April 23, 2014
Sunset Review of Alternative Process for UW Medical Facility Construction ProjectsProposed Scope & Objectives
Mark Fleming, JLARC Staff
UW May Use Alternative Process for Certain Medical Facility Construction Projects Alternative process allows UW to pre-qualify
contractors for certain projects: Within a UW building that is used directly for
critical patient care or highly specialized medical research; and
Estimated cost is $5 million or less Authority established in 2010
Expires June 30, 2015 unless reauthorized by Legislature
April 23, 2014 UW Alternative Public Works S&O 2
UW Alternative Public Works S&O 3
Process Has Been Used for Projects at Two Medical Centers
April 23, 2014
Statute Establishes Specific Requirements for Pre-Qualifying Contractors
Publish a notice annually to solicit contractor qualifications Solicitations must include evaluation criteria
identified in statute Contractors may apply at any time
Make an effort to solicit proposals from certified minority or certified woman-owned contractors
Establish committee to evaluate contractors submitting qualifications
April 23, 2014 UW Alternative Public Works S&O 4
UW must:
Contractors Meeting Qualification Requirements Are Added to Roster
Invitations to bid on specialized hospital construction projects are sent to all contractors on roster
Award is made to responsible bidder submitting the lowest responsive bid
April 23, 2014 UW Alternative Public Works S&O 5
$ Low bid $ Med bid $ High bid
Responsive Bids
from
Responsible Bidders
UW Alternative Public Works S&O 6
Emphasis on Contracting Speed and Contractor Quality Testimony during legislative
hearings focused on the challenges and complexity of working in an occupied hospital facility
Pre-qualification is expected to reduce time needed to select contractor Also provides contractors
assurance that they meet qualifications before submitting bids.
April 23, 2014
UW Alternative Public Works S&O 7
Sunset Review Objectives
1. Has the University of Washington’s use of the alternative process complied with legislative intent?
2. Does the alternative process provide for efficient and economical public works construction, with adequate cost controls in place?
3. Have projects constructed using the alternative process achieved expected performance goals and targets?
4. To what extent does the alternative process duplicate the activities of another agency or the private sector?
April 23, 2014
Next Steps and ContactsPreliminary Report September 2014Proposed Final Report December 2014
Mark Fleming, Project Leadmark.fleming@leg.wa.gov 360-786-5181
Valerie Whitener, Project Supervisorvalerie.whitener@leg.wa.gov 360-786-5191
www.jlarc.leg.wa.gov