Customer Energy Retrofit
Integration with Local Improvement Charges
22CONFIDENTIAL
Enbridge Consultation Background
• On Bill Financing was proposed by Intervenors as part of
Enbridge’s DSM 2013/2014 negotiations
• On October 3, 2012 EGD agreed with OBA and DSM
consultation participants to work towards the possibility of
offering a program such that
– it would be feasible, viable and cost effective
– three Consultative meetings would held to develop a project plan
• On November 15, 2012 EGD and OBF consultative
agreed to integrate Community Energy Retrofit with LIC
– EGD is seeking for a municipality to partner and pilot LIC
33CONFIDENTIAL
EGD’s Guiding Principles
• Design a program that:
– has minimal impact on customers’ energy bill
– does not negatively affect Enbridge’s customer satisfaction
– provides reasonable savings to expenditure ratio
– leverages existing infrastructure and minimizes implementation
cost
44CONFIDENTIAL
What’s We Have Done So Far
• Launched Customer Energy Retrofit (CER) in July 2012
– Gained knowledge on what works and what doesn’t
– Incorporating lessons learned for our 2013 CER program
– 2013 Budget of $1.8 Million with increased targets
• Researched what other jurisdictions are doing
– Home retrofit funding models; target audience; loan mechanism
• Retained services of EnerFocus Consulting
• Outlined approach and goals for integration of CER with
LIC
– Listed key questions to be answered to help define the scope
55CONFIDENTIAL
The Challenge & Our Approach
• There are too many unanswered questions around scope
of LIC program
– A pilot partnering with a municipality is our recommended
approach
– Get a clear understanding/answers of these design questions:
define scope
• Identified eight key design elements that will constitute
EGD’s DSM LIC program and for any given municipality
– The approach is to discuss each element in a time-boxed fashion
during a design session with stakeholders
– When time runs out, we will park the topic for discussion to the
next meeting along with action items and issues list
66CONFIDENTIAL
LIC Pilot - Design Elements
LIC Program
Pilot
2. Transferability
of Debt
7. Reputable Professionals
5. Standardized
DSM Measures
4. Performance
Indices
3. Processes & Procedures
1. Financier / Lenders
6. Target Audience & Campaigns
8. LIC Infrastructure
Municipality Specific Elements
77CONFIDENTIAL
Design Element – Details
• Element 1: Financiers/Lenders
– City financed or banks/credit unions/insurance companies
– How many to target; selection criteria; economy of scale
– Secure low interest rates; who absorbs risks on default loans?
– Loan terms; credit rating; paperwork; lien; size of transaction
• Element 2: Transferability of debt
– Is it possible to tie debt to the property
• How to initiate, enforce and maintain
– Regulatory approval and legal obligations associated with
transferring debt from one account to another
– Should there be a lien mechanism in place
88CONFIDENTIAL
Design Element – Details (Cont’d.)
• Element 3: Processes & Procedures
– Bill calculation; Billing; Payment Processing; Collections
– Data and information flow
– Collections and methodology for partial payment
– Service Levels and Quality Control
• Element 4: Performance Indices
– Actual savings of DSM measures can be a challenge
• Insufficient data
• Consolidation of savings from gas, electricity and water
– What are the alternatives
• Deemed savings; AMR implementation; Additional meter readings at targeted
houses; Other options
99CONFIDENTIAL
Design Element – Details (Cont’d.)
• Element 5: Standardized DSM Measures
– Need for an approved DSM measure list
• Standardized costs for various DSM measures
– Include DSM measures for gas, electric and water?
• Non-DSM measures; Soft costs associated with retrofits
• Element 6: Target Audience & Campaign Programs
– Who is eligible for LIC program?
• Small business; Low income; Home owners; High Rises; C & I
– What marketing programs should be launched?
• Direct or Mass marketing
• Marketing Collateral (Flyers, posters, brochures, web content, visual aids, data
sheets, white papers etc.)
– Volume analysis for LIC
1010CONFIDENTIAL
Design Element – Details (Cont’d.)
• Element 7: Reputable Professionals
– Standard to select reputable supplier and contractors in Ontario
• Training, licensing, monitoring, enforcing
– Standards to be used for pre and post audit
• Certified Measurement & Verification Professional
• NRCan standards
• Element 8: LIC Infrastructure
– Municipality to create/modify its existing IT infrastructure or
outsource?
– Support personnel
• Customer care processes; credit application processing; Liaison with
financiers/contractors/suppliers/service providers; Accounting; Legal support
1111CONFIDENTIAL
LIC Pilot Planning – Draft Roadmap
* Assuming that one municipality has approved implementation with EGD
of an LIC pilot
Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13
Meet with potential municipalities to partner
Identify municipal partner for LIC Pilot
List and finalize terms of partnership
Project Launch - Develop charter
Identify stakeholders and mobilize team
Conduct Design Sessions and Identify Scope
Create Project Plan for Pilot & Get Approval
Start LIC Pilot Implementation
Develop Processes & Procedures
Design & Implement Infrastructure
Develop Marketing Plan
Prepare for Design Sessions
Communicate with key stakeholders
EGD's DSM LIC Pilot
Planning - Roadmap
ASHOK cvcvcvcv cv cvcv
1212CONFIDENTIAL
LIC Project Plan Outputs
• Template style ‘Information packet’ for municipalities
– Draft plan and components to implement LIC
– Draft plan and components to integrate with Enbridge CER
– List of recommendations around what works; where
standardization is beneficial
• Option to leverage EGD OBA functionality – Bill Ready
Charge
• Enbridge CER program adjusted to adopt LIC
– Attuned campaign plan and marketing collateral that will maximize
uptake
– Revise program plan to dovetail LIC with minimal disruption
1313CONFIDENTIAL
Next Steps
• Conduct meetings with Municipalities:
– Present approach and identify interest
– Conduct design session(s)
– Define high level scope for pilot
• Report back to OBF and DSM consultation on Dec/11/’12
and going forward
• Participate in TAF working group and provide updates
• Develop project plan for pilot
– Estimate costs, work effort, dependencies and constraints
– Get approval for pilot implementation