amir asphalt compactor trial #3 hwy. 28 contract … · ministry of transportation, ontario 1 amir...
TRANSCRIPT
Ministry of Transportation, Ontario
1
AMIR Asphalt Compactor Trial #3
Hwy. 28 Contract 2011-4007
Frank Pinder P.Eng Head, Quality Assurance Section
MTO, Operations Office, East Region
Ministry of Transportation, Ontario
2
Presentation Outline:
• Hwy. 28 Test Section Details• AMIR Roller - Pre-contract Preparation• Test Section Construction
• Steel Roller• AMIR - Observed Benefits• AMIR - Challenges
• Sampling and Testing Plan• Preliminary results
• Next Steps• Acknowledgements
Ministry of Transportation, Ontario
3
Cont: 2011-4007Hwy: 28Location:
Peterborough / Haliburton County Boundary N’ly to Haliburton / Hastings County Boundary
Constructed: September 13, 2012.
Contractor:
Test Section Details:
Ministry of Transportation, Ontario
4
SBL NBL
250m Control Section Normal Compaction Process
250m AMIR Test Section AMIR Asphalt Compactor
Test Section Layout• 250m long, both lanes;• placed end-to-end, same day
Project Features:• 40mm Superpave 12.5 Surface
over 60mm SP 19 over pulverized base;
• PGAC 58-40 Trial – highly polymer-modified;
• 0.5m single lift partial paved shoulders;
• Centerline joint construction observed.
Test Section Details:
Ministry of Transportation, Ontario
5
AMIR Roller – Pre-contract Preparation by
• Replaced damaged rubber belts;
• Cleaned fuel tank and purged fuel system;
• Added master “power- off” switch and replaced battery
• Welded a few cracks in frame
Ministry of Transportation, Ontario
6
AMIR Roller – Pre-contract Preparation by
Test on sand
Test on asphalt
Russ Perry, Highway Division Manager, operating AMIRChecking compaction
• conducted at Tomlinson’s asphalt plant in Ottawa;
• went well; confirmed AMIR was ready for the field trial
Ministry of Transportation, Ontario
7
Pre-construction Hwy. 28 – Sept. 13, 2012 Start:
• MTO staff from East Region and Central Region in attendance;
• Tailgate meeting with Contractor staff prior to start
Ministry of Transportation, Ontario
8
Steel Control Section:• Standard compaction equipment and operation; Steel vibratory, rubber tired and steel finish.
Steel vibratory break-down roller behind paver
Rubber-tired roller and steel finishing roller off in the distance
Ministry of Transportation, Ontario
9
Steel Control Section:
Open texture and cracks perpendicular to direction of roller
• appearance after steel roller;
Ministry of Transportation, Ontario
10
Steel Control Section:
Cracks still under the surface ?
steel + rubber
Rubber-tired roller improves surface appearance
Ministry of Transportation, Ontario
11
Steel Control to AMIR Test Section Transition:• Only the AMIR roller was allowed on test section
AMIR
steel
Hwy. 28 Looking south (west)
Ministry of Transportation, Ontario
12
• compaction evident; each roller pass was (visually) compressing the mat;
• Nuclear gauge consistently indicated low compaction, 90% +/- and even lower;
•expect core results to be good, based on similar experience from previous trials (93.1% ave. from Thousand Islands Parkway Trial)
AMIR – Observed Benefits: Excellent Compaction:
Ministry of Transportation, Ontario
13
Excellent Texture:
• after 1 roller pass, texture is tight;
• Mat has a uniform appearance in all directions;
AMIR – Observed Benefits:
Ministry of Transportation, Ontario
14
AMIR – Observed Benefits:
Neat Vertical Edges at Lane Edges:
• good compaction and minimal lateral shoving of asphalt at EP
Ministry of Transportation, Ontario
15
AMIR – Observed Benefits:
Lower permeability = Longer Life
Steel Roller AMIR Roller(cm/s X 1000) (cm/s X 1000)
Midlane 1.16 0.58 2.0Centerline Edges 6.20 1.53 4.1Outside Edges 3.42 1.31 2.6
Unrestrained Edges 3.90 1.19 3.3Ave. All 3.59 1.11 3.2
In‐situ Permeability Comparison
Sample LocationFactor of
Improvement
Ministry of Transportation, Ontario
16
AMIR - Potential Benefits:
Improved Smoothness?• No chatter from vibratory roller – TBD• Smoothness to be measured with high speed profiler
Ministry of Transportation, Ontario
17
AMIR - Potential Benefits:Centerline Joint Performance?• Improved due to lower permeability and higher compaction at lane edges?
