ANADARKO PETROLEUM CORPORATIOn
ANADARKO PETROLEUM CORPORATION
– 2 –
LUCIUS PROJECTHIGHLIGHTS
Lucius – Lighting the Way to a bright future• Dec. 10, 2009 Discovery
• Jan. 27, 2010 Successful Appraisal well
• May 28, 2011 Successful Flow Test Confirmed Deliverability
• Dec. 15, 2011 Project Sanction
• July 2, 2012 signed Carried-Interest Agreement
• May 26, 2013 80,000 BOPD Spar Arrives in the gulf of mexico
• Jan 16, 2015 First Production
• 400+ MMBOE resource
• World-class reservoir quality and deliverability
• Anchor project in active area
• established $2.8 billion of market value
• ~3 Years from sanction to first oil
At work or away from the job site, Anadarko’s Gulf of Mexico operations team views safety as a top priority. Anadarko employees and contractors promote a culture of safety by following the LiveSAFE program.
KEATHLEY CANYON 875
WWW.ANADARKO.COM
– 3 –
LUCIUS TRUSS SPAR
CAPACITY
80,000 bopd450 mmcf/d
spar diameter
110 feet
spar length
605 feet
hull weight
23,000 tons
water depth
7,100 feet
history of the LUCIUS NAME
Lucius means “Light” in Latin, and the field was named after an Heir to the Roman throne.
LARGEST SPAR BUILT TO DATE BY ANADARKO
TRUSS SECTION
KEEL TANKOIL & GAS EXPORT LINES
HEAVE PLATE
HARD TANK
LIVING QUARTERS
STRAKE
MOORING FAIRLEAD
MOORING LINE
SPAR CHAIN
CHAIN JACKS
CELLAR DECK
PRODUCTION DECK
MAIN DECK
SUB CELLAR DECK
TOPSIDESSPAR HULL
ANADARKO PETROLEUM CORPORATION
– 4 –
SUBSEA ARCHITECTURE
LUCIUS PARTNERS• Anadarko* 48.951%
• ExxonMobil 23.295%
• Petrobras 11.500%
• INPEX 7.753%
• Eni 8.500%
* Operator
KEATHLEY CANYON 875
UMBILICALS
FLOWLINE
EXPORT
1
5
7
2
3
4
6
6
1 5 6
7
2
3
4
PLEM PR#2 PLEM PR#3 KC 919 WELL #3 KC 919 WELL #4
PLEM PR #4
KC 875 WELL #1
KC 875 WEST MANIFOLD
KC 875 EAST MANIFOLD
Subsea TiebackAnadarko WI BlockOil FieldSubsea Tieback
WWW.ANADARKO.COM
– 5 –
hull constructionPORI, FINLAND
ANADARKO PETROLEUM CORPORATION
– 6 –
Voyage from finland to texasAPRIL 30, 2013 TO MAY 26, 2013
MIGHTY SERVANT I OFF LOAD IN INGLESIDE, TX
WWW.ANADARKO.COM
– 7 –
ROUTE FROM PORI, FINLAND TO INGLESIDE, TEXAS
PoriApril 30, 2013
InglesideMay 26, 2013
ANADARKO PETROLEUM CORPORATION
– 8 –
suction anchor installationAPRIL 2013
WWW.ANADARKO.COM
– 9 –
BALDER
ANADARKO PETROLEUM CORPORATION
– 10 –
deep water INSTALLATION VESSELS
DEEP BLUE
EXPORT RISER FABRICATION AND REELING
IRON HORSE
JUMPER INSTALLATION
THIALF
TOPSIDE INSTALLATION
CASTORONE
20" GAS EXPORT INSTALLATION
EXPORT PIPELINE
BUILT IN HOUSTON, TX
SUBSEA TREE
MANIFOLD
HULL
TOPSIDE
MOORING LINES
CHAIN
SUCTION PILES AT SEA BOTTOM
MANIFOLD
FLOWLINES
JUMPER
WWW.ANADARKO.COM
– 11 –
ORION
MOORING COMMISSIONING
AEGIR
RISERS AND FLOWLINES INSTALLATION
DEEP ENERGY
UMBILICAL INSTALLATION
BALDER
HULL AND MOORING INSTALLATION
MOORING CHAIN
BUILT IN SPAINBUILT IN PORTUGAL
POLYESTER MOORING ROPES
SOLITAIRE
18" OIL EXPORT PIPELINE INSTALLATION
MOORING LINES
CHAIN
BUILT IN PORT OF W. ST. MARY, LA
SUCTION PILEUMBILICAL LINE
MANIFOLD
SUBSEA TREE
ANADARKO PETROLEUM CORPORATION
– 12 –
THIALF EDDA FIDES~350 PEOPLE REQUIRED FOR HOOK-UP & COMMISSIONING
FLARE
EAST COMPRESSOR MODULE
WEST COMPRESSOR MODULE
WEST CRANE
NORTH STAIR TOWER
COMPRESSOR MODULE
BUILT IN HOUMA, LA
ACCOMMODATION VESSELHEAVY LIFT VESSEL
LIVING QUARTERS
BUILT IN ORANGE, TX
topsides
WEST STAIR TOWER
4
5
6
7
8
9
NOTE: NUMBERS DO NOT REPRESENT THE ORDER OF INSTALLATION LIFTS
WWW.ANADARKO.COM
– 13 –
MOTOR CONTROL CENTER LIFT ONTO PRODUCTION DECK
EAST COMPRESSOR MODULE
LIVING QUARTERS
MAIN MODULE DECK STRUCTURE
TEMPORARY WORK DECK
SUB CELLAR MODULE
TEMPORARY WORK DECK
