construction method statement -...
Post on 07-Feb-2018
258 Views
Preview:
TRANSCRIPT
Construction Method Statement
Contents
SECTION 1
1. Master programme
1.1 Purpose of the document
1.2 Description of the Construction Programme
SECTION 2 – Projects
2. Shepherd Road
2.1 Executive Summary
2.2 Specific Construction Activities
2.3 Construction phasing and sequence requirements
2.4 Programme (incl decant)
2.5 Key Constraints (including existing services)
2.6 Management Staff
2.7 Logistics
3. Keynsham Road
3.1 Executive Summary
3.2 Specific Construction Activities
3.3 Construction phasing and sequence requirements
3.4 Programme (incl decant)
3.5 Key Constraints (including existing services)
3.6 Management Staff
3.7 Logistics
4. Cheltenham Road East
4.1 Executive Summary
4.2 Specific Construction Activities
4.3 Construction phasing and sequence requirements
4.4 Programme (incl decant)
4.5 Key Constraints (including existing services)
4.6 Management Staff
4.7 Logistics
5. Uckington
5.1 Executive Summary
5.2 Specific Construction Activities
5.3 Construction phasing and sequence requirements
5.4 Programme (incl decant)
5.5 Key Constraints (including existing services)
5.6 Management Staff
5.7 Logistics
SECTION 3 – General Approach
6.1 General Management
6.2 Considerate Constructors Scheme
6.3 Quality Plan
6.4 General Liaison
6.5 Meetings and Liaison
6.6 Reviewable Design Data
6.7 Safety, Health and Environment
6.8 Completion and Handover
SECTION 4 – Appendices
A – Draft Quality Plan Contents
B - Draft Construction Phase Health and Safety Plan Contents
C - Staff Organisational Charts
D- Site Establishment Plans
E - Programmes
SECTION 1 - Master Programme
Purpose of this document
The purpose of this document is to outline the strategic principles of the
construction management approach from Financial Close through to Full Services
Availability (The Construction Phase).
It is intended to provide sufficient detail to offer a reasonable understanding of
how each project will be managed and developed through the construction phase,
and to provide a suitable structure to interface and co-ordinate further detailed
information, procured through the completion of design and selection of key sub
contract packages, to ensure a successful project.
Description of the Construction Programme
The master programme reference T09046 – PB Opt 2c illustrates the latest
agreements and summarises the construction sequence for each Fire Station
including the temporary facility at Kingsditch lane. It details key milestones and
dates required by the building contract.
Financial close is 14 February 2011, following the judicial review period for
Uckington.
Start on site of the first station is Shepherd Road on the 7 March 2011, a
minimum of 3 weeks following Financial Close, with completion of the buildings on
the Full Services Availability date 21 May 2012. Decanting from the existing
facilities and providing the facilities to meet operational requirements generally
follows after a 4 week period from the Services availability date of each station.
GRFS deployment to new Stations has been programmed not to occur
concurrently and 4-week deployment periods are included together with a
provisional disband period for the temporary Fire Station:
• Uckington handed over end week 38
• Keynsham Road handed over end week 48
• Cheltenham Road East handed over end week 40
• Shepherd Road handed over end week 63
Following commencement of Shepherd Road, the remaining stations follow with
staggered start dates to take advantage of and maximise procurement
opportunities; particularly the asbestos removal and demolition at the Shepherd
Road and Keynsham Road sites.
Following a robust development of the design, and the procurement of key sub
contractors, earlier commencement on site at Uckington, Cheltenham Road East
and Keynsham Road may be considered.
SECTION 2 – Projects
2.0 Shepherd Road
2.1 Executive Summary
The structure at Shepherd Road, principally comprises, simple pad and strip
concrete foundations, a ground bearing concrete slab, and steel frame with
gluelam beams over the Street.
The buildings are clad in a combination of render, standing seam roof,
composite metal cladding, larch cladding, and red brick.
The majority of internal finishes includes plasterboard partitions, carpet and
vinyl and specific FF&E.
The overall duration for the works is 63 weeks including a 14 week period for
initial demolition and enabling works.
Site access, hoarding and logistics are shown on the logistics layout attached
in Appendix D of Section 4 - ref 5092 – 2 SHE site establishment plan.
2.2 Specific Construction Activities
The site works commence with the temporary fencing, making the site safe
and establishment of the site office and welfare facilities.
Site ‘Enabling’
During the initial site clearance and preparation, it is essential to establish the
site compound including welfare provision at the earliest opportunity. For the
immediate stages of the project self-contained ‘Oasis units’ will be employed
to provide instant welfare facilities until temporary site services are
established.
Asbestos and Demolition
All asbestos works will be carried out in accordance with our detailed policy’s
& procedures with the work being undertaken by competent surveyors, having
personal certification to BOHS P402 or similar, and whose organisation should
be accredited by UKAS to BS EN 17020.’
Demolition will then be carried out by specialist demolition contractors
affiliated to NFDC or similar. A detailed method statement, which will include
the measures to be implemented to reduce dust and noise, will be received
and approved prior to the works being undertaken on site. The requirement
to minimise dust and noise will include, appropriate and ‘silenced’ machinery
at source, and the introduction of ‘dampening down’ with fine mist water
cannons.
Known existing services will have already been located on site and
subsequently removed or diverted as necessary upon commencement on site.
Location of unforeseen services will require a hold point in the programme to
assess the implications. All unaffected works will be progressed during this
period.
Existing foundations, pits and obvious ground obstructions will be removed at
this stage and crushed along with the other demolition arisings. Were
possible, these materials will be recycled, either on site as backfill material or
as engineering fill at a recycling site. Existing pits will be filled to the
engineer’s recommendations. Appropriate licences will be obtained for this
prior to the works commencing.
Highway Works and Section 278 works
Following receipt of the necessary consents, these works will be started at the
earliest opportunity. A temporary site entrance will be formed for the
construction access over the land identified for future development, therefore
not impacting on the Section 278 works.
Life Skills Centre
The life skills centre has been programmed to be constructed in conjunction
with the main building as shown on the detailed construction programme. A
critical element is the construction of the roof structure which has been
carefully planned to be installed between the main roof’s 1 and 2.
2.3 General Construction Activities
These will follow the principles set out in Section 3 ‘General Principles’ below.
2. 4 Programme
General Principles
The works have been planned in accordance with the detailed construction
programme attached in Appendix E of Section 4 - ref 5092/2-SHE-1
The programme details the following key activities;
• Site preparation / establishment and enabling works
• Foundations
• Frame erection and commence external drainage
• Upper floor and ground slabs
• Roof coverings
• Masonry / facades and commencement of training building
• Off site external works
• Internal services and finishes
• Progress remaining external works / surface finishes
• Soft landscaping
• Final tests and commissioning
Works generally commence from the main accommodation bay (with the
frame) and work out toward the appliance bay and the life skills centre.
Whilst each area can be programmed individually, each phase will be over
lapped to maximise the efficiency of site operations and minimise the time on
site of each key trade. This at time will increase the resources on site at any
one time and we are therefore cognisant of the increased pressure this puts
on site parking etc (see further details sections below). Completion of higher-
level roofs / elevations that are above lower level and the roofs over the main
parts of the building with the most room density is critical. Our aim is to
achieve internal weather protection as soon as possible to allow M+E first fix
to commence.
