descriptive analysis of construction scheduling data
Post on 04-Nov-2021
5 Views
Preview:
TRANSCRIPT
DESCRIPTIVE ANALYSIS OF CONSTRUCTION SCHEDULING DATA TOWARDS
AUTOMATION OF 4D BUILDING INFORMATION MODELING
BY
ABEL RICHARD VERA IGLESIAS
THESIS
Submitted in partial fulfillment of the requirements
for the degree of Master of Science in Civil Engineering
in the Graduate College of the
University of Illinois at Urbana-Champaign, 2019
Urbana, Illinois
Adviser:
Associate Professor Mani Golparvar-Fard
ii
ABSTRACT
The integration of construction planning and scheduling into Building Information
Modeling (BIM) workflows is still evolving. The common workflow to integrate the fourth
dimensional (4D) of BIM still relies on the ability of manually linking construction activity tasks
with 3D BIM-based objects. This process is arduous and requires high levels of accuracy and
strong communication between design and construction trades. Identifying the corresponding
objects and its tasks could even be a more complex process in large projects. Although this 4D
BIM procedure tends to be troublesome, the benefits of completing it are various: project
visualization, project monitoring and controls, construction safety, etc. Different efforts for
leveraging its uses and application have been released, nonetheless there are a lack of studies
focused on the analysis of the two main variables entailed within 4D BIM towards its
automation: construction schedules and 3D BIM-based objects. This study is intended to cover
this gap.
Analyzing the relation between construction scheduling data and BIM-based objects
provides an opportunity to identify ways to fully-automate 4D BIM under a systematic approach.
Therefore, this research includes a comprehensive diagnosis of the current construction planning
and scheduling, and 4D BIM practices in the industry. This diagnosis has been elaborated based
on a survey of professional testimonies and reflections offered by members of the Architecture,
Engineering and Construction (AEC) community. The status quo shows that at least 60% of the
participants do not count with standards to create Work Breakdown Structures and majority of
them perform their schedules based on in-house conventions. Moreover, the diagnosis indicates
iii
that 53% update their construction master schedule on a monthly basis and up to 85% use
multiple approaches to track project progress. Similarly, the study reveals that 87% of the
recipients are familiar with 4D BIM to some extent and 94% leverage multiple uses from it.
Construction visualization and project monitoring account as the main 4D BIM uses within the
industry.
Finally, this study includes a descriptive analysis and interpretation of construction
scheduling data retrieved from real estate projects. This data has been related to object-driven
standards such as Uniformat. The results show that 77% of construction activities are BIM-based
and only 19% present a high level of detail regarding the type of object. Categories such as
services present the largest amount of BIM-based data, and elements such as HVAC, walls and
framing account for the highest level of detail incorporated within construction schedules.
Discussion regarding the status quo of construction scheduling data analysis results, professional
practices, and methods towards 4D BIM automation has been discussed and suggested.
iv
ACKNOWLEDGEMENTS
Special thanks to my adviser Dr. Mani Golparvar-Fard for inspiring this research journey
and guiding me through the steps of completing the master’s program at the Civil and
Environmental Engineering Department in the University of Illinois at Urbana-Champaign.
Working on transforming the construction industry with cutting-edge methods to reinvent
traditional workflows in project monitoring and controls account as the most exciting academic
work I have done. Thank you for considering me a part of the lead team aimed to achieve such
reinvention. In addition, my gratefulness to the RAAMAC team for providing the data to conduct
this study.
Similarly, all my gratitude to the CEE-UIUC faculty and staff for this 2-year of
outstanding learning experience in Construction Engineering and Management. So grateful to be
part of the best Graduate Department in Civil Engineering in the U.S. Distinctive recognition to
the CEE Office of Alumni & Corporate Relationships and the UIUC Technology Services for
their support with distributing the survey contained in this Thesis, and to all the participants who
devoted part of their time to collaborate with this research work. Many thanks to all.
Additionally, remarkable mention to the Fulbright Program Scholarship for facilitating
my academic journey. It has been an incomparable life experience. I am truly convinced this
contribution will help with shaping the world in a better way, as the Senator J. W. Fulbright
envisioned one day.
Finally, all my appreciation to my family, colleagues and friends in Moquegua, Peru.
Your motivation and encouragement were fundamental to start and conclude this academic
chapter successfully.
v
DEDICATION
With much Love to
Abelino & Deysi,
my Parents,
and,
Deysi & Joaquin,
my Sister and Brother.
Your example is the best source of Inspiration I have in life. Thanks for showing me that nothing
is impossible when you truly want to achieve it.
And Chris,
it would not be possible without your support.
Love you all.
