alternative to floating slab track high attenuation sleeper by ian robertson alstom

26
URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper Presented by Ian Robertson, ALSTOM 24 June 2010, Prague

Upload: irwan-joe

Post on 01-Oct-2015

38 views

Category:

Documents


7 download

DESCRIPTION

Develop slab track with following technical characteristics-metro environment (18t axle load, 100 kph)-equivalent vibration performance to Floating Slab Track -ability to meet all railway constraints- Safety (derailment) including track level evacuation- Comfort- maintenanceConstruction method-for standard equipment and methodsproduction rate as conventional track slabLower costs compared to Alternative Floating Slab Track-For capital portion (design+procure+build)-For maintenance portion

TRANSCRIPT

  • URBAN TRACK Final Conference Alternative to Floating Track Slab

    High Attenuation Sleeper

    Presented by Ian Robertson, ALSTOM24 June 2010, Prague

  • Final Conference 24 June 2010 2

    Contents

    Specific objectives of study

    Chosen concept

    Detailed design and laboratory test

    Site test (ongoing)

    Conclusions

  • Final Conference 24 June 2010 3

    Specific objectives of study

    Develop slab track with following technical characteristics

    metro environment (18t axle load, 100 kph)

    equivalent vibration performance to Floating Slab Track

    ability to meet all railway constraints

    Safety (derailment) including track level evacuation

    Comfort

    maintenance

    Construction method

    for standard equipment and methods

    production rate as conventional track slab

    Lower costs compared to AFST

    For capital portion (design+procure+build)

    For maintenance portion

  • Final Conference 24 June 2010 4

    Chosen conceptReview of existing systems worldwidePrevious generation bi-block sleepers for CTRL

    Relatively low weight Tie bar overstressed with very soft pads Track gauge variations with very soft padsChosen concept = mono-block resilient sleeper High attenuation due to

    High sleeper mass (350

    400 kg)Very soft resilient inserts (8KN/mm/fastener)Adapted to tracklaying gantriesMaintenance friendly

  • Final Conference 24 June 2010 5

    Detailed design and laboratory testHAS mono-bloc sleeper concept

    Rigid boot

    Concrete sleeperFastening

    system according

    to customer

    choicesealing

    Holes for conductor rail support

  • Final Conference 24 June 2010 6

    Detailed design and laboratory test

    Comparison of Different Antivibratile System

    -60

    -50

    -40

    -30

    -20

    -10

    0

    10

    201

    1

    ,

    6

    2

    ,

    5

    4

    6

    ,

    3

    1

    0

    1

    6

    2

    5

    4

    0

    6

    3

    1

    0

    0

    1

    5

    8

    2

    5

    1

    Frequency (Hz)

    I

    n

    s

    e

    r

    t

    i

    o

    n

    G

    a

    i

    n

    (

    d

    B

    )

    Insertion Gain SFS 312 (dB)

    Insertion Gain DFC Pandrol (dB)

    Insertion Gain CTRL 2(dB)

    Insertion Gain FST (Taipei) (dB)

    Insertion Gain EGG_2(dB)

    Insertion gain target

  • Final Conference 24 June 2010 7

    Detailed design and laboratory test

    DESIGN FULLY COMPLIANT WITH MOST RAIL FASTENERS

    Typical tunnel layout

  • Final Conference 24 June 2010 8

    Detailed design and laboratory test

    Based on OBLEX project 20 cm gain

    Dia.5.8 Dia. 5.6

    Typical case of impact on tunnel diameter

  • Final Conference 24 June 2010 9

    Detailed design and laboratory test

    Time

    Load 2 Hz

    5 HzFmax

    .Fmax

    Actual load diagram with sine shape

    Optimum load diagram with triangle shape simulating wheel passage

    Simplified load diagram used during fatigue test to simulate bogie passage

    ACHIEVED 4,5 MILLIONS LOAD CYCLE WITH SUCCESS

    HAS mono-bloc sleeper dynamic testing regime

  • Final Conference 24 June 2010 10

    Detailed design and laboratory test

    Mechanical test carried out Fatigue test with inclined loads according to the

    following phases :

    1M Cycles @ low frequency (3 Hz) applied load between 10kN et 75kN, centred, inclined at 38

    0.5MCycles @ moderate frequency (5 Hz) applied load between 30/40kN et 75kN centred , inclined at 38

    2M Cycles @ low frequency (3 Hz) applied load between 10kN et 75kN, inclined at 10

    and 38

    1 M Cycles @ moderate frequency (5 Hz) applied load between 30/40kN et 75kN, inclined at 10

    and 38

    NO PAD WEARING & NO VERTICAL STIFFNESS LOSS AFTER 4.5M CYCLES

    (EN13230: 2M CYCLES)

