1 bcsi 06 for information on: jobsite storage truss handling temporary bracing fall protection ...

Post on 16-Dec-2015

223 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

TRANSCRIPT

1

BCSI 06

For information on: Jobsite storage Truss handling Temporary bracing Fall protection Construction loading

2

ContentsB1 – Handling, Installation and

BracingB2 – Installation and BracingB3 – Web Bracing/ReinforcementB4 – Construction LoadingB5 – Damage, Modifications and ErrorsB6 – Gable End Frame BracingB7 – Parallel Chord TrussesB8 – Toe-nailing for UpliftB9 – Multi-Ply TrussesB10 – Post Frame TrussesB11 – Fall Protection

Development of BCSI

Engineers Manufacturers

Manufacturers Suppliers Contractors

4

BCSI Booklet Replaces…

HIB-91 Booklet

5

BCSI B-Series

6

BCSI B-Series Replaces...

HIB-91 Sheet

HIB-98 Poster

WTCA-B1 Warning Poster TTB WTCA-B2

B1 Guide for Handling,Installing & Bracing

Consequences of improper installation may be collapse of the structure

8

B1 Summary Sheet

HIB-91 Sheet

WTCA-B1 Warning Poster

9

B1 Banding Warning

10

B1 Handling

11

B1 Handling

12

B1 Storage

13

B1 Storage

14

B1 Hand Erection

15

B1 Hoisting

16

B1 Hoisting Recommendations

From BCSI Booklet

17

B1 Hoisting Recommendations

From BCSI Booklet

18

B1 Hoisting Recommendations

From BCSI Booklet

19

B1 Bracing Warning

20

B1 Ground Bracing

B1 Top Chord BracingSee

TCTLBTable

22

B1 Bottom Chord Bracing

23

B1 Web Plane Bracing

Lateral brace splicing

24

Look for “Truss Brace Splicing Methods” in the November SBC Magazine

25

B1 PCT Bracing

(PCT)(PCT)

26

B1 Diagonal Bracing

27

B1 Truss Installation

28

B1 Constructions Loads

29

B1 Construction Loads

30

B1 Alterations

31

B2 Truss Installation & Temporary Bracing

32

B2 Scope

From p.8:

33

B2 Scope

B2 Doesn’t Cover These3x2 or 4x2 Flat Trusses Trusses spaced > 2 ft. o.c.

From p. 8 From p. 8

34

B2 Warnings

B2 Top Chord Bracing

Ground bracing not shown Take special care with spans over 60 ft.

B2 Checklist

37

B2 Steps to Setting Trusses

B2 Step 2 - Ground Braces

B2 Step 3 - Set First Truss

B2 Step 4 - Next 4 Trusses

41

B2 Step 4 - TCTLB Options

42

B2 Note on Bracing Materials

43

B2 Step 5 - Top Chord Diagonals

44

B2 Step 5 - Top Chord Sheathing

45

B2 Step 6 – Web Bracing

46

B2 Step 6 – High End Trusses

47

B2 Step 7 – Bottom Chord Bracing

48

B2 Step 8 – Repeat Groups of 4

49

B2 Sheath Early and Often

50

B2 Alternate Installation Method

51

B2 Special Conditions

52

B3 Web Member Permanent Bracing/Web Reinforcement

B3 Compression Web Members

Unstable if unrestrained Check Design Drawing if restraint

req’d

54

B3 Bracing vs. Reinforcement

Bracing provides lateral support, reducing buckling length

Reinforcement increases cross-section, making web more stable

55

B3 Six Methods of Restraint

These items apply to all six methods:

56

B3 CLBs and Diagonals

57

B3 CLBs and Diagonals

58

B3 CLBs and Diagonals

59

B3 T-Reinforcement

60

B3 L-Reinforcement

61

B3 Scab Reinforcement

62

B3 Metal Reinforcement

63

B3 Stacked Webs

64

B3 Gable End Frame Bracing

65

B3 Gable End Frames Designed to

transfer vertical loads

But may also experience lateral loads Sheathing,

bracing and connections must be designed for this transfer

66

B3 Load Transfer Path

B3 Poorly Designed System

B3 Design Considerations Gable End Frame

Reinforcement prevents failure of individual vertical webs

Frame to End Wall

Correct connection prevents hinge joint

Bracing, blocking and diaphragm design creates safe load path

69

B3 Bracing and Blocking

70

B3 Bracing and Blocking

B3 Gable End Reinforcement

Horizontal reinforcement:

72

B3 Gable End Reinforcement

Individual L- or T-reinforcements

B3 Gable End Reinforcement

Scab reinforcements

74

B3 Building Designer Detail

B3 Building Designer Detail

B3 Avoid Hinge Joint

Balloon Framed End Wall

77

B3 Scissor Truss End Wall

78

B3 Avoid hinge points in walls!

Additional Note: This wall will not meet the prescriptive method criteria under IRC for a braced wall.

79

B4 Construction Loading

80

B4 Construction Loads

81

B4 Loading DOs and DON’Ts

82

B4 Loading DOs and DON’Ts

83

B4 Loading DOs and DON’Ts

84

B4 Loading DOs and DON’Ts

85

B4 Loading DOs and DON’Ts

86

B4 Loading DOs and DON’Ts

87

B4 Loading DOs and DON’Ts

B4 Loading DOs and DON’Ts

89

B5 Truss Damage, Modifications and Installation

Errors

B5 Truss Damages

91

B5 Steps for Repair

B5 Repair Techniques

93

B5 Report Damage

B5 Truss Repair Detail

B6 Section

B6 used to be on Gable end bracing that information has now moved to section B3.

