1s. virostek - lbnl spectrometer solenoid fabrication update vendor still expecting to complete...
Post on 21-Dec-2015
213 Views
Preview:
TRANSCRIPT
1S. Virostek - LBNL
Spectrometer Solenoid Fabrication Update
•Vendor still expecting to complete first magnet by the end of November, before X-mas more likely•Cold mass for the first magnet to be completed by the end of Sept., final magnet assy to begin soon•Fabrication of parts for the thermal shields and vacuum vessels is complete, parts are @ vendor •Assembly of the vacuum vessels and fabrication of the support stands are under way•Overall winding of 2nd magnet now ~70% complete•All cold mass supp’ts complete, 300 A supplies in•Apparatus for cooler tests under construction
2S. Virostek - LBNL
Winding progress of 2nd spectrometer solenoid magnet
9/11/07
3S. Virostek - LBNL
Nearly completed cold mass for first spectrometer solenoid magnet
9/11/07
4S. Virostek - LBNL
Internal wiring of first spectrometer solenoid magnet
9/11/07
5S. Virostek - LBNL
Vacuum vessel warm bore tubes
9/11/07
6S. Virostek - LBNL
300 A power supply and controller
9/11/07
top related