building construction - ircwash.org · 2.5.1 bricks 10 2.5.2 quality control 11 2.6 concrete blocks...
Post on 04-Jun-2018
214 Views
Preview:
TRANSCRIPT
SERIES OF MANUALS ON DRINKING WATER SUPPLY
2 0 1 OOBU VOLUME 3
Building Construction
Christian Meuli, Karl Wehrle,Heini Muller, Heini Pfiffner
•
\
'<vh
!.
I .
1
OF.MANUALS ON
VOLUME
Building Construction
Christian Meuli, Karl Wehrie,Heini Muller, Heini Pfiffner
LIBRARY IRCPO Box 93190, 2509 AD THE HAGUE
Tel.: +31 70 30 689 80Fax: +31 70 35 899 64
BARCODE:
Contents
Contents
1. Introduction 1
2. Basic Information and Selection Criteria of Building Materials 32.0 General remarks 3
2.1 Stones 32.1.0 General 32.1.1 Classification 32.1.2 Selection 42.1.3 Testing 4
2.2 Gravel, sand, silt and clay 42.2.0 General remarks 42.2.1 Characteristics 42.2.2 Testing of sand and gravel 5
2.3 Cement 82.3.0 General 82.3.1 Hydration 82.3.2 Density, volume and mass 82.3.3 Storage of cement 8
2.4 Other binders 92.4.0 General 92.4.1 Pozzolanas 92.4.2 Limes 10
2.5 Burned bricks 102.5.0 General 102.5.1 Bricks 102.5.2 Quality control 11
2.6 Concrete blocks 112.6.0 General 112.6.1 Solid and hollow concrete block 112.6.2 Production process 122.6.3 Construction 122.6.4 Quality control 12
2.7 Wood and timber 122.70 General 122.7.1 Growth characteristics 132.7.2 Types and properties of timber 132.7.3 Timber preservation and seasoning 14
2.8 Bamboo 152.8.0 General 152.8.1 Application of bamboo in a water supply system 152.8.2 Advantages and disadvantages of bamboo 16
Building Construction
3. Site Management 17
3.0 General 17
3.1 Preliminaries on site 173.1.0 General 173.1.1 Setting up a work camp 183.1.2 Work planning 18
3.2 Site Management 183.2.0 General 183.2.1 Preparation before construction 193.2.2 Implementation 193.2.3 Reporting 20
3.3 Setting out 203.3.0 General 203.3.1 Measuring of distances 203.3.2 Setting out of angles 203.3.3 Setting out of levels 213.3.4 Setting out of buildings 21
4. Excavation and Backfilling 23
4.0 General 23
4.1 For trenches 234.1.0 General 234.1.1 Permissible slope 234.1.2 Boundary rods 244.1.3 Depth of the trenches 244.1.4 Width of the trench 264.1.5 Trench strutting 264.1.6 Backfilling 28
4.2 At tank sites 294.2.0 General 29
5. Foundation 31
5.0 General 31
5.1 Types of foundations at water supply structures 315.1.0 General 315.1.1 Bearing capacity 315.1.2 Size of foundation 325.1.3 Strip foundation 325.1.4 Slab foundation 325.1.5 General rules for foundation construction 32
5.2 Special foundations 345.2.0 General 345.2.1 Foundation on uneven ground 345.2.2 Foundation on steep slopes 34
6. Masonry Work 35
6.0 General 35
6.1 Cement mortar 356.1.0 General 356.1.1 Mortar mixtures 356.1.2 Recommended mortar and plaster mixtures and their use 36
Contents
6.2 Pointing, plastering and topping 376.2.0 General 376.2.1 Pointing 376.2.2 Plastering 376.2.3 Topping 39
6.3 Brick and block masonry 406.3.0 General 406.3.1 Brick bonding 406.3.2 Cement block bonding 416.3.3 General rules for bricks and cement block masonry (cement hollow blocks) 416.4.1 Stone shaping 43
6.4 Stone masonry 436.4.0 General 436.4.2 Stone masonry 45
7. Concrete Work 4770 General 47
7.1 Concrete 4771.0 General 477.1.1 Aggregates 4771.2 Water 487.1.3 Water-cement ratio 487.1.4 Concrete mixtures 48
7.2 Mixing and processing of concrete 4972.0 General 497.2.1 Hand mixing 497.2.2 Machine mixing 507.2.3 Processing of concrete 50
7.3 Quality of concrete 5173.0 General 5173.1 Cube test 517.3.2 Rebound hammer test 51
7.4 Reinforced concrete 5274.0 General 527.4.1 Reinforcement 5274.2 Form work 537.4.3 Precast concrete 53
8. Construction of a Masonry Tank 558.1.0 General 558.1.1 Site preparation 558.1.2 Construction 558.1.3 Finishing work 56
Reference Books 57
1.Introduction
Introduction
The aim of this manual is to describe the variety ofwork as well as to provide a survey of the types ofmaterials used in rural water supply construction.Some of the materials and their use are only brieflydescribed. This manual refers in many chapters tothe existing sourcebook on Appropriate BuildingMaterials, a co-production of SKAT, IT and Gatepublished in 1988; third revised edition 1993.
In general a water supply project has to be plannedand constructed with the highest possible quality ofmaterials and craftsmanship.
The following few key factors determine the long-term sustainability of water supply systems:
A. Water supply systemThe key factors are: simplicity of design,availability of local materials, quality ofconstruction, reliability of supply, acceptability ofsupply standards, operation and maintenancefriendliness.
B. Vil lages capabil i tyThe key factors are: to adjust to the required
social changes, to make effective use of thesystem, to manage the system, to maintain thesystem, to pay for operation and maintenance(ability and willingness).
C.Government interest and capabilityThe key factors are: to provide the legal basefor operation and maintenance (so that forexample sanctions can be applied), to enablerepairs which go beyond the villagers' capacity,to provide long-term controlling and guidancesupport.
D. Protection of environmentThe key factors are: political, economic, physicaland natural (e.g. deforestation = soil erosion =decreased ground water)
If these factors are well considered a water supplyscheme should last for 30 to 50 years withoutrequiring major repairs or renovation. This manualprovides the information needed to achieve therequired high quality of construction, and thereby tocreate a long lasting and reliable water supply.
Basic Information and Selection Criteria
2.Information and Selection Criteria
of Building Materials
2.0 General remarksEach construction site requires specific buildingmaterials. Some of the material may be availablelocally, while other material has to be organizedfrom far away. Available natural and local materialsare of different characteristics and quality. There-fore, knowledge of how to select the best materialand how to make efficient and economical use ofthe materials is essential.
2.1 Stones2.1.0 General
Natural stone is perhaps the oldest, most abundantand most durable "ready-made" building material,and is found predominantly in hilly areas.Stones for construction purposes like the buildingof structures, are prepared by breaking raw piecesfrom large rocks or stones into stones of the appro-priate size. Various types of stones with specificcharacteristics are used in the construction of wa-ter supply systems.
2.1.1 Classification
In the following section the most common stonesused for construction are described: igneous, sedi-mentary, and metamorphic stones.
a. Igneous stones
Volcanic in origin, they have been fused by heatand then cooled and crystallized. These hardstones have a very good compressive strengthand are compact. When working with thesestones keep in mind that because of the hard-ness stone shaping of igneous rocks is very dif-ficult. The principal stones in this class aregranites and basalt.
Igneous stones can be used for all water supply
related masonry work like:• Catchments• Chambers• Storage tanks• Standpipes• Surrounding work• Dry walls
b. Sedimentary stones
These are formed by the weathering of landmasses and the removal of the particles bywater and wind and the deposition over thou-sands of years in lakes or the sea. The depos-ited grains are united by some cementitiousmaterial. The sedimentary stones are compara-tively weak stones. They are less compact (po-rous), and where exposed to the weather oftennot of long durability. Whenever sedimentarystones are used for construction purposes theyhave to be checked for durability. The principalstones in this class are sandstone and lime-stones.
Sedimentary stones can be used for:• Catchments (testing for durability required)• Chambers (testing required)• Storage tanks (testing required)• Standpipes (testing required)• Surrounding work• Dry walls
c. Metamorphic stones
These stones are sedimentary or igneous in ori-gin, but have undergone a change caused byimmense heat and pressure to such an extentthat they assume a new structure and form newmaterials. The principal stones in this class areslates (derived from clay), quartzites (from sand-stone) and marble (from limestone).
Metamorphic stones can be used for:• Catchments (testing for durability required)
Building Construction
• Chambers• Storage tanks (testing for durability required)• Standpipes• Surrounding work• Dry walls
2.1.2 Selection
In general, the stones for construction should becollected at the usual places where the villagers findtheir building materials. If stones are used for localbuildings their quality can be checked at those ex-isting buildings. Stones used for tank constructionshould always be tested as described in the follow-ing Chapter 2.1.3 Testing. If there is no long termexperience of building with the local stone, the test-ing of the stone's quality and durability becomesvery important.
If stones are not used for the local buildings, thecollection of the stones can be done in the follow-ing ways:
a. Collecting stones at the surfaceIf stones are collected at the surface they gen-erally need a lot of shaping to obtain the requiredshape for masonry work. Therefore this is ingeneral not a economical way of preparing thestones for construction.
b. Breaking (cutting) rocks at thesurfaceIf surface rocks can be cut in pieces it is the bestway to obtain stones for the construction. Thecutting should be done in such a way that as lit-tle as possible shaping is necessary after-wards.
Remark:Igneous and sedimentary rocks are widespread andare the most common building stones used. When-ever natural stones are to be used for constructionwork the durability has to be tested first. However,in general the local masons will know the best qual-ity stones available, and this knowledge should beconsidered and used.
2.1.3 Testing
A simple testing procedure can be done in the fieldas described below. More detailed testing has to bedone by a trained person. Internal or surface cracksin the stone can with time weaken a structure.
The quality of the stone can be assessed by strik-ing the stone lightly with a hammer. A bell-like highsound indicates good quality, and a dull low soundbad quality. This test is very important when usingsedimentary rocks.
Another test can be done by laying the stone inwater, take it out after one day, let it dry out, cleanit from organic matter and put it back into the wa-ter again. Continue with this procedure for at leasttwo weeks. If the stone does not break into piecesor develop cracks, it is considered adequate forconstruction purposes.
2.2 Gravel, sand, siltand clay
2.2.0 General remarks
Sand and gravel are the types of aggregates neededfor the manufacture of concrete, plaster or mortar.Aggregates should consist of clean, hard, strongand durable particles. Sand and gravel used in con-nection with cement should be not polluted by anyleaves, wood, grass, humus or clay, because thisnegatively influences the quality of the product. Themethod of crushing stones to obtain gravel for con-struction is sometimes the only solution to get theraw material. River sand does normally not needfurther treatment before using.
Silt and clay are used only secondarily at water sup-ply constructions, for example to cover and there-fore watertighten the spring catchment, or to sealthe foundation of a catchment.
2.2.1 Characteristics
To obtain good quality concrete or mortar it is es-sential to have aggregates which meet the require-ments. Following are described the characteristicsof the most frequently used aggregates:
a. GravelCoarse pieces of rocks like granite, lime, marble,etc. of any shape (round, flat or angular). Gravelforms the skeleton of the soil and limits its cap-illarity and shrinkage.
The size of the particles are 2mm to 60mm.
Basic Information and Selection Criteria
Gravel is used for:• concrete• permeable construction at catchments• drainage• levelling
b. SandParticles mainly comprising of silica or quartz;beach sand contains calcium carbonate (shellfragments). Sand grains lack cohesion in thepresence of water, and limit swelling and shrink-age.
The size of the particles are 0.06mm to 2mm(this is the smallest grain size that can be dis-cerned by the naked eye).
•-WmmSand is used for:• concrete• mortar• pipe filling• levelling
c. SiltPhysically and chemically the same as sand, onlymuch finer. Silt gives soil stability by increasing
its natural friction, and holds together when wetand compressed.
