american university of beirut - introduction quotation...  · web view2019-06-20 · if the...

22
Sealed Quotation NFSC-675861 Microplate Reader ا ت ري ت ش م ل ا رة ئ دا لProcurement and Contracts Administration

Upload: others

Post on 04-Feb-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

Sealed Quotation NFSC-675861 Microplate Reader

دائــــــــــرةالمشتريـــــــــا ت

و العقود

Procurement and Contracts

Administration

Page 2: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

Table of Contents

1. Introduction..............................................................................................................................31.1 Background..............................................................................................................................3

2. Provision for............................................................................................................................42.1 Specifications...........................................................................................................................4

3. Required Documents................................................................................................................54. Requirements Process..............................................................................................................6

4.1 Participation to Sealed Quotation............................................................................................64.2 Inquiries...................................................................................................................................6

4.3 Apology...................................................................................................................................64.4 Pricing......................................................................................................................................6

4.5 Payment...................................................................................................................................64.6 Submission Date and Time......................................................................................................6

4.7 Submission Address.................................................................................................................74.8 Confidentiality.........................................................................................................................7

4.9 Insufficient Data......................................................................................................................74.10 Sealed Quotation Award & Execution.....................................................................................7

4.11 Validity....................................................................................................................................74.12 Proposal Ownership.................................................................................................................8

4.13 Costs.........................................................................................................................................84.14 Liquidated Damages on late dEliveries...................................................................................8

4.15 Restrictions..............................................................................................................................84.16 Disclosure................................................................................................................................9

4.17 Governing Laws.......................................................................................................................9Appendix A Bill of quantity and price form.................................................................................. 10

Appendix B Bidder Contact Information and Proposal Checklist.....................................................13Appendix C Bidder TECHNICAL COMPLIANCE SHEET............................................................15

PLEASE USE THIS FORM AND INCLUDE IT IN YOUR OFFERType not hand writing

2

Page 3: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

1 INTRODUCTION

1.1 BACKGROUND

The American University of Beirut (hereinafter referred to as ‘AUB’ or the ‘University’) (http://www.aub.edu.lb) is a private, independent, educational not-for-profit corporation, founded in 1866, established under the laws of the State of New York, U.S.A., including a Campus and a Medical Center, in Beirut, Lebanon, and an office in the U.S.A., in New York (NY), U.S.A and is governed by an autonomous Board of Trustees.

AUB serves over 14,000 users. It consists of more than 6,000 faculty and staff, and has an enrolment of approximately 9,000 students, more than 1,200 of whom reside on Campus.

3

Page 4: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

2. PROVISION FOR AUB is requesting offers from qualified suppliers for the provision of the following :Fluorescence Microplate Readeras specified under Section 2.1.

2.1 Specifications

1. Microplate Reader Quantity = 1 each

System specifications- Description: Microplate reader for 96 and 384-well plates.- Wavelength Range: 200 to 1000 nm with 1nm steps; UV-Visible absorbance,

Fluorescence- Linearity: 96-well plate: 0-2.5 Abs- Accuracy: 1-2% Abs at 450nm- Incubator Temperature: +5° to 45°C- Measurement Speed:

- 5 to 10 seconds 96-well- 40 to 50 seconds 384-well

- Should be supplied with at least below filters:- for Absorbance (White light): 405-450-520-630-660 nm- for fluorescence: 450-480-520-550-600-660 nm- UV: 250/260-280 nm

- Plate shaking option is required- 3- Plate incubation is required

Power requirements- System should operate on 220-240 V, 50 Hz.

Installation and warranty:- Warranty: minimum 2 years full warranty, including parts and labor.- On-site installation and training should be carried by supplier/manufacturer certified

engineers/technicians.General conditions

- Should be supplied with user and service documentation.- Should be supplied with required tools, accessories and basic spare parts for proper

uninterrupted operation.- List all prices (for options/accessories/installation/training, etc.) should be itemized in

Appendix A.

