© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
Configuration Management Information System (CMIS) using the PIM for the Power Industry. Opportunities, Challenges and Lessons Learnt
Kevin Gribbin June 2015
© 2015. Intergraph Corporation. All Rights Reserved
Topics
Intergraph Who are and What do we do
CMIS and PIM
PIM – “Current State”
Integration and Automation Opportunities
Handover – Turnover
PIM – “Future State”
Questions
© 2015. Intergraph Corporation. All Rights Reserved
Introduction
Kevin Gribbin – Director, Integrated Management Systems
Global Power Group
Global Presence Responsibilities – SEA – India – Europe – South Africa
35 years of Information/Configuration Management Experience
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
Headquartered in Huntsville, Alabama
In business for 45 years
© 2015. Intergraph Corporation. All Rights Reserved
PP&M Worldwide Representation
3,000 Intergraph PP&M team members offer services and support in more than 40 countries
© 2015. Intergraph Corporation. All Rights Reserved
Intergraph Technology Portfolio
© 2015. Intergraph Corporation. All Rights Reserved
© 2015. Intergraph Corporation. All Rights Reserved 8
Standards and Open Platform
Standards – Exchange standards , CCITT Group IV, CGM – Content standards – “De facto” File Format Standards – Direct Interfaces (APIs) – Alliances
Open Platform – Microsoft operating systems – Relational databases – Development environment – Integration frameworks & portal
© 2015. Intergraph Corporation. All Rights Reserved
The CHALLENGE: Managing and Controlling Change
From 2009 EPRI Report “New Nuclear Power Plant Information Handover Guide” : “Configuration Management is a set of processes, practices, and tools necessary to effectively manage all the obligations regarding the design, construction, operation, maintenance, and decommissioning of a NPP, thereby maintaining consistency between the design and licensing basis requirements (what needs to be
there), the physical configuration (what actually is there), and the configuration information (what we say is there).” “Design & Licensing Basis Information (DLBI) is one of the cornerstones of configuration management.”
© 2015. Intergraph Corporation. All Rights Reserved
What is a CMIS?
Configuration management helps ensure the plant’s safe operation by providing fast & reliable answers to these fundamental questions:
– For any item or system in my plant, what are the relevant design documents and governing requirements & regulations?
– For any regulatory document or design basis document, what are the affected items or systems in my plant?
– What documents do I have that prove the systems in my plant are operating in compliance with the above?
– What tags are in a particular system and what is the manufacturer and model number of each?
– Where in my plant are the following tag numbers located?
– What drawings contain these tags and when was the drawing last updated?
Configuration Management and Information System is an advanced plant information management system for nuclear power plants.
10
© 2015. Intergraph Corporation. All Rights Reserved
What is CMIS and who requires it?
6/23/2015
NRC's regulations are found in Chapter I of Title 10, "Energy," of the Code of Federal Regulations (CFR). Principal parts governing the licensing and operation of nuclear reactors: • Part 26 - Fitness-for-duty programs • Part 50 - Domestic licensing of product and utilization
facilities • Part 51 - Environmental protection regulations for
domestic licensing and related regulatory functions • Part 52 - Early site permits; standard design certifications;
and combined licenses for nuclear power plants • Part 54 - Requirements for renewal of operating licenses
for nuclear power plants • Part 100 - Reactor site criteria
Institute of Nuclear Power Operations
(INPO)
AP929
“Configuration Control”
Institute of Nuclear Power
Operations (INPO)
INPO-09-00
“New Plant Configuration Management
Development & Implementation
Process”
• In many countries, regulatory authorities require a CMIS to obtain an operating permit.
• CMIS may include a document management capability, but a document management system is not a CMIS.
• CMIS principles being defined by the nuclear industry.
