Building for Learning ProjectPhoto Progress Report
October 2009
Project commencement 21st September 2009
New roof going up (over rooms 4 and 5)
If you look closely, you will see the old
wooden shingles which were the original roof dating back to the late
1890’s
1st Oct 2009
Admin empty ready for refurbishment to begin by 19th Oct2nd Oct 2009
New roof being added to original school building dating back to 1874 – 2nd Oct 2009
Major roof works completed – 5th Oct 2009
Internal Demolition Begins 6th Oct 2009
Classrooms 6-9 Demolition continues Oct 2009
Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor
Racking construction for refurbishment storage 14th Oct 2009
Demolition continues Oct 2009
Corporate Services area refurbishment 19th Oct 2009
Windows removed Ceiling Fans replaced
Floor demolition 19th Oct 2009
Graeme Connelly supervising wall demolition 21st Oct 2009
Internal framing and windows being cut in 27th Oct 2009
Framing and floors added 28th Oct 2009
Staff inspections of works
Outside area demolition ready for major works to begin 29th Oct 2009