SUB CELLAR MODULE
STAIR TOWER FABRICATION
MAIN MODULE DECK STRUCTURE
BUILT IN INGLESIDE, TX
}
9 INSTALLATION LIFTS
1
2
3
ANADARKO PETROLEUM CORPORATION
– 14 –
18" OIL EXPORT PIPELINE
AUDACIA INSTALLING OIL EXPORT PLET IN KEATHLEY CANYON 831
lucius oil export
WWW.ANADARKO.COM
– 15 –
OIL EXPORT INSTALLATIONS• 100 miles of new pipeline installed
• ~50 miles of existing pipeline reused (Retired Red Hawk Export Line)
• South Marsh Island (SMI) - 205 Platform Additions to Increase Capacity
GALVESTON
PORT FOURCHON
GARDEN BANKS GREEN CANYON
KEATHLEY CANYON WALKER RIDGE
KC 875
TEXASLOUISIANA
SOUTH MARSH ISLAND 205 PLATFORM
TO CLOVELLY
TO ST. JAMES
ANADARKO PETROLEUM CORPORATION
– 16 –
CASTORONE BERTHED AT GALVESTON
20" GAS EXPORT PIPELINElucius gas export
WWW.ANADARKO.COM
– 17 –
GAS EXPORT INSTALLATIONS• 230 miles of pipeline to be installed
GALVESTON
PORT FOURCHON
GARDEN BANKS GREEN CANYON
KEATHLEY CANYON WALKER RIDGE
SOUTH TIMBALIER 283 JUNCTION PLATFORM
LAROSE GAS PROCESSING PLANT
KC 875
TEXASLOUISIANA
ANADARKO PETROLEUM CORPORATION
– 18 –
LUCIUS: PATH TO FIRST OIL
2012 - 2014
• 18" OIL EXPORT LINE INSTALLATION
• HULL SAIL-AWAY TO GULF OF MEXICO
• INSTALL HULL, FLOW LINES, RISERS, UMBILICALS
• LOAD-OUT AND INSTALL TOPSIDES
• HOOK-UP AND COMMISSIONING
• CONCLUDE INITIAL DRILLING AND COMPLETIONS
JANUARY 2015
• ACHIEVED FIRST OIL
DEVE
LOPM
ENT D
RILL
ING
AND
WEL
L COM
PLET
IONS
WWW.ANADARKO.COM
– 19 –
design one, build two.
LUCIUS: 80,000 BOPD
HEIDELBERG: 80,000 BOPD
FIRST OIL 2015 FIRST OIL 2016
REGARDING FORWARD-LOOKING STATEMENTS AND OTHER MATTERS
This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Anadarko believes that its expectations are based on reasonable assumptions. No assurance, however, can be given that such expectations will prove to have been correct. A number of factors could cause actual results to differ materially from the projections, anticipated results or other expectations expressed in this presentation, including Anadarko’s ability to meet financial and operating guidance; to achieve its production targets, successfully manage its capital expenditures and complete, test and commercially operate the wells and prospects identified in this presentation; and to achieve its production and budget expectations on its mega projects. See “Risk Factors” in the company’s 2012 Annual Report on Form 10-K, Quarterly Reports on Form 10-Q and other public filings and press releases. Anadarko undertakes no obligation to publicly update or revise any forward-looking statements.
Cautionary Note to U.S. Investors: The United States Securities and Exchange Commission (“SEC”) permits oil and gas companies, in their filings with the SEC, to disclose only proved, probable and possible reserves that meet the SEC’s definitions for such terms. Anadarko uses certain terms in this news release, such as “resources,” and similar terms that the SEC’s guidelines strictly prohibit Anadarko from including in filings with the SEC. U.S. investors are urged to consider closely the disclosure in Anadarko’s Form 10-K for the year ended Dec. 31, 2012, File No. 001-08968, available from Anadarko at www.anadarko.com or by writing Anadarko at: Anadarko Petroleum Corporation, 1201 Lake Robbins Drive, The Woodlands, Texas 77380, Attn: Investor Relations. This form may also be obtained by contacting the SEC at 1-800-SEC-0330.
1201 LAKE ROBBINS DRIVE | THE WOODLANDS, TEXAS 77380
1.832.636.1000 | WWW.ANADARKO.COM | NYSE: APC
FOLLOW US ON WWW.YOUTUBE.COM/ANADARKOTV
LIKE US ON WWW.FACEBOOK/ANADARKOPETROLEUMCORPORATION
top related