Internally, service distributions gets underway and first fix on floor levels
progress to allow plastering works and floor screeds to follow and dry out in
sufficient time prior to accepting final finishes.
• BWIC Services + Services Distribution + Plantroom Installations
• 1st Fix M+E Installations + Carpentry
• Plaster / Render / Stud / Board / Skim Walls
• Lift Installation
• Stopping / Fire Barriers
• Floor Screed
• Wall Tiling
• Suspended Ceiling Grids
• 2nd Fix M+E Installations + Carpentry
• Main Decorations + Whiterock
• Floor Finishes
• Final Fix / Snag All Trades + Complete Ceiling Tiles
• Stair Balustrade / Handrails
• Air Test
• Street Floor Finishes
• M+E + Lift Final Tests & Commission
• Final Cleaning
• Loose Furniture / Fittings
The programme incorporates the access, safety and construction challenges
on this project and any specific constraints detailed in Section 2.5 below.
Completion, Handover, Decant and Defects
The completion process will follow the requirements of the Building Contract.
After Services Availability, we will assist with the decant process with the
following measures;
• Provision of packing crates
• Provision of labour to assist packing
• Provision of labour and vans to move equipment
• Transfer of crates
• Assist with the unloading and positioning of equipment.
• Connect and test equipment.
A 4 week period, along with a decent manager has been provided to manage
these activities.
All other measures will follow the general completion and handover process
noted in Section 3 below.
2.5 Specific Constraints
We are cognisant of the brook and the cycle path located to the east of the
site adjacent to the land proposed for future development. Our environmental
impact assessment will specifically deal with these issues in terms of surface
water disposal, contamination, concrete wash out and ecology. The site will
not encroach into this area and our heras fence will secure this line. Surface
water will be collected were possible and the fines removed and discharged
into the local surface water sewer. Concrete wagons will wash out into a pre
designated area with a lined skip, which will be removed and disposed of off
site in the appropriate manner by a waste transfer company employed on our
behalf. Waste transfer notes will be collected and administered in accordance
with our site waste management plan.
The local playing fields will attract youths into the area, and although Tuffley
Lane separates the site and this area, we are mindful of the interest this could
have. A secure heras fence will be erected along this boundary, supported as
required by scaffolding to provide additional rigidity and security. This area
will then be monitored closely as the works proceed.
The new housing development to the West of the site will be sensitive to our
construction works. Good communication will be essential to maintain good
relations and our commitment to the Considerate Contractors Scheme should
prove to be beneficial in this instance. We would initially propose early letter
drops followed by regular news letters. We would then follow the GRFS
communications protocol.
Further general information is provided in Section 3 below.
Tree Protection
The existing trees adjacent to the site boundary along Tuffley lane will need
particular care during the course of the works to avoid damage to either roots
and or branches. Initially they will be protected with fencing and barriers in
accordance with BS 5837. The specific aboricultural method statement below
will be developed to work around these tress and will deal specifically with
methods of excavation, root protection and working at height. This will be
approved by the Local Authority prior to commencing.
The tree protection installed in the locations identified on the attached
logistics plan. Appropriate signage ‘tree protection zone keep out’ will be
provided.
Appropriate pruning will be commissioned prior to the works commencing to
ensure the trees are in a proper state of repair and do not over hang the TPZ.
Existing soil levels in the close vicinity will not be significantly raised and or
lowered.
Design of the works will take due care of the TPZ and will where possible any
of the works interfering with the trunks, branches and roots of the trees.
As such, excavation within the TPZ is not anticipated. In the event this
changes, further approval will be sought from the LPA and manual excavation
may be introduced.
Statutory Services
Further survey works will be required prior to Financial Close to establish what
services, if any, need to be marked, protected, lowered or the like. Much
further planning cannot be developed until this exercise has been undertaken.
2.6 Management Staff
The site team will be lead by senior project manager Chris Lane.
Following the enabling phase, Chris will be supported by a Site Manager until
the works are substantially complete. A senior site engineer will be utilised
for the construction of the substructures and the superstructure elements of
the build.
A project Quantity Surveyor will work from the outset on procuring all
elements of the project, working with a design and build co-ordinator up to
the completion of design development.
Decant Manager
A specific member of the site team will be allocated to these exercises. They
will have responsibility for liaising with Blue 3, the Authority and the FM
Provider, the upfront planning of the move, managing the move itself
including the relocation of FF&E.
Working closely with our building services manager and the commissioning
manager, they will ensure that each decant phase is completed,
commissioned and operational prior to the facility being ‘live’.
Building Services Manager
The site team will be backed up with support from Trevor Hewer, building
services co-ordinator. Trevor’s role is particularly important during the
completion of the M&E design and commissioning of each of the systems. As
a result of the structure of the programme, Trevor will manage all 4 project
ensuring at high level of consistency.
A Staff organisation chart is shown in Appendix C of Section 4.
2.7 Logistics
Site Entrance
The main site entrance is located off Shepherd Road as illustrated on the site
establishment plan shown in Appendix D of Section 4. This main access point
will include a holding area to allow vehicles an undisrupted flow of traffic from
the highway into the site. Suitable signage regarding site operations will be
erected to warn the public, delivery vehicles and other users and assist in
traffic management. A Gateman will be based in an office adjacent to the
construction entrance gate to manage and supervise the flow of traffic and
receipt of goods inward and site visitors.
Wheel Washing
Due precautions will be taken when excavated material is being removed from
site to ensure that the road is kept clean at all times. The main strategy will
be to mitigate at the production of ‘muck’ at source via strict house keeping
and the installation of well designed temporary roads. Wheel washing plant is
not appropriate for this site as there is insufficient space to locate such
equipment; however the gateman will also manage the cleanliness of vehicles
leaving site with the aid of an industrial jet wash. This process will be
supported by regular visits from road sweepers as necessary.
Materials Deliveries, Storage and Handling
All material deliveries including the removal of waste will be scheduled within
the agreed site working hours, with any requirement outside of this being
agreed in advance with the Local Authority. All materials will be delivered
through the main site entrance.
A permanent Gateman will be employed to control and secure the site
entrance, managing the goods deliveries in line with a traffic management
plan. This will incorporate a delivery route from the adjacent major road
network agreed in advance with the Police and Highways Authority.
The following principal items of plant will be utilised:-
• Fork Lift - Servicing bricklayers, general off-loading and distribution
• Mobile Crane – Steelwork and Glulam erection, load out decking, placing
pre-cast units, M+E plant, rooflights
• Pumps - Pumping concrete to floor slabs and screed to upper floors
• Scissors Lifts / Cherry Pickers - frame connections, fixing safety netting
and guardrails, installation of windows and cladding / elevational finishes
where more appropriate than scaffold
Deliveries of materials will be carefully unloaded in the delivery area.
Materials will then be distributed via telescopic forklift truck, directly to the
work face, or if appropriate (such as bulk regular use materials) to the
materials holding areas around the site. Distribution of materials and hoisting
onto scaffold will also be by means of a telescopic truck, operating around the
haul road and access bay facility. These will be positioned around the
building, and located strategically to take advantage of natural openings
within the structure. The materials will then be transported to final location by
powered pallet trucks across the floor slabs.
Secure containers will be used for storage of small materials.
