ORATOperational Readiness & Airport Transfer
Christoph Aumüller, On-Block GmbH
Bahrain, 10 October 2017
Fraport AG
Fraport & On-Block
Operational Readiness & Airport Transfer, 10.10.20172
From Asia to South America
Recent ORAT and other projects
Fraport AG
PAX 2016 mn YOY
Frankfurt 60.8 -0,4%
Delhi 55.6 21.0%
Xi'an 37.0 12.2%
Antalya 19.0 -30.9%
Lima 18.8 10.1%
St. Petersburg 13.3 -1.7%
Hanover 5.4 -0.8%
Burgas 2.9 22.0%
Varna 1.7 20.8%
Ljubljana 1.4 -2,3%
TOTAL 215.9 3.4%
ex FRA 155.1 5.0%
On April 11, 2017, Fraport has started to operate 14 Greek regional airports. Fraport is active at 31 international
airports, operating and managing 24 of them. Fortaleza and Porto Alegre in Brazil will follow by mid 2017.
Operational Readiness & Airport Transfer, 10.10.20173
From Asia to South AmericaOur know-how is in demand around the world
Fraport AG
KPI project with LH
Consulting
Spring 2017
Full scale ORAT
May 2017
ORAT trial operations
2014
Guarulhos T3
Bogotá
Bahrain
ORAT Trial
Operations 2013
Marketing and
Commercial Plan
2016 /2017
St Petersburg
Entebbe
Design Review &
ORAT tender
development
2016 - 2017
Taipei
Operational Readiness & Airport Transfer, 10.10.20174
Recent ORAT and other projects
Fraport AG
What is ORAT?
Opening Day Scenarios
What is ORAT?
ORAT Essence & Processes
ORAT Project Key Stakeholders
Ideal ORAT Project Setup
ORAT Indicator, Schedule, Open Issue List and Risk Register
Operational Readiness & Airport Transfer, 10.10.20175
Fraport AGOperational Readiness & Airport Transfer, 10.10.20176
Opening day scenariosA lot can go wrong during a terminal inauguration!
Fraport AG
Operational
Readiness
Airport
Transfer
Landside/Terminal Ops IT & Systems
BHS/HBS
Airside/Apron
Ramp Handling
Operational Control
From
the old…
… to the
new
What does an ORAT Project
need to facilitate?
Prioritize topics before & after
opening
Manage all operational
stakeholders
Identify and track critical issues for
opening
Mediate between construction and
operations
Focus on key topics
Dedicated ORAT team to support
airport operator
What do we want to achieve?
All facilities in place
and systems running
without interruptions
Confident stakeholders
operating the new
facilities and systems
No negative
press media
Smooth airport
operations from
opening day onwards
Operational Readiness & Airport Transfer, 10.10.20177
What is ORAT?Operational Readiness and Airport Transfer
Fraport AG
Driven by airport processes
Check-in Boarding Bridges Resource Allocation
HBS & Sortation System Control Emergency Control
Stakeholders
ORAT
Operational Readiness & Airport Transfer, 10.10.20178
ORAT Essence Holistic Approach Integrating Operations, Construction and Stakeholder
Fraport AG
ORAT Team Airlines
3rd party Service ProvidersAuthorities
Concessionaires
Construction
Ground Handling
Bahrain Airport Company
ORAT Platform
Operational Readiness & Airport Transfer, 10.10.20179
ORAT Project Key Stakeholders
Fraport AG
Ideal ORAT Project SetupStructure and Organization
Organizational Set Up
Operations &
Technical
Management
Training &
FamiliarizationAirport Transfer
Operational
Trials
OR AT
ORAT Project Management
ORAT
Modules
Stakeholder Knowledge Transfer
BAC Construction
AuthoritiesOther
Stakeholders
ORAT
Assigned to the airport operator
Is neutral
Detached from day to day business & politics
Project Set Up
ORAT Project
ORAT
Operational Readiness & Airport Transfer, 10.10.201715
Fraport AG
ORAT ExecutionORAT Indicator and ORAT Schedule
ORAT Schedule
ORAT Indicator
Operational Readiness & Airport Transfer, 10.10.201711
Fraport AG
BAH ORAT Project
Bahrain International Airport AMPORAT Team for Bahrain AMP
Bahrain Airport AMP
BAH ORAT timeline
Challenges
Operational Readiness & Airport Transfer, 10.10.201712
Fraport AG
Alexander Larisch – Project Manager
- 22 years of airport, airline and logistics experience
- Education: Bachelor of Arts in Aviation Management, Logistics Management
- Expertise: ORAT (18 worldwide ORAT projects in 13 past years), project
management, air cargo, airport operations management, logistics
Chris Aumüller – Manager ORAT PMO
- 10 years of airport, aviation, handling and business aviation experience
- Education: Master of Engineering in Aviation
- Expertise: ORAT (6 worldwide ORAT projects in past 8 years), project
management, business aviation & VIP handling management
ORAT Team for Bahrain AMPFraport & On-Block
Operational Readiness & Airport Transfer, 10.10.201713
Fraport AG
• New Passenger Terminal
• Apron
• ATC Tower
• Fuel Farm & Hydrant System
• MRO
• Fire Station
Bahrain Airport AMPAirport Modernization Programm
Operational Readiness & Airport Transfer, 10.10.201714
Fraport AG
BAH ORAT TimelineORAT Project Timeline as part of the overall AMP Program
H1 H
1
Phase 1
D-22 D-21 D-18 D-16 D-14 D-6D-8 D-5D-9D-19 D-7D-20 D-17 D-15 D-13 D-12 D-11 D-10 D-4 D-3 D-2 D-1 D-4 D-3 D-2 D-1D+1 D+2D-23D-24D-25D-26
Sep Oct Jan May Sep May Aug Sep Oct Nov DecAugJul JunMay Mar JanNov FebOctDec DecNov Feb Apr Jun Jul Aug Mar Apr Jun Jul
2017 2018 2019
ORAT Project Management
Start of
Operations 10.07.
Training & Familiarization
Operational Trials
Terminal Transfer
Mobilization & ORAT
Audit
Phase 2 Phase 3
15
Knowledge Transfer Stakeholders
Operational and
Technical Baseline
(Post-)Opening
Support
Operational Readiness & Airport Transfer, 10.10.2017
Fraport AG
BAH ORAT Challenges
People Readiness
Construction
Readiness
On-going Day-to-Day
Operation
Technical &
Operational
IntegrationPublic Expectations
Opening Strategy
Operational Readiness & Airport Transfer, 10.10.201716
Thank you.