The size of the particles is 0.002mm to 0.06mm.Silt should not be used for concrete or mortarbecause silt can interfere with the bond betweencement and aggregate, and it requires morewater (large specific surface).
d. ClayClay results from chemical weathering of rocks,mainly silicates. The hydrated aluminosilicateparticles are thin plates of extremely great spe-cific surface area, causing strong cohesion in thepresence of water, but also causing excessiveswelling and shrinkage.
The size of the particles is smaller than0.002mm.
Clay is used for:• Clay is hardly used for water supply construc-
tion, however it may be useful to improve thewatertightness of a spring catchment.
• As raw material clay is used for the fabrica-tion of bricks
2.2.2 Testing of sand and gravel
To guarantee the quality of the structures it is veryimportant to ensure the required quality of the rawmaterials. The sand and gravel, for example, mustbe free of clay or organic matters. Clay and organicmatters reduce the quality of binding in cement, andwill swell and shrink, therefore causing cracks in thestructure. There are several different field and labo-ratory tests described in the Manual on Appropri-ate Building Materials, as well as in Properties ofConcrete (Ref. 1 and 2). In the present manual onlysimple field testing is described.
a. Sieve analysis (grain size)Most natural soils are mixtures of sand, silt andclay. The relative proportion of individual soil frac-
Building Construction
tion is determined by sieve analysis. Sieve analy-sis is the simple operation of dividing a sampleof aggregate into fractions, each consisting ofparticles of the same size. In practice, each frac-tion contains particles between specific limits,these corresponding to the openings (apertures)of standard test sieves.
The test sieves used for concrete aggregatehave square openings. Sieve sizes are desig-nated by the nominal aperture size in millime-tres.
Sieves smaller then 4mm (0.16in.) are normallymade of wire cloth although, if required, this canbe used up to 16mm (0.62in.). Coarse testsieves (4mm (0.16m.) and larger) are made ofperforated mild steel plate.
All test sieves are mounted in frames which cannest. It is thus possible to place the sieves oneabove the other in order of size with the largestsieve at the top, and the material retained oneach sieve after shaking represents the fractionof aggregate coarser then the sieve in questionbut finer than the sieve above.
The sieves used for concrete aggregate consistof a series in which the clear opening of anysieve is approximately one-half of the opening ofthe next larger sieve size.
Before the analysis is performed, the aggregatesample has to be air-dried in order to avoidlumps of fine particles being classified as largeparticles and also to prevent clogging of finersieves. The international sieve sizes as well asthe minimum weight of sample to be taken areas following:
Sieve Analysis I
Project:
Location of Project:
Aggregate total sample weight
Test No.
Tested by:
Date:
Sieve size
mm
Weightretained
9
Percentageretained
%
Cumulativepercentage
passing%
Cumulativepercentage
retained%
Basic Information and Selection Criteria
Sieve sizes
mm
63504028201410
6 or 5 or 3
Minimum weight ofsample to be takenfor sieving
kg
503515521
0.50.2
The actual sieving operation can be performedby hand, each sieve in turn being shaken untilnot more than a trace continues to pass. Themovement should be backwards and forwards,sideways left and right, circular clockwise andanticlockwise, all these motions following oneanother so that every particle "has a chance" ofpassing through the sieve.
The results of a sieve analysis are best reportedin a table form as shown below.
The results of a sieve analysis can be graspedmuch more easily if represented graphically, andfor this reason grading charts are very helpful touse. By using a chart it is possible to see at aglance wether the grading of given sample con-forms to that specified, or is too coarse or too fine.For more details on sieve analysis see Ref. 2.1. If the tested sample is within this area, it can
be used.2. If the tested sample is within this area,
course or fine sand has to be added.
b. Hand-test:The hand filled with the aggregates to be testedis clenched and then opened again. If the ma-terial is clean it should not stick together in alump. When the material is rubbed between thehands, the hands should remain almost clean.Otherwise the silt and foreign material has to bewashed out by thorough rinsing with water.
c. Bott le-test:A clear one litre bottle filled two-thirds withmaterial and topped with water is shaken vigor-ously. Allow it to settle for half an hour. If thewater is still dirty, and a sediment has settled ontop of the sand of more then 4mm in height, thematerial needs to be considered for washing,depending on its use.
Grading curve 0 - 32 mm100
90
80
70
60
50
a*= 40
ISi 30c41
S 200.
10
0
—' • —
— • — ^ .
\
\ \
\ \
\ \
\ \
0.1 0.2 0.4 1 2 4 8
- Sieve size diameter in mm —
16 32 64
Building Construction
Remark:It is very important to use material of the requiredquality. If the quality of local materials can not beclearly confirmed, materials of other areas shouldbe investigated or an experienced person should beconsulted.
2.3 Cement2.3.0 General
Of the large variety of cements available today, or-dinary Portland cement (OPC) is the most common,and usually the type referred to when speaking ofcement. It is the fine, grey powder that can bemixed with sand, gravel and water to produce astrong and long lasting mortar or concrete. Cementis a hydraulic binder that can harden under water.Normally Portland cement is sold in 50 kg bags.When the adequate amount of water is added, ithardens after approximately 2 V2 hours at a tem-perature of at least 5°C. After 28 days a good qual-ity concrete mortar with 300 kg cement per 1 m3
has a compressive strength of up to 300 kg/cm2.Cement is made of limestone (calcium carbonate)and clay (silica, alumina and iron oxide) that areground and mixed with water to form a slurry. Thisraw materials is burned at the temperature of1300°-1400°C in a kiln. The burnt cement (clinker)is then broken, mixed with a small percentage (ingeneral 3%) of gypsum and then ground to a veryfine powder. The finer it is ground, the higher therate of the setting and strength development.
2.3.1 Hydration
The Portland cements are classified as hydrauliccements for the reason that they have the propertyof hardening under water. The hardening processinvolves the reaction between the cement and thewater. This type of chemical reaction is known ashydration. Hydration of cement is divided into twoprocesses called setting and hardening. When wa-ter is added to cement a chemical reaction takesplace. After a period of V7 to 2 hours (depending onthe air temperature) the setting time starts and lasts6 to 8 hours. Already during the setting time thecement starts to harden. Theoretically the harden-ing time of Portland cement is unlimited. In practicethe expected strength of the cement constructionis reached after 25-30 days.
During the hardening process the cement tends todry out too quickly, particularly in dry climatic con-ditions. For this reason curing (see Chapter 7.2.3)of cement-based products is required for at leasttwo weeks.
2.3.2 Density, volume and mass
The cement leaves the factory in bags containing40 litres (or 40 dm3). On the scale this shows 50 kg.
Therefore, cement has the following specific na-tures.
Density:50 kg -f 40 dm3 = 1.25 kg/dm3
Volume:50 kg T- 1.25 kg/dm3 = 40 dm3 or litres
Mass:1.25 kg/dm3 x 40 dm3 = 50 kg
These figures can be used for exact calculations ofthe different mortar mixtures and concrete mix-tures.
2.3.3 Storage of cement
In general cement should not be stored over longperiods of time (more than two months). Moisturedestroys cement, therefore it must be stored dry.If the cement contains lumps it is a clear sign thatit has been exposed to moisture. A storing placewith a secure roof and good ventilation is required.It is recommended to use a separate store room.To avoid rising damp do not store the cement di-rectly on the floor, but for instance on timber pal-lets. Avoid contact of the cement bags with outerwalls and floor. Walls and floors could be a sourceof moisture. In addition proper ventilation is pre-vented when the cement bags lay directly on thefloor or against a wall. The cement stack should notbe more then 10 bags high.
GoodStoring on timber pallets and no contact withouther wall.
WrongStoring directly on the floor and at the outer wallCement should not be kept longer than 2 months.
Basic Information and Selection Criteria
min 50 cm
This is especially important in humid climates. Theold stock should always be used before the newone. Cement can be expected to lose from its po-tential strength because of storage time as follows:
20 %30 %40 %50 %
afterafterafterafter
36
1224
monthsmonthsmonths (1months (2
year)years)
Remark:Proper storage, as well as handling with care is veryimportant when working with cement. If the ce-ment has lumps, the bags are hard, or the qualityof cement is doubtful in any way, it should not beused anymore. Cement with only a few lumps maystill contain some quantities which can be used. Inthis case it should be sieved through a 0.5mm sieveand used for less sophisticated construction worklike foundation or lean concrete work.
2.4 Other binders
2.4.0 General
Lime and lime-pozzolanas are other common bind-ers in construction work because of their low pro-duction costs and compatibility with traditional
building materials such as earth. They are, however,unsuitable for reinforced concrete or high or me-dium strength concrete. Pozzolanas can also beblended with Portland cement to give a cementwith similar properties to Portland cement providedthat replacement rates are kept to below 20 or30%. Lime by itself can be classified as hydraulicor non-hydraulic. In general, for reasons given be-low, the use of non-hydraulic lime as a cement isnot recommended for use in any part of a watersupply system. Lime-pozzolana cement or hydrau-lic lime could be used in some cases provided thelimitations of these materials are known about.Portland-pozzolana cement can be used in the sameway as portland cement and there could even beadvantages in using this cement in certain applica-tions, as explained below.
2.4.1 Pozzolanas
Pozzolans are siliceous or siliceous together withaluminous materials which in themselves posseslittle or no cementitious value but react chemically,when in a finely divided form, with calcium hydrox-ide (lime) in the presence of water to give a solidmaterial similar to that produced by hardening ofPortland cement. When pozzolanas are mixed withPortland cement they react with the excess limewhich is produced when Portland cement hardens.Examples of pozzolanas are pulverized fuel ash fromcoal-burning power stations, finely ground burntclay, certain types of volcanic ash and ash producedby burning rice husk.
With Portland-pozzolana cements the addition ofpozzolanic material in general increases the waterdemand. This may sometimes necessitate an in-crease in the cement content of the mix and thereis also an increase in the risk of cracking caused bydrying shrinkage. The main advantage of addingpozzolana to Portland cement is that the alkalinityof the cement matrix is reduced. Thus there is lesslikelihood of an alkali-silica reaction with aggregatesusceptible to this reaction, and mortars and con-crete made with this cement are more resistant toacidic environments.
There is little point in using lime-pozzolana cementsfor any part of the water supply system. Not onlyare the setting and hardening times longer com-pared with Portland cement but also there is a needto test the materials often to ensure that they are
Building Construction
of a good and consistent quality. Variation in prop-erties of lime and pozzolanas is a potential sourceof trouble unless they come from one or two reli-able suppliers and have been mixed together well.In contrast the quality of Portland cement should beassured by the supplier.
2.4.2 Limes
Hydraulic limeHydraulic lime is produced from limestone contain-ing a proportion of clay which is burned in a kiln andthen hydrated with a minimum quantity of water.This lime reacts like non-hydraulic lime with carbondioxide in the air, and also with water in a similarway to Portland cement. Hydraulic limes have theability to harden under water. If the limestone hasa sizable proportion of clay and is burned to an in-creased temperature (IOOV2C or so more than withnon-hydraulic lime) the lime begins to resemblePortland cement and is classified as "eminentlyhydraulic". With less clay and a lower burning tem-perature the lime would be only moderately ormildly hydraulic. Only eminently hydraulic limemight have some potential for use in a water sup-ply system, but as with lime-pozzolana cementsthere would be no advantage in doing so andgreater attention would need to be paid to qualitycontrol than when using Portland cement. Beforethe use of Portland cement became widespreadearly in this century, eminently hydraulic lime wasused for structures in contact with water, usually incombination with pozzolanic material.
Non-hydraulic limeNon-hydraulic lime is produced by burning almostpure calcium carbonate limestone in a kiln and hydrat-ing the resulting quicklime with water. It is not resist-ant to water when it is constantly exposed to it andin addition it makes the water excessively alkaline (pH11 -12.5) and possibly cloudy. Lime is attacked particu-larly by acidic water with a pH below 6.0. The use ofnon-hydraulic lime by itself is not recommended forany parts of a water supply system.