4

Page 5: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

3 REQUIRED DOCUMENTS

All proposal documents should be provided in English and submitted with the following:

One (1) separate zipped folder with the following name:Sealed Quotation NFSC-675861 Microplate Reader - ORIGINAL (FINANCIAL) - Name of bidder Includes:

- AUB Price form with prices (Appendix A), (ORIGINAL) in MS Word- Bidder Contact Information Form and Proposal Check list (Appendix B).- Bidder Technical compliance Sheet (Appendix C) (ORIGINAL) in MS Word- Bidder Company offer form with prices, (ORIGINAL).- Technical brochures.

One (1) separate zipped folder with the following name:Sealed Quotation NFSC-675861 Microplate Reader - COPY (TECHNICAL) - Name of bidder

Includes:- AUB Price form, without prices, (Appendix A), (COPY) in MS Word- Bidder Contact Information Form and Proposal Check list (Appendix B).- Bidder Technical compliance Sheet (Appendix C) in MS Word- Bidder Company Offer form with out prices , (COPY).- Technical brochures.

NOTES The bidder’s offer must have a quote reference number. Offers must be submitted to the following email address: [email protected] ONLY Do not copy anyone on your offer sent by email. Inform Mr. George Sader by email ([email protected]) that you have already submitted

an offer.

Page 6: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

4 REQUIREMENTS PROCESS

4.1 PARTICIPATION TO SEALED QUOTATION

Suppliers willing to submit their offers should confirm by sending an Intent to Respond through an email to Mr. George Sader (Email [email protected] ) within 3 business days of receiving the Sealed Quotation.

4.2 INQUIRIES

Inquiries related to specific parts of this Sealed Quotation should be addressed to [email protected] .

4.3 APOLOGY

In case the requested services are not available, or you do not want to participate in this bid, you are kindly requested to respond by submitting a written apology to [email protected]. indicating the reason and the bid reference number.

4.4 PRICING

Please use Appendix A (Bill of Quantity and Price Form) for submitting your financial offers. Prices are to be quoted excluding VAT, and currencies used are only USD or LBP.

4.5 PAYMENT

AUB Standard Payment Terms for goods procured is 100% 45-60 days after delivery, installation and following the end user satisfaction written confirmation, and 100% 7 days for services rendered and following end user satisfaction written confirmation. Advance payments for large contracts are authorized on exceptional basis and after receipt of Bank letter of Guarantee in the same amount of the advance payment.

4.6 SUBMISSION DATE AND TIME

Offers must be submitted on or before:

Tuesday 09-July-2019 1:00 PM

In the event that AUB offices are officially closed on the date the proposals are due, the deadline for submission shall be automatically extended until the next business day.

6

Page 7: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

4.7 SUBMISSION ADDRESS

Offers must be submitted to the following address ONLY:

Offers must be submitted to the following email address: [email protected]

as indicated in section 3.

4.8 CONFIDENTIALITY

All information included in this Sealed Quotation are confidential and only for the recipient knowledge. No information included in this document or in discussions connected to it may be disclosed to any other party. AUB may require bidders to execute a Non-Disclosure Agreement before being provided with some or all of the information included in the tenders.

4.9 INSUFFICIENT DATA

It is the responsibility of the person submitting the proposal to ensure the completeness of the information submitted. Failure to do so may result in the elimination of the proposal from consideration.

4.10 SEALED QUOTATION AWARD & EXECUTION

AUB reserves the right to cancel the Sealed Quotation without giving the reasons, at any stage prior to the execution of the contract whether before or after the selection of the successful Supplier. AUB reserves the right to reject any proposal without giving the reasons for such rejection. Unless otherwise stipulated, the Sealed Quotation and proposal of the selected bidder will become part of any contract initiated by AUB. The contract form will be provided by AUB upon selection of the successful bidder. AUB will not incur any liability to any bidder as a result of using its rights hereunder or any other right provided for by law.

4.11 VALIDITY

Proposals submitted shall be valid for 6 months from the date of submission. Proposals will be treated as final and binding offers and may not be amended or withdrawn without the written permission of the University.

7

Page 8: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

4.12 PROPOSAL OWNERSHIP

All materials submitted in response to this Sealed Quotation shall become the property of AUB. Selection or rejection of a proposal does not affect such right.