vi
TABLE OF CONTENTS
CHAPTER 1: INTRODUCTION ................................................................................................... 1
CHAPTER 2: LITERATURE REVIEW ........................................................................................ 7
CHAPTER 3: CONSTRUCTION SCHEDULING AND 4D BIM PRACTICES ....................... 18
CHAPTER 4: CONSTRUCTION SCHEDULING DATA ANALYSIS ..................................... 44
CHAPTER 5: RESULTS AND DISCUSSION ............................................................................ 67
CHAPTER 6: CONCLUSION & FUTURE WORK.................................................................... 78
REFERENCES ............................................................................................................................. 83
APPENDIX A: RESEARCH SURVEY ....................................................................................... 95
APPENDIX B: SURVEY RESULTS ......................................................................................... 104
1
CHAPTER 1: INTRODUCTION
1.1 State of Practice in Construction Planning and Scheduling & BIM
In the U.S, the total value of productivity in construction has declined half way since
1960 (Sveikauskas L. , Rowe, Mildenberger, Price, & Young, 2016). Indeed, there is an annual
$1 trillion shortfall across the world in infrastructure due to the delays and over budgets of
current infrastructure projects (The Economist, 2017). Remarkable issues in construction
productivity are associated with the complexity of its process in comparison with other sectors
like retail and manufacturing. The advance digitalization and automation of these markets have
transformed them enormously creating a huge gap in productivity in comparison with
construction. This difference is observed by comparing labor-productivity rates over the past two
decades. Construction productivity has grown only 1 percent in average, whereas the global
economy and manufacturing have reached 2.8 percent and 3.6 percent respectively (McKinsey
Global Institute, 2017). Despite the pessimism of this trend towards the future, new studies have
demonstrated that at least three industries in the sector show positive and strong productivity
rates. These sectors are: single-family residential construction, multifamily residential
construction, and industrial construction. (Sveikauskas L. , Rowe, Mildenberger, Price, &
Young, 2018). According to experts, higher labor productivity values in construction are
associated with less complex and more reliable schedules (McKinsey Global Institute, 2017).
Therefore, efforts to enhance schedule quality control workflows during preconstruction and
construction monitoring during construction are necessary.
2
The concept of Building Information Modeling (BIM) was implemented in the
Architecture Engineering and Construction (AEC) industry in the early 2000’s (Volk, Stengel, &
F., 2013). Although initially introduced as an object-oriented product for Computer Aided
Design (CAD), BIM has been visualized as a productivity booster, cost reducer and management
aid integrated system during all the stages of the construction process (Succar, 2009). In fact,
there is a wide range of benefits obtained from the use of BIM such as technical, knowledge
management, standardization, diversity management benefits, integration, economics,
planning/scheduling, building lifecycle assessment (LCA), and decision support benefits
(Ghaffarianhoseini, et al., 2017). Due to these proven benefits, BIM has expanded its
functionality and applicability across the world (Enshassi, Abuhamra, & Alkilani, 2018).
Although some practitioners still hesitate on the idea of fully adopting BIM, studies show that a
surge from 28% in 2007 up to 71% in 2012 indicates that BIM workflows have continuously
been incorporated. Additionally, 91% of large companies and 49% of small firms have
introduced BIM within their organizations (Bernstein, Jones, & Russo, 2012). Exceptional
interest has been focused on the interaction between BIM and construction planning &
scheduling within the AEC community in recent years (Hartmann, Gao, & Fischer, 2008). This is
due to the increased number of opportunities to provide a comprehensive understanding of the
construction phase through visualization and project progress monitoring (Koo & Fischer, 2000).
Under the integrated BIM platform, automated models to track project performance can save
time and cost invested in collecting data and updating construction schedule. In addition,
problems like the lack of frequent communication amongst subcontractors and project
management teams can be improved. (Navon & Sacks, 2007). All these benefits can be
achievable through construction visualization offered by the fourth dimensional (4D) of BIM
3
(Ding, Zhou, & Akinci, 2014), where the combination of construction planning and scheduling
data and BIM workflows play a fundamental role.
1.2 Role of 4D BIM in Construction
Research to demonstrate the cost and return of implementing BIM have shown promising
and encouraging upfront benefits (Giel, Raja, & Issa, 2013). One of the underlying uses of BIM
relies on its fourth dimensional (4D), which is gaining remarkable interest of practitioners and
users across the world (Gledson & Greennwood, 2017). 4D BIM improves communication,
approval and continuous improvement of construction schedules amongst different trades in
construction projects such as design, construction management, owner, subcontractors and
community members (Issa, Flood, & O'Brien, 2005). Even though the benefits of 4D BIM are
clear, still many users consider this workflow time-consuming and impractical due to the
required work to update the model, specifically the schedule, to bring the model to its as-built
conditions (Lopez, Chong, Wang, & Graham, 2016). Achieving this goal requires the execution
of two tasks: capturing reality of as-built conditions and updated construction schedule based on
such conditions. Extensive research on this field has demonstrated the impact of reality capture
throughout imaging and geospatial technologies to compare as-planned versus as-built conditions
by detecting schedule variances, track project progress and visualize it (Golparvar-Fard, Peña-
Mora, & Savarese, 2011). Efforts to automate this procedure continuously evolve. Leite et al.
(2016) have identified the automation of retrieved captured data into 4D BIM systems as one of
the main challenges to overcome. Moreover, some authors such as Chen et al. (2015) indicate
that there is still a gap to fully automate 4D BIM updating of construction schedules based on 3D
object-driven data. Indeed, attempts to bridge this gap have been published. Experiments with
4
real construction projects demonstrated high levels of accuracy in real-time performances
strengthening the likelihood to automate schedule updating relying on object-based standards
such as the industry foundation classes (IFC) (Hamledari, McCabe, Davari, & Shahi, 2017).
The intent of this research is focused on the analysis of scheduling data towards the full
automation of 4D BIM under construction planning and scheduling standards.
1.3 Need for automated integration of Construction Scheduling & 4D BIM
interface
Construction planning and scheduling can be a cumbersome process that requires full
coordination among Architectural, Engineering Construction (AEC) agents. It entails a
comprehensive and detailed understanding of the project and its workflows from start to end of
the construction phase. It also requires the standardization of tasks and their conventions
amongst trades (Hall D. J., 2008). The construction industry has widely accepted and used
Construction Specifications Institute CSI® as standards to classify construction information
(Chang & Tsai, 2003). Some of these standards are MasterFormat® and UniFormatTM. While
MasterFormat® has been utilized as the industry standard to retrieve classified construction
information regarding the type of work result in the project, UniFormat® has been used as a the
classifier of elements and assemblies within the project such as walls, floors, ceilings, roofs and
others (Weygant, 2011). In relationship with BIM, Weygant (2011) indicates that UniFormatTM
provides opportunities to organize and cross reference element information. Since this standard
provides a comprehensive object-driven approach of construction operations, its applicability
towards automated schedule generation in a 4D BIM environment is significant.