Compound / Offices and temporary Car parking
The office area and compound will be accessed via the temporary road leading
from the construction site entrance the main visitors and staff site parking
area. The compound will accommodate the requirement for the temporary site
parking, and space allocated accordingly, fluctuating in conjunction with the
numbers of operatives on site. It is envisaged that this will be adequate for
our needs and offensive off site parking by any member of the construction
team strictly enforced in parallel with the local authorities. These terms will
be included within the sub contract of all our supply chain appointed on this
project.
Site offices and welfare facilities, provided to current regulations, will consist
of ‘Portakabin’ type units with secure containers for storage of small /
vulnerable materials. This is where our site team of managers, engineers,
design co-coordinators and surveyors will work from. The area will also
include welfare provision for our site operatives including, non catering
canteens and secure stores. Smoking will not be permitted on site. Space for
Two work stations (excluding IT arrangements) will be provided at the
Sherherd road site for the Blue 3 project manager, and the Authorities
representative.
Units are complete with safety lighting and fire alarms and stacked, as
necessary, to save space. Due to the proximity of the adjacent buildings the
accommodation units may have to be fire rated to comply with the code of
practice for the prevention of fires on construction sites.
Pedestrian barriers will define the safe access route to the facilities.
This main establishment will be provided following completion of the enabling
works, and will remain in situation until the final weeks of the project, leaving
sufficient time to finish and clear the area.
Scaffolding / Access
A fully boarded external perimeter scaffolding will be provided for render and
brick elevational materials and will be of the traditional independent type,
erected, maintained and adapted as necessary by a specialist contractor.
Cladding and other treatments will be installed from Mobile Elevated Working
Platform (Scissor lifts). The scaffold will be erected to give clear safe working
platforms and access to all floor levels and for roofing operations. Loading
towers will be incorporated within the external scaffold to receive heavy
materials. A mixture of cantilevered and double scaffolds will be used where
necessary to give access to the roof overhang to the street.
Temporary staircases will be provided to access the scaffold. In conjunction
with the perimeter scaffold, guardrails will be erected to give perimeter edge
protection, and, together with safety netting will allow an early start for floor
and roof decks. Within ‘Streets’, voids and staircases, birdcage scaffold
platforms enable safe working at high level for rooflight installations, services
and finishes.
3 Keynsham Road
3.1 Executive Summary
The structure at Keynsham Road, principally comprises, simple pad and strip
concrete foundations, a ground bearing concrete slab, and steel frame with
gluelam beams over the Street.
The buildings are clad in a combination of render, standing seam roof,
composite metal cladding, larch cladding, and Cheltenham buff brick.
The majority of internal finishes comprise plasterboard partitions, carpet and
vinyl and specific FF&E.
The overall duration for the works is 48 weeks including a 12 week period for
initial demolition and enabling works.
Site access, hoarding and logistics are shown on the logistics layout attached
in Appendix D of Section 4 - ref 5092 – 3 KEY site establishment plan.
3.2 Specific Construction Activities
The site works commence with the temporary fencing, making the site safe
and establishment of the site office and welfare facilities.
Site ‘Enabling’
During the initial site clearance and preparation, it is essential to establish the
site compound including welfare provision at the earliest opportunity. For the
immediate stages of the project we employ self-contained ‘Oasis units’ that
provide instant welfare facilities until temporary site services are established.
Asbestos and Demolition
All asbestos works will be carried out in accordance with our detailed policies
& procedures with the work being undertaken by competent surveyors with
personal certification to BOHS P402 or similar, and whose organisation should
be accredited by UKAS to BS EN 17020.’
Demolition will then be carried out by specialist demolition contractors
affiliated to NFDC or similar. A detailed method statement, which will include
the measures to be implemented to reduce dust and noise, will be received
and approved prior to the works being undertaken on site. The requirement
to minimise dust and noise will include, appropriate and ‘silenced’ machinery
at source, and the introduction of ‘dampening down’ with fine mist water
cannons.
Known existing services will have already been located on site and will be
subsequently removed or diverted as necessary upon commencement on site.
Location of unforeseen services will require a hold point in the programme to
assess the implications. All unaffected works will be progressed during this
period.
Particular care will be given to the demolition of the training tower, in close
proximity to the college baths buildings. A temporary protective fan will be
erected along parts of this boundary. It is anticipated that the Authority will
have removed all aerials and telephone masts prior to our commencement on
site.
Existing foundations and obvious ground obstructions will be removed at this
stage and crushed along with the other demolition arisings. Were possible,
these materials will be recycled, either on site as backfill material or a
engineering fill at a recycling site. Existing pits will be filled to the engineer’s
recommendations. Appropriate licences will be obtained for this prior to the
works commencing.
Highway Works and Section 278 works
Following receipt of the necessary consents, these works will be started at the
earliest opportunity. The existing site entrance will initially be utilised for the
temporary site entrance for the construction access. The Section 278 works
will however be progressed at the earliest opportunity to provide greater
flexibility in manoeuvrability around the site.
3.3 General Construction Activities
These will follow the principles set out in Section 3 ‘General Principles’ below.
3. 4 Programme
General Principles
The works have been planned in accordance with the detailed construction
programme attached in Appendix E of Section 4 - ref 5092/3-KEY-1
The programme details the following key activities;
• Site preparation / establishment and enabling works
• Foundations
• Frame erection and commence external drainage
• Upper floor and ground slabs
• Roof coverings
• Masonry / facades
• Off site external works
• Internal services and finishes
• Progress remaining external works / surface finishes
• Soft landscaping
• Final tests and commissioning
Works generally commence from the main accommodation bay, allowing the
steel frame to commence along grid line C and work out toward the appliance
bay. The community area will follow with the street being infilled in sequence.
Whilst each area can be programmed individually, each phase will be over
lapped to maximise the efficiency of site operations and minimise the time on
site of each key trade. This at time will increase the resources on site at any
one time and we are therefore cognisant of the increased pressure this puts
on site parking etc (see further details sections below). Completion of higher-
level roofs / elevations that are above lower level and the roofs over the main
parts of the building with the most room density is critical. Our aim is to
achieve internal weather protection as soon as possible to allow M+E first fix
to commence.
Internally, service distributions gets underway and first fix on floor levels
progress to allow plastering works and floor screeds to follow and dry out in
sufficient time prior to accepting final finishes.
• BWIC Services + Services Distribution + Plantroom Installations
• 1st Fix M+E Installations + Carpentry
• Plaster / Render / Stud / Board / Skim Walls
• Lift Installation
• Stopping / Fire Barriers
• Floor Screed
• Wall Tiling
• Suspended Ceiling Grids
• 2nd Fix M+E Installations + Carpentry
• Main Decorations + Whiterock
• Floor Finishes
• Final Fix / Snag All Trades + Complete Ceiling Tiles
• Stair Balustrade / Handrails
• Air Test
• Street Floor Finishes
• M+E + Lift Final Tests & Commission
• Final Cleaning
• Loose Furniture / Fittings
The programme incorporates the access, safety and construction challenges
on this project and any specific constraints detailed in Section 3.5 below.
Completion, Handover, Decant and Defects
The completion process will follow the requirements of the Project agreement
/ Building Contract. After Services Availability, we will assist with the decant
process with the following measures;
• Provision of packing crates
• Provision of labour to assist packing
• Provision of labour and vans to move equipment
• Transfer of crates
• Assist with the unloading and positioning of equipment.
