Placing Boom Blockout", which show structural details for a
concrete placing boom blockout. This blockout will be located between GLs G/H (in the pour strip) and
centered on GL 4.5. The blockouts will start on Level P1/C1 and continue upwards through the rooftop,
shown from S2.5-S2.13.
The structural engineering for the blockout has already been provided from Seattle Structural. However,
please verify if the attached means and methods modifications to the existing design are acceptable.
Answer:
Response (Answered) from: Bart Blans (Swenson Say Faget)
Remarks:
Acceptable.
Response (Answered) from: Kevin Reed (GGLO)
Remarks:
Per Bart Blans (SSF) on 5/8/2014, this is acceptable.
Kevin Reed (GGLO) 5/9/2014
Importance:
Normal
Name:
Skanska USA Building Inc.
Author Contact ID:
SEAWIL
Author RFI Number:
Name - Answer Company:
GGLO
Answer Contact ID:
KEVREE
Discipline:
Architectural
Detailed, RFIs Grouped by RFI Number
Request for Information 0171
Alley 111 Apartments Skanska USA Building Inc.Project # 4212049-000
Tel: Fax:
RFI #: 0171 Date Created: 5/6/2014
Author Company Authored ByAnswer Company Answered By
GGLO Kevin Reed Skanska USA Building Inc. Sean Williams
1301 First Avenue Suite 301
Seattle, WA 98101
221 Yale Ave. N., Suite 400
Seattle, WA 98109
Co-Respondent Author RFI Number
DisciplineSubject Category
ArchitecturalPlacing Boom Blockout
Company Name Contact Name Copies NotesCc:
Question Date Required: 5/13/2014
Reference: "Sketches for Placing Boom Blockout", S2.5-S2.13
Please see the attached "Sketches for Placing Boom Blockout", which show structural details for a concrete placing boom
blockout. This blockout will be located between GLs G/H (in the pour strip) and centered on GL 4.5. The blockouts will start
on Level P1/C1 and continue upwards through the rooftop, shown from S2.5-S2.13.
The structural engineering for the blockout has already been provided from Seattle Structural. However, please verify if the
attached means and methods modifications to the existing design are acceptable.
Suggestion
Answer Date Answered: 5/9/2014
Response (Answered) from: Bart Blans (Swenson Say Faget)
Remarks:
Acceptable.
Response (Answered) from: Kevin Reed (GGLO)
Remarks:
Per Bart Blans (SSF) on 5/8/2014, this is acceptable.
Kevin Reed (GGLO) 5/9/2014
Prolog Manager Printed on: 5/9/2014 6West Page 1 of 1
Detailed, RFIs Grouped by RFI Number
Request for Information 0171
Alley 111 Apartments Skanska USA Building Inc.Project # 4212049-000
Tel: Fax:
RFI #: 0171 Date Created: 5/6/2014
Author Company Authored ByAnswer Company Answered By
GGLO Kevin Reed Skanska USA Building Inc. Sean Williams
1301 First Avenue Suite 301
Seattle, WA 98101
221 Yale Ave. N., Suite 400
Seattle, WA 98109
Co-Respondent Author RFI Number
DisciplineSubject Category
ArchitecturalPlacing Boom Blockout
Company Name Contact Name Copies NotesCc:
Question Date Required: 5/13/2014
Reference: "Sketches for Placing Boom Blockout", S2.5-S2.13
Please see the attached "Sketches for Placing Boom Blockout", which show structural details for a concrete placing boom
blockout. This blockout will be located between GLs G/H (in the pour strip) and centered on GL 4.5. The blockouts will start
on Level P1/C1 and continue upwards through the rooftop, shown from S2.5-S2.13.
The structural engineering for the blockout has already been provided from Seattle Structural. However, please verify if the
attached means and methods modifications to the existing design are acceptable.
Suggestion
Answer Date Answered: 5/9/2014
Response (Answered) from: Bart Blans (Swenson Say Faget)
Remarks:
Acceptable.
Response (Answered) from: Kevin Reed (GGLO)
Remarks:
Per Bart Blans (SSF) on 5/8/2014, this is acceptable.