5
The computational possibilities of developing automated schedules based on object-
driven conventions have been studied (Hamledari, McCabe, Davari, & Shahi, 2017).
Furthermore, its benefits have been stablished. Automating 4D model updates offers
opportunities for reducing the cost of modeling and user training, which represents a huge step
for BIM adoption (Leite, et al., 2016). These steps bring BIM closer to the AEC community,
nonetheless updating schedules in 4D BIM should rely on the most common practices used in the
industry. This gap has not been covered yet. The intent of this work is to contribute to the
automation of 4D BIM schedule updating by researching the current practices in construction
planning and scheduling adopted by the industry and analyzing such practices in relation with
object-driven standards.
1.4 Organization of this Thesis
This thesis is structured by chapters. Its organization is indicated below:
- Chapter 2 presents literature review describing the state-of-the-art regarding the
evolution of construction planning and scheduling towards automation of 4D BIM
schedule updating for tracking progress and project controls.
- Chapter 3 describes the current tendencies in construction planning, scheduling and
4D BIM. This provides a diagnostic of the status quo of construction operations
towards the implementation of 4D BIM automation procedures.
- Chapter 4 explains the methods utilized to analyze collected construction scheduling
data from real estate infrastructure projects and parameters adopted to identify BIM-
based tasks within construction schedules.
6
- Chapter 5 summarizes the results obtained from this study and opens the discussion
for future research on this field.
- Chapter 6 outlines the conclusions established with the analysis of construction
scheduling data towards 4D BIM automation.
7
CHAPTER 2: LITERATURE REVIEW
2.1 Planning & Scheduling in Construction Operations and BIM
The decision of undertaking planning and scheduling workflows during the construction
of infrastructure projects has been widely discussed. It is commonly known that the main goal of
planning in construction is associated with the on-time delivery of a project. This goal takes into
consideration not only the time, but the cost, safety and quality of the tasks and procedures
required to complete the project. Extensive research to optimize time, cost and resources in
construction schedules has been studied (Faghihi, Reinschmidt, & Kang, 2016). Regardless the
amount of research developed within this field, it is necessary to clearly understand the typical
workflow for formulating and controlling construction schedules during the execution of
construction projects. Baldwin & Bordoli (2014) provide a comprehensive study of planning and
scheduling with real case studies regarding the common practices in construction. They describe
the hierarchy led by the owner and project manager who mutually agree on the creation of the
Master Schedule. This document is a contractual binding agreement commonly used to control
project progress along the execution phase. Trades such as consultant (owner’s representative),
design (architects and engineers) and construction (constructor manager, general contractor and
subcontractors) are obligated to use this document as a guide, or a tighter replica of it (Target
Construction Programme) through the entire process. In addition, these trades have the
possibility to elaborate packages that suit their specific targets based on Work Breakdown
Structures. Yet, these packages do not constitute contractual documents. Meaning that, AEC
members tend to create their own version of the master schedule by establishing coordinated
conventions approved by the project manager, and eventually, by the owner’s consultant team.
8
The introduction of BIM in the construction domain has generated potential to go beyond
the manual generation of construction schedules. Particular attention has been payed to the
likelihood of creating schedules within a BIM environment to improve construction operations.
This is the case of automated schedules in BIM. Dong, Fisher, Haddad, & Levit (2013)
introduced the automation of look-ahead schedules for the final stage of complex construction
projects. This innovative approach was achieved by the combination of lean principles and
algorithms in charge of optimizing and reducing the amount of errors produced during project
completion to zero. Zhang et al. (2013) identified a holistic approach to connect jobsite safety
issues with BIM. They explored the possibilities of linking construction tasks with their
associated fall-related hazards. In addition, they developed systematic outputs in form of reports
/ schedules to prevent accidents during the execution period. Similarly, Moon, Kim, Kamat, &
Kang (2015) conducted research on computational methodologies to enhance project planning
performance. Their study establishes a link between the generation of optimal schedules and 4D
BIM environments. Furthermore, researchers such as Liu, Al-Hussein & Lu (2015) discussed
the possibility of performing BIM-based schedules relying on the integration of BIM platforms
and construction schedule packages by developing “activity level construction schedules”. This
approach was formulated under resource constraints and represents a forward step towards the
automation of planning and scheduling in project management. More recently, other efforts to
understand the relationship of BIM workflows into scheduling practices were led by Sigalov &
König (2017). They suggest the use of BIM-based schedules to decrease planning time and foster
productivity in the jobsite. This study relies on the association of construction processes with
their correspondent tasks by dividing the schedule into smaller parts. Identifying this pattern
provide opportunities to develop schedule templates to be, eventually, widely applied for specific
9
construction packages. In other words, the method emphasizes the probability of automating
BIM-based schedules by the identification of relationships amongst construction scheduling data
established under specific parameters.
2.2 Schedule Classification Standards & BIM
Construction planning and scheduling requires collaborative work and coordination
among trades. In this process, BIM plays an important role since its integrative approach
facilitates the standardization and familiarity of the procedure. For this reason, the
implementation of BIM requires the standardization of processes (Migilinskas, Popov,
Juocevicius, & Ustinovichius, 2013). Similarly, it mandates the need for interoperability and
exchange of information (Honti & Erdélyi, 2018). Through the incorporation of BIM system in
the U.K., EuroBIM (2017) encouraged the adoption of international standards to generate a
common basis in the construction supply chain for exchanging information. These standards
promote legal and regulatory frameworks and serve as a guidance throughout the life-cycle of the
project. They explained cases such as the Estonian AEC industry, where in-house standards
where established to set a benchmark for the developing of BIM workflows, and foster
productivity in their operations.