ConclusionCement is the only binder that fulfills the qualityrequirements for water supply schemes.
2.5 Burned bricks2.5.0 General
Bricks can be used for many structures at villagewater supply systems. Today many different meth-ods of brick making exist. The construction of awater supply scheme requires high quality materi-als, therefore this manual refers only to high qual-ity burned bricks. For more detailed informationabout brick refer to Appropriate Building Materials(Ref.1).
Bricks can be used for all water supply relatedmasonry work like:• Catchment chambers• Storage tanks• Standpipes• Surrounding work• Pumphouses
Advantages of bricksNo dimension and design limitationEqual dimensionEasy to transportFast buildingLocal materialHigh quality if from professional productionJob creation (Building industries)
Disadvantages of bricksCostlyMay not be locally availableLocally made bricks can often not be usedfor water tanks because they lack the re-quired quality (always testing required)Need of firing with great use of scarce rawmaterials (wood, ore, fuel)High percentage of breakage, leading towaste
2.5.1 Bricks
In general the raw material for brick manufacturingis clay. If the clay is too fine, the bricks have a highshrinkage rate and tend to develop cracks duringthe drying process. If the clay contains too muchsand it will cause the bricks to loose strength.
10
Basic Information and Selection Criteria
The manufacturing process of burned bricks in-cludes:
miningmixing
formingdryingfiring
use in building construction
Factory made bricks are in general of constant uni-formity and strength. Locally made bricks are oftenof uneven dimensions and vary in strength, andtherefore are not always useful for the construc-tional work at water supplies.
2.5.2 Quality control
The quality requirements of locally burned brickscan be checked as follows:
a. With a hammerAs explained in Chapter 2.1.3 (Testing forstones) cracks inside the bricks will be recog-nized when there is a low dull sound whenstruck with a hammer. Good quality bricks willgive a high bell-like sound when struck with ahammer.
b. Dropping the brickA good quality brick should not break or crack af-ter being dropped from 1 m of height. Always testwith the hammer after the brick has beendropped, to ensure that there are no cracks inside.
2.6 Concrete blocks2.6.0 General
There exist several types of concrete blocks, themost common being solid block, cellular block, hol-low block, and interlocking block. Concrete blockconstruction is gaining importance in many coun-tries, even in drinking water system construction.It is a valid alternative to fired clay bricks, concrete,stone, timber and other common construction ma-terials, provided the raw materials are available lo-cally and they are of good quality and economicallyviable.
2.6.1 Solid and hollow concreteblock
Both type of blocks are suitable for the constructionof certain parts of a water supply system.
Solid concrete blocks:For a circular type of water tank it is recommendedto use solid concrete blocks. However, horizontalsteel rod reinforcement is recommended, which islaid into the different mortar layers.
Hollow concrete blocks:This type of concrete block can be used for all kindsof construction. One advantage is that the hollowscan be filled with concrete and steel bars for rein-forcement of the construction.
However, it is advised not to use hollow concreteblocks for water tank construction since the qual-ity of the concrete blocks can be different. For otherparts of the water supply system, assuming that theingredients and workmanship of the hollow con-crete blocks are of good quality, the use of hollowconcrete blocks can be as good as any other rel-evant building material.
Hollow concrete blocks can be used for water sup-ply schemes for the following structures:
11
Building Construction
CatchmentsStandpostsDry wallsOperation chambersBreak pressure tanksPumphouse
The main characteristics of the common typesof hollow concrete blocks are:• high compressive strength, resistance to
weathering, impact and abrasion• low tensile strength (but can be overcome
with steel reinforcement and filling withconcrete)
• capability of being moulded into compo-nents of any shapes
• good fire resistance up to 400°C
The main problems, particularly with regard todeveloping countries, are:• the need for relatively large amount of ce-
ment• the need for relatively large amount of clean
water for mixing and curing, which can bea serious problem in dry regions;
• the need for special knowledge and experi-ence in the production process as well asin the construction process
• the risk of deterioration through sulfates inthe soil or water to which the concreteblock is exposed
2.6.2 Production process
The ingredients of concrete blocks can be of verydifferent types and qualities, not only depending ontheir local availability, but also on the desired strengthproperties of the blocks. Therefore it is not possibleto give detailed recommendations on material andmix proportions, other than general guidelines.
The raw material for the production of concreteblocks consists of cement, sand and water. Thecorrect sand-cement ratio must be found by trialswith different ratios (4:1, 6:1, 8:1, etc.).
Determining the water-cement ratio needs specialexperience from the producer. Only trials will givethe correct ratio, and depends strongly on the mois-ture content of the aggregates.
Batching and mixing, moulding, curing and storingis the usual production procedure for the concreteblocks.
2.6.3 Construction
Concrete blocks must be dried out thoroughly be-fore use, otherwise drying will continue after build-ing the wall and shrinkage cracks may develop.Mortars used for bedding should not be too rich incement. It is important that the strength of themortar does not exceed that of the blocks, so thatthe joints can absorb a limited amount of move-ment, preventing the blocks from cracking.
2.6.4 Quality control
Manually produced concrete blocks are not likely toattain the superior qualities that are achieved bymechanized production. It is therefore advisable touse mechanized produced concrete blocks for theconstruction of any type of building for a water sup-ply system. Minimal quality requirements of con-crete blocks are checked the same way as forburned bricks, see Chapter 2.5.2
Advantages of concrete blocks:equal dimensionsfast buildinglocal production possiblelow production costrelatively easy to produceenvironment friendly
Disadvantages of concrete blocks:transportation cost if locally not availabledepends on a reliable cement supplyraw material quality not always consistentneeds a relatively long curing time (28 days)
2.7 Wood and timber2.7.0 General
Timber is not only one of the oldest building mate-rials, but has remained until today the most versa-tile one. However, timber is an extremely complexmaterial, available in great varieties and forms, withgreatly differing properties between regions.
Basic Information and Selection Criteria
Timber is basically a renewable material. Neverthe-less, there is an universal concern about the rapiddepletion of forests and the great environmental,climatic and economic disaster that follows. Al-though construction timber represents only a smallfraction of the timber harvested, it should be usedthriftily and wastage should be minimized. Also, re-afforestation programs should be promoted.
2.7.1 Growth characteristics
The cross section of a trunk or branch reveals anumber of concentric rings. The trunk thicknessincreases by the addition of new rings, usually onering each year.
The early wood (spring-wood) formed during thegrowth period has larger cells, while in the dry sea-son the late wood (summer-wood) grows moreslowly, has thicker cell walls and smaller apertures,forming a narrower, denser and darker ring, whichgives the tree structural strength.
HEAHIWOOD
JUVENuE WOOD
GROWTHRING
BAST HIVING CELLS;THAT !«AHSPO«T NAND I A T M BECOME RIMDI
*IHD IOEAO OUTER LAYERTHAT PSOTECTS 1HE TREEf«OM HEAT, COLO AN3I0L0CICAL HAZAR
Structure of a tree trunk (hardwood and soft wood)As each ring forms a new band of "active"sapwood, starch is extracted from an innersapwood ring, adding further to the "inactive"heartwood core. Mechanically there is hardly anydifference between sapwood and heartwood, butsapwood is usually lighter in color and containssubstances (e.g. starch, sugar, water) which attractfungi and some insects.
The slower the tree grows, the narrower are thegrowth rings, and the denser and stronger is thetimber. Its resistance to biological hazards is alsousually greater.
2.7.2 Types and properties oftimber
Woods are classified as either hardwood orsoftwood. There are different methods of distin-guishing these woods, but the most commonmethod is that hardwood comes from broad leavedtrees, in the tropics usually evergreen, in temper-ate zones usually deciduous (shedding their leavesannually). Softwood is generally from coniferous(cone-bearing) trees, commonly known as ever-greens, and found mainly in temperate zones. Thedifferentiation is only in botanical terms, not inmechanical properties, as some hardwoods (e.g.balsa) are much softer than most softwoods.
There are many other methods of classifyingwoods, and the definitions differ often betweenregions. For instance in West Africa the term "redwood" commonly refers to hard and strong timberand "white wood" refers to soft and weak timber.In other regions this terminology is not known, oris used in an other sense.
Timber categoriesTimber for building construction can be divided intotwo or more categories according to the mechani-cal strength. Often one distinguishes between pri-mary and secondary timber species.• Primary timbers are generally slow-grown, aes-
thetically appealing hardwoods which have con-siderable natural resistance to biological attack,moisture, movement and distortion. As a result,they are expensive and in short supply.
• Secondary timber are mainly fast-grown specieswith low natural durability, however, with appro-priate seasoning and preservative treatment,their physical properties and durability can begreatly improved. With the rising costs and di-minishing supplies of primary timbers, the im-portance of using secondary species is rapidlyincreasing.
SizingWhen sizing structures, the bearing capacity of thetimber at hand has to be taken into account. Thisshould be done in consultation with the local normsand standards.
Sawn timber productsSawn timber is cut mainly from older trees withlarge diameter trunks, in rectangular sections as
Building Construction
Low
Good
beams or boards. The part of the trunk from whichthey are cut and the slope of grain have great ef-fect on the quality of the product. Therefore, whenselecting timber, the direction of the grain has to beobserved.
High quality boards are used for heavily stressedstructural members, e.g. purlins and in trusses.
Highquality
Highquality
Low quality boards are used for wall plates etc.
Lowqual i ty
To make the best use out of a trunk, the cuttingmethod has to be considered. The commonlyknown cutting types are illustrated in the figurebelow.
Quarter cut
Lowerhalf bil-let sawn
True quartercut
*— Boxed heart
Selection of timberFor structural members which are under highstress, such as purlins and rafters and in trusses,the selection of timber is of great importance. Tim-ber with cracks, knots or with grains that are notlongitudinal should not be used. Such timber shouldonly be used in situations with reduced stress, suchas wall plates.
CracksDuring harvesting and transport cracks may occur.Such timber should be rejected.Cracks may also occur due to shrinkage which is
unavoidable. Such timber should be tolerated to acertain extent, but not used for heavily stressedparts of the structure.
Hidden cracks are also possible but very difficult todetect. This risk is considered within the safety fac-tor in the sizing calculations. The strength of beamscan be greatly reduced by knots, especially whenlocated in the area of the greatest bending momentand in situations with tensile stress.
For example, a knot in the upper third of the beamheight situated between the supporting points, re-duces the strength of the beam by up to 35%. Ifthe knot is situated at the lower side of the beam,the reduction is even up to 56%.
The weakening depends much on the growth char-acteristic of the knot, how well it is grown into theadjoining wood.
Direction of grainThe strength depends also on the direction of thegrain. It should be longitudinal. If not, then thestrength is drastically reduced.
Good
Bad
Seasoned timberTo avoid cracking and warping, only seasoned tim-ber should be used.
2.7.3 Timber preservation andseasoning
Timber is a highly valuable and durable material.However it must be carefully selected. Also it mustbe used in a competent way to retain this durabil-ity. The following aspects are important in this re-spect:• Timber which is cut in the non-growing time
(winter) is more durable.• Cambium parts should not be used.• Proper seasoning prior to use.
74
Basic Information and Selection Criteria
SeasoningPrior to the manufacturing of timber componentsthe timber has to be properly seasoned. One rea-son is that during drying timber shrinks. The shrink-age varies according to the direction of the grain:radial shrinkage is about 8% from the green to thedry state; the tangential shrinkage is about 14 to16%; in the longitudinal direction shrinkage can beneglected (0.1 to 0.2%). The use of unseasonedtimber results in cracks and warping parts.
