appendix h pipeline route selection...volume 1: project description appendix h: pipeline route...
Post on 27-Jun-2020
6 Views
Preview:
TRANSCRIPT
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010
Appendix H Pipeline Route Selection
Appendix H: Pipeline Route Selection Quest Carbon Capture and Storage Project
Volume 1: Project Description
November 2010 Shell Canada Limited
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010 Page H-i
Table of Contents
Appendix H Pipeline Route Selection H.1 Pipeline Route Selection Criteria .................................................................................... H-1 H.2 Route Options Considered .............................................................................................. H-1
H.2.1 Initial Five Route Options ................................................................................... H-1 H.2.2 Final Route Selection .......................................................................................... H-3
H.3 Re-Routes to Selected Route .......................................................................................... H-5 H.3.1 Well Location Adjustments ................................................................................ H-5 H.3.2 Pipeline Length Optimized ................................................................................. H-5 H.3.3 North Saskatchewan River Re-Route ................................................................. H-5 H.3.4 Northwest of Bruderheim Natural Area Re-route ............................................... H-5
List of Tables
Table H-1 Pipeline Route Selection Criteria ........................................................................ H-1 Table H-2 Pipeline Route Selection Criteria ........................................................................ H-3
List of Figures
Figure H-1 Original Route Options ....................................................................................... H-2 Figure H-2 Re-Routes to Final Route .................................................................................... H-4
Appendix H: Pipeline Route Selection Quest Carbon Capture and Storage Project
Volume 1: Project Description
November 2010 Shell Canada Limited Page H-ii
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010 Page H-iii
Acronyms
AOSPL ....................................................................................... Alberta Oil Sands Pipeline HDD ....................................................................................... horizontal directional drilling
Appendix H: Pipeline Route Selection Quest Carbon Capture and Storage Project
Volume 1: Project Description
November 2010 Shell Canada Limited Page H-iv
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010 Page H-1
H.1 Pipeline Route Selection Criteria The route selection for the pipeline involved careful review and consideration of selected criteria to determine preferred and optional routing (see Table H-1).
Table H-1 Pipeline Route Selection Criteria Criteria Considerations
Health and safety • limiting the number of infrastructure crossings • limiting the potential for line strikes
Environment • limiting pipeline and tie-in length • using existing corridors where possible • limiting the number of watercourse and wetland crossings • crossing waterbodies at appropriate locations and during appropriate timing windows,
where feasible • avoiding the Northwest of Bruderheim Natural Area
Regulatory and landowner access requirements
• responding to public and landowner input on route • coordinating with existing and planned land use along the proposed route • avoiding potential future development possibilities
Cost • limiting pipeline and tie-in length • limiting construction costs by avoiding identified obstacles and locations with additional
construction challenges
H.2 Route Options Considered
H.2.1 Initial Five Route Options Prior to public disclosure, five pipeline routes were identified for further study (see Figure H-1). These routes generally paralleled existing corridors and were identified, west to east, as the Access, Enhance, Suncor Oil Sands Pipeline, Enbridge Waupisoo and Alberta Oil Sands Pipeline (AOSPL) routes.
All five route options began at the Scotford Upgrader and ended north of the village of Thorhild, at the CO2 storage area. The number and location of injection wells had yet to be determined when these five route options underwent a review based on available information. Therefore, two potential endpoints were considered in the routing selection.
Endpoint 1 (03-059-20 W4M) was the meeting point for the four more westerly routes (Access, Enhance, Suncor and Enbridge), all of which then followed the same route proceeding northeast to Endpoint 2 (09-060-19 W4M). The most easterly route, AOSPL, bypassed Endpoint 1, terminating north at Endpoint 2.
All five route options had the potential for further commercial options and phased capital expansion, through the use of the CO2 pipeline for enhanced oil recovery in the Redwater Reef.
The Suncor route was removed from consideration because the Suncor pipeline corridor is highly congested, requiring multiple line crossings and increasing the potential for a line strike. Additionally, this route passes directly through the Hamlet of Radway and the Redwater Natural Area, which would potentially increase environmental effects, as well as increasing regulatory requirements and emergency response planning.