In the U.S., the AEC industry also strives to develop standards and collaboration with
BIM workflows. The decision of the General Services Administration (GSA) to establish BIM as
a minimum requirement for the submission and collaboration of Public Building Information
Technology Services has set an inflection point for the acquisition of BIM within construction
operations in the country (Antwi-Afari, Li, Pärn, & Edwards, 2018). Within this scope, studies to
measure the success of BIM implementation have been released. Antwi-Afari, Li, Pärn, &
10
Edwards (2018) indicate that there are similar factors that have contributed to the expansion of
BIM, and coordination and planning of construction work lies within this list. In order to
accomplish an exemplary phasing between construction scheduling and BIM, the General
Administration Services (2009) recommends the adoption of two type of activities in
construction schedules: generic activity categories and project specific activity types. This
differentiation allows, in one hand, to have a complete idea of the flows involved in construction
activities (construction, temporal or demolition). On the other hand, it encourages the creation of
more detailed schedules throughout the incorporation of level of development according to
activity types, which includes construction and non-construction tasks. Also, it indicates that
similarities between activity names and BIM-driven objects facilitates the linking process
amongst 3D and schedule. For this reason, the creation of object-oriented schedules counts as a
possibility to enable intelligent models to automate the interface between construction planning
and scheduling and BIM (Wang, Weng, Wang, & Chen, 2014).
The implementation of standards to maximize the benefits of BIM through object-
oriented schedules has been widely discussed (Issa & Ol bina, 2015). Attempts to classify
construction activities by type of building element have been introduced by the Construction
Specification Institute (CSI, 2010) through UniFormatTM. This classification provided four levels
to categorize construction tasks plus one detailed list of designated elements, usually considered
as“Level 5”. For further reference, the first level consigns a total of eight classifiers denominated
major categories: substructure, shell, interiors, services, equipment and furnishing, special
construction and demolition, building sitework, and general. The purpose of this level is aimed to
cover a wide range of types of construction. Diverse attempts for leveraging the use CSI®
standards into engineering workflows have been released. Researchers like Chang & Tsai (2003)
11
have analyzed the use of CSI® standards for engineering management workflows. More
specifically, the bridge between UniFormatTM and BIM has been explained by Weygant (2011).
The author indicates that UniFormatTM is one of the common methods to organize construction
information. Furthermore, he highlights the advantage of arranging BIM data into tabular
UniFormatTM classifiers and recommends the adoption of methods to categorize BIM-based
elements to optimize the use of such standards. This practice is denominated BIM analytics, and
its adoption has shown incredible endeavors towards automation of BIM workflows (Kensek &
Noble, 2014). Therefore, there is a significant need to understand the existing patterns between
current practices in construction scheduling and object-driven standards towards automation of
4D BIM.
Accordingly, the scope of this paper lies on the intention to tabulate construction
scheduling data into UniFormatTM classifiers.
2.3 Construction Scheduling & 4D BIM
The process of incorporating the variable time into modeling of 3D CAD objects or 4D
CAD for visualization purposes has been studied since the early 2000’s (Issa, Flood, & O'Brien,
2005). Lately, this process evolved and new advantages from the fourth dimensional (4D) of
BIM were leveraged (Borges, Cavalcanti de Souza, Melo, & Giesta, 2018).
Golparvar-Fard, Peña-Mora, & Savarese (2011) developed the connection between point-
cloud prototypes – based on the computational analysis of imaging and geo-spatial condition–
and 4D BIM. The objective of this study was retrieving as-built conditions of construction sites
and compare them with the original as-planned baseline. As a result, 4D BIM models were able
to perform not only construction visualization, but progress monitoring. The outputs of this study
12
opened opportunities for investigation in reality capture for construction safety, quality assurance
and project controls. Likewise, Chen & Luo (2014) studied the potential of 4D BIM to perform
schedule quality control by leveraging BIM as a product, process and organization. This study
introduced color coding to distinguish different stages of quality control of BIM-based elements.
This differentiation was visualized during 4D BIM. Stepping forward, Dimitris & Golparvar-
Fard (2014) designed an interface for project monitoring and BIM. Their model was capable to
retrieve imaging information and automatically recognize BIM material patterns. This method
achieved around 97% of accuracy in imaging detection compared with 95% average standards of
groundbreaking technologies in computer vision for the construction industry. Lately, Golparvar-
Fard, Peña-Mora, & Savarese (2015) created an approach for tracking project progress
automatically. This automation was based on a systematic recognition of as-build object-driven
elements in comparison with as-planned BIM-based objects. By developing this comparison, the
authors evolved capabilities to calculate physical progress relying on probabilistic machine
learning techniques though the analysis of imaging data. Industry Foundation Classes (IFC)
played an important role in this achievement. The authors enabled the automatic recognition of
3D objects classified according to IFC-based categories. In other words, 4D BIM became an
automatic procedure for object-driven data analysis. Further research demonstrated increased
benefits of 4D BIM progress tracking throughout the adoption of unmanned aerial vehicles
(UVA) to capture as-built information (Hamledari, et al., 2017). The benefits of progress
monitoring in construction operations have been measured. Alizadehsalehi & Yitmen (2019)
demonstrated the positive impact of leveraging the uses of 4D BIM to track physical progress in
combination with reality-capture technologies. They found that the overall project delivery is
benefited in terms of duration, cost and quality due to the incorporation of BIM workflows.