4.13 COSTS

The University will not be liable for any costs incurred by Suppliers prior to issuance of or entering into a contract. Costs associated with developing the proposal, preparing for oral presentations, and any other expenses incurred by the Suppliers in responding to this Sealed Quotation are entirely the responsibility of the Supplier, and shall not be reimbursed in any manner by AUB.

4.14 LIQUIDATED DAMAGES ON LATE DELIVERIES

If the supplier fails to supply the specified goods/services within the lead time stipulated by its proposal, or within a period specified by an order or a contract, AUB shall, without prejudice to other remedies under the purchase order or contract, deduct from the purchase order or contract price, as liquidated damages, a sum equivalent to 1% of the delivered price of the delayed goods/services for each commenced week of delay until actual delivery, to a maximum deduction of 10% of the contract value.

4.15 RESTRICTIONS

The University will not be liable for any costs incurred by Suppliers prior to issuance of or entering into a contract. Costs associated with developing the proposal, preparing for oral presentations, and any other expenses incurred by the Suppliers in responding to this Sealed Quotation are entirely the responsibility of the Supplier, and shall not be reimbursed in any manner by AUB.

Individual foreign suppliers working in Lebanon need to provide a copy of work permit for non-Lebanese.

AUB is a tobacco free university; as such Tobacco companies and/or their subsidiaries are not allowed to participate in this Sealed Quotation. Contractors and/or suppliers should ensure that their workers and staff comply with AUB’s non-smoking policy while on site.

8

Page 9: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

4.16 DISCLOSURE

Supplier represents and certifies that the offer has not been knowingly disclosed directly or indirectly to any competitor or AUB staff or other Supplier before the opening of proposals by AUB. Supplier represents and certifies that the financial terms have been established independently without consultation, communication, or agreement for the purpose of restricting competition or any matter relating to such prices with any competitor or other Supplier. Supplier represents and certifies that no attempt has been made to induce any other company or person to submit or not to submit a proposal in response to this Sealed Quotation for the purpose of restricting competition.

4.17 GOVERNING LAWS

The laws of Lebanon shall govern the validity, interpretation, construction, performance, and implementation of this Sealed Quotation. Any dispute arising out of this Sealed Quotation shall be exclusively settled by the courts of Beirut, Lebanon.

Hanan Itani RamadanDirector of Procurement & Contracts Administration

9

Page 10: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

APPENDIX A BILL OF QUANTITY AND PRICE FORM - OPTION 1

PLEASE USE THIS FORM AND INCLUDE IT IN YOUR OFFER NOTE: PRICE SHOULD BE IN USD OR LBP AND EXCLUDING VAT

Type not hand writing

Item #

Item Description UOM QTY Brand Model Part No. Made In Unit Price Amount Currency(USD,LBP)

Delivery Date Warranty

1 Microplate Reader Each 12345678910

Total: USDVAT 11 % USDTOTAL: USD

Bidders my duplicate the above table in case of multiple alternatives and/or options. Change the title to OPTION 2, OPTION 3…

Page 11: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

Price list of Accessories and Upgrade options suggested by bidderItem Item Description UOM QTY Brand Model Part No. Unit Price Amount Currency

(USD,LBP)Delivery Date Warranty

1.11.21.3

2.12.22.3

Note: 1. Accessories and upgrades to be priced in the above table . Additional items to be listed on above sheet.2. Please type “Included” in the unit price cell, in case the accessory item is included in the main item.3. Please type “N/A” in the unit price cell, in case the accessory item is Not Available or Not Applicable within the main item.

11

Page 12: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

Please advise whether your offer complies with the below requirements Comply In case of additional costYes NO US$ exc. VAT

Minimum Two (2) years Warranty on parts and labor starting the day the equipment are handed over to AUB as operational and certified by AUB.

The warranty needs to come from the supplier in written form of an official letter, agreement, certificate, etc.; to be delivered to the end user with the equipment.

Installation and after-sales support starting the day the equipment handed over to AUB as operational.

