by ghanendra fago cost concepts, cost classification and estimation

Post on 23-Dec-2015

226 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

BY GHANENDRA FAGO

Cost concepts, Cost Classification and

Estimation

Cost Concepts

Cost refers the amount of expenses spent to generate product or services.

Cost refers expenditure that may be actual or nominal expenses incurred to generate output.

Cost is the value of economic resources used as result of producing or doing the things.

Cost has many meaning but in management cost refers the expenditure not the price.

As a manager we use cost information for taking decisions and making plans, programs and policies and strategies.

Cost according to elements of cost

Direct material Direct laborDirect expenses Overheads

Cost According to function- Manufacturing Vs. Non-manufacturing costs

Manufacturing Costs Manufacturing costs involves the cost of raw

material, labour and use of equipment to finished goods

Composed up of the following elements. Direct material Direct labour Overheads

Elements of Manufacturing Cost

Materials LabourOverheads- indirect material labors and

factory expenses

Non manufacturing Cost

Cost other than manufacturing cost that are incurred for sale

Non-manufacturing costs are: Selling expenses /marketing expenses Promotion, or Advertisement costs, Administrative costs

Cost according to behavior

Variable costMixed costFixed cost

Variable costs

Variable costs are based on activity. The variable costs should be zero at zero activity. They change directly with changes in activity level

in a responsibility center. If output is doubled, variable expenses is to be

doubled, if output increases by 15% the variable expenses

also increase by 15%, if output is zero, the variable cost also zero.

Variable costs are usually characterized by:

Unit cost remains constant.

Total costs that increase as activity increases.

Total costs that decrease as activity decreases.

Total costs changes proportionality with changes in output.

Variable cost

Units of products 0

cost

Variable cost per unit

Variable cost

Fixed Cost

Fixed cost is also called period cost or capacity cost.

It does not change in short term period or within a relevant range.

They accrue primarily with the passage time.Fixed costs are caused by holding of assets

and other factors of production in a state of readiness to produce.

Characteristics of fixed cost

Unit cost increase as activities/outputs decrease.

Costs that remain constant even activities are decreased or decreased

Cost per unit that increases as activity decreases and vice versa

Total costs that remain constant.

Fixed cost curve

Fixed cost

Units of products 0

cost

Committed fixed cost

Committed cost arises from the ownership, facilities or possession of assets.

Committed cost can not be changed by a simple decision.

Major decisions to change. For example: property tax, Loan installments depreciation, insurance etc.

Discretionary fixed Cost

Arises from management decision Controllable costsCan be easily changed by decisions Examples:

Advertisement,Training costsmarketing expenses, promotional expenses etc.

Step fixed costs

Remains constant over fixed range of activities but jumps to different amount for the activities levels outside the range

Semi–Variable Expenses/ Mixed costs

Semi–variable expenses also changes with changes in output or activity but not in proportion to changes in activity or output

Semi variable expenses have some of the characteristics of both fixed and variable costs.

Semi variable expenses are caused by combined effect of passage of time, activity or output and management discretion decisions.

Methods of Cost Segregation

Engineering analysisAccounting analysisHigh Low point methodsLeast Square Regression Analysis

Engineering Analysis

Systematic review of costs for product and services

Measuring cost behaviors according to what cost should be, not by what have been

Mixed Cost Function = Rs4,000 + Rs.600 X Per Day

Accounting analysis

This is a simple method Segregates cost into fixed and variables

based on certain cost driver.

Example: The Directorium Manufacturing Company produced and sold 80,000 units at Rs. 50 each. The cost for 1976 were as follows:

Particular Fixed Cost Variable Cost

Direct materials - Rs.200,000

Direct labour - 160,000

Manufacturing overhead Rs.440,000 20,000

Selling and admi. expenses 280,000 100,000

Mixed cost function = Rs.720,000 + Rs.6 X units of production

High Low Point method

Under this method, semi variable cost can be segregated into variable and fixed cost based on the two extreme levels of activities using the following formulas.

Variable rate (b) = [Cost at high point- Cost at low Point]/

[High point –Low point]Fixed cost (a) = Total cost – Variable rate Level of

activitiesTherefore, the cost volume formula:Total cost = Fixed cost + (Variable rate levels of

activities)

Advantages and Disadvantages

Advantages:It is easy and less time consuming.Cost behavior is restricted to the relevant

ranges.It will be more suitable when there are two

levels of activities to estimate cost.Disadvantages Use of only two extreme conditions may not

be representative of normal conditionsIt may give the unreliable estimate of fixed

cost (a) and variable rate (b).It does not specify the fixed cost below and

above the two levels of activities.

Least Square Analysis

One of the best and widely used methods in cost estimation, A statistical procedure for estimating mathematically the

average relationship between the dependent variable (y) and independent variable (a).

