The Assignment Problem
-
8/3/2019 Assignment Model Mba 2012
2/29
MODULE IIMODULE II
ySensitivity analysis ;allocation problems
Assignment anddistribution problems
-
8/3/2019 Assignment Model Mba 2012
3/29
The Assignment ProblemyIn many business situations, management needsto assign - personnel to jobs, - jobs to machines, -machines to job locations, or - salespersons toterritories.
yConsider the situation of assigning n jobs to nmachines.
yWhen a job i (= 1, 2,...., n) is assigned to machine j
(= 1, 2, ....., n) the cost incurred is Cij.yThe objective is to assign the jobs to machines so
that the total cost is minimised.
-
8/3/2019 Assignment Model Mba 2012
4/29
The Assignment Problem
yThis situation is a special case of theTransportation Model and it is known as
the assignment problem.yHere, jobs represent sources and
machines represent destinations.
yThe supply available at each source is 1unit And demand at each destination is 1unit.
-
8/3/2019 Assignment Model Mba 2012
5/29
"One machine can do the work offifty ordinary men. No machine can
do the work of one extraordinaryman."
-- Elbert Hubbard
-
8/3/2019 Assignment Model Mba 2012
6/29
The Assignment Problem
The assignment model can be expressed
mathematically as follows:
Xij= 0, if the job j is not assigned to machine i
1, if the job j is assigned to machine i
-
8/3/2019 Assignment Model Mba 2012
7/29
The Assignment Problem
-
8/3/2019 Assignment Model Mba 2012
8/29
The Assignment Problem
yAssignment problem can be either formulatedas a linear programming model, or it can beformulated as a transportation model.
yHowever, An algorithm known as HungarianMethodhas proven to be a quick and efficient
way to solve such problems.
-
8/3/2019 Assignment Model Mba 2012
9/29
Hungarian Method Example
The following table gives the costs incurred in assigning
jobs to certain machines in a factory. Determine the
assignment that minimizes the cost.
-
8/3/2019 Assignment Model Mba 2012
10/29
Hungarian Method Example
Step 1: Select the smallest value in each row.
Subtract this value from each value in that row
Step 2: Select the smallest value in each column.
Subtract this value from each value in that
column.
-
8/3/2019 Assignment Model Mba 2012
11/29
Hungarian Method Example
-
8/3/2019 Assignment Model Mba 2012
12/29
Hungarian Method Example
Step 3 : (i) Examine the rows successively starting from thefirst, until a row with exactly one zero element is found. Puta box around the zero as an assigned element and cross outall other zeroes in that column. Proceed in this manner
until all the rows have been examined.I
f there are morethan one zero in any row, then do not consider that row butproceed to the next.
(ii) Examine the columns successively starting from the
first, until a column with exactly one zero element is found.Put a box around the zero as an assigned element and crossout all other zeroes in that row. Proceed in this manneruntil all the columns have been examined. If there are morethan one zero in any column, then do not consider that rowbut proceed to the next.
-
8/3/2019 Assignment Model Mba 2012
13/29
Hungarian Method Example
-
8/3/2019 Assignment Model Mba 2012
14/29
Hungarian Method Example
Step 4 : If each row and column contain exactly oneassigned zero then the assignment is optimal
.
y Therefore, we assign job 1 to machine 1; job 2 tomachine 3, and job 3 to machine 2.
y Total cost is 5+12+13 = 30.
y It is not always possible to obtain a feasibleassignment as in here.
-
8/3/2019 Assignment Model Mba 2012
15/29
PROBLEM 1y Assign Jobs 1, 2, 3, 4 to inspectors A, B, C, D so that the cost is
minimised using the following data.
JOBS
INSPECTORS
1 2 3 4
5 7 9 8
2 3 4 5
7 8 9 1
5 3 2 4
-
8/3/2019 Assignment Model Mba 2012
16/29
PROBLEM 2
y A department has 5 employees and 5 jobs to be performed. The time( in hours) that each employee takes is given below. Determine the
job allocation that will minimise the man hours.
E
M
P
L
O
Y
E
E
S
Jobs
1 2 3 4 5
A 8 4 2 6 1
B 0 9 5 5 4
C 3 8 9 2 6
D 4 3 1 0 3
E 9 5 8 9 5
-
8/3/2019 Assignment Model Mba 2012
17/29
HOMEWORK 1y Find the optimal assignment schedule given the following data.
JOBS
EMPLOYEES
1 2 3 4
10 5 13 15
3 9 8 3
10 7 3 2
5 11 9 7
-
8/3/2019 Assignment Model Mba 2012
18/29
Hungarian Method Example 2
-
8/3/2019 Assignment Model Mba 2012
19/29
Hungarian Method Example 2
y A feasible assignment is not possible at this moment.
y In such a case, The procedure is to draw a minimum
number oflines through some of the rows andcolumns, Such that all zero values are crossed out.