Ministry of Transportation, Ontario
18
AMIR - Challenges:Roller Operation:• Tomlinson manager Russ Perry and mechanic Stewart Allan both operated the AMIR roller very effectively; with care and precision;
• improved result compared to previous trials !
Ministry of Transportation, Ontario
19
AMIR - Challenges:
Roller Marks:• Source of some
roller marks easily addressed?
Asphalt fines on scraper bar fall on surface
Low clearance of guide plate between main rollers shoves asphalt when turning
Ministry of Transportation, Ontario
20
AMIR - Challenges:
Roller Marks:
• Unusual visual appearance;
• Cosmetic or a performance problem? TBD
Some roller marks remain after final compaction
Ministry of Transportation, Ontario
21
AMIR - Challenges:
Roller Pick-up:
• Special PGAC 58-40 used in trial (very sticky);
• Excessive use of unapproved degreasing solution used to complete the trial;
• Better solution needed;
• Broader industry problem?
Ministry of Transportation, Ontario
22
Asphalt Core Sampling and Testing Plan:Random Core Sample Layout
(Duplicated for AMIR and Control Sections)
-4.0
-3.0
-2.0
-1.0
0.0
1.0
2.0
3.0
4.0
12875 12925 12975 13025 13075
Station (m)
Offs
et (m
)
SBL’s
NBL’s
- 30 150mm diametre cores taken from AMIR and Control Sections - Cores to be tested for compaction and indirect tensile strength
Ministry of Transportation, Ontario
23
In-situ Asphalt Permeability Testing Plan:
SBL’s
NBL’s
10 permeability tests conducted in each of the AMIR and Control Sections focused on lane edges and centreline of lanes
Random Permeability Test Locations
-4.0
-3.0
-2.0
-1.0
0.0
1.0
2.0
3.0
4.0
10000 10050 10100 10150 10200 10250
Station
Off
set f
rom
CL
Ministry of Transportation, Ontario
24
Next Steps:
• Complete testing and evaluate results of all 3 trial contracts;• Carleton to prepare report(s) and present to MTO and
broader technical community;• Carleton and MTO to monitor performance of trials;• Confirm and document the benefits to the AMIR
technology;• Consider opportunities for further study and
additional trials on MTO contracts;• Other?
Ministry of Transportation, Ontario
25
Acknowledgements:• Thanks to Tomlinson Group for supporting the AMIR trial on Hwy 28 and
accommodating the ministry’s scheduling requirements;• Especially Bert Hendriks, Russ Perry and Barry Kuiack
• Thanks to Tomlinson’s mechanics for providing exceptional service, completing repairs and upgrades on the AMIR in a timely manner which allowed the Hwy 28 trial to be completed on schedule, without any mechanical issues:
• Especially Stewart Allan and Al Conboy• Thanks to Tomlinson’s paving crew and field staff for the extra effort to
ensure a good job was done, • Especially Glen Pye and Bonnie Robertson
• Thanks to Russ Perry for operating the AMIR roller in expert fashion;• Thanks to MTO’s CA staff on the project, McIntosh Perry Ltd., for
coordinating the trial and providing excellent inspection services for MTO and Carleton University, especially Hotze DeWal and Dalton Peel
Without all these special efforts, this trial would not have been such a success.