J5 *
By proper seasoning the moisture content of tim-ber is reduced to its equilibrium moisture content(between 8 and 20% by weight, depending on thetimber species and climatic conditions). This proc-ess, which can take a few weeks to several months(depending on timber species and age, time of har-vesting, climate, method of seasoning), makes thewood more resistant to biological decay, increasesits strength, stiffness and dimensional stability.
Seasoning methodsBasically, three different methods of seasoning canbe used:• Air seasoning is done by stacking timber such
that air can pass around every piece. Protectionfrom rain and avoidance of contact with theground are essential.
• Forced air drying is principally the same as airseasoning, but controls the rate of drying bystacking in an enclosed shed and using fans.
• Kiln drying achieves accelerated seasoning inclosed chambers by heating and controlling aircirculation and humidity, thus reducing the dry-ing time by 50 to 75%, but incurring highercosts. An economic alternative is to use solarheated kilns.
Remark:Seasoning time is greatly reduced if the timber isharvested in the non-growing season (winter) whenthe moisture content of the tree is low.
2.8 Bamboo2.8.0 General
Bamboo is, as well as timber, one of the oldestbuilding material and is still widely used today inmany countries. The main area of distribution ofbamboo is the tropics. Some robust species arealso found in subtropical and temperate latitudes.Untreated bamboo deteriorates within 2 or 3 years,but with correct harvesting and preservative treat-ment, its life expectancy can increase about 4times. The following factors must be considered inbuilding with bamboo:• protection from moisture• access of air circulation• avoidance of contact with soil• only matured culms should be used
2.8.1 Application of bamboo in awater supply system
Bamboo as a building material can be used in theconstruction of a water supply system for the fol-lowing work:• bamboo reinforced structure, like standpost
floor etc.• for all kinds of shuttering work• scaffolding• temporary roofing• fencing• temporary pipes• framing work
15
Building Construction
2.8.2 Advantages anddisadvantages of bamboo
Advantages:• in many regions bamboo is abundantly avail-
able• easy handling• no waste• environment friendly (quick growing)• good tensile strength
Disadvantages:bamboo has a relatively low durabilityeasily attacked by biological agentspredrilling is essential to avoid splittingbamboo is not fire resistantbamboo is becoming in many countries arather expensive building material
16
3.Site Management
Site management
3.0 General
Before the construction of a water supply projectcan be started, there is a great deal of preparationwork to be done in the office as well as in the field.For successful constructions this preparatory phaseis very important. In this manual, only the techni-cal aspects of preparing a construction site are de-scribed. Nevertheless a good planning and siteorganization can avoid many social problems toowhen the preparation work is carefully thought outand implemented. Most of the following commentsare given under the assunption that at least someof the civil works are carried out with voluntary la-bour.
3.1 Preliminaries on site3.1.0 General
Before any building materials are broughtto the construction site the arrangementsfor proper storing needs to be organized.On a large construction site the required buildingmaterial should be stored close to the structureswhere it will be needed to reduce the transporta-tion within the construction site. All these placeshave to be shown to the villagers, so that whenmaterial arrives at the site before the constructioncrew is present the villagers can showthe proper places to store the various materials.
17
Building Construction
Before the construction crew arrives at the site thenecessary arrangements like accommodations, worktime, required labour etc. have to be worked out.
If the villagers contribute with labour to the project,work like shaping stones, excavating trenches etc.has to be organized as well as checked by regularvisits of a supervisor to the project site.
3.1.1 Setting up a work camp
The work camp at a rural water supply constructionsite should include a store room for building mate-rials, dicing equipment as well as necessary smallmachines like vibrators, jackhammers etc.
3.1.2 Work planning
Before starting with the construction there shouldfirst be a clear understanding of which parts of thesupply are to be built first and the actual construc-tion procedure.
Therefore, a work programme should be developedwhich includes the phases and sequences of theconstruction. Such a work programme is normally
designed by the supervisor and technician in chargeof the site, and subsequently discussed and agreedupon with the villagers concerned. This is very im-portant since villagers will need to know when theywill have to provide labour, local materials etc.
The advantages of a work programme are:• to know the amount of time needed for con-
struction• to know the required material needed, as
well as at what time it has to be at the site• to give an idea of the village labour required• to optimize the work procedures• to plan for the following project
3.2 Site Management3.2.0 General
On every construction site must be one person incharge of the work. This person needs to have thetechnical know how and professional ability, as wellas a disciplined personal behaviour (authority) towardshis workers, supervisors and villagers. He is author-ized and supervised by a supervisor or engineer.
Project name:Name of engineer:Name of supervisor:
Village Water Supply
Form:Date:
Structure
Spring catchment
Siltbox
Pipeline SB - Tank
Tank 3 qmPipelineTank - Tap 1 - 6
Springeatchment
Tank 5 qmPipelineTank - Tap 7 - 9
Standpipes
Work completed
Staff requirement
Section
ExcavationBuildingExcavation
ExcavationMountingRarldWtinn
BuildingExcavationMountingBackfillingRuilriinnExcavationBuildingBuildingExcavationMountingBuildingBuilding
within total 6 months
ForemanMason 1Mason 1
|1
1i-••I
3
—
111
1••!
t
i—
1
1
5
!
I 1
—
7
J-
-—
8 9 10
18
Site management
3.2.1 Preparation beforeconstruction
Before the construction of a project starts the fol-lowing things need to be organized, implementedand checked:a. The involved villagers have to be informed about
the ongoing activities, as well as the proposedwork programme.
b. The location of the structures and the alignmentof the pipeline is marked in the field.
c. The official agreement with the villagers for thecontribution of labour (stone shaping, trench dig-ging, etc.) as well as for the preparation workmust now be settled.
d. The confirmation that the locally prepared ma-terial fulfills the required quality standards.
e. If necessary, the accommodations for theskilled labour are prepared.
f. The required building material for the first phase(that is not available in the village) is transportedto the site.
Remark:Projects should only be started after the preparationwork is finished. Otherwise the construction time
will be increased as well as creating the unfortunatesituation of labourers just standing around. It is veryimportant to motivate the people to do good qual-ity work, to insure a well built and long lasting wa-ter supply system.
3.2.2 Implementation
When the construction of the project has startedthe person in charge has to organize and coordinatedaily the ongoing work. This is, as mentioned be-fore, a very important part of the construction. Thefollowing points have to be checked daily:
a. Organize and supervise the work on the siteb. Explain the job to the workers as well as to the
villagers, and make clear the daily target whichis expected from them.
c. Check the work, and if necessary correct it, oradapt it to the situation.
d. Plan the work for the next day, and inform theworkers and villagers.
e. Organize in time the ordering and delivery of therequired building materials.
f. Keep the administration like daily reports, storebook, orders for materials and transport up todate, as well as the controlling of material at thesite.
19
Building Construction
3.2.3 Reporting
The reporting is an essential component of the projectand will help to avoid mistakes, as well as to keep ahigh standard of work at the construction site.
Reports are made for ordering and controlling ofmaterials as well as controlling the progress at theconstruction site and the engagement of the con-struction crew.
The implementation of reporting depends of thesize of the project and the format must be carefullyconsidered to produce useful application.
To make the administrative and reporting part of awater supply as simple and efficient as possiblethere are different examples of forms given in theappendix to report and describe:• Materials requirements for pipes, fittings, build-
ing materials• Standard tools and equipment• Additional tools• Construction site report• Personal report• Construction labour evaluation
Computer based reportingHELVETAS Nepal has developed a useful compu-terised reporting programme for processing andanalysing of technical data, stock control data andstatistical data of drinking water projects.This computer based reporting programme can bepurchased. Please contact HELVETAS, Switzerlandor HELVETAS, Nepal.
3.3 Setting out3.3.0 General
Setting out is bringing the indications from a planto the real situation. In this manual simple methodsused for setting out are described. A basic knowl-edge of measuring distances is required.(This series of manuals always uses the metricsystem.)Materials used for setting out:• staff• straight edge• meter• meter ruler
• plump bob line• spirit level• tape
3.3.1 Measuring of distances
Short distances are measured with a staff, meter orruler, longer distances with a tape. All the distanceshave to be measured horizontally, therefore, if work-ing on a slope, a straight edge or staff have to beused. The tape should always be stretched, a saggingtape gives incorrect measurements of the length.
c+d+e+f=a
3.3.2 Setting out of angles
The setting out of a right angle is very important forall construction work at water supply projects. Theright triangle method is very simple and handy forthis purpose.
Example:Measure the distance from point A to point B of 3metres along a given line x. Locate point C at a dis-tance of 4m from point A, and 5m from point B. The
20
Site management
right angle is found at point A formed by the lines x
and y.
Other combinations of distances are:
1IIIII
PointA - B
6812
PointA - C
4.569
PointB - C
7.5
1015
3.3.3 Setting out of levels
The levels on a construction site are related to fixpoints, where the level is known. Therefore, a tem-porary bench mark should be set next to each struc-ture. This bench mark has to be surveyed by theengineer or technician in charge. The specified levelof the structure can be found by using a straightedge and spirit level.
3.3.4 Setting out of buildings
Permanent buildings require an exact setting out.According to the measurement on the site plan thebuilding is set out with batter boards. The follow-ing steps should be taken for the construction ofbatter boards, as shown in the figure below:
1. Install batter boards at all corners, approx. 1.5m away from the proposed outside wall of thebuilding. Use poles (A) of approx. 12 cm diam-eter, and planks (B) of about 4 cm thickness.
2. Make sure that all batter boards are approx. ata same level using the water hose levellingmethod.
3. Mark the outer wall using strong thread line (C)and tape measurment. Tighten the layout,thread by stones. (D)
4. Check that the layout thread lines are in right an-gle. (E) Use the 3 : 4 : 5 string or wooden square.
5. Check the diagonal, (to be of equal length) forperfect layout.
6. Mark the building lines on slopping terrain withthe help of the plump line. (F)
Remark:The procedure described above is one possiblemethod for setting out for tank construction. Forsmall structures it is not necessary to use stakesand boards. The required accuracy can be achievedwith spirit level and plump. When the setting outis made it is important to build a durable strongbatter board construction which can stand and re-main stable throughout the construction time.
Excavation and backfilling
4.Excavation and Backfilling
4.0 GeneralChoosing sites for proposed structures and trenchesrequires careful consideration in regard to the techni-cal requirements (altitude, soil bearing capacity) aswell as the entire environmental and possible weatherinfluence. Therefore the choosing of the location isof greatest importance, before any earth work is un-dertaken. Another important point is to avoid as muchas possible damage to the surrounding nature, likethe unnecessary cutting of trees and subsequentcreation of erosion problems due to large disturbanceof the overgrowth. If possible no excavation shouldbe foreseen in rocky areas, because it is extremelydifficult and labour intensive. Therefore laying of pipe-lines should be avoided in rocky areas. Other-wise thepipeline has to be covered differently as describedlater in this chapter. Special attention is also neces-sary to guarantee the security of labourers workingon deep excavations for wells and deep trenches inrocky areas.
4.1 For trenches4.1.0 General
Trenches not deeper than 1.2 metres can be exca-vated normally with vertical walls, as collapsing ofthe walls at this depth should not be dangerous forthe working person inside the excavation. Trenchesor excavations of more than 1.2 metres depth re-quire a careful consideration of the soil stability onwhich the necessary "safe slope" depends. Specialattention is required near houses, rivers or roads toprevent sliding of large areas.
4.1.1 Permissible slope
In general the permissible slopes are as follows:
With solid ground
solid ground
:•• 0 ' a-"o-C
loose ground wrong excavation
80 - max. 150 cm 60 cm
•V.: ^ ^ W .
A \:£-'° •
v o'' . ' • • ' • • ' : • ' . ' /
V • o
o ' • •* • . *
loose ground correct excavation
23
Building Construction
4.1.2 Boundary rods
With the use of boundary rods on the constructionsite the slope of the trench can be easily markedand continuously checked during construction. If theslope of the trench because of certain circum-stances is very little (less then 3%) the use ofboundary rod is most important to guarantee aproper pipe laying.
