american electric power ercot kickoff
DESCRIPTION
American Electric Power Project Kickoff for ERCOT a $600M project managed by John Napier PMP, CSMTRANSCRIPT
ERCOT Nodal Project Kick Off ERCOT Nodal
Project Kick Off
November 23, 2009
2 2
High Level Project ScopeHigh Level Project Scope
The objective of this project is to meet the new requirements of the ERCOT Nodal market utilizing existing infrastructure and information systems where possible in order to keep cost and timeline minimal.
Specific technical deliverables include the following:
• webTrader to GCSS – Ancillary service schedules by unit
• PI to webTrader – base points
• webTrader to ODS - replace Base Power Schedule with Energy Trade, Self Schedule, and Output Schedule
• 3rd Party Checkout modifications to replace Base Power Schedule
• Off-System Invoicing to manage the replacement of Base Power Schedule
• New schedule report in webTrader for FPA daily processes
3 3
Plan Phase StrategyPlan Phase Strategy
Project Budget• The total Capital amount approved is $813,155 • The total O&M amount approved is $59,376• Quoted dollar amounts include IT, BU, Fringes, and Incentives
Plan Phase Execution
• Document Business Processes• Develop Requirements• Develop System Design• Develop Component Design• Begin Detailed Designs• Ongoing testing with ERCOT
4 4
Program TeamsProgram Teams
Steering Committee Members: • David Hesser• Mike Sullivan• Rick Bale• Julie Standley
Core Team Members:
• Mark Boggs• Lori Mahood• John Napier• Rezaur Rahman• Bhooma Raghunathan• Ashutosh Tewari• Krishna K Somisetty• Shane Aleksic• Michele Seward• Susan DeMoen• Jeff Rice• Meera Vijayalakshmi• Kent Feliks• Dale Woodruff• Mark Diggs
ERCOT Liaisons:
• Trina Molnar• Richard Ross• Bob Bradish
5 5
Steering Committee Role Steering Committee Role
• Provides strategic direction, vision and goals to the project
• Supports the team in tactical decision making, resolution of issues that go beyond the scope and duration of the project and spans multiple business areas
• Approve, endorse and support combined projects governance process
6 6
Core Team RoleCore Team Role
What We Need From You!
• Provide necessary issue resolution and clarification
• Ensure effort and time expectations are appropriate to steering committee expectations
• Remove barriers across business functions for optimal project and program performance
• Escalate to steering committee as needed
7 7
Project TeamProject Team
Planning • IT PM – John Napier• TSO – Rezaur Rahman• BSA – Lori Mahood
Development & Support• Lead Developers – Bhooma Raghunathan,
Ashutosh Tewari, Krishna K Somisetty• Support – Krishna K Somisetty, Shane Aleksic,
Andy Kellett• Tech Writer – TBD• Test Coordinator - TBD
Resource Managers• Comm Ops Planning – Julie Standley• Support – Nalini D Selvaraj, Zachary Van
Tassel• Development – John T McCrystal, Rod Boswell,
Dennis P DeVendra• QA – Evelyn McElhaney
8 8
BSA – Business System Analyst
BSA – Business System Analyst
• Define and manage scope of project
• Gather and document business requirements and process changes
• Champion business interest within project
• Develop system test cases and assist with system test execution
• Assist business unit with user acceptance testing
• Provide general coordination between the functional and the technical teams.
9 9
TSO - Technical Solution Owner
TSO - Technical Solution Owner
• Accountable for end to end technology solution for the project.
• Ensure execution of the technical solution across project’s technical contributors
• Resolve technical project issues/risks or escalate to the Project Manager
10 10
Lead DevelopersLead Developers
• Responsible for detailed design based on approved requirements
• Provide development input to Project Plan
• Responsible for development commitment estimates - hours and dates
• Responsible for delivering coded requirements
• Identify/mitigate changes, issues, and risks
• Coordinates technical team• Main interaction with PM, BSA,
TSO, Support Lead, and Business Unit as needed
11 11
SupportSupport
• Responsible for technical environment setup and maintenance
• Provide support input to Project Plan
• Responsible for support commitment estimates - hours and dates
• Contribute to the design process
• Identify/mitigate changes, issues, and risks
• Responsible for migration to production
12 12
QAQA
• Responsible for IT test strategy development
• Provide QA input to Project Plan
• Responsible for QA commitment estimates - hours and dates
• Coordinates the efforts of the project team and BU in the development and execution of IT test cases
13 13
Project ActivitiesProject ActivitiesPhase Task Responsible Secondary
Plan Document Business Processes BSA
Plan Document Requirements BSA
Plan Project Plan PC PM
Plan Project Charter PM PC
Plan System Design TSO
Plan Detail Design Lead Developer
Plan Test Strategy QA Lead
Plan Quality Plan PC PM
Plan Deployment and Transition Plan TSO Lead Developer
Construct Coding Lead Developer
Construct Unit Testing Lead Developer
Construct Create Test Cases BSA Support Lead
Test System Testing Support Lead BSA
Test Regression Testing Support Lead Lead Developer
Test Stress Testing Support Lead Lead Developer
Test Performance Testing Performance Architect Test Lead
Test User Acceptance Testing BU BSA
Deliver Migrate to Production Support Lead Lead Developer
14 14
Project TimelineProject Timeline
11/2/09 - 12/4/09Requirements
12/7/09 - 12/18/09System Design
Component Design
12/28/09 - 2/19/10Detailed Design
CodeUnit Test
2/22/10 - 3/5/10Integration Test
3/8/10 - 3/26/10System Test
3/29/10 - 4/16/10UAT
4/19/10IT
Complete
15 15
Communication Communication
Type of Communication Recipients Responsibilities Update frequency
Status report which includes issues and risks
Steering Committee, CORE Team, Project Team
John Napier Bi-Weekly
Admin
Update to Core Team Core Team Mark Boggs Bi-Weekly
Scope change control Steering Committee, CORE Team, Project Team
Lori Mahood Immediately
Issues Project Manager ALL Immediately
Risks Project Manager ALL Immediately
ERCOT Activities AEP Corporate Trina Molnar As needed
16 16
Guiding Principles to Project Success
Guiding Principles to Project Success
1. Remember it is what is right, not who is right.
2. Candid feedback is always
helpful feedback.
3. Work and Communicate across teams when needed to make a process work effectively.
4. Each member is representing their entire organization (not just their group) and should take the ownership of gaining input from all applicable groups in that organization.
17 17
QuestionsQuestions
• Issues?
• Concerns?
• Comments?