COPYRIGHT © AREMA 2008

of 42 1

TUNNELS

COPYRIGHT © AREMA 2008

of 42 2

General

• Tunnel Inspections present unique challenges• Track Time Sensitive• Good lighting source required• Various types of Tunnels and

– Construction Materials• Conditions found may warrant Expert Evaluation

of structure

COPYRIGHT © AREMA 2008

of 42 3

SAFETY

• Confined / Enclosed Space• Fumes from motorized Inspection Vehicle• Adequate Lighting• Walking Hazards- Wet / Ice• Wildlife

COPYRIGHT © AREMA 2008

of 42 4

External Environment

Note areas over & around Portals• Vegetation• Ground Water• Adjacent Slopes• Rock Slopes

COPYRIGHT © AREMA 2008

of 42 5

Internal Environment

• Natural Gas Pockets / Ground Water

• Conduits for Utilities / Fiber Optics

• Cut-Outs for Inspectors

• Drainage

• Pumps

COPYRIGHT © AREMA 2008

of 42 6

Vegetation Adjacent Slopes

COPYRIGHT © AREMA 2008

of 42 7

Rock Slopes

COPYRIGHT © AREMA 2008

of 42 8

Portals (Tunnel Inspection)

• Openings at each end of Tunnel

• Headwalls / Wingwalls

• Concrete/Stone/Timber/Natural Rock– Height of Headwall / Wingwalls– Stability / Structural Integrity

• Lateral movement / water seepage

– Note Condition / Deficiency• Timber Decay / Concrete Cracks,Deterioration

COPYRIGHT © AREMA 2008

of 42 9

Headwalls(date)/Wingwalls

COPYRIGHT © AREMA 2008

of 42 10

Natural Rock Portal

COPYRIGHT © AREMA 2008

of 42 11

Drains in Wall

COPYRIGHT © AREMA 2008

of 42 12

Tunnel Shaft

• Fundamental Tunnel Structure– Detailed Inspection Notes Thru Tunnel– Permanent Stationing Makers Thru Tunnel

• Various Types of Construction or Combination of Types of Construction

- Natural Rock

COPYRIGHT © AREMA 2008

of 42 13

Natural Rock

COPYRIGHT © AREMA 2008

of 42 14

Natural Rock-Anchor Bolts

COPYRIGHT © AREMA 2008

of 42 15

Timber & Steel Sets

• Timber Posts on Sides of Tunnel with Timber cut at angles to form Arch

• Timber Mud Sills on Stone or Concrete

• Spacing of Timber Sets determined by stability of the surrounding material

• Steel Sets are fabricated similar to the Timber Sets construction with Steel Beams

COPYRIGHT © AREMA 2008

of 42 16

Original Construction

COPYRIGHT © AREMA 2008

of 42 17

Timber Portal /Shed

COPYRIGHT © AREMA 2008

of 42 18

Steel Set / Lagging

COPYRIGHT © AREMA 2008

of 42 19

Steel Set / Lagging

COPYRIGHT © AREMA 2008

of 42 20

Lagging / Cribbing

• Lagging-Timber or Steel placed horizontally between Timber or Steel Sets

• Lagging can fully line the tunnel or support only unstable areas

• Cribbing/Packing: Material Placed behind Lagging or Liner to fill void between lagging and failed material.

COPYRIGHT © AREMA 2008

of 42 21

Cribbing Behind Liner

COPYRIGHT © AREMA 2008

of 42 22

Concrete / Masonry

• Reinforced Concrete Walls / Arch

• Masonry Walls / Arch ( Brick, Stone)

COPYRIGHT © AREMA 2008

of 42 23

Concrete Lined Tunnel

COPYRIGHT © AREMA 2008

of 42 24

Brick Lined Tunnel

COPYRIGHT © AREMA 2008

of 42 25

Steel Lining

• Corrugated Steel

• Ribbed Tunnel Liner Plates

COPYRIGHT © AREMA 2008

of 42 26

Tunnel Floor

• Natural Ground when Tunnel was cut

• Struts below ballast to each side of Tunnel

• Reinforced Concrete

COPYRIGHT © AREMA 2008

of 42 27

Problems / Conditions

• Natural / Exposed Material– Cracks, Openings, Movement– New pieces of Rock on floor– Loose Rock Bolts, Anchors

COPYRIGHT © AREMA 2008

of 42 28

Material on Tunnel Floor

COPYRIGHT © AREMA 2008

of 42 29

Loose Rock Bolts

COPYRIGHT © AREMA 2008

of 42 30

Problems / Conditions

• Timber Sets / Lining– Decay; Sound and/or Drill for voids– Bottom Sill; Bearing Area, Crushing, Bulging– Joints, Gaps, Alignment– Bolts, Drift Pins

COPYRIGHT © AREMA 2008

of 42 31

Problems / Conditions

• Steel Sets / Lining– Benchwall: Anchors, Corrosion– Columns / Struts: Corrosion, Section Loss,

Buckling / Alignment– Bulging in Walls / Arch

COPYRIGHT © AREMA 2008

of 42 32

Failed Steel Liner

COPYRIGHT © AREMA 2008

of 42 33

Problems / Conditions

• Lagging: Timber, Steel– Decay , Corrosion, Section loss– Openings at Seams / Joints, Bulging– Ground or Failures behind lagging

COPYRIGHT © AREMA 2008

of 42 34

Problems / Conditions

• Concrete / Masonry Lining– New Cracks, Spalling, Bulging– Movement at Construction Joints– Water Seeping, weep holes– Brick / Concrete on floor– Movement , Hinging at Spring Line– Bulging of Walls and Arch – Benchwall / Footer

COPYRIGHT © AREMA 2008

of 42 35

Failed Concrete Liner

COPYRIGHT © AREMA 2008

of 42 36

Problems / Conditions

• Tunnel Floor / Roadbed– Track Surface– Muddy / Pumping / Fouled Ballast– Drainage Ditches / Culverts

• Train Impacts / Clearance– Signs of Impacts– Verify Dimensions-

• Top/Rail & Centerline Track

COPYRIGHT © AREMA 2008

of 42 37

Impact Damage

COPYRIGHT © AREMA 2008

of 42 38

Tunnel Inspection Checklist

• PORTALS– Soil / Rock Stability– Condition of Headwall and Wingwalls– Drainage behind Headwall and Wingwalls– Surface Drainage

COPYRIGHT © AREMA 2008

of 42 39

Tunnel Inspection Checklist

• SHAFT– Clearances-Bulges in Ceilings / Walls– Fractured or Scaling Stone– Condition of Rock Bolts and Anchors– Condition of Timber/ Steel Sets /Lagging

COPYRIGHT © AREMA 2008

of 42 40

Tunnel Inspection Checklist

• SHAFT– Condition of Concrete / Masonry Lining

• Bulges• Cracks• Tuckpointing• Surface voids

COPYRIGHT © AREMA 2008

of 42 41

Tunnel Inspection Checklist

• SHAFT– Tunnel Floor

• Debris on floor indicating problems• Buckling or heave• Fouled Ballast• Drainage• Water / Ice accumulation

COPYRIGHT © AREMA 2008

of 42 42

EMERGENCYIf the bridge inspector encounters a tunnel condition that affects the safe operations of trains in, or near the tunnel, contact the railroad dispatcher and responsible authority to stop any trains and arrange for immediate repairs. Criteria for limits of acceptable/tolerable conditions must be provided by the Railroad Owner or their designated engineer based on the principles of acceptable rating contained in the appropriate chapter of the AREMA Manual for Railway Engineering