• Connect and test equipment.
A 4 week period, along with a decent manager has been provided to manage
these activities.
All other measures will follow the general completion and handover process
noted in Section 3 below.
3.5 Specific Constraints
To enable the construction of the works the footpaths adjacent to the site will
be diverted, with the agreement of the Local Authority, to the opposite side of
the road. This is primarily to protect the public and to create sufficient space
to allow the construction of the works.
The existing trees to the west of the site will need particular care during the
course of the works. They will be protected with fencing and barriers in
accordance with BS 5837. A specific aboricultural method statement will be
developed to work around these tress and will deal specifically with methods
of excavation, root protection and working at height. This will be approved by
the Local Authority prior to commencing. Waste transfer notes will be
collected and administered in accordance with our site waste management
plan.
We are aware of the close proximity of the buildings surrounding the site and
have considered protection etc accordingly.
The local housing around the site will be sensitive to our construction works.
Good communication will be essential to maintain good relations and our
commitment to the Considerate Contractors Scheme should prove to be
beneficial in this instance. We would initially propose early letter drops
followed by regular news letters. We would then follow the GRFS
communications protocol.
The right of way from the fire escape of the Sandford Education Centre will be
maintained, via a protected walkway out onto Keynsham Road.
Further general information is provided in Section 3 below.
Statutory Services
Further survey works will be required prior to Financial Close to establish what
services, if any, need to be marked, protected lowered or the like. Much
further planning cannot be developed until this exercise has been undertaken.
3.6 Management Staff
The site team will be lead by a project manager name TBC.
Following the enabling phase, they will be supported by a Site Manager until
the works are substantially complete. A senior site engineer will be utilised
for the construction of the substructures and the superstructure elements of
the build.
A project Quantity Surveyor will work from the outset on procuring all
elements of the project, working with a design and build co-ordinator up to
the completion of design development.
Decant Manager
A specific member of the site team will be allocated to these exercises. They
will have responsibility for liaising with Blue 3’ the Authority and the FM
Provider, the upfront planning of the move, managing the move itself
including the relocation of FF&E.
Working closely with our building services manager and the commissioning
manager, they will ensure that each decant phase is completed,
commissioned and operational prior to the facility being ‘live’.
Building Services Manager
The site team will be backed up with support from Trevor Hewer, building
services co-ordinator. Trevor’s role is particularly important during the
completion of the M&E design and commissioning of each of the systems. As
a result of the structure of the programme, Trevor will manage all 4 project
ensuring at high level of consistency.
A Staff organisation chart is shown in Appendix C of Section 4.
3.7 Logistics
Site Entrance
The main site entrance is located off College Bath Road as illustrated on the
site establishment plan shown in Appendix D of Section 4. This main access
point will include a holding area to allow vehicles an undisrupted flow of traffic
from the highway into the site. Suitable signage regarding site operations will
be erected to warn the public, delivery vehicles and other users and assist in
traffic management. A Gateman will be based in an office adjacent to the
construction entrance gate to manage and supervise the flow of traffic and
receipt of goods inward and visitors.
Wheel Washing
Due precautions will be taken when excavated material is being removed from
site to ensure that the road is kept clean at all times. The main strategy will
be to mitigate at the production of ‘muck’ at source via strict house keeping
and the installation of well designed temporary roads. Wheel washing plant is
not appropriate for this site as there is insufficient space to locate such
equipment; however the gateman will also manage the cleanliness of vehicles
leaving site with the aid of an industrial jet wash. This process will be
supported by regular visits from road sweepers as necessary.
Materials Deliveries, Storage and Handling
All material deliveries including the removal of waste will be scheduled within
the agreed site working hours, with any requirement outside of this being
agreed in advance with the Local Authority. All materials will be delivered
through the main site entrance.
The Gateman will be employed to control and secure the site entrance,
managing the goods deliveries in line with a traffic management plan. This
will incorporate a delivery route from the adjacent major road network agreed
in advance with the Police and Highways Authority.
The following principal items of plant will be utilised:-
• Fork Lift - Servicing bricklayers, general off-loading and distribution
• Mobile Crane – Steelwork and Glulam erection, load out decking, placing
pre-cast units, M+E plant, rooflights Pumps - Pumping concrete to floor
slabs and screed to upper floors
• Scissors Lifts / Cherry Pickers - frame connections, fixing safety netting
and guardrails, installation of windows and cladding / elevational finishes
where more appropriate than scaffold
Deliveries of materials will be carefully unloaded in the delivery area.
Materials will then be distributed via telescopic forklift truck, directly to the
work face, or if appropriate (such as bulk regular use materials) to the
materials holding areas around the site. Distribution of materials and hoisting
onto scaffold will also be by means of a telescopic truck, operating around the
haul road and access bay facility. These will be positioned around the
building, and located strategically to take advantage of natural openings
within the structure. The materials will then be transported to final location by
powered pallet trucks across the floor slabs.
Secure containers will be used for storage of small materials.
Compound/ Offices and temporary Car parking
The office area and compound will be accessed and located adjacent to the
temporary road leading from the construction site entrance the main visitors
and staff site parking area. The compound will some temporary site parking,
and space will be allocated accordingly, fluctuating in conjunction with the
numbers of operatives on site. It is likely however that this will not be
adequate for all parking during the duration of the project and it is envisaged
that use of the public car park at the Lido will be utilised as overflow during
peak time. It is understood that this car park is not fully utilised, however
this will be monitored closely. Notwithstanding that, offensive off site parking
by any member of the construction team, particularly on the residential roads
adjacent to the site, will not be acceptable and will be monitored closely These
terms will be included within the sub contracts of all our supply chain
appointed on this project.
Site offices and welfare facilities, provided to current regulations, will consist
of ‘Portakabin’ type units with secure containers for storage of small /
vulnerable materials. This is where our site team of managers, engineers,
design co-coordinators and surveyors will work from. The area will also
include welfare provision for our site operatives including, non catering
canteens and secure stores. Smoking will not be permitted on site.
Units are complete with safety lighting and fire alarms and stacked, as
necessary, to save space. Due to the proximity of the adjacent buildings the
accommodation units may have to be fire rated to comply with the code of
practice for the prevention of fires on construction sites.
Pedestrian barriers will define the safe access route to the facilities.
This main establishment will be provided following completion of the enabling
works, and will remain in situation until the final weeks of the project, leaving
sufficient time to finish and clear the area.
Scaffolding / Access
A fully boarded external perimeter scaffolding will be provided for render and
brick elevational materials and will be of the traditional independent type,
erected, maintained and adapted as necessary by a specialist contractor.
Cladding and other treatments will be installed from Mobile Elevated Working
Platform (Scissor lifts). The scaffold will be erected to give clear safe working
platforms and access to all floor levels and for roofing operations. Loading
towers will be incorporated within the external scaffold to receive heavy
materials. A mixture of cantilevered and double scaffolds will be used where
necessary to give access to the roof overhang to street.
Temporary staircases will be provided to access the scaffold. In conjunction
with the perimeter scaffold, guardrails will be erected to give perimeter edge
protection, and, together with safety netting will allow an early start for floor
and roof decks. Within ‘Streets’, voids and staircases, birdcage scaffold
platforms enable safe working at high level for rooflight installations, services
and finishes.