ANSI/NIRMA
CM-1.0 2000
“Configuration Management of
Nuclear Facilities”
IAEA
TecDoc 1335
“Configuration Management in Nuclear Power
Plants”
© 2015. Intergraph Corporation. All Rights Reserved
Key Industry Publications & Recommended Practices
EPRI: • Advanced Nuclear Technology: New
Nuclear Power Plant Information Handover Guide (2009)
• Elements of Pre-Operational and Operational Configuration Management for a New Nuclear Facility (2011)
IAEA: • Safety Reports Series – No.65 Application
of Configuration Management in Nuclear Power Plants (2010)
• Managing the First Nuclear Power Plant Project (2007)
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
CMIS and PIM
© 2015. Intergraph Corporation. All Rights Reserved
Integrated CMIS Scope
14
CMIS Scope
© 2015. Intergraph Corporation. All Rights Reserved
Construction planning, mat’l mgt, and ITAAC tracking activities occur in Reference Design phase
Configuration Management: A Lifecycle Approach
CMIS ‘A’ CMIS ‘C’ CMIS ‘B’
Load Data & Documents from
Vendors, Contractors, etc
For Prime Contractor
Load Other Data &
Documents
For O/O
Inquiries & Commitments
with regulators, others
MCAD & Other
Tools
A/E or NSSS Vendor Reference Plant or Reactor Development
Prime Contractor Site Specific Project
Plant Operator Generating Plant System
Project Award
CM principles begin in design with effective change management and data correlation between disciplines
CMIS ‘A’ manages design basis, deliverables, tests & requirements
CMIS ‘B’ manages design basis, procured items, tests, commitments & requirements
CMIS ‘C’ manages design basis, assets/SSC’s; margin & requirements, In-Service Testing, operations support
Inquiries & Commitments
with owner, regulators, others
Turnover Data Load Handover
Load Other App
Data For A/E or NSSS
Project Turnover
ITAAC Tracking
ITAAC Tracking IST
Tracking
Tools
© 2015. Intergraph Corporation. All Rights Reserved
Construction planning, mat’l mgt, and ITAAC tracking activities occur in Reference Design phase
Configuration Management: A Lifecycle Approach
CMIS ‘A’ CMIS ‘C’ CMIS ‘B’
Load Data & Documents from
Vendors, Contractors, etc
For Prime Contractor
Load Other Data &
Documents
For O/O
Inquiries & Commitments
with regulators, others
MCAD & Other
Tools
A/E or NSSS Vendor Reference Plant or Reactor Development
Prime Contractor Site Specific Project
Plant Operator Generating Plant System
Project Award
CM principles begin in design with effective change management and data correlation between disciplines
CMIS ‘A’ manages design basis, deliverables, tests & requirements
CMIS ‘B’ manages design basis, procured items, tests, commitments & requirements
CMIS ‘C’ manages design basis, assets/SSC’s; margin & requirements, In-Service Testing, operations support
Inquiries & Commitments
with owner, regulators, others
Turnover Data Load Handover
Load Other App
Data For A/E or NSSS
Project Turnover
ITAAC Tracking
ITAAC Tracking IST
Tracking
Tools
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
PIM
“Current State”
© 2015. Intergraph Corporation. All Rights Reserved
Typical Situation
Design Basis (SSC’s)
Change Management
Transmittals
Requirements Management
Inspection and Testing
Document Management
Configuration Management
Operations and Maintenance
© 2015. Intergraph Corporation. All Rights Reserved
Typical Situation – What is the Context
Design Basis (SSC’s)
3rd party app
In-house app
Requirements Management
Inspection and Testing
Document Management
3rd party app
Operations and Maintenance
Why? What? When? Where? Who?
© 2015. Intergraph Corporation. All Rights Reserved
Typical Situation – What are the Risks
Design Basis (SSC’s)
3rd party app
In-house app
Requirements Management
Inspection and Testing
Document Management
3rd party app
Operations and Maintenance
Incompatible Formats Data Duplication/Replication Poor Information Integrity Complex Change Management No Auditability/Traceability
• What/When/Who Geometric IT Cost Curve Upgrade Options
© 2015. Intergraph Corporation. All Rights Reserved
Requirements Management
Document & Data
Management
Plant Structure
Management
Change Impact
Analysis & Management
Configuration Management
Project Management
& Collaboration
Intergraph Solution
Engineering Design Basis
© 2015. Intergraph Corporation. All Rights Reserved
Re-task and Re-Purpose
Composite Applets
Information Browsing
Document & Transmittals Management
Tag Management
Action & Issue Tracking
Project Execution
Project Management of Change
Interface Management
Non-Conformities Management
Technical / Site Queries
System Completions
Risk Reducing Measures
Composite Applets - continued…
Integrated Information Handover
Legacy Data Gathering (SmartPlant Fusion)
SPO Mobile Apps
Requirements Management
Turnaround Planning – SPO R&D
Management of Operations Change
Inspection Assistant Building Information for Plant Maintenance Systems SPO R&D
Information Validation, Transformation & Loading (Smart Data Validator)
© 2015. Intergraph Corporation. All Rights Reserved
Installation Form X-Ray
Manufacturer Operating Parameters
Operational Check 2/1/03
Supporting Regulatory Compliance Controlling Plant Configurations
Dynamic Weld Inspection Data
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
Integration and Automation
Opportunities
© 2015. Intergraph Corporation. All Rights Reserved
Why Integration and Automation
Guidelines for Specifying Integrated Computer-Aided Engineering Applications for Electric Power
Plants.