Kevin Reed (GGLO) 5/9/2014
Prolog Manager Printed on: 5/9/2014 6West Page 1 of 1
Detailed, RFIs Grouped by RFI Number
Request for Information 0171
Alley 111 Apartments Skanska USA Building Inc.Project # 4212049-000
Tel: Fax:
RFI #: 0171 Date Created: 5/6/2014
Author Company Authored ByAnswer Company Answered By
GGLO Kevin Reed Skanska USA Building Inc. Sean Williams
1301 First Avenue Suite 301
Seattle, WA 98101
221 Yale Ave. N., Suite 400
Seattle, WA 98109
Co-Respondent Author RFI Number
DisciplineSubject Category
ArchitecturalPlacing Boom Blockout
Company Name Contact Name Copies NotesCc:
Question Date Required: 5/13/2014
Reference: "Sketches for Placing Boom Blockout", S2.5-S2.13
Please see the attached "Sketches for Placing Boom Blockout", which show structural details for a concrete placing boom
blockout. This blockout will be located between GLs G/H (in the pour strip) and centered on GL 4.5. The blockouts will
start on Level P1/C1 and continue upwards through the rooftop, shown from S2.5-S2.13.
The structural engineering for the blockout has already been provided from Seattle Structural. However, please verify if the
attached means and methods modifications to the existing design are acceptable.
Suggestion
Answer Date Answered:
Prolog Manager Printed on: 5/6/2014 6West Page 1 of 1
RFI TransmittalGGLO | 1301 First Ave. Suite 301 Seattle WA 98101 United States
Page 1 of 3
PROJECT Skanska: Alley 1112012033.00
DATE SENT 5/9/2014
SUBJECT Placing Boom Blockout RFI ID 0171
TYPE RFI TRANSMITTAL ID 00784
PURPOSE Answered VIA Info Exchange
QUESTION: ****** Request For Information: 0171 - Placing Boom Blockout ******RFI ID:112577
Number:0171
Subject:Placing Boom Blockout
Is Official:1
Is Closed:0
Date Created:5/6/2014
Date Required:5/13/2014
Date Responded:
Question:Reference: "Sketches for Placing Boom Blockout", S2.5-S2.13
Please see the attached "Sketches for Placing Boom Blockout", which showstructural details for a concrete placing boom blockout. This blockout willbe located between GLs G/H (in the pour strip) and centered on GL 4.5. Theblockouts will start on Level P1/C1 and continue upwards through therooftop, shown from S2.5-S2.13.
The structural engineering for the blockout has already been provided fromSeattle Structural. However, please verify if the attached means andmethods modifications to the existing design are acceptable.
Answer:
RFI TransmittalDATE: 5/9/2014
ID: 00784
Page 2 of 3
Importance:Normal
Name:Skanska USA Building Inc.
Author Contact ID:SEAWIL
Author RFI Number:
Name - Answer Company:GGLO
Answer Contact ID:KEVREE
Discipline:Architectural
SUGGESTION:
ANSWER:Response (Answered) from: Bart Blans (Swenson Say Faget)Remarks:
Acceptable.
Response (Answered) from: Kevin Reed (GGLO)Remarks:Per Bart Blans (SSF) on 5/8/2014, this is acceptable. Kevin Reed (GGLO) 5/9/2014
FROM
NAME COMPANY EMAIL PHONE
Kevin Reed GGLO [email protected] 206-902-5420
TO
NAME COMPANY EMAIL PHONE
Sean Williams Skanska USA [email protected] (206) 498-
RFI TransmittalDATE: 5/9/2014
ID: 00784
Page 3 of 3
NAME COMPANY EMAIL PHONE
Building om 0107
DESCRIPTION OF CONTENTS
QTY DATED TITLE NUMBER SCALE SIZE NOTES
1 5/9/2014 RFI 0171 response.pdf
COPIES:
Albert Martin (Skanska USA Building Inc.) Andrea Smith (Skanska USA Building) Anuja Mohare (GGLO) Christian Gunter (SKANSKA USA Commercial) Dale Smith (Skanska USA Building) Jim Bradford (Skanska USA Building) Kevin Reed (GGLO) Sean Williams (Skanska USA Building) Stewart Germain (SKANSKA USA Commercial) Terry Bendrick (SKANSKA USA Commercial) Tom Leptich (Skanska USA Building) William Castillo