4 Cheltenham Road East
4.1 Executive Summary
The structure at Cheltenham Road East, principally comprises, simple pad and
strip concrete foundations, a ground bearing concrete slab, and steel frame
with gluelam beams over the Street.
The buildings are clad in a combination of render, standing seam roof,
composite metal cladding, larch cladding, and Cotswold stone.
The majority of internal finishes comprise plasterboard partitions, carpet and
vinyl and specific FF&E.
The overall duration for the works is 40 weeks.
Site access, hoarding and logistics are shown on the logistics layout attached
in Appendix D of section 4 - ref 5092 – 4 CRE site establishment plan.
4.2 Specific Construction Activities
The site works commence with the temporary fencing, making the site safe
and establishment of the site office and welfare facilities.
Site ‘Enabling’
During the initial site clearance, which will be carried out in conjunction with
the ecologist it is essential to establish the site compound including welfare
provision at the earliest opportunity. For the immediate stages of the project
self-contained ‘Oasis units’ will be employed to provide instant welfare
facilities until temporary site services are established.
Highway Works and Section 278 works
Following receipt of the necessary consents, these works will be started at the
earliest opportunity. A temporary site entrance will be formed for the
construction access over the land identified for access to the land for future
development. The access and egressexit to the site will be formed initially
over the permanent site entrance. During the construction of the permanent
access road, access and egress will be gained over the permanent exit. The
temporary site parking facilities will be relocated to the rear of the site.
4.3 General Construction Activities
These will follow the principles set out in Section 3 ‘General Principles’ below.
4. 4 Programme
General Principles
The works have been planned in accordance with the detailed construction
programme attached in Appendix E of Section 4 - ref 5092/2-CRE-1
The programme details the following key activities;
• Site preparation / establishment and enabling works
• Foundations
• Frame erection and commence external drainage
• Upper floor and ground slabs
• Roof coverings
• Masonry / facades
• Off site external works
• Internal services and finishes
• Progress remaining external works / surface finishes
• Soft landscaping
• Final tests and commissioning
Works generally commence from the main accommodation bay, allowing the
steel frame to commence along grid line C and work out toward the appliance
bay. The community area will follow with the street being infilled in sequence.
This at time will increase the resources on site at any one time and we are
therefore cognisant of the increased pressure this puts on site parking etc
(see further details sections below). Completion of higher-level roofs /
elevations that are above lower level and the roofs over the main parts of the
building with the most room density is critical. Our aim is to achieve internal
weather protection as soon as possible to allow M+E first fix to commence.
Internally, service distributions gets underway and first fix on floor levels
progress to allow plastering works and floor screeds to follow and dry out in
sufficient time prior to accepting final finishes.
• BWIC Services + Services Distribution + Plantroom Installations
• 1st Fix M+E Installations + Carpentry
• Plaster / Render / Stud / Board / Skim Walls
• Lift Installation
• Stopping / Fire Barriers
• Floor Screed
• Wall Tiling
• Suspended Ceiling Grids
• 2nd Fix M+E Installations + Carpentry
• Main Decorations + Whiterock
• Floor Finishes
• Final Fix / Snag All Trades + Complete Ceiling Tiles
• Stair Balustrade / Handrails
• Air Test
• Street Floor Finishes
• M+E + Lift Final Tests & Commission
• Final Cleaning
• Loose Furniture / Fittings
The programme incorporates the access, safety and construction challenges
on this project and any specific constraints detailed in Section 4.5 below.
Completion, Handover, Decant and Defects
The completion process will follow the requirements of the Project Agreement
/ Building Contract. After Services Availability, we will assist with the decant
process with the following measures;
• Provision of packing crates
• Provision of labour to assist packing
• Provision of labour and vans to move equipment
• Transfer of crates
• Assist with the unloading and positioning of equipment.
• Connect and test equipment.
A 4 week period, along with a decent manager has been provided to manage
these activities.
All other measures will follow the general completion and handover process
noted below in Section 3 below.
4.5 Specific Constraints
We are cognisant of the brook and the cycle path located to the west and east
of the site respectively. Our environmental impact assessment will specifically
deal with these issues in terms of surface water disposal, contamination,
concrete wash out and ecology. The site will not encroach into this area and
our heras fence will secure this line, in addition to a topsoil bund which will be
provided in such a way to prevent any accidental discharge of surface water ot
other site contaminants from the area. Aided by the bund, surface water will
be collected were possible and the fines removed and discharged into the local
surface water sewer. Concrete wagons will wash out into a pre designated
area with a lined skip, which will be removed and disposed of off site in the
appropriate manner by a waste transfer company employed on our behalf.
Waste transfer notes will be collected and administered in accordance with our
site waste management plan.
Storage of all fuel and hazardous liquids, will be securely store within bunded
containers, away from the immediate vicinity.
Temporary access to the adjacent future development site may be required,
and will require finalisation prior to FC.
Initial access onto the site will require temporary approval to be obtained prior
to financial close.
We will keep the owner of the over head power lines abreast of our works on
site to ensure our works do not interrupt their service or access wayleave
requirements.
Further general information is provided in Section 3 below.
Statutory Services
Further survey works will be required prior to Financial Close to establish what
services, if any, need to be marked, protected lowered or the like. Much
further planning cannot be developed until this exercise has been undertaken.
4.6 Management Staff
The site team will be lead by a project manager TBA.
Following the enabling phase, they will be supported by a Site Manager until
the works are substantially complete. A senior site engineer will be utilised
for the construction of the substructures and the superstructure elements of
the build.
A project Quantity Surveyor will work from the outset on procuring all
elements of the project, working with a design and build co-ordinator up to
the completion of design development.
Decant Manager
A specific member of the site team will be allocated to these exercises. They
will have responsibility for liaising with Blue 3 and the Authority and the FM
Provider, the upfront planning of the move, managing the move itself
including the relocation of FF&E.
Working closely with our building services manager and the commissioning
manager, they will ensure that each decant phase is completed,
commissioned and operational prior to the facility being ‘live’.
Building Services Manager
The site team will be backed up with support from Trevor Hewer, building
services co-ordinator. Trevor’s role is particularly important during the
completion of the M&E design and commissioning of each of the systems. As
a result of the structure of the programme, Trevor will manage all 4 project
ensuring at high level of consistency.
A Staff organisation chart is shown Appendix C of Section 4.
4.7 Logistics
Site Entrance
The main site entrance is located off Cheltenham Road East as illustrated on
the site establishment plan shown in Appendix D of Section 4. This main
access point will include a holding area to allow vehicles an undisrupted flow
of traffic from the highway into the site. Suitable signage regarding site
operations will be erected to warn the public, delivery vehicles and other users
and assist in traffic management. A Gateman will be based in an office
adjacent to the construction entrance gate to manage and supervise the flow
of traffic and receipt of goods inward and visitors.
Wheel Washing
Due precautions will be taken when excavated material is being removed from
site to ensure that the road is kept clean at all times. The main strategy will
be to mitigate at the production of ‘muck’ at source via strict house keeping
and the installation of well designed temporary roads. Wheel washing plant is
not appropriate for this site as there is insufficient space to locate such
equipment; however the gateman will also manage the cleanliness of vehicles
leaving site with the aid of an industrial jet wash. This process will be
supported by regular visits from road sweepers as necessary.