B6 is intended to be used for additional topics in future additions of BCSI

95

96

B7 Parallel Chord Trusses

97

B7 Lumber Orientation

Guidelines for 3x2 or 4x2 only

For 2x_ orientationsee BCSI-B2

B7 PCT Bearing

99

B7 Temporary Bracing

100

B7 Stabilize Truss Ends Temporary Bracing or Permanent Blocking

101

B7 Correct Placement

102

B7 Truss Tags

B7 Strongback Bridging Helps limit deflection and/or

vibration

104

B7 Construction Loads on PCT

105

B8 Toe-Nailing for Uplift

106

B8 Uplift Forces

107

B8 Toe-Nailed Connections Are three toe-nails enough?

108

B8 1- Proper Toenail Installation

109

B8 2- Top Plate Lumber Grade and

species

110

B8 3- Type of Nails

0.162″ x 3.5″

B8 Is Toe-Nailing Enough? Toe-nail values must exceed expected uplift

For example:A 16d common ina Southern Pinetop plate offers72 pounds ofuplift resistance.

If there are threetoe-nails, the totaluplift resistanceIs 3x72=216 pounds

72

112

B8 Load Duration Factors

For wind uplift resistance use the factor of 1.6.Therefore, 216x1.6 = 346 pounds

113

B8 Alternatives to Toe-Nailing

Check published uplift capacities of mechanical connectors

114

R802.10.5 Truss to wall connection

Trusses shall be connected to wall plates by the use of approved connectors having a resistance to uplift of not less than 175 pounds (79.45 kg.) and shall be installed in accordance with the manufacturer's specifications. For roof assemblies subject to wind uplift pressures of 20 pounds per square foot (0.958 kN/m2) or greater, as established in Table R301.2(2), adjusted for height and exposure per Table R301.2(3), see section R802.11.

115

IRC R802.10.5 The code requirement was added in the IRC

2003 in a perhaps well-intentioned effort to address a perceived issue from the proponent's point of view. Now that it is in the code, it is proving difficult to

remove.  A number of code jurisdictions have amended the language

or struck the language out of their code adoption. The 175 lb value is unrelated to any real design parameters

or linked to any truss length. It arbitrarily discriminates against one well respected construction method. No specific evidence was or can be provided to justify this requirement.

116

IRC R802.10.5 TPI 1 requires that a Truss Design

Drawing include reaction forces and directions, which would include a value for uplift based upon the structure's design parameters for wind. There is no valid reason for not using this

calculated value in the consideration of the uplift connection requirements.

IRC R802.10.5 Much of the US is in the 90 mph basic wind speed

zone. The resistance for uplift, beyond the prescriptive fastening

requirements of Table R602.3(1) is really seldom an issue, especially for structures categorized as Exposure B and with a Mean Roof Height of less than 30 feet. IRC Table R301.2(2) is used to trigger the need for special

connection requirements per Table R802.11. Only high wind speed areas, highly exposed structures or extremely tall structures ever qualify for the special requirements. When the calculated uplift requires a connection of a specific value, WTCA supports providing resistance in a manner acceptable to the EOR or building code official, not based upon an arbitrary requirement.

118

B9 Multi-ply Girders

B9 Girders Designed to carry extra loads Max. 6 plies, fastened together to act as one

4-ply 5-ply

120

B9 Fastener Schedule Specified on

Truss Design Drawing

SAMPLE

121

B9 Nail Fasteners Fasteners using nails only are

specified on girders with three plies or less

122

B9 Screw Fasteners Special screws on up to four plies

123

B9 Screw Fasteners Screws on 2-ply 3x or 4x2 floor-type

trusses

124

B9 Bolt Fasteners Bolts on 4 to 6 plies In addition, nails may also be required

125

B9 Good Installation Practices

Fasten plies together before lifting, if possible

126

B10 Post Frame Trusses

HIB-98 Poster

B10 Post Frame Trusses Part of an engineered building system Spaced at 4′ to 12′ o.c. Heels attached to posts fixed in ground or

slab Purlins attached directly to truss top chords

B10 Truss Storage

129

B10 Installation

130

B10 Installation

131

B10 1- Ensure Stable Columns

132

B10 2- Stable Base Unit

133

B10 3- Bracing of Base Unit Top Chord

A professional engineer should design a bracing plan for truss spans over 60’ per BCSI Fig.B2-13

134

B10 3- Bracing of Base Unit Bottom Chord

135

B10 3- Bracing of Base Unit In the Roof Plane

- or -

136

B10 3- Bracing of Base Unit In the Web Plane

137

B11 Fall Protection & Trusses

138

B11 Fall Protection Warning

Trusses alone are notdesigned to supportfall protection anchors

B11 Impact Loads A falling worker could cause the

trusses to collapse in a domino effect

140

B11 Safer Options

Option 1: Scaffolding

141

B11 Safer Options

Option 1: Roof Peak Anchor

142

B11 Safer Options

Option 1: Ground Assembly

143

Jobsite Safety Package B1 through B4 Handling Checklist

144

Truss Tags

145Questions on BCSI?Questions on BCSI?

top related