13
Although this accomplishment represented an exemplary step towards fully automation of 4D
BIM, the automation of construction schedules is still left for further research development.
Remarkable research has been conducted towards automation of construction schedules
in 4D BIM. The first attempts to achieve this goal were presented by Han, Cline, & Golparvar-
Fard (2015). They incorporated construction scheduling into as-built data and BIM workflows.
The authors depicted three main challenges derived from current AEC industry practices that add
complexity to the automation process: 1) lack of enough level of details in the designed model
(as-planned); 2) lack of level of detail in WBS of construction schedules; and 3) presence of
static/dynamic visual obstructions when collecting as-built data. More recently, Hamledari,
McCabe, Davari, & Shahi (2017) defined a systematic approach to update construction tasks
duration and finish dates in 4D BIM. This prototype was capable to update progress ratios and
assign color codes to BIM-based objects based on their actual progress status. To retrofit the
process more accurately, the authors differentiated the incorporation of level of detail
(construction schedule information) from level of development. (3D objects) The foundation of
this technique was based in three modules: model preparation, model updating and schedule
updating. While model preparation and model updated represented the modification and
apprising of BIM-based objects, schedule updating represented a groundbreaking innovation to
turn the updated BIMs into updated schedule information. The validation of the prototype
showed 73% of accuracy during performance. For research purposes, this number lies into a high
level of accuracy achieved.
A comprehensive investigation regarding the status quo of 4D BIM in the AEC industry
has been conducted (Abath, De Sourza, Sampario, & Pinto, 2018). Additionally, applications
such as constructability analysis in virtual reality (VR) environments are still in evolution. Even
14
though the limitations found, studies have shown the creation of frameworks to increase team
coordination in remote mediums of a single construction project (Boton, 2018).
Accordingly, the automation of 4D BIM updating with construction schedule inputs has
been achieved, nonetheless the fully generation of construction schedules based on BIM-based
information has not been accomplished yet.
2.4 Big Data for BIM Automation
Distinctive attention has characterized the analysis of BIM data among researchers.
Predictive analysis to design intelligent models to optimize BIM workflows has been tendency in
the last few years. Indeed, the introduction of algorithms in natural language processing (NLP)
have endeavored opportunities for the development of automated models within BIM
applications. These methodologies has been utilized to predict injuries during construction phase
(Tixier, Hallowell, Rajagopalan, & Bowman, 2016), and tested results have reach high levels of
accuracy: up to 95% (Tixier, Hallowell, Rajagopalan, & & Bowman, 2016)or to support
decision-making in risk management with the use of machine learning algorithms (Zou, Jones, &
& Kiviniemi, 2017). Either way, the utilization of these approaches takes into consideration the
use of empirical data to predict results based on retrofit processes.
Multiple applications have been developed thanks to the use of reasoning-based
approaches. Goh & Ubeynarayana (2017) have compared the response of multiple machine
learning algorithms to predict narrative accident classification reports. They found that methods
such as Support Vector Machine (SVM) provide more accurate results (up to 62% accuracy) for
experimental data analyzed with text mining. Similarly, Poh, Ubeynarayana, & Goh (2018) have
analyzed safety records and number of accidents of a total of twenty-seven construction projects.
15
Their study concluded that Random Forest (RF) method provided most accurate results for the
prediction of accidents and fatalities in the jobsite. They achieved a total of 72% of accuracy in
their calculations. More recently, research focused on the analysis of text analytics for
contractual documents in construction has been conducted (Marzouk & Enaba, 2019). The study
provides an output of the frequent terms found in contractual language for the execution of
construction projects and contributes with a framework to develop analysis of unstructured data
in a BIM platform.
Specifically, the use of NLP has also played an important role in its interface with BIM.
Studies under Latent Semantic Analysis (LSA) to consolidate and analyze relevant BIM
literature dataset have been performed (Yalcinkaya & Singh, 2015), This technique facilitated
the classification and organization of data into different structures. Results show a remarkable
interest of 4D BIM to retrieve as-built conditions of construction projects. Other studies have
defined a framework for cloud-based data retrieval of BIM under NLP methods (Lin, Hu, Zhang,
& Yu, 2016). The authors suggest the utility of such a framework to develop systematic
procedures for data retrieval and, eventually, elaborate automatic reports based on the
information acquired. Under the information retrieval perspective, Zhang & El-Gohary (2016)
leveraged the retrieval of documentation by extracting design and contractual information from
BIM-based models. The intent of this study was the generation of fully-automated code
compliance systems under reliable conditions given the nature of information to be checked. This
study accomplished 87.6% of precision in anticipated non-compliance results.
Given the cases described, the use of emerged big data in the AEC operations is
becoming a more frequent practice that undertakes promising opportunities (Maaz, Bandi, &
Amirudin, 2018). Fundamental literature review to set a background of the needs in
16
constructability in the AEC industry has been developed (Kifokeris & Xenidis, 2017). Similarly,
the importance of critical factors – reliability, relevance and speed – associated with the success
in construction analytics and BIM practices have been described (Han & Golparvar-Fard, 2017).
In this scenario, Bilal et al. (2016) reflect on the way of how big data analytics is transforming
the construction industry. In fact, the author explains that researchers are using big data analytics
for several techniques such as regression, classification, clustering, NLP, and information
retrieval. Classification of data into CSI® like UniFormatTM appears as one the utilities of big
data in the AEC industry. Opportunities for developing value added services such as generative
design, clash detection and resolution, performance prediction, visual analytics, among other are
some of the tendencies where research has been invested. Special emphasis has been applied to
the prediction of different domains in the industry through computational intelligence techniques
like Artificial Neural Network (ANN) which utility can contribute to the future prediction of
automatic schedules in real-time activities such as 4D BIM and progress monitoring. In parallel,
other uses of data analytics to study the autonomy of building performance based on big city data
has been released (Scaysbrook, 2016).