  • Final Conference 24 June 2010 11

    Detailed design and laboratory test

    EXCITATIO N

    MONOBLOC SLEEPER

    RAIL

    RIGID HULL

    RAIL

    PRELOAD

    CONCRETE BASE

    SENSOR S

    Testing arrangementsAcoustic test

    mechanical test

  • Final Conference 24 June 2010 12

    Detailed design and laboratory test

    0

    2

    4

    6

    8

    10

    12

    MN/m

    0 32 40 50 64kN

    Stifffness vs static load at 8Hz

    K (MN/m)

    Dynamic test results

  • Final Conference 24 June 2010 13

    Site test (ongoing)

    Several possibilities reviewed notably SINGAPORE Circle LineCEF test site (Valenciennes)

    CEF chosen Easier logistics To respect URBAN TRACK timing

    Construction just completed June 11

    Vibration tests scheduled July

    Introduction

  • Final Conference 24 June 2010 14

    Site test -

    Situation

    Test section 190m radius 160mm cant

    Situation within CEF site

    Actual track to replace

    ballasted track

    fishplated U50 rail

    good ground conditions EV2 above 80 MPA

  • Final Conference 24 June 2010 15

    Site test

    50m of High

    Attenuation

    Track 2 x 6.5m of transition slab with ballasted track Sleeper spacing

    700mmWelded

    rail on high attenuation zone Fishplated

    joints allowing

    movement

    at

    each

    end of test

    General Layout

  • Final Conference 24 June 2010 16

    Site test Typical section

  • Final Conference 24 June 2010 17

    Site test

    Detailed design concept

    230

    230

    80

    2583 80 200

    Reinforced

    U-shaped foundationTrack

    slab

    concrete

    unreinforced With frequent joints to avoid shrinkage cracking

  • Final Conference 24 June 2010 18

    Site test

    After

    HAS vibration testingAxle

    load

    = 25 tonnes

    Total load = 280MGT HAS resilient

    inserts to replace by stiffer inserts

    (30MN/M)

    Structural design based on Eurocode

    2 Load

    Model 71

    Crack 0.2mm

    Detailed design assumptions

  • Final Conference 24 June 2010 19

    Site test

    Neighbouring (existing) ballast track

    Total dynamic

    stiffness

    around

    80kN/mm per

    fastener

    High

    Attenuation

    Sleeper Track

    Under sleeper pad

    = 1,5*8 kN/mm

    Total stiffness = 11kN/mm per

    fastener

    Transition zone

    Target total stiffness

    = 46kN/mm

    Under sleeper pad

    = 70 to 80 kN/mm per

    fastener

    Total stiffness

    = 47 to 52 kN/mm per

    fastener

    0.70.6 0.7

    HAS Track

    Ballast track

    Transition zone

    70.7

    Transition slab design

  • Final Conference 24 June 2010 20

    Site test Construction after concreting of foundation

  • Final Conference 24 June 2010 21

    Site testConstruction before track slab concreting

  • Final Conference 24 June 2010 22

    Site test

    In July testing of following zonesHAS track Transition trackStatic measurements

    Soil impedance

    Unloaded and loaded track impedance Determination of in situ HAS track characteristics

    Rail surface quality

    Testing

  • Final Conference 24 June 2010 23

    Site test

    Dynamic measurements (6 pass-bys) train induced

    vibration levels

    on track slab concrete

    outside U shaped foundation

    rail and sleeper deflection

    of both rails rail and sleeper lateral displacements

    Testing

  • Final Conference 24 June 2010 24

    Site test

    Strain measurementsCaptors on rail foot 5 sleeper spacing per measurement site

    Testing

  • Final Conference 24 June 2010 25

    Site test

    Vibration simulationHAS track

    parameters

    measured

    PACT reference

    track

    parametersMeasured

    roughness

    Rolling

    Stock data Insertion gain calculation

    in 1/3rd octave bands

    Testing

  • Final Conference 24 June 2010 26

    Conclusions

    High performance alternative to floating track slab

    Ideal for underground metro applications

    Could absorb railway loads applied to sensitive bridges

    In high speed tunnel application

    Theoretically compared to S3

    high speed 4dB (halved the vibration level)

    Limiting operational criteria (mixed operations, speed, twist) to determine

    Costing being completed but ballpark figures are

    Compared to typical metro floating track slab

    Design, procure and build cost HAS gives 10% saving

    Maintenance costs for HAS are much lower

    Potential to reduce tunnelling costs

    Further information

    final report will be ready after completion of CEF tests in August 2010

    See URBAN TRACK website http://www.urbantrack.eu/

    RGCF no 191 February 2010

    Railway Engineering 2009

    High Attenuation Sleeper