4.1.3 Depth of the trenches
The depth of the trenches required for water sup-plies depends on different aspects. The main idea
of covering the pipes is to protect them from dam-age through stepping on them, cuttings by plough-ing or burning by bushfires. The achievement is alonger lasting supply system. Burying the pipe alsoprevents the problem of freezing, that would dam-age the pipes, because of the expansion of the icebreaking the pipe. These aspects show clearly thatin setting the depth of trenches only a general rulecan be made. For each project the depth of thetrench has to be considered individually accordingto the local circumstances.
24
Recommended depth of trenches
Excavation and backfilling
field/bush min. 0.8 m village min. 1.0 m
V \
along roads min. 1.0 m road crossings min. 1.3 m
terraces min. 0.8 m
25
Building Construction
4.1.4 Width of the trench
The width of the trench is determined togetherwith the depth to allow a proper working space.The width depends as well on the size of the pipe.It is important that the required work for pipingcan be carried out easily inside the trench.
4.1.5 Trench strutting
Alignment of pipe trenches should be carried out ina way to avoid unnecessary deep excavations. Ifthere is no other solution other than a deep trenchthere is still the possibility to excavate with a safeslope of 1:1 (relation of height to depth). If this so-lution cannot be considered the strutting of thetrench is the only possibility. The construction of thestrutting has to be done carefully and requires anexperienced builder.
Horizontal Trench Strutting
• • • . ' . o» : • ' • •
•:3 ©
1J L I . . . . J . . . l l . . . . , W, •Jl-U,-^..r
Vertical Trench Strutting
Excavation and backfilling
, v.v6'
•:-^.-;:S
;.••..•.; • ! ? • • .;•/*..••: vx-_g-. o . .^ .p- .g . - , • ; • . . ;
&:?
r%$
l&H
:i-.:'?
- ?nr nnn n® \ ® © II ©
f V •;•:
® © II o
m
27
Building Construction
4.1.6 Backfilling
Backfilling of any excavation needs proper compact-ing in layers of maximum 30cm of height, otherwisedamage can occur to the structure of the pipeline,and occasionally can cause a sunken area at the topof the trench causing accidents. A backfilling thatis even well compacted experiences over long pe-riods a certain settling. Therefore, the backfillingshould always be a little bit higher then the sur-rounding area. The aim of compacting is to reducesuch settling to a minimum and to avoid erosionproblems. The excavated material is normally usedagain for the backfilling. Never put stones directlyon top of the pipe because this will definitely causedamage to the pipe. To avoid damage to pipes it is
important to backfill fine material or sand directlyaround the pipe. Special care in backfilling is re-quired in the case of PVC-pipes.
A special backfilling procedure is required fortrenches on steep slopes. To avoid erosion it is veryimportant to build dry wall at least every 5 metresand on very steep slopes at even shorter distances,determined by the angle a, as given in the sketchbelow.
28
4.2 At tank sites4.2.0 General
The excavation and backfilling work at the tank sidefollows the same procedure and rules as mentionedabove. At the tank site the excavation always hasto be done in such a way that workers still haveenough space to work around the structure (to buildthe wall).
The excavation at the tank site always needs safeslopes of 1:1. Strutting at tank excavations is notpossible because the excavation area is in generallarge and in the middle of the excavation the workhas to be carried out. The water tap for the con-struction of the tank should be positioned so thatno water (waste) can enter the excavation area, aswet soil can not be used for a foundation bed (seechapter 5.1.1 Bearing capacity). This can also occur
Excavation and backfilling
when rainwater softens the foundation bed, there-fore it is recommended to excavate the last 10cmjust before the foundation is cast. For the safety ofworkers, villagers, and animals, a deep tank exca-vation should be fenced during construction.
The backfilling has to be done in layers of about 30cm that are properly compacted. The area ofbackfilling around the tank side should be plantedwith grass to keep the area clean, as well as toprevent erosion.
29
5.Foundation
Foundation
5.0 General
Foundation is the name for the structural part onwhich structures like tanks, catchments, chambersand walls rest. It is the lowest part of a building andin general below the ground level. The ground onwhich the foundation rests is called the foundationbed.
According to the weight of the structure and the typeof the soil the size of the foundation needs to bedesigned. At too small foundation cannot be usedin a low capacity bearing soil, it will sink into thesoil.
5.1 Types of foundationsat water supplystructures
5.1.0 General
Structures like walls, single pillars and tanks requiredifferent types of foundations. Where ever founda-tions are built the foundation bed should be of uni-form material. The strip and plate foundations arecommon for water supply structures.
5.1.1 Bearing capacity
The foundation bed or the ground upon which thestructure stands has a defined bearing capacitywhich depends on the nature of the ground. Hardand crack free rock as building ground is most suit-able, and there is no costly foundation necessaryother than some levelling for the respective ma-sonry afterwards.
If the ground is humid or wet the bearing capacityis strongly reduced. Therefore, foundations on wetunderground do not fulfill the requirements forwater supply structures. If just the topsoil is wet ithas to be removed before starting with the con-struction of the foundation.
The best foundation bed is rock, and the worst arewet clay and/or silt. The following are the mostcommon foundation beds, and their bearing capaci-ties are described below:
Rock: (3-10 kg/cm2)When rock forms the foundation bed it is usuallysufficient to cut the rock into a level bed and washit before the foundation is cast. Instead of cuttingthe rock to a level bed it can be levelled also byusing lean concrete or gravel.
Gravel: (dry and humid 2-5 kg/cm2)Gravel is the next best foundation bed. It has a highcompressive strength and is unaffected by atmos-
31
Building Construction
pheric influences like rain or frost because the wa-ter is drained properly through the gravel.
Sand: (0-1 kg/cm2)is usually not recommended as a foundation bed.It requires a complicated and expensive foundationthat should be avoided.
Sand, silt and clay: (0.5-5kg/cm2)The combination of these materials can provide areasonable foundation bed, but it is most importantto keep the water out of this material. The presenceof water strongly reduces the bearing capacity.Foundations on this material have to be carefullyplanned and constructed.
5.1.2 Size of foundation
The size of the foundation is designed according tothe bearing capacity of the foundation bed. The loadto be applied is a combination of the "dead load"which is the weight of the structure itself, and the"live load" which is for example the weight of the wa-ter in a storage tank. This combined load is the weightwhich the foundation transfers into the foundationbed, and therefore has to be supported by the foun-dation bed. Possible designs of foundations are de-scribed in the manual Engineering of this series.
5.1.3 Strip foundation
Strip foundations are the easiest and most oftenused foundations for simple constructions
The width of a strip foundation depends on thebearing capacity of the ground, and the thicknessof the wall. The height of the unreinforced stripfoundation should be bigger than the thickness of
5-1 Ocm lean concrete ' •• - " : ' •
the wall.
Typical measurements for un-reinforced strip foun-dations on a foundation bed with low bearing capac-ity (1-2kg/cm2) are:
Thicknessof wall, t [cm]
~ 10
~ 25
~ 35
distancea [cm]
10
30
40
heighth [cm]
15
30
40
widthw [cm]
30
85
115
On soils with a higher bearing capacity (~4kg/cm2)the angle a can be increased to: a > 60°.
5.1.4 Slab foundation
The slab foundation is a slab of reinforced concretelaid over the ground. The size of the foundation isslightly larger then the building, so that the load isspread evenly into the foundation bed as explainedbefore. It is very economical for small structuresand the most suitable for water containing cham-bers like storage tanks, spring chambers etc.
The reinforcement for plate foundations is set in ontop and on the bottom of the slab. This reinforce-ment is required because of the different distribu-tion of the load by the walls and the water.
5.1.5 General rules forfoundation construction
• The soil of the foundation bed must be uniform.If not so, it is better to shift the building to aplace where the ground is uniform.
32
Foundation
The foundation bed must always be levelled.On steep hills the levelling is achieved bymeans of steps.
The depth of the foundation below the grounddepends on the nature of the ground. Topsoillike humus always has to be removed.Erosion of the foundation has to be carefullyconsidered and precautionary measures have tobe foreseen to drain the rainwater around thestructure.
In cold climates the depth of the foundation hasto be designed so that freezing of the founda-tion bed is avoided. Freezing causes an expan-sion of the soil which creates a strong forcewhich can lift up the structure, causing cracksand therefore disturbing the building.All the loose material which may fall into thefoundation has to be secured or removed beforecasting the foundation.
If the excavation is dug too deeply, don't fill insoil to save concrete, use lean concrete or com-pacted gravel.
If the excavation is finished, the foundationshould be built as quickly as possible, especiallyduring the rainy season (to prevent swelling ofthe ground due to rain water).
Building Construction
5.2 Special foundations5.2.0 General
Sometimes the location of the building is on a placewhere it is not possible to build strip or plate foun-dations. Therefore it is sometimes necessarily toadapt these types of foundations according to theindividual circumstances, as described below.
5.2.1 Foundation on unevenground
If the ground in the excavation cannot not be lev-elled, it needs to be levelled through the use of leanconcrete. The construction of the foundation can bestarted only when a level foundation bed is created.
5.2.2 Foundation on steep slopes
If a tank site or other water supply structure needsto be placed on a steep slope, the foundation hasto be constructed as shown below:
34
6.Masonry Work
Masonry work
6.0 GeneralThe selection of suitable material for stone and brickconstruction depends on the required strength ofthe structure and the availability of usable localmaterials. The quality and strength of masonry de-pends also on consistent high quality and accurateworkmanship.
6.1 Cement mortar6.1.0 General
Mortar may be defined as a material composed offine aggregate and cement which forms a hardenedmass after mixing with water. It is used in the bedsand site joints of masonry work in order to bind thestones, bricks or blocks together, and thereby dis-tribute the pressure throughout the blockwork.Good mortar used for masonry consists of cement,sand and water in the correct proportions. The sandhas to be clean and needs the correct granulation.Sand without fines (below 0.5mm) gives a harshmortar with low compressive strength and badworkability. Cement mortar usually gives the bestresult when the sand comprises of the following:
0 - 0.5 mm (60% 0-0.2 mm) 1 part0.5 - 2 mm 1 part2 - 4 mm 1 part
6.1.1 Mortar mixtures
For mortar mixtures it is very important to use cleansand and water as well as a proper granulation asmentioned before. A uniform mixture of sand andcement (mixed 2 to 3 times) before adding wateris required. Mortar mixed with water must be usedwithin 1 hour, otherwise the mortar hardens andcannot be used any more without essential loss ofquality.
The plasticity of the mixture varies according to the
amount of water added as well as being influencedby the original water content of the raw material.
a. Volumetr ic methodThe mix method for small quantities (hand mixes)is the so-called "volumetric ratio cement : sand"method. It is commonly used at village water sup-ply construction sites.
For example the ratio 1:4 means that 1 part ce-ment and 4 parts sand are used for the mortar.
b. Weight methodMortar mixtures are also expressed in kg of ce-ment per 1.0 m3 of cement mortar. For exam-ple PC 250 means that 250 kg of cement, ~1000litres of sand and 120 litres of water are usedto obtain about 1.0m3 cement mortar.
c. PlasticityThe plasticity determines the workability of themortar. Dry mortar is difficult to work with, butalso slurry mortar can cause problems in han-dling. Different mortar mixtures with differentplasticity characteristics are used in village wa-ter supply structures according to the table givenin the next chapter.
35
Building Construction
6.1.2 Recommended mortar and plaster mixtures and their use
The following chart shows the various recommended mixtures and their use for water supply structures.The required mortar mixture should be described in the construction plan of the structure, or defined bythe engineer or supervisor in charge.