BCSK
AB
FIGURE NO.
H-1
Areaof
Interest
PREPARED FOR
Last
Mod
ified
: Nov
09,
201
0 B
y: a
olso
nQUEST CARBON CAPTURE AND STORAGE PROJECT
Acknowledgements: Original Drawing by StantecPipeline: Sunstone Engineering August 11, 2010, Wells: Shell August 26, 2010, Basedata: National Road Network, Canvec, Altalis. Pipelines: Shell Canada
PREPARED BY
Original Route Options
RGE 23 RGE 22 RGE 21 RGE 20 RGE 19 RGE 18W4M
TWP 61
TWP 60
TWP 59
TWP 58
TWP 57
TWP 56
Smoky Lake
RGE 24
E 25
TWP 55
831
18
661
63
Endpoint 1
Endpoint 2
Lamont
Warspite
Egremont Radway
Opal
Star
Thorhild
Abee
Newbrook
Tawatinaw
Rochester
Namao
JosephburgFortSaskatchewan
Bon Accord
Gibbons
Bruderheim
Redwater
Redwater River
Sturg
eon
River
Beaverhill Creek
North Saskatchewan River
16
15
45
29
28829
825
28A
28
651
830
15
37
830
15
827
WP 10-6
WP 8-19
WP 7-11
WP 15-29
WP 12-14
Elk IslandNational Park
North BruderheimNatural Area
RedwaterNatural Area
Northwest of BruderheimNatural Area
TawatinawNatural Area
345000
345000
365000
365000
385000
385000
5965
000
5965
000
5985
000
5985
000
6005
000
6005
000
6025
000
6025
000
123510425-123 REVD
4 0 4 8
Kilometres
Endpoint
Route Options
Access Pipeline
AOSPL
Enbridge Waupisoo Pipeline
Enhance Pipeline
Suncor Pipeline
Injection Well
Pipeline Route
Shell Scotford
Major Road
Railway
Watercourse
Waterbody
Protected Area
Urban Area
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010 Page H-3
The Access and Enhance routes are similar, following the same route from the Redwater River north to Endpoint 1. However, the Access route is shorter and more direct between the Scotford Upgrader and the Redwater River. Therefore the Access route was chosen.
The AOSPL route closely follows the Enbridge Waupisoo route until diverging at the town of Bruderheim. The Enbridge Waupisoo route was preferred, because the AOSPL route bypasses Endpoint 1 and would not be able to access any potential injection well sites between Endpoint 1 and Endpoint 2.
The Enbridge Waupisoo (east) and Access (west) routes remained as the preferred options.
H.2.2 Final Route Selection The east (Enbridge) and west (Access) routes were compared using route selection criteria (see Table H-2). Based on these criteria, the east (Enbridge) route was chosen.
Table H-2 Pipeline Route Selection Criteria Criteria East Route West Route Comments
Health and safety Preferred Not preferred • West route requires greater number of pipeline crossings in the Redwater Reef, with increased chance of a line strike
Environment Preferred Not preferred • East route has fewer watercourse crossings
• West route has challenging soil conditions at the Redwater and North Saskatchewan River crossing locations
• East route passes through Northwest of Bruderheim Natural Area
Regulatory and landowner access requirements
Preferred Not preferred • East route has more established community relations
Cost Both options viable • East route estimated at $70 million • West route estimated at $66 million
Schedule Both options viable
The east (Enbridge) route was selected as the preferred route because it avoids the congested Redwater Reef area, and encounters more favourable geotechnical conditions at the North Saskatchewan River crossing location. The initial 10 km of the east (Enbridge) route passes through an area where Shell had existing community relations with landowners. However, the east (Enbridge) route originally passed through the Northwest of Bruderheim Natural Area.
The preferred route is east from Shell Scotford, before turning north to parallel the Enbridge Waupisoo pipeline. After crossing the North Saskatchewan River, the preferred route goes north for approximately 10 km before proceeding northwest to the CO2 storage area (see Figure H-2).
BC SKAB
FIGURE NO.
