Site Survey 1.Dealer will verify the lead and gather more details about the property 2.Dealer schedules and performs a Site Survey 3.Dealer changes the sales stage to: BOM Design review Required fields: Estimated Property Launch Date, Site Survey Completion Date SLA: 90 days 3 Site SurveyBOM DesignProperty Valuation Sales & Marketing Plan Required Sales & Marketing Plan Review ROE & Property Registration ROE Review LegalBuild OutInspection RequestInspection CompleteClosed/Won

TRANSCRIPT

About Salesforce.com OpportunityStages and OwnersKnow Who has the Ball

1

Overview of MDU Sales Stages

2

Order Stage Owner SLA (days) Main Owner Action(s)

1 Site Survey Dealer 90 Upload Site Survey

2 BOM Design Field Ops 3 Upload BOM & system design

3 Property Valuation Sales Ops 5 Classify property

4 Sales & Marketing Plan Required* Dealer 90 Upload Sales & Marketing Plan

5 Sales & Marketing Plan Review* Sales 3 Approve Sales & Marketing Plan

6 ROE & Property Registration Dealer 90 Negotiate ROE

7 ROE Review Legal Legal 9 Review ROE

8 Build Out Dealer 90 Build out property

9 Inspection Request Field Ops 5Determine if inspection is needed; 45 day SLA if inspection is needed

10 Inspection Complete Dealer 30 Launch property & create PID

11 Closed/Won

*This stage only applicable to DTH properties that have been classified as Red

Site Survey

1. Dealer will verify the lead and gather more details about the property

2. Dealer schedules and performs a Site Survey3. Dealer changes the sales stage to:

BOM Design review

Required fields: Estimated Property Launch Date, Site Survey Completion DateSLA: 90 days

3

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

4

Site Survey

BOM Design Review

1. Field Ops reviews Site Survey information2. If design is rejected, reasons will be provided

and Field Ops will move the sales stage back to Site Survey

3. If design is accepted, Field Ops will move the sales stage to Property Valuation

SLA: 3 days

5

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

BOM Design Review Update

• Due to feedback from our valued partners, we have determined to adjust the opportunity sales stage process. The BOM Design Review sales stage will be required after “Property Valuation.” The systemic change is slated for a Q3 2014 release.

• Until the change has been made systemically, BOM Design Review paperwork requirements will be required at the Inspection Request stage instead of BOM Design Review.

6

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

7

BOM Design

Rejected BOM Design

Approved BOM Design

Property Valuation

1. Sales Ops reviews property and classifies as Green, Yellow or Red

2. Sales Ops moves the sales stage to the next stepa. DTH & Red = Sales & Marketing Plan Requiredb. Not DTH & Red = ROE & Property Registration

SLA: 5 days

8

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

9

Property Valuation

Sales & Marketing Plan Required

1. Dealer completes provided Sales & Marketing Plan form

2. Dealer uploads Sales & Marketing Plan to SFDC

3. Dealer moves sales stage to: Sales & Marketing Plan Review

SLA: 14 days

10

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

11

Sales & Marketing Plan Required

Edit Mode

12

Attaching a File

Attach File

Uploading Documents

Required Field

Sales & Marketing Plan Review

1. The MDU Sales Team will review Sales & Marketing Plan

2. If approved, stage is moved to ROE & Property Registration

3. If rejected, the stage is moved back to: Sales & Marketing Plan Requireda. Rejected sales plans will show a reject reason

4. Dealer may close the opportunity or resubmit a Sales & Marketing Plan

SLA: 5 days

13

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

14

Sales & Marketing Plan Required

Approved Sales & Marketing Plan Rejected Sales & Marketing Plan

ROE & Property Registration

1. Dealer negotiates ROE with property. 2. At this stage, dealer may submit a draft

ROE to Legal for pre-approval3. Once final ROE has been executed,

dealer uploads ROE to SFDC and changes Sales Stage to ROE Review Legal

SLA: 90 daysFields Required: ROE expected close date, Counter-sign date, ROE term (years)

15

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

16

ROE & Property Registration

ROE Review Legal

1. Legal team reviews ROE for required content

2. Accepted, executed ROEs are noted and the sales stage is moved to Build Out

3. Rejected or draft ROEs are noted and the sales stage is moved to ROE & Property Registration

4. Legal team will upload review sheet for both approved and rejected ROEs

SLA: 9 days

17

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

18

ROE Review Legal

Pre-Approved ROERejected ROE

Approved ROE

Build Out

1. Once ROE is approved, dealer may begin system build out.

2. Dealer collects required paperwork, including Rep & Warranty and BOM documents.

3. Dealer uploads Rep & Warranty form, BOM. Dealer must check the “Rep & Warranty doc” box.

4. Dealer moves sales stage to Inspection Request.

SLA: 90 days

19

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

20

Build Out Required Documents

Site Survey (optional) Materials

Technical SpecificationsRep & Warranty

21

Build Out

Rep & Warranty Uploaded

Attach Rep & Warranty Document & BOM Design

Rep & Warranty not Uploaded

Inspection Request

1. Field Ops reviews Rep & Warranty and BOM.

2. If inspection is required, SLA changes to 45 days

3. Once the Inspection has been approved or waived, Field Ops will move the sales stage to Inspection Complete

SLA: 5 days to determine if inspection is required

22

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

23

Inspection Request

Inspection Complete

1. Once the inspection is complete, dealer has green light to create the property and request a PID

2. Dealer completes additional paperwork required for property launch (including bulk BMU creation, etc.).

3. Once property has been created, dealer moves sales stage to Closed/Won.

SLA: 30 daysRequired fields: PID Number

24

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

25

Inspection Complete

Edit Mode

Closed/Won

1. Property is fully launched2. Opportunity is closed

26

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Won

27

Closed/Won

Closed/Lost

1. Used for Opportunities that are rejected2. Reasons may include

1. BOM does not make sense2. Can’t close the deal

3. Opportunity will automatically change to Closed/Lost if the sales stage has not been moved to ROE Review Legal within the 365 day SLA

28

Site Survey

BOM Design

Property Valuation

Sales & Marketing Plan Required

Sales & Marketing Plan Review

ROE & Property Registration

ROE Review Legal

Build Out

Inspection Request

Inspection Complete

Closed/Lost

29

Closed/Lost

top related