Finally, the introduction of big data has shown the evolution of automated BIM models
along the time. Models for enhancing monitoring systems to track project performance have been
analyzed (Navon & Sacks, 2007). Furthermore, stochastic prototypes to foster productivity
relying on schedule animations in 4D BIM has been released (Gelisen & Griffis, 2014). To
leverage 4D BIM visualization, intelligent models designed under systematic approach to track
earned value analysis (EVA) project performance have been studied (Turkan, Bosché, Haas, &
Haas, 2013). More recently, outlines to generate automatic schedules during operation and
maintenance phase of infrastructure projects have been set and released (Chen, Chen, Cheng,
17
Gan, & Wang, 2018). These evolutions are transforming the perspective of productivity in the
construction industry, and most importantly, are creating the foundation for future development
in data analytics and BIM.
Regardless the approach where research has focused on, the use of data analytics
techniques is evolving operations in the construction industry by enabling opportunities to
automate typical workflows that affect quality, safety and productivity. In addition, the study of
BIM-based data has brought the technical basis to explore the possibilities to create automated
linkage 4D BIM between construction schedule and 3D-objects. For this reason, the study of
scheduling data represents a potential opportunity to develop future prototypes based on the
prediction of standardized tasks under object-oriented standards.
18
CHAPTER 3: CONSTRUCTION SCHEDULING
AND 4D BIM PRACTICES
A survey study has been conducted in order to have a better understanding of current
practices in construction planning & scheduling and 4D BIM in the AEC industry. This study has
been conducted in coordination with the Real-Time and Automated Monitoring and Control Lab
of the department of Civil and Environmental Engineering at the University of Illinois at Urbana-
Champaign under the supervision of Dr. Mani Golparvar-Fard. The intent of this work was to
identify challenges and key factors that would contribute to the adoption of automated 4D BIM
scheduling practices under BIM-based environments. The responses provided constituted
professional testimony as a result of involvement in construction activities. Therefore, the results
do not follow policies of any design/construction firms, but to represent genuine opinions of
dealing with planning, scheduling, progress monitoring and project controls in 4D BIM on a
daily basis.
The survey was divided into four different sections: participant background, construction
planning and scheduling, 4D BIM, and areas of improvement. The results and analysis of each of
the aforementioned sections has been developed in this chapter.
3.1 AEC Participant Background
A total of 40 experts in construction operations workflows were surveyed through
GoogleTM Forms. With the purpose of validate the responses within an AEC background, the
experts were asked to identify the type of business where they focus their operations in. Majority
of them responded to pertain to general contractors’ backgrounds (see Fig. 1). In addition, 78%
identified building as the type of industry where they mainly develop AEC operations. Other
19
responses identified heavy civil infrastructure, commercial facilities and renovation/restauration
as other relevant industry backgrounds (see Fig. 2).
Fig. 1. Business type of the AEC industry.
The main professional background of the participants is Civil Engineering (88%),
followed by a 7% of Architects and 5% of other engineering backgrounds (see Fig. 3). That
being said, the total of participants have professional background related to design and
construction of infrastructure projects. In addition, their responses are reliable since their
perspective is familiar to the existing workflows in construction practices.
3%
60%
5%
5%
10%
3%
8%
3%
3%
Design firm
General contractor
Subcontractor
Consultant
Construction management agency
Academic / research
Design-Build firm
Public agency
Technology/construction
0% 10% 20% 30% 40% 50% 60% 70%
AEC Type of Business
20
Fig. 2. AEC industry type.
Fig. 3. Main professional backgrounds of the AEC industry.
78%
18%
30%
13%
5%
15%
38%
23%
3%
10%
30%
3%
3%
3%
Buildings
Heavy industrial
Heavy civil / infrastructure
Mechanical / Electrical / Plumbing
Timber
Railroad
Commercial
Government facilities
Software
Engineering
Facilities restauration / renovation
Aviation
Educational
Subdivisions
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
AEC Type of Industry
7%
88%
5%
Participant Professional Background
Architect
Civil Engineer
Engineer
21
For more specificity in construction workflow participation, the recipients were asked to
indicate the role they developed in their daily basis in construction projects. Their responses
define Project and Construction Management as the main role of the participant’s profile in
construction workflows (see Fig. 4). This category is followed by more specific roles within
project management positions (project engineer, scheduler, project controls) and include most of
the members of the supply chain in construction.
Fig. 4. Job Titles distribution of the AEC industry.
The gross number of surveyed participant’s years of experience is between 1 to 5 years of
in the industry (around 75% of them). The remaining candidates indicated more than 5-years of
experience in the field I(see Fig. 5) .
10%
40%
28%
5%
8%
3%
3%
5%
Owner / Executive
Project / Construction Manager
Project Engineer / Scheduler / Controls
VDC Engineer
VDC Manager
Superintendent
Research
Other
0% 5% 10% 15% 20% 25% 30% 35% 40% 45%
Partcipant Job Title
22
Fig. 5. Accounted Years of Professional experience within the AEC industry.
In order to understand the level of involvement with BIM workflows and groundbreaking
technologies based on the size of business, the participants were asked to indicate the annual
revenue (AR) range of their organizations. Results evidence that majority of participants develop
roles within large companies, whose AR accounts for more than $1 billion / year (see Fig. 6).
