7/28/2019 BoreGage CRC Training
1/7
Bore Gage Se it ng Reference Card
1. Clean both of the receiver pads and mounting
surfaces of the flat face anvil using the cloth
and ZEP I.D. Red cleaner.
2. Place the shoulder side of the flat face anvil
against the left receiver pad shoulder.
3. While holding the anvil against the receiver pad
shoulder, insert the two cap screws into the
holes on either side of the anvil.
4. While applying pressure toward the receiver
pad shoulder, use a 5/32" hex wrench to
slightly tighten the screws.
5. Use a 30 in/lbs torque wrench to secure thecap screws.
MIC TRAC MT-3000
1 2000 Gagemaker, Inc.
RCBASMT30007-00
SetupM
aterials Needed:
MIC TRAC MT-3000 base unit and CPU readout 30 in/lb torque wrench
Bore gage support fixture (TF-BA Block) and cap screws Cloth
Flat face anvils (TF-1F Blocks) and cap screws ZEP I.D. Red cleaner
5/32" hex wrench
-
7/28/2019 BoreGage CRC Training
2/7
Bore Gage Se it ng Reference CardSetup
MIC TRAC MT-3000
2 2000 Gagemaker, Inc.
RCBASMT30007-00
6. Repeat the same process with the right flatface anvil, but before completely tightening the
screws, be sure the anvils are aligned:
Bring the flat face anvils together using the
coarse adjust knob.
While holding the anvils together with your
fingers, move your finger back and forth
along the backside of the anvils to verify
alignment.
If not aligned, loosen the right anvil and
align. Once aligned, use the torque wrench to
secure the right anvil.
7. Clean the mounting surfaces of the bore gage
support fixture using the cloth and ZEP I.D.
Red cleaner.
8. Place the bore gage support fixture over the leftflat face anvil and rest it on the left receiver
pad.
-
7/28/2019 BoreGage CRC Training
3/7
Bore Gage Se it ng Reference CardSetup
9. Insert the two cap screws into the holes on
either side of the bore gage support fixture.
10. While holding the bore gage support fixture,
use a 5/32" hex wrench to tighten the screws.
11. Turn the coarse adjust knob counterclockwise
to bring the flat face anvils together.
12. On the front panel of the CPU, press the INT
(internal measurement) pad.
13. Press the ZERO pad on the CPU panel twice.
The readout displays 0.00000.
MIC TRAC MT-3000
3 2000 Gagemaker, Inc.
RCBASMT30007-00
-
7/28/2019 BoreGage CRC Training
4/7
Bore Gage Se it ng Reference CardSetup
14. Turn the coarse adjust knob clockwise until the
CPU reading is close to the desired bore gage
setting value.
15. Secure the coarse adjust lock.
17. Turn the fine adjust knob clockwise until the
CPU reads the exact bore gage setting value.
MIC TRAC MT-3000
4 2000 Gagemaker, Inc.
RCBASMT30007-00
-
7/28/2019 BoreGage CRC Training
5/7
Bore Gage Se it ng Reference CardSetup
18. Secure the fine adjust lock.
MIC TRAC MT-3000
5 2000 Gagemaker, Inc.
RCBASMT30007-00
-
7/28/2019 BoreGage CRC Training
6/7
Bore Gage Se it ng Reference Card
MIC TRAC MT-3000
6 2000 Gagemaker, Inc.
RCBASMT30007-00
M
aterials Needed:
MIC TRAC MT-3000 base unit and CPU readout 5/32" hex wrench
Bore gage with extension Lightweight gage oil
Bridge supports
1. Place the bridge support across the sides of
the bore gage support fixture to form a platform
for the bore gage. You may need to use both
bridge supports, if the bore gage is large.
2. Place the bore gage on the bridge support so
the bore gage extension touches the right flat
face anvil and the bore gage contact point
touches the left flat face anvil.
3. To ensure the gage is properly seated in thefixture, sweep the bore gage back and forth to
locate the smallest reading on the gages
indicator dial.
4. Align the gages indicator dial with zero.
Gage Setting
-
7/28/2019 BoreGage CRC Training
7/7
Bore Gage Se it ng Reference CardGage Setting
5. After setting the bore gage, be sure to remove
the flat face anvils, bore gage support fixture,
and bridge supports from the MT-3000. Oil the
fixtures and return them to the storage case.
MIC TRAC MT-3000
7 2000 Gagemaker, Inc.