2018 ASHE Luncheon Presentation
2018 ASHE LUNCHEON
JANUARY 30, 2018
2018 Project Presentation
Delaware County Engineer
2018 ASHE Luncheon Presentation
New County Logos and Website Redesign
GIS Upgrades
Drone Program
Planning for the Future
ROADS, ROADS, ROADS!!!
What’s New at DCEO?
2018 ASHE Luncheon Presentation
New County Logos!
Website redesign coming this spring!
2018 ASHE Luncheon Presentation
Collecting GIS inventory and inspection data for roads, culverts, guardrail, storm sewers,
Information will be available soon through DCEO webmap
GIS Upgrades
2018 ASHE Luncheon Presentation
Two FAA Part 109 certified commercial remote pilots on staff
Drone equipment has become very affordable
Dozens of different applications
Drone Program
2018 ASHE Luncheon Presentation
Construction Photos
2018 ASHE Luncheon Presentation
Construction Photos
2018 ASHE Luncheon Presentation
Construction Videos
2018 ASHE Luncheon Presentation
Bridge Inspection
2018 ASHE Luncheon Presentation
Traffic Studies
2018 ASHE Luncheon Presentation
DCEO 5-year Capital Improvement Plan includes $120 million investment of County funds over next 5 years, leveraging another $125 million in federal, state and other local revenues
Roads, Roads, Roads!!!
2018 ASHE Luncheon Presentation
8 road and bridge construction contracts◦ East Powell Road, Phase 1 (final 35%) - $0.8M of $2M
◦ Lewis Center and Bale Kenyon Intersection - $2.2M
◦ Bale Kenyon Road, Phase 1 - $2.4M
◦ Worthington and Big Walnut Intersection - $2.5M
◦ Klondike Road Bridge - $0.8M
◦ 2017 Design-Build Bridges (2 rural bridges) - $0.6M
◦ South Old State Road (30% complete) - $5M of $15M
◦ 2018 Road Improvement Program (resurfacing) - $8.2M
$22.5 million of work completed
2017 Construction Summary
2018 ASHE Luncheon Presentation
11 construction projects scheduled◦ Worthington & Highland Lakes Traffic Signal - $0.2M
◦ Liberty Road and Jewett Road Intersection - $1.3M
◦ Home Road at SR 315 (50% in 2018) - $3M of $6M
◦ South Old 3C Improvements (40% in 2018) - $2.5M of $6M
◦ Piatt Road Extension (30% in 2018) – $1M of $3.2M
◦ Bainbridge Mills Drive Relocation - $0.4M
◦ S.R. 3 and Galena Road Intersection - $1.2M
◦ Home Road & Scioto Chase Traffic Signal - $0.2M
◦ Lewis Center & North Road Improvements 20% - $0.7M of $3.2M
◦ South Old State Road (completion) - $10M
◦ 2018 Road Improvement Program - $7.2M
$28 million estimated work to be completed
2018 Construction Program
2018 ASHE Luncheon Presentation
South Old State Road – Polaris Pkwy to Orange Road
$15 million project, completion scheduled for fall 2018
North-South Corridor Projects
2018 ASHE Luncheon Presentation
Piatt Road Extension – Cheshire to Berlin Station Rd.
$3.2 million project, completion scheduled summer 2019
North-South Corridor Projects
2018 ASHE Luncheon Presentation
Home Road at S.R. 315
Construction summer 2018 to Fall 2019 – $6M estimate
East-West Corridor Projects
2018 ASHE Luncheon Presentation
Lewis Center & North Road
$3.2 million construction
Fall 2018 to Summer 2019
East-West Corridor Projects
2018 ASHE Luncheon Presentation
270
Home Rd.
Big Walnut Rd.
Lewis Center Rd.
37
124DELAWARE
36
37
36
106DELAWARE
109DELAWARE
71
42
121
131
124
119
Delaware
Sunbury
Polaris Pkwy.
I-71/I-270
Center Village Rd.
25DELAWARE
33
2018 ASHE Luncheon Presentation
2 interchanges serving nearly
200,000 residents
131
121
140
119
2018 ASHE Luncheon Presentation
Phase 1 (Interchange and Nearby Local Roads) = $36.34 M
Schedule:◦ Preliminary Engineering: 2016-19
◦ Right of Way & Utilities: 2019-21
◦ Construction: 2022
Costs:◦ TRAC: $15 million (FY 2022)
◦ ODOT: $3.58 million (FY 2016-19)
◦ Local: $17.76 million
Big Walnut Interchange
2018 ASHE Luncheon Presentation
Current Status:
Received TRAC approval for Tier II Status in January 2018
Completion of feasibility study scheduled for spring 2018
Interchange Justification Study and final design planned for 2018 to 2020
Construction of Phase 1 planned 2022+
Big Walnut Interchange
2018 ASHE Luncheon Presentation
Consultant selection two times per year
Announcements and scope of services advertised last week of January and July each year
http://www.co.delaware.oh.us/engineer/Design/consultantinfo.htm
Upcoming Design Contracts
2018 ASHE Luncheon Presentation
Currently advertised – Letters of Interest due February 19
1. Liberty Road and Salisbury Drive Intersection◦ $1.8M construction estimate
2. 2018-1 General Engineering Services◦ $200,000 two-year task-order agreement
January 2018
2018 ASHE Luncheon Presentation
Liberty Road and Salisbury Drive – single lane roundabout
2018 ASHE Luncheon Presentation
Scheduled for advertisement July 25, 2018
1. Cheshire Road over CSX Railroad Grade Separation◦ $12M construction estimate
◦ Currently studying conceptual alternatives
2. Berlin Station Road Improvements, Phase 1 and 2◦ Currently studying conceptual alternatives
July 2018
2018 ASHE Luncheon Presentation
Scheduled for advertisement January 28, 2019
1. Africa Road Improvements, Phase 1◦ Widening from Worthington Road to Big Walnut Road
2. CR 54 over Big Walnut Creek◦ 135-foot span bridge replacement plus approach realignment
3. General Engineering Services◦ $200,000 two-year task-order agreement
January 2019
2018 ASHE Luncheon Presentation
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
2018 2019 2020 2021
County Funds Federal Funds
2018-21 Consultant Program
2018 ASHE Luncheon Presentation
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
2018 2019 2020 2021
County Funds Other Funds
2018-21 Construction Work
2018 ASHE Luncheon Presentation
Mostly roadway and intersection projects focused on major corridors
$24 million average annual construction program
$2.7 million average annual consultant design program
2018-21 Capital Summary
2018 ASHE Luncheon Presentation
Don’t Do This…
2018 ASHE Luncheon Presentation
Questions?
Robert Riley, PE, PS
Chief Deputy Engineer
Delaware County Engineer’s Office