Used for
MORTAR
Building withbricks
Building withblocks
Building withstones
Topping
Pointing
WATERPROOFPLASTERING
Spatterdash
Rendering coat
Setting coat
Cement paste
ratiocement : sand
1 : 4
1 : 4
1 : 4
1 : 3
1 : 2
1 : 2
1 : 4
1 : 2
1 : 0
biggestgrain
4mm
4mm
4mm
3mm
2-3 mm
4mm
4mm
1-2mm
-
consistency
plastic
plastic/stiff
plastic/stiff
stiff
plastic
slurry
plastic
slurry
slurry
remark
biggest grainmax V2 thicknessof the joints
Sand should beclean and coarseif possible
Remark:Increasing the cement content in mortar does not increase the strength of the wall built. It is also importantthat the bricks, blocks or stones are of good quality and soaked in water before use. Decreasing cement con-tent will weaken the strength of the mortar, and the structure will not fulfill the requirements. A badly builtstructure will be maintenance intensive and could even collapse during or just after construction.Remember any construction is only as strong as the weakest element used in the structure.
36
Masonry work
6.2 Pointing, plasteringand topping
6.2.0 General
A great many constructions, even in exposed areas,are never plastered. It is wrong to think that the du-rability of a building is systematically and only linkedto the presence of a plaster. The first function of aplaster finish is to improve the appearance of abuilding. If using a plaster is to be avoided, the build-ing must therefore be carefully constructed andwhere necessary pointing work made. Externalplaster finishes have an additional function which isto protect the body of the wall from weathering aswell as to protect surfaces from the effect of flow-ing water or of regular submersion in water such asinner walls of water storage tanks.
Pointing, plastering and topping are important worksfor the correct finishing of many construction detailsfor a water supply system. The quality of this workdetermines the final durability of the building, andhas a direct influence on the future maintenancework for the system.
6.2.1 PointingThe reasons for pointing the surface of blockworkare to increase its weather resistance and to givea neat looking finish to the work.
Pointing can be carried out as the construction ofthe blockwork proceeds, using ordinary mortar inwhich the blocks are bedded. This type of pointingis called struck jointing and is much cheaper thanthe pointing methods described below. Anothermethod is to finish the masonry work first and thento make the pointing work with a 1:2 cement mor-
tar later. The joints must be racked out to a depthof about 1 to 1.5 cm, brushed, washed and filledwith a 1 part cement and 2 part sand mortar.
For masonry in general the following mortar point-ing finishing is suitable. It will help to avoid that rain-water penetrates into the structure through thehorizontal or vertical mortar bed layers. Because themortar bed layers are the weakest part of the wall,they must be protected properly.
a. Flush-pointingFor not-exposed buildings. It can be used belowground level and as well if the wall will be plas-tered.
tr^y'o'::'•'•''•'.* •"V*.*;
b. Curved-pointingUsed for exposed unplastered walls built inburned bricks or cement-blocks. Especially forexposed stone masonry walls.
Made with pointing tool or a piece of small pipe.Two centimeters of the set mortar is scratchedout of the joints and later filled with pointingmortar of a ratio 1:3 to 1:2 as shown in the draw-ing. This pointing is work intensive and expen-sive, but has a big influence on the quality of thestructure.
6.2.2 Plastering
Plastering is the process of covering walls with asubstance which is applied while still plastic andwhich hardens later. Plastering may be carried outin one, two, three or more coats, depending uponthe quality requirement.
37
Building Construction
Plaster consists of the same materials as mortar,but sometimes mixed with lime to make betterworkability. For ordinary internal plastering it is advis-able to use fine sand to obtain after floating a smoothsurface on which the application of lime is not nec-essary. The addition of lime is appropriate for opera-tion chamber or inside wall plastering, but must beavoided for plastering exposed to water or rain be-cause of swelling and shrinking. Plastering in generalis applied to protect and strengthen the masonry, togive straightness and cleanliness to the wall surface.At water supply structures the use of plastering isvery important for the waterproof structures.
a. Waterproof plasteringWater containing structures are plastered in orderto make them completely waterproof, and toachieve a smooth surface which allows propercleaning. Accurate application of the 4 coat plas-tering as shown below makes application of ad-ditional waterproof coating unnecessary. Butwhen cement aggressive water is present addi-tional chemical applications are recommended toprotect the cement plaster from disintegration.
Storage tanks, chambers and other water keep-ing structures in village water supply constructionare plastered to waterproof as well to obtain asmooth surface which can easily be cleaned. Af-ter years of experience the following differentplastering coats can be recommended for waterkeeping structures:
b. The WallSurface must be rough, clean, free from dust,and wet.
• Spatterdash (1 : 2)The thickness is 4mm, and this coat ensuresa proper connection of the plaster to thewall. It makes the plastering waterproof. Ithas to be mixed slurry with rough sand, andshould be applied with force. If necessary(with not completely covered spots) applythis coat twice, then allow it to set for atleast 10 days, to avoid cracks in the follow-ing coats.
• Rendering coat (1 : 4)The thickness is 15-20mrn and gives thenecessary straightness to the plastering(screeds). Never should be floated if a set-ting coat is to be applied too.
38
Masonry work
• Setting coat ( 1 : 2 )
The thickness is 2-3mm. This coat smoothsthe surface. It can be applied immediatelyafter the rendering coat has set. This coathas to be properly floated.
• Cement paste (1:1)This coat is applied immediately after thesetting coat is floated. It must be appliedslurry and not thicker than 1mm. This coatensures easy cleaning.
Besides rendering, there are other methods to im-prove watertightness.
Additives can be added to the concrete mixture(plasticizer, water repellent agents, liquifier, etc).Rendering with special mortar (e.g. Sika productslike Sika 101a, Sika Top-Seal 107). Such specialmortars have to be approved (accepted) by the re-spective health authorities or standard organisationsbefore they can be used for water supply struc-tures.
Coatings with epoxy cannot be recommended.Epoxy coatings require a fully dry surface (beforeapplication), which can hardly be guaranteed forwater supply structures.
6.2.3 Topping
Topping is a cement mortar in a stiff consistency.It is applied mostly as a coat on floors, slabs, wallsetc. to protect, give level, and cleanliness to thesurface. The best connection to concrete slabs isachieved if stiff topping is floated on concrete whichhas just started to set. This is the so- called "wetinto wet method" and should be used wheneverpossible. The application of topping on old concreterequires more work steps: chiselling and cleaningof surface, and watering and curing before and af-ter topping. When additional cement paste is re-quired, apply the cement paste immediately afterscreeching and floating the topping.
Process of shrinkage must be completed beforeany watertight mortar is applied. Joint betweenfloor and wall has to be improved with a hollowrounded fillet.
39
Building Construction
6.3 Brick and blockmasonry
6.3.0 General
The building procedure for bricks or blocks is thesame. Bricks and blocks must be bonded to givemaximum strength and adequate distribution ofloads over the wall. Only buildings with bondedwalls guarantee that the building is safe for theassigned purpose, and will not collapse during theconstruction.
Unbounded or insufficient bonding produces verti-cal joints with the accompanying risk of failure asshown below.
Bonded walls provide stability and resistance to theside thrust, as seen in the figure above. The bondcan be selected to give an attractive appearance tothe wall face.
6.3.1 Brick bonding
The term bonding means the arrangements ofbricks in which no vertical joint of one course isexactly over the one below. That means the brickis laid in such a way that it overlaps and breaks thejoint below. The amount of lap is generally half ofthe length of a brick. The minimum lap is V4 of thelength of a brick.
Bricks with the dimension of 22.5 x 10.5 x 7.5cmare handy to work with and suitable for all kinds ofbonding.
For horizontal joints (mortar bed) the thickness of12mm is recommended for brick work to ensure:• levelling of the mortar bed• placing of bricks completely in mortar• no uneven or incomplete support of the bricks
due to stones in the mortar
If the horizontal joints are too thick (more then12mm) it is a waste of expensive mortar (cement),as well as a weakening of the structure, becausethe joints are the weakest part of the masonrystructure.
For vertical joints (buttering) a thickness of 10mmis recommended for brick work because of the rea-sons in the list mentioned above. The reduction of2mm to the horizontal joints is possible because thecontact area is much smaller at the side than at thebottom.
In order to obtain a bond it is necessary to introduce"bats" (parts of bricks). Some of the commonlyused brick terms are:
40
Masonry work
Three quarter brick Half brick
There are many ways a brick can be laid. The mostcommon ways are:
Stretcher Header
Bricks can be laid in a variety of bondings. To pre-vent the crushing of bricks use bondings of as manyfull bricks as possible, three quarter and half bricks.There are other bondings possible, but they are notused for water supply structures.
6.3.2 Cement block bonding
The rules for cement block bonding are the sameas the rules for brick masonry. Blocks of differentsizes are available.
The most common type and size is:
40cm x 20cm x 20cm
Horizontal and vertical joints are increased to 15mmbecause of the reasons mentioned above (levelling,placing the blocks completely in mortar, and toavoid uneven or incomplete support). The increasedsize of cement blocks in comparison to bricks
makes cement block masonry very economical. Forcement blocks the stretcher bonding is most com-monly used.
6.3.3 General rules for bricksand cement block masonry(cement hollow blocks)
The rules required for construction in brick masonrywork are:a. Lay out exactly the proposed structure by mark-
ing the external side of the walls on the foun-dation (see Chapter 3.3.4).
b. Clean the foundation with a steel brush, wet itproperly, if necessary rough it by chiselling.
c. Lay the first two courses without mortar tocheck that the correct bond is achieved.
d. Cement bricks are cleaned and sprinkled withwater, burned bricks are soaked in water for 1minute before using them. This is important sothat the water of the mortar is not soaked awayby the bricks or blocks, which would reducequality and strength. If the brick is not clean, itwill reduce the strength of binding with themortar, as well as producing cracks caused byswelling and shrinking.
e. Check every brick for its brittleness (sound test)before using it for construction.
f. Lay the corners exactly with mortar and stretcha line from one corner to the other. There afterbuild the first course in between these markedlines.
g. In order that all courses have the same height,use a baton (straight edge) marking all courseson it.
41
h. Build the cornersj 4 to 5 courses high, thenwork along the line.
i. Make sure each course is exactly horizontal byusing a spirit level.
j . Build the walls exactly vertical by using a spiritlevel or a plumb bob line.
k. Quarter bricks should never be used at the endof a wall.
I. Use the same bond throughout the job.m. Use as many full bricks as possible.n. The left over mortar after each layer should be
cleaned from the bricks as well as from theground, so that it can be reused.
Masonry work
6.4 Stone masonry6.4.0 General
With regard to quality and durability stone masonryis one of the best, but work intensive. For buildingpurposes a good stone should possess strengthand durability. The strength of a stone under com-pression is an important quality factor. Therefore thestones used for water supply structures need to betested and selected as described in Chapter 2.1.2and 2.1.3. To obtain a minimum bonding, stonesfirst have to be shaped to their respective sizes. Theminimal wall thickness should not be less then 30cm. Stone masonry requires about 1.5 times moremortar in comparison to brick masonry.
6.4.1 Stone shaping
The surfaces of the stones which needs to be cutand shaped are:• Face
This is the front surface of the stone in eleva-tion.
Face
Side
Bed
Returned faceThis is the side surface of the stone.
BedThis is the top or the bottom of a stone. Thelower surface on which the stone rests and theupper surface which supports the stone above.
bed
43
Building Construction
Type of StonesTo shape a stone well is not a problem if enoughtime is taken to do it properly. Stone shaping canbe done by workers who can be trained and super-vised locally.
The following shapes of stones are used for con-struction:
Line stone
Arch stone
Stones built between corner stones are called linestones. They should be (but not necessarily) plainsurfaced. The combination of plain surface cornersand rough hammer dressed line stones give thestone masonry an attractive appearance.
Corner stone
The two faces should be squared and shaped withchisel and club hammer to a plain surface, or atleast hammer dressed to make accurate plumbingpossible.