Materials Deliveries, Storage and Handling
All material deliveries including the removal of waste will be scheduled within
the agreed site working hours, with any requirement outside of this being
agreed in advance with the Local Authority. All materials will be delivered
through the main site entrance.
The Gateman will be employed to control and secure the site entrance,
managing the goods deliveries in line with a traffic management plan. This
will incorporate a delivery route from the adjacent major road network agreed
in advance with the Police and Highways Authority.
The following principal items of plant will be utilised:-
• Fork Lift - Servicing bricklayers, general off-loading and distribution
• Mobile Crane – Steelwork and Glulam erection, load out decking, placing
pre-cast units, M+E plant, rooflights and sedum
• Pumps - Pumping concrete to floor slabs and screed to upper floors
• Scissors Lifts / Cherry Pickers - frame connections, fixing safety netting
and guardrails, installation of windows and cladding / elevational finishes
where more appropriate than scaffold
Deliveries of materials will be carefully unloaded in the delivery area.
Materials will then be distributed via telescopic forklift truck, directly to the
work face, or if appropriate (such as bulk regular use materials) to the
materials holding areas around the site. Distribution of materials and hoisting
onto scaffold will also be by means of a telescopic truck, operating around the
haul road and access bay facility. These will be positioned around the
building, and located strategically to take advantage of natural openings
within the structure. The materials will then be transported to final location by
powered pallet trucks across the floor slabs.
Secure containers will be used for storage of small materials.
Compound/ Offices and temporary Car parking
The office area and compound will be accessed via the temporary road leading
from the construction site entrance the main visitors and staff site parking
area.
The compound will accommodate the requirement for the temporary site
parking, and space allocated accordingly, fluctuating in conjunction with the
numbers of operatives on site. It is envisaged that this will be adequate for
our needs and offensive off site parking by any member of the construction
team strictly enforced in parallel with the local authorities. These terms will
be included within the sub contract of all our supply chain appointed on this
project.
The compound will be located off the finished site area and approval for this
will be sought from the local authority in conjunction with the temporary site
entrance.
Site offices and welfare facilities, to current regulations, will consist of
‘Portakabin’ type units with secure containers for storage of small / vulnerable
materials. This is where our site team of managers, engineers, design co-
coordinators and surveyors will work from. The area will also include welfare
provision for our site operatives including, non catering canteens and secure
stores. Smoking will not be permitted on site.
Units are complete with safety lighting and fire alarms and stacked, as
necessary, to save space. Due to the proximity of the adjacent buildings the
accommodation units may have to be fire rated to comply with the code of
practice for the prevention of fires on construction sites.
Pedestrian barriers will define the safe access route to the facilities.
This main establishment will be provided following completion of the enabling
works, and will remain in situation until the final weeks of the project, leaving
sufficient time to finish and clear the area.
Scaffolding / Access
A fully boarded external perimeter scaffolding will be provided for render and
brick elevational materials and will be of the traditional independent type,
erected, maintained and adapted as necessary by a specialist contractor.
Cladding and other treatments will be installed from Mobile Elevated Working
Platform (Scissor lifts). The scaffold will be erected to give clear safe working
platforms and access to all floor levels and for roofing operations. Loading
towers will be incorporated within the external scaffold to receive heavy
materials. A mixture of cantilevered and double scaffolds will be used where
necessary to give access to the roof overhang to the street
Temporary staircases will be provided to access the scaffold. In conjunction
with the perimeter scaffold, guardrails will be erected to give perimeter edge
protection, and, together with safety netting will allow an early start for floor
and roof decks. Within ‘Streets’, voids and staircases, birdcage scaffold
platforms enable safe working at high level for rooflight installations, services
and finishes.
5 Uckington
5.1 Executive Summary
The structure at Uckington principally comprises, simple pad and strip
concrete foundations, a ground bearing concrete slab, and steel frame with
gluelam beams over the Street.
The buildings are clad in a combination of render, standing seam roof,
composite metal cladding, larch cladding, and Gloucestershire red brick.
The majority of internal finishes comprise plasterboard partitions, carpet and
vinyl and specific FF&E.
The overall duration for the works is 38 weeks.
Site access, hoarding and logistics are shown on the logistics layout attached
in Appendix D of Section 4 - ref 5092 – 5 UCK site establishment plan.
5.2 Specific Construction Activities
The site works commence with the temporary fencing, making the site safe
and establishment of the site office and welfare facilities.
Site ‘Enabling’
During the initial site clearance and preparation, it is essential to establish the
site compound including welfare provision at the earliest opportunity. For the
immediate stages of the project self-contained ‘Oasis units’ will be employed
to provide instant welfare facilities until temporary site services are
established. The vegetation will be cleared and bund to the east of the site
established early.
Highway Works and Section 278 works
Following receipt of the necessary consents, these works will be started at the
earliest opportunity. A temporary site entrance will be formed over the final
exit route, whilst the return vehicle route is constructed. This will be utilised
when the permanent exit routes are being constructed.
5.3 General Construction Activities
These will follow the principles set out in Section 3 ‘General Principles’ below.
5. 4 Programme
General Principles
The works have been planned in accordance with the detailed construction
programme attached in Appendix E of Section 4 - ref 5092/5-UCK-1
The programme details the following key activities;
• Site preparation / establishment and enabling works
• Foundations
• Frame erection and commence external drainage
• Upper floor and ground slabs
• Roof coverings
• Masonry / facades and commencement of training building
• Off site external works
• Internal services and finishes
• Progress remaining external works / surface finishes
• Soft landscaping
• Final tests and commissioning
Works generally commence from the main accommodation bay, allowing the
steel frame to commence along grid line C and work out toward the appliance
bay. The community area will follow with the street being infilled in sequence.
Whilst each area can be programmed individually, each phase will be over
lapped to maximise the efficiency of site operations and minimise the time on
site of each key trade. This at time will increase the resources on site at any
one time and we are therefore cognisant of the increased pressure this puts
on site parking etc (see further details sections below). Completion of higher-
level roofs / elevations that are above lower level and the roofs over the main
parts of the building with the most room density is critical. Our aim is to
achieve internal weather protection as soon as possible to allow M+E first fix
to commence.
Internally, service distributions gets underway and first fix on floor levels
progress to allow plastering works and floor screeds to follow and dry out in
sufficient time prior to accepting final finishes.
• BWIC Services + Services Distribution + Plantroom Installations
• 1st Fix M+E Installations + Carpentry
• Plaster / Render / Stud / Board / Skim Walls
• Lift Installation
• Stopping / Fire Barriers
• Floor Screed
• Wall Tiling
• Suspended Ceiling Grids
• 2nd Fix M+E Installations + Carpentry
• Main Decorations + Whiterock
• Floor Finishes
• Final Fix / Snag All Trades + Complete Ceiling Tiles
• Stair Balustrade / Handrails
• Air Test
• Street Floor Finishes
• M+E + Lift Final Tests & Commission
• Final Cleaning
• Loose Furniture / Fittings
The programme incorporates the access, safety and construction challenges
on this project and any specific constraints detailed in Section 5.5 below.
Completion, Handover, Decant and Defects
The completion process will follow the requirements of the Project Agreement
/ Building Contract. After Services Availability, we will assist with the decant
process with the following measures;
• Provision of packing crates
• Provision of labour to assist packing
• Provision of labour and vans to move equipment
• Transfer of crates
• Assist with the unloading and positioning of equipment.