EPRI (Electric Power Research Institute) report NP-5159M, Research Project 2514-3, May 1987
© 2015. Intergraph Corporation. All Rights Reserved
Relative Annual Savings From Automation and Integration at an Average Nuclear Power Plant
Data set savings Automation savings
Integration savings
Delta x increase in savings between automation and integration
Equipment Tagout $69,000 $124,000 1.79x Valve Index $21,600 $167,600 7.76x Instrument Identification $17,800 $135,100 7.59x
Motor Index $15,200 $123,100 8.09x Piping Index $12,000 $84,400 7.03x Action Request $12,100 $44,200 3.65x Commitment Tracking $5,000 $14,900 2.98x
Circuit Breaker Index $5,000 $37,700 7.54x EPRI (Electric Power Research Institute) report NP-5159M, Research Project 2514-3, May 1987
© 2015. Intergraph Corporation. All Rights Reserved
Affect on RAM (Reliability, Availability and Maintainability) by re-using the data more than once in other activities
example equipment valve specs and associated activities
[including:- performance monitor, performance analysis, reliability assurance, reactor safety, incident investigation, industrial safety assurance and analysis, valve/valve operator maintenance, maintenance procedure development, equipment history analysis, operational procedure development, emergency operations, operating experience evaluation]
yielded an annual cost saving of $8M alone (in 1987!).
EPRI (Electric Power Research Institute) report NP-5159M, Research Project 2514-3, May 1987
© 2015. Intergraph Corporation. All Rights Reserved
Aggregation and Consolidation
Discipline Information
R&D Pump Duty: 1500m3/h Spec: AP610 Type: Centrifugal Location: Area B12
Engineering System: 27 (Potable Water) Function: Water Injection Tag No.: P-101 Materials: 25% Cr. Duplex Power: 550 kw Motor Tag: PM101
Planning WBS: 24 Site Lead: 20 days Unit Test: 5 days Hydro Test : 2 days Completion: 20July2002
Estimating Pump Duty: 1500m3/h Number Required: 20 Cost Per Unit: $3000
Discipline Information
Procurement Vendor: Sulzer Model No: 1173K74H Connections:16in Suction, 12in Discharge Weight: 11000kg Structure: Skid Seals: Crane BSTFN Power Supply: 11kv, 3ph, 60hz
Construction As Built: Dimensional data, Spool changes Test data: Inst. Records, pressure, Serial Number: 12993MN66
Controls Comm Records: Performance, NPSH Control Settings, Operating Limits Operating records: MTBF Performance curves
Operations IOM Procedures, QC Test: Hydro, String, Performance
Maintenance Equipment replacement & spares data, Lubrication and strip down records
© 2015. Intergraph Corporation. All Rights Reserved
‘Presentation’ Integration
Tiers of Integration
‘Data’ Integration
‘Application’ Integration
‘Business Process’ Integration
Valu
e to
the
busi
ness
Effort to Deploy
‘Integrated Composite Applet Implementation’
Consolidation
Access
Transport
Messaging
Leverage
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
Handover – Turnover
“What does this mean?”