Unlike the cornerstone the arch stone is shaped likea wedge and is more difficult to shape than anyother stone, because it has to be shaped to specificmeasurements.
Remark:The commonly used stones are corner and linestones, the arch stone is not so common and needsa work intensive shaping. The preparation in ad-vance of suitable cut and shaped stones is essen-tial for all stone masonry work. Large quantities ofsquared two and three face stones as well as cor-ner and line stones will greatly help the masons tofind the suitable stone.
Rules for stone shaping:• Workers shaping stones should always use eye
protection glasses.• All the stones should be of a size and weight
that can be carried by one person.• Select the stone and then choose the way you
want to shape it.
• Cut it first roughly on all sides, if possible ac-cording to its natural shape.
• No angle of the face to side surface should bebigger than 90°.
• Dress the face straight and check it with asquare or a straight edge.
• Select the stones which could be used as cor-ners and shape the reverse face.
• During the supervision time while stone shap-ing the simple quality test should be regularlydone as described in Chapter 2.1.3.
Remark:Make sure that the quality of the shaped stonesfulfill the requirements. Eye protection is extremelyimportant for the workers shaping stones.
44
Masonry work
6.4.2 Stone masonry
There are different kinds of stone masonry possi-ble. For water supply structures like storage tanksand chambers only uncoursed rubble masonry isrecommended. Coursed or squared-uncoursedstone masonry (similar to bricks) need a very pre-cise shaping and are therefore not appropriate be-cause of the precise specifications and workintensive shaping.
Uncoursed rubble masonry
Coursed or squared-uncoursed masonry
Uncoursed rubble masonry needs relatively littleshaping and less precise jointing work. The layoutand building of the structure will show clearly thebuilder's skill. Therefore, it is important to train build-ers in the special subject of stone masonry work.This kind of stone masonry uses all sizes of stoneswhose faces, joints and beds are roughly shaped.No attention is given to maintain level courses.
The rules for plumbing and lining are the same asfor brick laying. It is advisable to hang one line forthe inner wall and to work with two masons at thesame time. One mason builds on the outside, theother on the inside of the line.
Advantages of stone masonry:local available building materialhigh quality if properly selected and shapedmostly traditional building material of theregion
Disadvantage of stone masonry:needs about 1.5 times more cement andsand for construction than brick masonrylabour intensive cutting and shapingdifficult to transport
can cause erosion if not properly extracteddangerous for workers who cut and shapethe stones (eye and other accidents)
The rules for good construction in uncoursed stonemasonry work are:
A. Preparationa. Layout exactly the proposed structure by
marking the external side of the walls on thefoundation (Chapter 3.3.4).
b. Clean the foundation with a steel brush, wetit properly, if necessary rough it by chiselling
c. Two masons should work at the same timeon a wall, one inside and one outside thewall.
d. Use crack-free and washed stones
45
Building Construction
e. Stiff mortar should be used. Never fill theinside of the wall with slurry mortar becausethis will reduce the strength.
B. Construct iona. Use two-faced shaped and squared stones
for corners as well as for the top of the wall.b. Use the largest and straightest stones on the
ground and as corner stones.c. The stones should be laid on a mortar
bed and then knocked in the mortar with ahammer.
d. Build the cornerstones inside and outside,make also the back filling, then hang 2 lineson each side and build in between the lines.
e. The left over mortar after each layer shouldbe cleaned from the stones as well as fromthe ground so that it can be reused.
f. The overlap of the stones should be a mini-mum of 10cm.
Good Bad
g. The face and the inner part of the wall mustbe built at the same time.
h. The joints should not be thicker than 2.0-2.5cm but never less than 1.0 cm, dependingalso of the size of the stone.
i. Small pieces of stones are used for betterseating of shaped stones but they should notbe visible at the outside of the wall. It is im-portant that the small pieces of stones arewell bonded with mortar all around.
k. 4 joints should never come together at theface of the wall. Straight joints longer thentwo stones should be avoided.
I. Every third stone horizontally and verticallyshould be a binder. The length of the bind-ers should be at a minimum2/.j of the thickness of the wall.
m.The top of the wall should be built withshaped stones which are properly bondedinto the rest of the wall.
Bad
46
7.Concrete Work
Concrete work
7.0 GeneralWhere conventional building materials like stonemasonry, brick masonry, timber etc. do not fulfill therequirements, or are not available a concrete con-struction is the only other solution. Therefore, con-crete has a large range of applications. It is mostsuitable where high comprehensive strength is re-quired. In combination with steel a high tensilestrength can be achieved. Concrete work requiresa special and different work procedure. Each nec-essary step to produce concrete is of importancefor the quality of the end product.
7.1 Concrete7.1.0 General
Concrete means a mixture of cement, water, fineand coarse aggregates (sand and gravel). The qual-ity of concrete depends on the requirements beingmaintained for the aggregate as described in Chap-ter 2.2.2 Testing. Additionally important are mixing,water cement ratio, transporting, placing and com-pacting as well as curing.
7.1.1 Aggregates
Sand and gravel need to be clean (see Chapter2.2.2) and in the required granulation as describedbefore. If there is too much sand or silt the surfaceof the aggregates is increased and the cement hasto bind this larger surface together. Therefore, withtoo much sand or silt more cement is required orthe strength of the concrete is reduced. Too muchgravel causes spaces inside the concrete, the work-ability is reduced, and proper compacting is notpossible.
Good composition
3v^frfflr"?
Too much sand
Too many stones
If possible use coarse grained sand andnever the fine sieved sand used for masonry work.Remainders of coarse sand fromsieved masonry sand can be added to the aggre-gates when mixed with coarse grained sand.
To obtain a proper granulation the componentsof grains should be within the range shown inthe following chart. The test itself is described inChapter 2.2.2.
47
Building Construction
The test (sieve analysis) should be made by atrained laboratory assistant or an experienced per-son. In properly made concrete each particle ofaggregate, no matter how large or how small, iscompletely surrounded by cement paste and allspaces between the aggregate particles are filledwith the paste.
In a well graded mixture the portion of large grainsshould be higher then the portion of medium grains,and the portion of medium grains should be higherthan the portion of fine grains.
The quality of the concrete is reduced in the follow-ing cases:
Too much sand:Enlarges the surface and therefore causes porosity,resulting in reduced compressive strength and den-sity (not waterproof).
Too much gravel:Causes large spaces and therefore reduces thecompressive strength and density (not waterproof).
7.1.2 Water
Water in the concrete mixtures serves two purposes:• First to take part in the hydration reaction (set-
ting and hardening) of the cement.• Secondly to make the mix fluid and plastic
enough so that it can be easily worked andplaced.
The quality of water that is fit for drinking is also fitfor mixing concrete. The consistency of concrete isinfluenced by the amount of water added.
The plasticity varies according to the amount ofwater added as well as according to the amount ofwater contained in the aggregate.
7.1.3 Water-cement ratio
The water-cement ratio is an important factor inconcrete mixtures. Not only the workability of con-crete, but more importantly the strength dependson this ratio.
The water-cement ratio also depends onthe porosity and moisture content of theaggregates. If the aggregates are wet
(sand out of the river/rainy weather), the amount ofwater added has to be accordingly reduced.
The natural moisture of aggregates varies accord-ing to the weather conditions as shown below:
Weather
dry season
rain & sun mixed
rainy season
Sand
25-30 l/m3
70-80 l/m3
160-170 l/m3
Gravel
35-10 l/m3
25-35 l/m3
70-80 l/m3
Therefore, the water content in a concrete mixtureincludes the mixing water as well as the naturalmoisture of the aggregate.
The best results for strength and density areachieved by using a stiff plastic mixture with awater-cement ratio of 0.5 (1:2) or less.
water in kg (litre)water-cement ratio =
cement in kg (litre)
Remark:Only half of the water in the mixture is required forthe chemical reaction. The rest will remain or evapo-rate gradually as the concrete hardens, leaving smallholes. Not surprisingly holes weaken the concreteand so the more excess water there is in a mixture,the weaker will be the concrete.
7.1.4 Concrete mixtures
The mixtures of concrete are usually expressed in"PC" which gives the amount of cement requiredto produce 1.0 m3 finished concrete of specificquality. For example PC 300 means that 300 kg ofPortland cement per 1.0 m3 finished concrete isused (cast and compacted).
The mixtures can be calculated by one of the fol-lowing two methods:
a. Volumetric methodThe mix-method for small quantities (hand mixes)is the so-called volumetric ratio cement : sand :gravel method. It is commonly used at village wa-ter supply construction sites.
For example the ratio 1 : 2 V2: 4 means that 1 partcement and 2 V2 parts sand and 4 parts gravel areused for the mixture.
48
b. Weight methodConcrete mixtures are also expressed in kg ofcement per 1.0 m3 of concrete. For example PC250 means that 250 kg of cement, -1000 litresof sand and gravel, and 120 litres of water areused to produce about 1.0 m3 of concrete.
According to the mixture are produced the follow-ing types of concrete:
a. Lean concrete (PC 100-PC 150)This type of concrete is used in a stiff consist-ency for filling or surrounding purposes, and tocreate a clean bed to protect steel reinforcementfrom the soil. Lean concrete is rammed.
b. Unreinforced concrete(PC 2 0 0 - 2 5 0 )This type of concrete is used in a plastic ormedium consistency for structural parts withmoderate strength requirements like for small
Concrete work
foundations, pillars and floor slabs etc. Goodcompacting of unreinforced structures guaran-tees a strong and long lasting concrete. Unre-inforced concrete is rammed.
c. Reinforced concrete (PC 250-350)Reinforced concrete is of plastic or medium con-sistency.
This type of concrete is used for structures withhigh demands on compressive and tensilestrength. Pillars, lintels, beams and slabs are onlya few to be mentioned. Compacting with suit-able tools or a vibrator is very important.
The required concrete mixtures should be describedin the construction plan. Common mixtures used atvillage water supply structures are shown in thefollowing table:
PC
100
150
200
250
300
350
Part cement
1
1
1
1
1
1
Part sand
6
4
3
2 V2
2
1 V2
Part gravel
9
6
5
4
3
2 V2
Quality of concrete
Lean concrete
Lean concrete
unreinforced concrete
reinforced concrete
reinforced concrete
reinforced concrete
7.2 Mixing andprocessing ofconcrete
7.2.0 General
The correct mixture is an important first step in theprocessing of concrete, which also includes trans-porting, placing, compacting and curing. All thesefactors are very important and influence greatly thestrength and quality of concrete.
7.2.1 Hand mixing
49
Building Construction
Hand mixing does not require much equipment, buta lot of man power. A batch to be hand mixed shouldnot be larger than about 0.5 m3. Concrete shouldnever be mixed on soil because of the proved dan-ger of contamination by organic matters. A levelledplatform has to be prepared to prevent water or fluidmaterial from flowing out of the mixture.
The following points must be kept in mind whenhand mixed concrete is foreseen:a. Concrete should always be mixed on a level and
clean platform, which is sprinkled with waterbefore mixing starts.Suitable platforms are:- Concrete slabs / rock / moulds / or iron-
sheets- It is recommended that for a large construc-
tion site perhaps a concrete slab should bemade
b. Spread the first layer (sand) and the secondlayer (stones) on the platform, then spread thecement on top.
c. Mix the material dry until there is a uniform ap-pearance. Therefore, at least three times of mix-ing necessary.
d. The material is then shovelled into a flat heapwith a hollow in the centre into which about halfthe required water is poured.
e. Then the final step of the mixing procedurestarts by shovelling the material from the edgesto the centre, emptying each full shovel andthen turning it over again. Add water as neces-sary to obtain required consistency as the ma-terial is turned over again.
Remark:Setting time can start half an hour after pouringwater into the mixture. Therefore, do not mix morethan 0.5 m3 at once (10 wheelbarrows). If the con-crete mixture is disturbed during setting time (ifsetting time has already started before the concreteis put in place and rammed or vibrated) it will causeloss of strength.