The rest of the participants barely show an equal distribution between small and medium
business sizes.
3%
20%
18%
10%
3%
13%
8%
5% 5% 5%
3% 3% 3% 3% 3%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0%
5%
10%
15%
20%
25%
0.5 1 2 3 3.5 4 5 6 8 10 11 14 17 20 33
% o
f P
arti
cip
ants
Years of Experience
Participant Years of Experience
23
Fig. 6. Annual revenue representation of businesses of the AEC industry.
3.2 AEC Construction Planning & Scheduling Practices
The survey recipients were asked to indicate the type of convention and standards utilized
to perform construction planning and scheduling. The responses specify that 63% of the
participants count with in-house standards to perform scheduling activities. Other standards such
as MasterFormat® and UniFormatTM has relevant connotation in the elaboration of construction
schedules according to the participants (see Fig. 7).
19%
19%
25%
37%
Participant Organizations Annual Revenue
R < 10M (million)
10M < R < 100M
100M < R < 1B (billion)
R > 1B (billion)
24
Fig. 7. Type standard conventions in construction scheduling practices in the AEC
Industry
One of the significant procedures in construction scheduling is the creation of WBS.
Majority of participants (~60%) indicated that they do not count with guides to create WBS (see
Fig. 8). That being said, most practitioners in scheduling-related workflows adapt their own
standards to the creation of construction documents such as the Master Schedule.
Some practitioners with in-house standards for construction scheduling indicated that the
creation of a WBS depends on managerial decisions. Furthermore, they specified that most of in-
house standards is broken down into several attributes such as: tittle, description, position code,
account code, quantity and unit of measure.
33%
13%
63%
8%
3%
Masterformat
Uniformat
In-house standards
I don't know
Other
0% 10% 20% 30% 40% 50% 60% 70%
Construction Planning & Scheduling standard conventions
25
Fig. 8. Use of Work Breakdown Structure guide in the AEC Industry.
In addition to the creation of WBS, the experts were asked to mention the common
software interface they use to perform their daily construction scheduling activities. They
pointed out Primavera® P6 (~45%) as the main platform to create and control construction
activities (see Fig. 9).
Fig. 9. Software interface in Construction Planning and Scheduling in the AEC Industry.
35%
60%
5%
Work Breakdown Structure Guides Usage
Yes
No
N/A
45%
22%
8%
25%
Software Interface for scheduling construction
activities
Primavera P6
Microsoft Project
Microsoft Excel
Other
26
Other responses included: MS Project, MS Excel, P6 / MS Project / MS Excel combined,
Phoenix & MS Excel, BuildPro & MS Excel, Smartsheet, IHMS, ASTA Powerproject, and
Touchplan.
In addition, the participants were requested to indicate the techniques they utilize to
perform schedule quality control. 73% indicated face-to-face meetings amongst different trades
as the most conventional way to achieve quality control of construction schedules (see Fig. 10).
Early involvement in design, site visits and direct design/construction coordination count as
other relevant common practices in the industry.
Fig. 10. Schedule Quality Control techniques in the AEC Industry
In terms of multiplicity of approached performed, 78% of recipients indicated to use two
or more techniques to perform schedule quality control. Only 22% confirmed the utilization of a
single method for this activity (see Fig. 11).
18%
60%
58%
28%
60%
73%
3%
Contruction simulation
Direct design / construction coordination
Site visits
Virtual meetings with different trades
Early involvement of different trades
(design/GC/CM/subs)
Face-to-face meeting or input from different trades
(design/GC/CM/Subs)
3D models of critical spots
0% 10% 20% 30% 40% 50% 60% 70% 80%
Schedule Quality Control techniques
27
%
Fig. 11. Multiplicity of techniques to perform Schedule Quality Control in the AEC
Industry
One of the typical observations found in construction schedules is the inclusion of
abbreviation and other conventions to represent modules, location, and sequencing of
construction tasks. For instance, some tasks are represented in the next ways: a) Close shower
walls L1B3W - c1, which would mean: close shower walls, level 1, area B, west, cell1; or b)
FRP shaft D - CFE L1A2, which means Form/Rebar/Pour shaft D, system CFE, level 1, zone A2
The recipients were asked to indicate whether or not they use specific standards to include such
abbreviations in different construction activities or packages. Majority of participants (75%)
confirmed and they apply or sometimes apply such conventions. Only 25% indicated to avoid the
use of such conventions (see Fig. 12)
22%
78%
Single vs. Multi-approach Schedule Quality Control
techniques
Single approach
Multi-approach
28
Fig. 12. Implementation of Conventions / Abbreviations in Construction Planning &
Scheduling
Among the participants who confirmed the use of abbreviations, a representative 23%
indicated such conventions are established by the Superintendent and Project Manager, then are
incorporated. Other significant fraction of participants (17%) indicated other ways how these
standards are included in construction schedules such as owner requirements and batches of the
project (Fig. 13). These responses explain the complexity of the variables involved construction
planning and scheduling workflows. Therefore, the complexity of the standardization for
information retrieval, and the relevance of the classification of scheduling data.
35%
25%
40%
Use of Conventions / Abbreviations when performing
Construction Scheduling
Yes
No
Sometimes
29
Fig. 13. Implementation workflow for Conventions / Abbreviations in Construction
Planning & Scheduling
To establish an average frequency of the inclusion of abbreviation and other convention,
participants were asked to select a percentage of the frequency they have observed such
convention in construction schedules. Majority of participants indicate they see conventions in a
range of 50-80% of construction activities (see Fig. 14). Moreover, they define Mechanical,
Electrical, Plumbing and Fire Protection (MEPF) as the construction schedule package where
they see those conventions more frequently (see Fig. 15). Along with MEPF, participants
observed at least 47% of abbreviation in packages such as architecture, structures, and civil.