• Connect and test equipment.
A 4 week period, along with a decent manager has been provided to manage
these activities.
All other measures will follow the general completion and handover process
noted in Section 3 below.
5.5 Specific Constraints
We are cognisant of the sensitivity in the local community particularly in
relation to the planning. We will focus on the principle of good
communication, in conjunction with GRFS, as detailed in the section below.
There are a number of domestic properties to the east of the site. An earth
bund will be formed at an early stage to assist in reducing noise and obscure
views onto the construction site from these properties. Acoustic fencing will
follow this operation later in the programme. Good communication will be
essential to sustain relations and our commitment to Considerate Contractors
Scheme should prove to be beneficial in this instance. We would initially
propose early letter drops followed by regular news letters. We would then
follow the GRFS communications protocol.
Further general information is provided in Section 3 below.
Statutory Services
Further survey works will be required prior to Financial Close to establish what
services, if any, need to be marked, protected lowered or the like. Much
further planning cannot be developed until this exercise has been undertaken.
5.6 Management Staff
The site team will be lead by a project manager TBA.
Following the enabling phase, they will be supported by a Site Manager until
the works are substantially complete. A senior site engineer will be utilised
for the construction of the substructures and the superstructure elements of
the build.
A project Quantity Surveyor will work from the outset on procuring all
elements of the project, working with a design and build co-ordinator up to
the completion of design development.
Decant Manager
A specific member of the site team will be allocated to these exercises. They
will have responsibility for liaising with Blue 3, the Authority and the FM
Provider, the upfront planning of the move, managing the move itself
including the relocation of FF&E.
Working closely with our building services manager and the commissioning
manager, they will ensure that each decant phase is completed,
commissioned and operational prior to the facility being ‘live’.
Building Services Manager
The site team will be backed up with support from Trevor Hewer, building
services co-ordinator. Trevor’s role is particularly important during the
completion of the M&E design and commissioning of each of the systems. As
a result of the structure of the programme, Trevor will manage all 4 project
ensuring at high level of consistency.
A Staff organisation chart is shown in Appendix C of Section 4.
5.7 Logistics
Site Entrance
The main site entrance is located off Tewkesbury Road as illustrated on
the site establishment plan shown in Appendix D of Section 4. This main
access point will include a holding area to allow vehicles an undisrupted
flow of traffic from the highway into the site. Suitable signage regarding
site operations will be erected to warn the public, delivery vehicles and
other users and assist in traffic management. A Gateman will be based in
an office adjacent to the construction entrance gate to manage and
supervise the flow of traffic and receipt of goods inward and visitors.
Wheel Washing
Due precautions will be taken when excavated material is being removed from
site to ensure that the road is kept clean at all times. The main strategy will
be to mitigate at the production of ‘muck’ at source via strict house keeping
and the installation of well designed temporary roads. Wheel washing plant is
not appropriate for this site as there is insufficient space to locate such
equipment; however the gateman will also manage the cleanliness of vehicles
leaving site with the aid of an industrial jet wash. This process will be
supported by regular visits from road sweepers as necessary.
Materials Deliveries, Storage and Handling
All material deliveries including the removal of waste will be scheduled within
the agreed site working hours, with any requirement outside of this being
agreed in advance with the Local Authority. All materials will be delivered
through the main site entrance.
The Gateman will be employed to control and secure the site entrance,
managing the goods deliveries in line with a traffic management plan. This
will incorporate a delivery route from the adjacent major road network agreed
in advance with the Police and Highways Authority.
The following principal items of plant will be utilised:-
• Fork Lift - Servicing bricklayers, general off-loading and distribution
• Mobile Crane – Steelwork and Glulam erection, load out decking, placing
pre-cast units, M+E plant, rooflights and sedum
• Pumps - Pumping concrete to floor slabs and screed to upper floors
• Scissors Lifts / Cherry Pickers - frame connections, fixing safety netting
and guardrails, installation of windows and cladding / elevational finishes
where more appropriate than scaffold
Deliveries of materials will be carefully unloaded in the delivery area.
Materials will then be distributed via telescopic forklift truck, directly to the
work face, or if appropriate (such as bulk regular use materials) to the
materials holding areas around the site. Distribution of materials and hoisting
onto scaffold will also be by means of a telescopic truck, operating around the
haul road and access bay facility. These will be positioned around the
building, and located strategically to take advantage of natural openings
within the structure. The materials will then be transported to final location by
powered pallet trucks across the floor slabs.
Secure containers will be used for storage of small materials.
Compound/ Offices and temporary Car parking
The office area and compound will be accessed via the temporary road leading
from the construction site entrance the main visitors and staff site parking
area. The compound will accommodate the requirement for the temporary site
parking, and space allocated accordingly, fluctuating in conjunction with the
numbers of operatives on site. It is envisaged that this will be adequate for
our needs and offensive off site parking by any member of the construction
team strictly enforced in parallel with the local authorities. These terms will
be included within the sub contract of all our supply chain appointed on this
project.
Site offices and welfare facilities, provided to current regulations, will consist
of ‘Portakabin’ type units with secure containers for storage of small /
vulnerable materials. This is where our site team of managers, engineers,
design co-coordinators and surveyors will work from. The area will also
include welfare provision for our site operatives including, non catering
canteens and secure stores. Smoking will not be permitted on site.
Units are complete with safety lighting and fire alarms and stacked, as
necessary, to save space. Due to the proximity of the adjacent buildings the
accommodation units may have to be fire rated to comply with the code of
practice for the prevention of fires on construction sites.
Pedestrian barriers will define the safe access route to the facilities.
This main establishment will be provided following completion of the enabling
works, and will remain in situation until the final weeks of the project, leaving
sufficient time to finish and clear the area.
Scaffolding / Access
A fully boarded external perimeter scaffolding will be provided for render and
brick elevational materials and will be of the traditional independent type,
erected, maintained and adapted as necessary by a specialist contractor.
Cladding and other treatments will be installed from Mobile Elevated Working
Platform (Scissor lifts). The scaffold will be erected to give clear safe working
platforms and access to all floor levels and for roofing operations. Loading
towers will be incorporated within the external scaffold to receive heavy
materials. A mixture of cantilevered and double scaffolds will be used where
necessary to give access to the roof overhang to the street.
Temporary staircases will be provided to access the scaffold. In conjunction
with the perimeter scaffold, guardrails will be erected to give perimeter edge
protection, and, together with safety netting will allow an early start for floor
and roof decks. Within ‘Streets’, voids and staircases, birdcage scaffold
platforms enable safe working at high level for rooflight installations, services
and finishes.
SECTION 3 - General Management
6.1 General Management
The overall staff management organisation chart is shown in Appendix C of
Section 4 below.
The overall construction management responsibilities for the contract will be
with Contracts Manager Ben Ramsay, supported by John Gorman on design
matters and Phil Jones on commercial matters.
Steve Fletcher will undertake the role of planner and in conjunction with each
Project Manager will monitor the progress of the works and assist with
reporting on same within the progress reports. Effective control of production
and evaluation of project status will be carried out on a regular basis by:
• Constant monitoring of information flows from the Professional Services
team against an agreed Information Required Schedule
• Regularly updated Project Programmes
• Regular internal progress meetings
• Regular evaluation of action against projected cash flow
• Regular subcontract meetings
• Regular evaluation of updated contract requirements
This will allow the management team to take appropriate, prompt and
effective action, as required.