H-2
Areaof
Interest
PREPARED FOR
Last
Mod
ified
: Nov
. 9, 2
010
By:
aol
sonQUEST CARBON CAPTURE AND STORAGE PROJECT
Acknowledgements: Original Drawing by StantecPipeline: Sunstone Engineering August 11, 2010, Original Route: April 7, 2010, Reroutes: August 11, 2010 Wells: Shell August 26, 2010, Basedata: National Road Network, Canvec, Altalis
PREPARED BY
Re-Routes to Final Route
FortSaskatchewan
RGE 23 RGE 22 RGE 21 RGE 20 RGE 19 RGE 18W4M
RGE 17
TWP 61
TWP 60
TWP 59
TWP 58
TWP 57
TWP 56
Smoky Lake
Bon Accord
Gibbons
Redwater
Bruderheim
RGE 24
TWP 55
831
18
661
63
Lamont
Warspite
Egremont Radway
Opal
Star
Thorhild
Abee
Newbrook
Tawatinaw
Rochester
Redwater River
Sturg
eon
River
Beaverhill Creek
North Saskatchewan River
15
45
29
28829
Josephburg
Namao
825
28A
28
651
830
15
37
830
15
827
WP 10-6
WP 8-19
WP 7-11
WP 15-29
WP 12-14
TawatinawNatural Area
RedwaterNatural Area
Northwest of BruderheimNatural Area
North BruderheimNatural Area
Elk IslandNational Park
345000
345000
365000
365000
385000
385000
5965
000
5965
000
5985
000
5985
000
6005
000
6005
000
6025
000
6025
000
123510425-124 REVE
4 0 4 8
Kilometres
Route Options
Original Route
Route Reduction
Bruderheim Re-route
Well Location Adjustment
North Saskatchewan River Re-route
Injection Well
Shell Scotford
Major Road
Railway
Watercourse
Waterbody
Protected Area
Urban Area
Quest Carbon Capture and Storage Project Volume 1: Project Description Appendix H: Pipeline Route Selection
Shell Canada Limited November 2010 Page H-5
H.3 Re-Routes to Selected Route
H.3.1 Well Location Adjustments Several minor route modifications were made near the injection wells located in 12-14-60-21 W4M and 10-6-60-20 W4M based on landowner responses and feedback (see Figure H-2).
H.3.2 Pipeline Length Optimized The termination point for the pipeline was reviewed based on the following items:
• final section of pipeline route was located within traditional use areas identified by the Beaver Lake Cree Nation
• less favourable subsurface conditions would limit the effectiveness of CO2 storage, as a result of discontinuities in the BCS in the northeast portion of the storage area
As a result of these factors, the pipeline termination point was moved to 15-29-60-21 W4M (see Figure H-2).
H.3.3 North Saskatchewan River Re-Route The preferred route crosses the North Saskatchewan River at NW-14-57-20 W4M, parallel to the Waupisoo pipeline. This section of the river falls within the Beverly Channel, a subsurface palaeo-channel feature that is generally not suitable for horizontal directional drilling (HDD). To reduce the potential adverse environmental effects of the pipeline on the aquatic environment, Shell reviewed a number of alternative crossing locations for the North Saskatchewan River to determine if HDD was viable.
Geotechnical studies done in 2010 located a suitable HDD crossing location north of the Beverly Channel, at NW 36-57-20 W4M. Preliminary results of the geotechnical investigation indicated that this location would be suitable for a crossing, using either HDD (the preferred method) or alternatively by open cut. As a result, the pipeline was re-routed farther east by about 4 km.
H.3.4 Northwest of Bruderheim Natural Area Re-route The preferred route passes through the Northwest of Bruderheim Natural Area east of the Scotford Upgrader. However, consultation with Alberta Tourism, Parks and Recreation indicated it preferred Shell re-route the pipeline away from the Northwest of Bruderheim Natural Area. The pipeline ROW was re-routed to the south of the natural area, paralleling the Inter Pipeline (Corridor) Inc. Corridor Pipeline route for about 2 km before intersecting the existing route farther to the east.
Appendix H: Pipeline Route Selection Quest Carbon Capture and Storage Project
Volume 1: Project Description
November 2010 Shell Canada Limited Page H-6
top related