© 2015. Intergraph Corporation. All Rights Reserved
EPC “where time TO market
is imperative”
Engineering data in Execution is stateful, volatile, temporal and spread across disparate sources and owners
Progress Management
Instrumentation Design
Project Management
Instrument Data Sheets
Process Simulation
Specifications & Standards
P&ID
Contracts
Mechanical Equipment
Design
Electrical Design
Line Lists
Valve Lists
GA’s and ISO’s
Civil & Structural
Cabling & Lighting
Hook up & Installation
Document Control
Project Portal
Time allocation & measurement
PFD
Automation & Control Design
Hazop
Requistioning
Equipment Data Sheets
Plant 3D Modeling
SLD’s & Schematitcs
HVAC
Procurement
Cost Controls
Equipment Lists
EDMS
Supplier Gateway
Shipping
Construction Sequencing
Test & Commissioning
planning logic connectivity layout actual completion
© 2015. Intergraph Corporation. All Rights Reserved
Process Control SPC
Recipe Work Order Execution
Engineering data in Operations spreads across multiple plant operational systems and time domains
ERP
Product / plant Lifecycle mgmt
EDMS
Specialty Quality Admin
Product Specs
Plant Centric
ERP
Formula Mgt Batch
Mgt
SCADA
SPC / Trends
Process Planning
Optimisation
Data Historian
MES
LIMS
FCP Factory Schedule
Automation Control Logic
Data Capture
Procurement
Financials
CRM
Trading Exchange
Supply Chain
Machine Logic
Process Mgt
Plant Operations
Production Schedule
Business Process
Supply Chain
Customer
Plant
Supply Chain
Extended Supply Chain
Process Automation
In Process Testing
Enterprise
Production Unit
Production Process
Machine
Reliability monitoring & optimization
Original diagram source courtesy: AMR Research
OO “where time IN market
is imperative”
© 2015. Intergraph Corporation. All Rights Reserved
Handover & Uploading
ERP
Product / plant Lifecycle mgmt
EDMS
Specialty Quality Admin
Product Specs
Plant Centric ERP
Formula Mgt Batch
Mgt
SCADA
SPC / Trends
Process Planning
Optimisation
Data Historian
MES
LIMS
FCP Factory Schedule
Automation Control Logic
Data Capture
Procurement
Financials
CRM
Trading Exchange
Supply Chain
Process Automation
In Process Testing
Reliability monitoring & optimization OO
Progress Management
Instrumentation Design
Project Management
Instrument Data Sheets
Process Simulation
Specifications & Standards
P&ID
Contracts
Mechanical Equipment
Design
Electrical Design
Line Lists
Valve Lists
GA’s and ISO’s
Civil & Structural
Cabling & Lighting
Hook up & Installation
Document Control
Project Portal
Time allocation & measurement
PFD
Automation & Control Design
Hazop
Requistioning
Equipment Data Sheets
Plant 3D Modeling
SLD’s & Schematitcs
HVAC
Procurement
Cost Controls
Equipment Lists
EDMS
Supplier Gateway
Shipping
Construction Sequencing
Test & Commissioning
EPC
© 2015. Intergraph Corporation. All Rights Reserved © 2015. Intergraph Corporation. All Rights Reserved.
PIM
“Future State”
© 2015. Intergraph Corporation. All Rights Reserved
Tag: P-101
Inter-Relationships across line-of-business systems
Des Op Press: 100psi
What we need at the functional location
Model: CP-C-4020
What can be obtained to fulfill the need
Des Op Press: 150psi
Manfr: Weir
What are its capabilities
Asset no: 24X89
What did we buy which is at the functional location
Supplier: Simmons
Who did we get it from
Purchase Order: U9735
Maint Proc: MM101
BOM: 24X89/P101
What do we need to maintain it
System: 20 – Separation
Plant: Texas2
What is the plant’s configuration
P&ID Drawing: C056-SA-P-XR-2032-01
Spec Document: C056-KIV-1-DS-2001
What documentation supports the licence and safety …and so on data sheet
© 2015. Intergraph Corporation. All Rights Reserved
Hierarchical VS Molecular
Most hierarchical Document Management systems model their information as represented by the familiar cabinet → folder → file paradigm.
© 2015. Intergraph Corporation. All Rights Reserved
Think instead of objects and relationships as molecular…
© 2015. Intergraph Corporation. All Rights Reserved
Management Communication
38 8/31/2011
© 2015. Intergraph Corporation. All Rights Reserved
View by Reason for Issue
39
© 2015. Intergraph Corporation. All Rights Reserved
SAFETY QUALITY PRODUCTIVITY
© 2015. Intergraph Corporation. All Rights Reserved
QUESTIONS!