7.2.2 Machine mixing
There are a variety of mixing machines available. Itis important to maintain these machines daily (in-cluding cleaning). Before the aggregates are put intothe drum, the drum has to be sprinkled with water.The batch is to first mix dry, and after about 45seconds the water should be poured in. The mix-
ing procedure continues for about another 45 sec-onds. Mixing more than about 1 and a half minutesdoes not improve the quality of the concrete, butis a waste of energy.
7.2.3 Processing of concreteThe processing of concrete can be divided into fourphases:
Phase 1: TransportingTo avoid separation of aggregates keep the trans-port distance always as short as possible. Use tidebuckets or pans so that the cement milk can notflow out during the transport.
Phase 2: Placing and castingBefore any concrete is placed, the form work needsto be checked for cleanliness, strength, tightnessand alignment. It is essential to keep the form workwet and sprinkle with water before the castingstarts. If the form work is not sprinkled the boardswill absorb a large amount of water. This will nega-tively influence the chemical reaction during settingand cause a rough surface and a reduction instrength. The concrete should be placed in layers.Each layer must be compacted before the next oneis put down. The following layer should be put downbefore the setting of the previous one has started.
Phase 3: Compacting
After concrete is placed it contains entrapped air inthe form of voids. The object of compacting is toget rid of as much as possible of this entrapped air.Voids reduce strength, waterproofness, and properbinding to the reinforcement. Insufficient compact-ing is visible on the concrete surface by the pres-ence of large numbers of air bubbles and rockpockets. Compacting can be done by hand or witha vibrator. The vibrator should be operated by skilledpeople. The needle of the vibrator should not bebrought too close to the formwork or the reinforce-
50
Concrete work
?<=D^m
ment, to avoid vibration on the formwork or rein-forcement. The vibration can cause holes and there-fore weaken the structure.
!
i
' • I
' I 7
• •'•=>[]
<, a;('" '̂\
ii
".••. \ - ^ f ' / / •/•• •
i
|
;
:
' m : f •'•••:
Phase 4: Curing
Curing is necessary to provide sufficient moistureto enable the process of cement hydration. Curingshould be started at the very beginning of setting.The longer the period of curing, the better the qual-ity of concrete. Therefore the minimum period ofcuring should be at least 7 to 14 days, dependingalso on the weather influences. Methods of curingare sprinkling or flooding of water, covering thesand, or empty cement bags or plastic sheets. Ifthere is any danger of frost reduce the water cur-ing and cover additionally with suitable insulationmaterial like empty cement bags, grass, or woodplanks etc.
7.3 Quality of concrete7.3.0 General
Each different part of a structure may use a differ-ent strength of concrete. There exist several differ-ent methods to test the quality of concrete. The testprocedures of these methods are quite compli-cated, and require a laboratory with expensive in-frastructures. Therefore, in this manual only roughtesting is described. For more and detailed informa-tion refer to Ref. 2 in the bibliography at the end ofthis manual.
7.3.1 Cube test
The concrete specimens are cast in steel or cast-iron moulds, which should conform to the cubicalshape (generally a 150mm cube). The inside surfaceof the mould should be covered with a thin layer ofmineral oil in order to prevent the development ofbonding between the mould and the concrete. Themould is to be filled in three layers, whereby eachlayer is compacted by not less then 35 strokes ofa 25mm square steel punner. After the top surfaceof the cube has been finished by means of a trowel,the cube is stored undisturbed under the sameconditions as the structure to be built. After 28 daysthe cube is take for the compression test. At thistest the cube is placed with the cast faces in con-tact with the platens of the testing machine. Theload on the cube should be applied at a constantrate of increasing stress. The crushing strength isthen reported to the nearest 5kg/cm2.
7.3.2 Rebound hammer test
The difficulties of core cutting, and indeed the en-tire procedure of making, curing and testing ofstandard test specimens would all be avoided ifconcrete could be tested in such a manner harm-less to the part tested. One method that has foundpractical application within a limited scope is therebound hammer test. It is also known as the im-pact hammer, or sclerometer, test.
The test is based on the principle that the reboundof an elastic mass depends on the hardness of thesurface against which the mass impinges. In therebound hammer test a spring-loaded mass has afixed amount of energy imparted to it by extendinga spring to a fixed position; this is achieved by
51
Building Construction
pressing the plunger against the surface of the con-crete under test. Upon release, the mass reboundsfrom the plunger, still in contact with the concretesurface, and the distance travelled by the mass,expressed as a percentage of the initial extensionof the spring, is called the rebound number. In re-lation to this number the strength of the testedconcrete can be found. Multiple testing is requiredbecause the results may show considerable differ-ences. This is the case where the hammer hits astone or a point with only sand and cement. There-fore, it is recommended to perform at least at 5different place the test and calculate the average toget a reliable idea of the concrete strength.
Remark:For sophisticated structure in reinforced concretethe quality testing of the concrete is required. Ingeneral for water supply structures the testing ofthe concrete quality is not required. Still it is mostimportant to fulfil the quality requirements de-scribed hereafter:
Compressive Concrete Strength Table
Amount of Cementper m3 finishedconcrete (kg)
150
200
250
300
350
Compressive strength after
3 days 7 days(kg/cm2) (kg/cm2)
31.5
49.5
72.0
99.0
126.0
49
77
112
154
196
28 days(kg/cm2)
70
110
160
220
280
7.4 Reinforced concrete7.4.0 General
Concrete can support heavy loads in compression,but its tensile strength is relatively low, being aboutone-tenth of the compressive. On the other hand,steel has a very high tensile strength.
pI
By embedding steel bars in the concrete, advantageis taken of these properties to improve the loadcarrying capacity of the structure. The steel isplaced in the concrete that is subjected to tensionbut also to avoid cracks due to shrinking.
7.4.1 Reinforcement
There are two main categories of reinforcement bysteel. The main reinforcement to take over the ten-sion and the distribution reinforcement to spreadthe loads and to keep the main reinforcement inposition during casting.
The main reinforcement should always be at the sitewhere tension occurs. It should not be closer than 3.0cm to the shuttering or the top, to avoid corrosion ofthe reinforcement. Steel bars of plain surface (mildsteel) need to be hooked at the ends to obtain bet-ter adhesion, and therefore create a greater strengthfor the structure. Hooking is not necessary for steelbars with ripped surface (Thor steel).
52
Concrete work
A proper bond between the steelrods and the con-crete is the most important supposition for rein-forced concrete. The surface of the rod has to beclean and not to rusty. In order to provide a properbond the rods have to be surrounded completely bythe concrete. The reinforced concrete has to bevibrated with a vibrator. Plain bars must have endswith hooks which should be anchored in the pres-sure zone. Deformed bars with ripped projectionscan have straight ends but then the anchorage hasto be in the pressure zone of the structure.
If rods have to be overlapped the following rulesshow the minimum overlap length:rod with hook45 times diameter of the rodstraight65 times diameter of the rod
can be extended by using plastic or metal sheets.
Remark:The proper placing of reinforcement for structuresof high quality concrete requires a working drawingor reinforcement plan, containing all the necessaryinformation (see Engineering manual of this series).
7.4.2 Form work
Most structural concrete is made by casting con-crete into spaces of previously constructed boxescalled forms. Usually wall, column, beam and slapforms are build by joining boards edge on edge,sometimes plywood may nailed on setting since itis tighter and more wrap resistant. In certain casesmetal forms are used, e.g. when a large number ofequal structural members (precast elements) haveto be erected or when the parts should be veryexact in measurements.
The most suitable material for form work is wood, inparticular boards, rails, batten and planks. All this tim-ber is available in various quality and dimension. Hard-wood should not be used for parts where nailing isnecessary. Boards of less quality and boards of roughsurface do not last very long as shuttering. The reuse
All form work material (planks, boards, steel etc.) andelement form work (moulds) are sprinkled with wa-ter before placing concrete. After striking or disman-tling, the form work is cleaned and eventually oiledas well as properly stored and protected from sun andrain. This will guarantee the use of many times.
Form work for precast products like cover slabs,fence posts, well and culvert rings, and elementform work for standard structures like stand posts
should be made of quality timber or steel. The useof G.I. sheets as additional reinforcement for tim-ber form work is very suitable because nailing ofside boards or batten is still possible.
7.4.3 Precast concrete
Structural parts which are not possible to cast onsite or which are more economical to prefabricate,are precast concrete products like:• lintels• manhole covers• slabs• rings• pools etc.
The consistency, mixture and reinforcement ofprecast concrete depends on the purpose and/ortransporting facilities. The procedure of precastconcrete is the same as for other concrete. It isimportant to have sufficient working and storagespace and a proper follow up treatment like curing.No removal during setting and hardening time, aswell as good weather protection are essential. Thelocal stores may have some of the prefabricatedproducts like lintels. Therefore, it is to be decidedif locally made products are fulfilling the require-ments.
53
Building Construction
Advantages of precast concrete:
fast productionhigh quality
economical use of shutteringcheap
Disadvantages of precast concrete:
transporting to the siteexact working at the construction sitebecause no adjustment is possible
54
Construction of a masonry tank
8.Construction of a Masonry Tank
8.1.0 General
There are many different layouts of tanks possible,like round or rectangular ones. Important for thelayout is the proper water circulation from the inletwater to the outlet water. It is essential that thereis no standing water in the storage basin, otherwisethe quality of the drinking water is not guaranteed.The construction of round tanks is especially be-cause of the roof construction more sophisticatedand therefore in this manual not described. Thewidth of the tanks is limited to about 2.5m becauseof the roof construction with precast concrete slabs.The size and therefore the weight of these slabs islimited by the requirement that they still can be putin place without technical help. This type of con-struction has been successfully tested over yearsand has been found to be suitable for many watersupply projects all over the world.
This manual looks mainly at the building part andprocedure of the storage tank, whereby the manu-als Engineering and Storage and Distribution go intothe details of construction and arrangements ofstorage tanks.
8.1.1 Site preparation
Before the construction of the tank is started thefollowing preparation work needs to be done:• Preparing the required material according the to
construction plan.• Excavation of the tank side• Setting out of the structure
8.1.2 Construction
The construction of a 10 m3 tank for example canbe divided into the following steps:1. Casting and compacting the 20cm thick founda-
tion in concrete PC 250 with welded mesh ontop and on bottom. At this tank design the sup-ply, washout and overflow pipe is cast into theslab.
2. Building the wall according to the required bond-ing.
3. During construction of the wall the precast slabsshould be cast. For the 10 m3 tank there are 6slabs with the dimension 74*190*6cm required.The schedule for casting the slabs should bechosen that the last slab is finished at least 20days before they are going to be put on top.Otherwise the strength of the slap is not accord-ing to the requirements (see also Chapter 6.3).
4. As soon as the wall construction is finished theplastering to make the tank waterproof can bestarted. This procedure requires a stop of the
55
Building Construction
work at the tank site for at least 10 days (set-ting time of spaterdash). Therefore, during thistime the construction work of other parts of thesupply can be started.
5. During the time of plastering the pointing of theoutside wall can be done.
6. As soon as the plastering is finished the tankshould be filled up with water for about oneweek to test if it is watertight.
7. The last construction part of the building is tocover the tank. Therefore, the precast slabs areput in place. One special designed cover withan opening for a tank with a manhole (for main-tenance reasons) is put a the side where thesupply washout and overflow installations are.
8.1.3 Finishing work
The storage tank is after the spring chamber themost important building of the water supply. There-fore, the finishing work at the surrounding shouldbe done most carefully. The detailed arrangementsaround the tank site are described in the manual thesupply system.
56
Reference books
Reference Books
Ref.1 - Appropriate Building Materials, SKAT1981/1983/1993
Ref.2 - Properties of Concrete A M Neville(Longman Scientific & Technical)
57
top related