It includes all the observed data and attempts to find the line of best fit in estimation of variable and fixed cost.

Under this method, the following least square formula can be used to estimate cost.Y = a + bxWhere, a = Estimated fixed cost i.e. constant

b = Variable rate i.e. slope of regression lineY = Dependent variable i.e. estimated total

costX = Independent variable i.e. Level of activity

or units of products, hours etc

Least Square Formula

22 XXN

YXXYNb

22

2

XXN

XYXYX

XbYa

activitiesoflevelsX

rateaibleb

tfixeda

Where

var

cos

Regression Statistics

Least square regression method is used to estimate variable and fixed cost.

However, it doses not explain the accuracy and the reliability of the regression result.

To explain the accuracy and reliability of the regression result, Correlation coefficient (r) and Coefficient of Determination (r2)

Correlation Coefficient (r)

Goodness of fit regressions line can be measured by assessing correlation coefficient. The correlation coefficient can be computed as follows:

Correlation coefficient (r) =

Explanation: The correlation coefficient measures the degree of

correlation between y and x. Therefore, it should be between +1 and –1. If not, it means, it is unclear about the results. Then, coefficient of determinant should be computed to find the meaningful result using the following formula.

2222 YYNXXN

YXXYN

Coefficient of Determination (r2)

r2 = [ ]2

Explanation:It means that ….% of the goodness of fit in

regression line. Therefore, higher the degree, more the confidence in cost estimation. In other words, …. % means the total variation of total cost is due to change in levels of activities and remaining in due to other factors other than the independent variable.

2222 YYNXXN

YXXYN

Data for total power costs and machine hours are given below:Power Costs (000 omitted) Machine Hours (000 omitted)

Rs.7683488675

9884679586

Rs.62 70 hours

1. Required:a) Separate the power costs into the fixed and variable

components using the method of least squares. b. Estimate the power costs when 6.5 machine hours are used.c. Compute the coefficient of determination.d. Does the regression equation need to be improved?e. t-value, e) Standard error of coefficient (Sb)

Classification of cost according to decision making

Relevant Cost and Irrelevant Cost Avoidable and Unavoidable Costs Out of pocket costs, Opportunity, Sunk costs Period Cost and Product Cost Direct Vs. Indirect cost Controllable and Uncontrollable Cost Incremental Cost/Differential Cost Committed fixed cost and Discretionary fixed

Cost

Relevant cost

Costs and expenses which are directly influenced by decision are relevant costs.

All future cost are relevant cost. They are pertinent and valid costs.

Relevant costs include all variable costs and additional fixed costs which are incurred because of the decision being taken

Irrelevant Cost

In other hand, costs that cannot be changed are called irrelevant costs. Irrelevant costs include the existing fixed costs which are going to exist even after the decisions are taken. Such costs do not affect the decision

Controllable and Uncontrollable Cost

Controllable and uncontrollable cost depends on the point of reference.

Uncontrollable cost at lower level may be controllable at top level, uncontrollable in short term may be controllable in the long run. etc.

A cost is a called controllable at particular level if the level has power to authorize the cost.

If it has not, it is called uncontrollable cost.

Avoidable VS Unavoidable Costs

Avoidable costs can be saved simply by not doing the alternative courses of action.

They are relevant in decision makingUnavoidable costs are irrelevant cost because they

can not be avoided or eliminated by taking decisions or alternatives.

If the revenue generated by avoidable cost is high, we have to take decisions

Direct Cost and Indirect Cost

Direct costs are directly traceable or identifiable to a particular job or department or product and are controllable.

Indirect costs are uncontrollable and no-traceable costs.

Cost may be direct but the same may be indirect depends on the situation.

Incremental Cost/Differential Cost

Cost difference between two alternativesIf differential costs are increased, it is called

incremental cost and decreased, and called decremental cost

Incremental cost refers the only the increased cost from one alternative to another.

Differential cost or incremental cost can also be used to analyses alternatives for decision-making purpose

Period Cost

Period costs are not manufacturing cost. However, they are incurred and paid based on the period

They are deductible from revenue.Example: Rent, salaries, telephone etc.

Product Costs

Product costs are manufacturing costs They are incurred for the manufacturing of goodsThey include direct material, direct labour, and

manufacturing overheads. Example: direct material, labour cost,

manufacturing overhead etc.

Out of pocket expenses

Expenses incurred for activities for raw materials, labour overheads etc.

Opportunity Cost

Not recordable in the books of account but are considered in every decisions of managers.

It is the amount of benefit that is sacrificed when one alternative is selected.

Sunk costs

Costs are the cost incurred a result of past decisions.

Cost can not be changed by taking operating decision

Sunk costs are irrelevant from decision making.Sunk costs are depreciation of assets, lease rent

etc.

top related