CORNWALL’S MULTISPORT CENTRECity of Cornwall

COUNCIL PROGRESS UPDATE

Presented by:

Denny Bryan, P. Eng., OAA, MRAIC, CAPHC and William Weima, OAA, MRAIC

Summary of Activities to DateFundraising kick-off breakfastCompleted four (4) staff/technical design

meetingsSteering Committee PresentationGathering and reviewing existing site informationLand survey underwayEngineering soils investigation underwayEstablished a schedule of activitiesBuilding program reviewedHeld LEED® Workshop / delivered LEED® ScorecardCompleted several concept building/site studiesOur first milestone – concept site & building plan

developed

Concept Site Plan

Alternate Concept Site Plan(with football)

Concept Building Layout – Ground Floor

Concept Building Layout – Mezzanine Level

Concept Perspective View

Next StepsOpen House for community information and

feedbackProperty acquisitionAdvance the design/drawings based on concept

◦ Building Elevations◦ Materials◦ Construction Details

Develop and monitor construction budgetsContinue to monitor LEED components/scorecard

– LEED® Silver objectiveReport back to Council as the design is advanced

and finalizedTender the Project for March 2011 completion

CORNWALL’S MULTISPORT CENTRE City of Cornwall

QUESTIONS & ANSWERS