The installation does not cover civil works. The installation covers: configuration, programming, testing and

commissioning. On-site installation and training should be carried by supplier/manufacturer

certified engineers/technicians Copies of operation and maintenance manuals should be supplied with the

equipment.

12

Page 13: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

APPENDIX BBIDDER CONTACT INFORMATION AND PROPOSAL CHECKLIST

Contact InformationSupplier/Individual Name: Company stamp:Prepared by:Supplier quotation Ref.:Date:Email:Supplier Website:Brand Website:Tel:Technical Support Hot Line: Signature:Technical Support Engineer

Name:

Conflict of InterestDo you or any of your employees have an affiliation with any of AUB/AUBMC faculty, staff or a member of their family?

[ ] Yes [ ] No

If yes, please identify the pertinent individual(s) and their relationship to you (or your employees) as a supplier.

Name Affiliation

I declare that I am not a tobacco company or a subsidiary of a tobacco company

Name Signature Date

Please fill the below if you are applying as an individualI declare that I am not a U.S. Green Card Holder (Resident Alien Status) or a U.S. Citizen. I declare that should I become a U.S. Green Card Holder (Resident Alien Status) or a U.S. Citizen, I will advise the University promptly of my change in status. I understand that if I do not do so, I will be responsible for paying all U.S. social security and Medicare taxes and U.S. income taxes, if any, attributable to the period between my change of status and my advising the University of such change of status. I agree to indemnify and hold the University harmless from any such taxes, interest, and penalty, and I further agree that the University may deduct the amount of such taxes, interest and penalty from my future compensation.

Name Signature Date

Page 14: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

I declare that I am a U.S Green Card Holder (Resident Alien Status)Name Social

SecurityDate of Issuance

Signature Date

I declare that I am a U.S Citizen

Name Social Security

Date of Citizenship

Signature Date

Proposal Checklist

- Have you submitted your signed proposal as indicated in Article 2 above?

- Have you submitted you proposal to the correct address?

- Did you ensure that your prices are in either USD or LBP?

- Have you updated your supplier application form during the past three years? If not,

please contact Procurement and Contracts Administration Department immediately.

- Did you provide valid proof of quality / accreditation for the machine?

- Did you provide List of customers’ references with contact information for the same

offered equipment?

14

Page 15: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

APPENDIX CBIDDER TECHNICAL COMPLIANCE SHEET

PLEASE USE THIS FORM AND INCLUDE IT IN YOUR OFFER

Type not hand writing

1. Microplate Reader

Bidder Name:Bidder Option No:

Brand:Model Name:

Part No:Made in:

Minimum required specs Comply (Yes/No)

Details

System specifications- Microplate reader for 96 and 384-well

plates.- Wavelength Range: 200 to 1000 nm with

1nm steps; UV-Visible absorbance, Fluorescence

- Linearity: 96-well plate: 0-2.5 Abs- Accuracy: 1-2% Abs at 450nm- Incubator Temperature: +5° to 45°C- Measurement Speed:

- 5 to 10 seconds 96-well- Measurement Speed:

- 40 to 50 seconds 384-well- Should be supplied with at least below

filters:- for Absorbance (White light): 405-450-520-630-660 nm- for fluorescence: 450-480-520-550-600-660 nm- UV: 250/260-280 nm

- Plate shaking option is required- 3- Plate incubation is required

Power requirements- System should operate on 3 Phases, 380 V,

50 Hz.Warranty and Installation:Warranty:

- A minimum of 2 years, including all parts and labor.

Installation:- On-site installation and training should be

carried by supplier/manufacturer certified engineers/technicians.

- System should be delivered with a full set of user and service manuals.

General conditions- Should be supplied with user and service

documentation.- Should be supplied with required tools,

15

Page 16: American University of Beirut - Introduction Quotation...  · Web view2019-06-20 · If the supplier fails to supply the specified goods/services within the lead time stipulated

accessories and basic spare parts for proper uninterrupted operation.

- List all prices (for options/accessories/installation/training, etc.) should be itemized in Appendix A.

Delivery as of PO confirmed date

Bidders my duplicate the above table in case of multiple alternatives and/or options. Change the Bidder Option No: 2, 3…

Please Type not hand writing

16