8th, december 2006 1TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
PFC Thermal test program:
TPL sector dismantling (Q6A)
8th, december 2006 2TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
PFC program consists of 2 phases :
Phase A- selection of the spared TPL elements• technique • test process• manpower, cost
Phase B- Cartography of TPL sector• technique• test process• manpower, cost
TPL sector dismantling project
8th, december 2006 3TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
- Phase A - Select the best spared PFC by means of the SATIR
test bed upgraded
Output:Selection of spared TPL elements (best-adapted
component)
Manpower : 2 pers.
Experimental : 5 days
Exp. criteria definition : 3 d
Analyse/report : 3 d
8th, december 2006 4TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
(SATIR : French acronym for Infra Red Acquisition and Data Processing device)
SATIR facility principle
Its principle is based on the comparison of the surface temperature evolution of the inspected component with that of a “defect-free” reference one. The armour surface temperature is observed by means of a digital infrared camera.
Low heat transfer capability is detected by a slower temperature surface response
Output of the SATIR NDE : Cartography of quantitative criteria DTref is obtained
heat flux
Heatpath
control
Thermal transient method
time (sec.)
0
2
4
6
8
10
0 2 4 6 8 10
Difference (Ref. – Contr. Zone)
Criteria DT_ref_max (°C)
0
20
40
60
80
100
0 2 4 6 8 10
Evol. Tsurf. (°C)
Reference
Controlled (TCR)
Transient monitoring
time (sec.)
Reference.
Controlled zone
8th, december 2006 5TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA SATIR control (spared elements)
PFC Program A1) Analyse the former SATIR control results (v.2001)
2) Infrared thermography tests of 23 spared elements 3) Selection of the TPL elements versus flux deposition pattern4) Inspection report
8th, december 2006 6TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
- Phase B- Confirm the cartography of TPL sector by means of the LOCKIN Thermography
Output:1) Erosion / Deposition areas definition
2) Location of damaged tile
Manpower : 2 pers.Experimental : 0.5 day
Analyse : 5 daysSupplying : lamps (1KE)
8th, december 2006 7TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
LOCKIN technique and the in situ device
The LOCKIN is a method based on propagation in the CFC tiles of modulated thermal waves imposed at the surface of element.
Cartography of Q6A TPL sector
Magnitude and phase-shift of surface temperature vary in case of
thermal properties variation
Time (s)
Sinusoidalthermal
stimulation
CopperCFCFlux (W)
Time (s)Flaw
IR detectorHalogen lamps
Mechanical device
8th, december 2006 8TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA Cartography of Q6A TPL sector
phase-shift (TCR)
20° periodicity
Magnitude ()
Dotted lines = max deposit areas, dashed lines = erosion areaResults realised during the last campaign: feb. 2006
PFC Program B
(Use of the same device)
1- Confirm the damaged element (phase-shift) and the erosion / deposit zone (magnitude) by means of LOCKIN
2- SATIR test on damaged element (protect the test zone)
3- Validation : Cutting and metallurgical analyse
Damaged tile ?
8th, december 2006 9TPL Dismantling Project – alain.durocher@cea.fr
TORE SUPRAAssociationEURATOM-CEA
Added remarks for phase B:
TPL elements
• Plansee can repair 4 tiles (max) per element = possibility to repair the removed elements (used for analysis of D content).
• Observation of the chemical state of the channel (oxidation layer?) = protection against oxidation after the dismantling of sector (under Ar, N2)
Cartography of Q6A TPL sector