-
8/3/2019 Assignment Model Mba 2012
20/29
Hungarian Method Example 2y (i) Put a tick mark to those rows where no
assignments have been made.
y (ii) Put a tick mark to those columns which havezeros in the marked rows.
y (iii) Put a tick mark to those rows (not already
marked) which have assignments (boxed zeroes)in marked columns.
y (iv) Repeat (ii) and (iii) until no more rows andcolumns can be checked.
y Draw lines through unmarked rows and markedcolumns. If the number of these lines is equal tothe order of the matrix then the solution isoptimal. Else go to the next step.
-
8/3/2019 Assignment Model Mba 2012
21/29
Hungarian Method Example 2
The next step is to select the smallest uncrossed outelement. This element is subtracted from every uncrossed out
elementand added to every element at the intersectionof two lines.
-
8/3/2019 Assignment Model Mba 2012
22/29
Hungarian Method Example 2
y We can now easily assign to the zero values.Solution is to assign (1 to 1), (2 to 3), (3 to 2) and(4 to 4).
y If drawing lines do not provide an easysolution, then we should perform the task ofdrawing lines one more time.
y
Actually, we should continue drawing linesuntil a feasible assignment is possible.
-
8/3/2019 Assignment Model Mba 2012
23/29
Hungarian Algorithm
y
Step 1: Check whether the number of rows = thenumber of columns in the cost matrix. If so theassignment problem is said to be balanced and we canproceed to Step 2. If it is not balanced and the number
of rows is less than the number of columns adddummy rows with zero cost to balance the problem. Ifit is not balanced and the number of columns is lessthan the number of rows add dummy columns with
zero cost to balance the problem.y Step 2: Select the smallest value in each row. Subtract
this value from each value in that row.
y Step 3: Select the smallest value in each column.
Subtract this value from each value in that column.
-
8/3/2019 Assignment Model Mba 2012
24/29
Hungarian Method Example
Step 4 : (i) Examine the rows successively starting from thefirst, until a row with exactly one zero element is found. Puta box around the zero as an assigned element and cross outall other zeroes in that column. Proceed in this manner
until all the rows have been examined.I
f there are morethan one zero in any row, then do not consider that row butproceed to the next.
(ii) Examine the columns successively starting from the
first, until a column with exactly one zero element is found.Put a box around the zero as an assigned element and crossout all other zeroes in that row. Proceed in this manneruntil all the columns have been examined. If there are morethan one zero in any column, then do not consider that
column but proceed to the next.
-
8/3/2019 Assignment Model Mba 2012
25/29
Hungarian Algorithm
y
Step 5 : If each row and column contain exactly one assignedzero then the assignment is optimal. If either a row or acolumn does not contain exactly one assigned zero then theassignment is not optimal, go to Step 6.
y Step 6: Cover all the zeros by drawing minimal number oflines as follows :
y (i) Put a tick mark to those rows where no assignments havebeen made.
y (ii) Put a tick mark to those columns which have zeros in the
marked rows.y (iii) Put a tick mark to those rows (not already marked) which
have assignments (boxed zeroes) in marked columns.
y (iv) Repeat (ii) and (iii) until no more rows and columns can
be checked.
-
8/3/2019 Assignment Model Mba 2012
26/29
Hungarian Algorithmy Step 7 : Draw lines through unmarked rows and
marked columns. If the number of these lines is equalto the order of the matrix then the solution isoptimal. Else go to the next step.
y Step 8: Determine the smallest cost element notcovered by the straight lines. Subtract this elementfrom all the uncrossed elements, add it to theelements lying in the intersection of the straight linesand do not change the remaining elements on thestraight lines.
y Go to step 4 and repeat the procedure until anoptimal solution is reached.
-
8/3/2019 Assignment Model Mba 2012
27/29
PROBLEM 1
y A department has 5 employees and 5 jobs to be performed. The time( in hours) that each employee takes is given below. Determine the
job allocation that will minimise the man hours.
E
M
P
L
O
Y
E
E
S
Jobs
1 2 3 4 5
A 10 5 13 15 16
B 3 9 18 13 6
C 10 7 2 2 2
D 7 11 9 7 12
E 7 9 10 4 12
-
8/3/2019 Assignment Model Mba 2012
28/29
PROBLEM 2y The processing time ( in hours) for jobs when allocated
for different machines are indicated. Determine the joballocation that will minimise the total processing time.
M
A
C
H
I
N
E
S
JOBS
1 2 3 4 5
A 9 22 58 11 19
B 43 78 72 50 63
C 41 28 91 37 45
D 74 42 27 49 39
E 36 11 57 22 25
-
8/3/2019 Assignment Model Mba 2012
29/29
TheTraveling Salesman Problemy In the traveling salesman problem, there are m
locations (or nodes)y
And unit costs (Cij) are associated withtraveling between locations i and j.y The goal is to find the cycle that minimizes the
total (traveling) distance required to visit alllocations (nodes) without visiting any
location twice.y The Traveling salesman begins its journey from
his/her home city And visits other cities (in noparticular order) before returning home.