Construction Reportas on 28th July 2020
Keshav Nagar, Pune
Florida Riverwalk– July’20
• ‘A’ BUILDING:
• RCC work completed for all floors slabs
• Block work completed for all floors
• Electrical wall conducting completed for all floors
• Internal plaster work completed
• Gypsum work completed
• Internal toilet concealed plumbing work completed
• External plaster work completed
• Bath Dado tiles, kitchen platform and bath granite frames work completed
• Tile flooring work completed
• Waterproofing work completed
• UPVC window work completed
• 60% work complete of internal painting
• 60% work complete for external painting
• 98% work complete for external duct and terrace plumbing
• 98% work complete for door fixing & 90% work complete for SS railing
• Fire fighting work completed
• 85% Solar work completed
• 60% work complete for wiring and switch plate
Florida Riverwalk– July’20
• ‘B’ BUILDING:
• RCC work completed for 1st to 8th slab
• Brickwork completed for 1st to 4th floor
• INFRASTRUCTURE WORK:
• Underground water tank RCC work completed
• Club House: excavation work completed and 80% RCC work complete
• Transformer Room: excavation work, RCC, brickwork, plaster completed, commissioning is pending
• Swimming Pool: excavation work completed and 70% RCC work complete
• Compound Wall and Retaining Wall brickwork completed
• Underground Services Drainage + Storm + Electrical – RCC piping work completed
• Fire Fighting work completed
• Road Trimix work 90% complete for ‘A’ building surrounding area
• Genset work completed
• 90% STP RCC work complete
• 95% work completed for security cabin and gate