Stuart Pratt is the Director with overall responsibility for the delivery of the
scheme.
6.2 Considerate Constructors Scheme
As associate members of the Considerate Construction Scheme we will
register the site and adopt its principles and ethos.
6.3 Quality Plan
In accordance with our Construction Management procedures, a project
specific quality management plan will be developed for each site identifying
high risk areas and the management approach to minimising these risks and
the philosophy for delivering an appropriate quality project. A draft of the
contents of the Quality Plan is included in Appendix A of Section 4 below.
6.4 General Liaison
The Construction Phase Health and Safety Plan has been completed and all
relevant authorities have been informed of intended commencement date
including Building Control, Factories Inspectorate and Service Authorities.
The safety and well being of the general public living and working in the
vicinity of the new construction is of paramount importance to us.
Regular dialogue through a nominated single point of contact will be
maintained with local schools, residents, businesses and other establishments
in the vicinity of the site, keeping them abreast of progress, scheme
developments and anything that may impact on their normal daily activities.
6.5 Meetings and Liaison
We will agree with the SPV and the Authority the format and detail of monthly
Progress Meeting reports to be submitted to ensure they are user-friendly and
contain all the information necessary for upward reporting. In accordance with
the Project Agreement / Building Contract, the progress meeting agenda will
be:
• Progress on the design and / or construction
• Review of the Risk Register
• Occurrence, or likely occurrence, of events that will impact on cost or time
• Results of risk, planning or value engineering workshops
In addition to this we would also wish to include on the agenda health &
safety, zero defects management and community relations / liaison.
Each project manager will also agree with the SPV and the Authority any other
direct liaison channels required to manage particular aspects of the project
such as safety and local community liaison.
Our Client liaison philosophy is ‘no surprises’. Again each Project Manager will
work closely with the Independent Certifier, the SPV’s Representative and the
Authority’s Representative to understand precisely what information is
required, by when and in what format as the project progresses. They will
communicate this to the project team to make sure we meet these needs.
Other than meetings used to report progress, we would also propose to hold
the following meetings;
• Design review meetings to develop and sign off Reviewable Design Data
such as FF&E and room layouts
• Risk / Key issue workshops as required
6.6 Reviewable Design Data (RDD)
The RDD Schedule is included in Schedule xx of the Project Agreement. The
protocol for reviewing and agreeing RDD will, follow the requirements of the
Building Contract. Once known, timings for the issue of required design data
will be drawn up and agreed with the Contracotrs Representative and the
Authority’s Representative.
This process will be lead by the design and build co-ordinator, overseen by
each sites Project Manager.
6.7 Safety, Health and Environment
A Construction Phase Heath and Safety plan will be developed and approved
prior to commencing on site. This will identify all high risk activities and
include outline plans to avoid or minimise these risks. A draft of the contents
of the Construction Phase Heath and Safety Plan is included in Appendix B of
Section 4 below.
Prior to the commencement of the project we would undertake an
environmental risk assessment with regards to the processes and materials to
be employed on the project and formulate an action plan to deal with the
impact of any risks identified.
6.8 Completion and Handover
The completion protocol will follow the requirements of the uilding Contract.
In addition to this, we recognise the importance of more detailed and
controlled handover procedures for the successful completion of any project,
and are acutely aware of the dissatisfaction a poor handover can cause at the
end of an otherwise successful project particularly in relation to decanting. In
response to this, at a corporate level, a number of key strategies have been
implemented to manage this process effectively.
The three principle initiatives are:
• Our Quality Management System
• The implementation of our Target Zero defects strategy
• The establishment of dedicated aftercare teams within our business
Our project managers are charged with taking the lead in facilitating and
managing this most important phase of the project. Their role is to co-
ordinate the resources of their teams and communicate with all the various
stakeholders. They will be supported by our contacts manager, Ben Ramsay,
together with all the managers who play a part in a successful handover. It is
important to highlight that we will have management specifically allocated to
the following disciplines;
• M&E manager (to ensure systems are fully complete, commissioned,
tested and witnessed)
• The design and build co-ordinator will manage the O&M and H&S File co-
ordinator (to ensure all elements from sub-contractors and the like are
obtained for inclusion in the file and agree contents of a “simplified user
guide”)
• Decant manager (This may well be the project manager if possible) (to
ensure the smooth transition of equipment & personnel)
• Quality champion (to co-ordinate & ensure defects and snags are closed
out)
• Environmental champion (to ensure all the requirements for BREEAM are
in place to support the post construction assessment)
• Customer Services Manager (to provide a point of contact post completion)
In addition to our M & E installer, WYG will also appoint a commissioning
manager to lead a dedicated team of engineers to control all the
commissioning activities. The commissioning team will compliment the project
team by being dedicated to the testing and commissioning process therefore
alleviating this responsibility from other members of the team and ensuring a
quality installation of services in line with the construction programme.
SECTION 4 - Appendices
Appendix A – Draft Quality Plan Contents
CONTENTS
PAGE
1. PROJECT INFORMATION
2. PROJECT ORGANISATION CHART
3. KEY PERSONNEL RESPONSIBILITIES
4. COMPANY PROCEDURES
5. PROJECT PROCEDURES
6. METHOD STATEMENTS
7. INSPECTION AND TESTING
8. SPECIALIST WORK SECTIONS
9. SPECIFIC CLIENT REQUIREMENTS
10. SPECIFIC STATUTORY REQUIREMENTS
11. PROJECT QUALITY PLAN REVIEW
12. APPENDIX
12.1 List of Contract Documents
12.2 Contract Programme
12.3 Inspection and Test Plan
12.4 Register of Copy Holders
Appendix B – Draft Construction Phase Health and Safety
Plan Contents
1 – 1.1 Project Description
Description 1.2 Programme Details
of 1.3 Existing Records and Plans
Project 1.4 Client
1.5 CDM Co-ordinator
1.6 Designer(s)
1.7 Health and Safety Advisor
2 – 2.1 Project Management
Management 2.2 Key Project Appointments
Structure 2.3 Project Health and Safety Objectives
& 2.4 Consultation
Responsibilities 2.5 Construction Plan Review
2.6 Ongoing Design Work
2.7 Selection of Contractors
2.8 Exchange of H&S Information between Contractors
2.9 Site Security
2.10 Site Induction
2.11 Training and Information
2.12 Welfare Facilities 2.13 Reporting & Investigation of Accidents and Incidents
including near misses
2.14 Risk Assessments and Method Statements
2.15 Clients Site Rules & Restrictions
2.16 Site Rules
Appendices A Clients Pre Construction Information
B Health and Safety Considerations Kier Form 4093
C Project Health & Safety Risk Assessment Kier Form
4094
D Traffic Management Plan
E Working at Height Strategy
F Lifting Strategy
G Demolition Plan
H Fire Safety & Other Emergencies Plan
I Site Waste Management Plan
J Occupational Health Strategy
K Temporary Works Plan
L Services’ Plan
M Ecology and Heritage
N Risk Assessment & Method Statement Register
Appendix C – Staff Organisational Charts
Appendix D – Site Establishment Plans
Appendix E - Programmes
top related