Other packages were pipping & equipment, specialized residential construction and interior &
exterior finishes.
17%
13%
13%
13%
23%
3%
17%
Conventions / abbreviations are widely known in the
industry.
It is used according to historical projects within the
firm.
Acoording to company's policy.
Scheduler defines convention.
Superintendent / PM defines convention
It is coordinated amongst trades during
preconstruction (design / GC / subs / etc).
Other
0% 5% 10% 15% 20% 25%
Incorporation of Construction Scheduling Conventions /
Abbreviations
30
Fig. 14. Frequency distribution of Construction Planning & Scheduling Conventions /
Abbreviations in the AEC industry
According to the recipient responses, frequently, multiple construction schedule packages
include abbreviations and other conventions. Only 46% of participants manifested they have
seen convention in single packages of construction schedules (see Fig. 16). Therefore, the
practice of including abbreviations seem to customary in different trades involved in construction
planning and scheduling workflows.
8%
3% 3% 3%
22%
5%
14%
22%
3%
19%
0%
5%
10%
15%
20%
25%
up t
o 1
0%
up t
o 2
0%
up t
o 3
0%
up t
o 4
0%
up t
o 5
0%
up t
o 6
0%
up t
o 7
0%
up t
o 8
0%
up t
o 9
0%
up t
o 1
00%
0%
20%
40%
60%
80%
100%
120%
Frequency of Contruction Scheduling Conventions
% part % cumul
31
Fig. 15. AEC areas of adoption of Construction Planning & Scheduling Conventions /
Abbreviations
Fig. 16. Multiplicity Construction Planning & Scheduling Conventions / Abbreviations in
the AEC Industry
50%
59%
68%
47%
9%
Architecture
Structures
Mechanical / Electrical / Plumbing / Fire Protection
Civil
Other
0% 10% 20% 30% 40% 50% 60% 70% 80%
Construction Scheduling Conventions / Abbreviations
frequency in AEC Industry Areas
46%
54%
Single vs. Multiple areas of adoption of construction
scheduling Conventions / Abbreviations
Single
Two or more
32
Moving towards the analysis of construction planning and scheduling practices during
construction phase, the recipients were interrogated regarding the frequency of using the Master
Schedule or construction schedule during preconstruction in comparison with construction phase.
In both scenarios, majority of responders indicated they always use the construction schedule
(see Fig. 17). Within this category, the intensity of using the construction schedule is higher
during execution phase in comparison with preconstruction.
Fig. 17. Master schedule / Construction schedule usage in the AEC Industry
40%
30%
20%
3%
8%
60%
33%
8%
0% 0%
Alw
ays
Usu
ally
Som
etim
es
Rar
ely
Nev
er
0%
10%
20%
30%
40%
50%
60%
70%
Construction Schedule Usage: Preconstruction vs. Construction
Preconstruction phase Construction phase
33
Similarly, the recipients were asked to indicate the frequency for updating the Master
Schedule. The common practice in most responders lies on a monthly updating (~53%). Due the
complexity of this tasks and contractual agreements, majority of professional involved in
construction activities tend to update the master schedule once a month (see Fig. 18). Other
responders manifested a bi-weekly or weekly period (~34%). A minimum of participants
indicated an updating frequency on a less than a weekly basis (~3%) or more a longer scale than
a monthly basis (~10%).
Fig. 18. Master schedule / Construction schedule update practices in the AEC Industry
3%16%
18%
53%
5%
5%
Construction master schedule update frequency
Twice a week
Weekly
Bi-weekly
Monthly
Never
Other
34
3.3 AEC & 4D BIM Uses
To understand the needs and practices in 4D BIM, recipients were asked to indicate the
methods they utilize to perform progress tracking during the execution of construction projects.
Most participants manifested to update construction schedule baseline (68%), use look-ahead
schedules (63%), and tracking key milestones only (55%) to perform project progress (see Fig.
19). Regarding the multiplicity of approaches utilized for tracking progress, majority of
participants reveled the use of two or more techniques to control physical progress (see Fig. 20).
Fig. 19. Construction Project Progress Methods in the AEC Industry
30%
20%
3%
55%
45%
63%
20%
25%
68%
30%
15%
3%
Earned Value Analysis (EVA)
S Curve
Reality capture & cloud points
Tracking key milestones only
FIeld input quantification
Look ahead schedules
Location-based schedules
Excel workbook annotations
Updating construction/baseline schedule
Color-coding in drawings by subs/tasks
Handwriting annotations
PPC Reports - Percent Planned Complete
0% 10% 20% 30% 40% 50% 60% 70% 80%
Methods for tracking construction project progress
35
Fig. 20. Construction Project Progress Methods usage in the AEC Industry
Also, surveyed recipients indicated their level of familiarity with 4D BIM (see Fig. 21).
Fig. 21. Levels of Familiarity of 4D BIM in the AEC Industry
15%
85%
Methods Multiplicity for tracking Construction Project Progress
Single
Two or more methods
12.5%
7.5% 7.5% 7.5%
2.5%
12.5% 12.5%
7.5%
15.0%
5.0%
10.0%
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
14.0%
16.0%
up t
o 0
%
up t
o 1
0%
up t
o 2
0%
up t
o 3
0%
up t
o 4
0%
up t
o 5
0%
up t
o 6
0%
up t
o 7
0%
up t
o 8
0%
up t
o 9
0%
up t
o 1
00%
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
120.0%
4D BIM Levels of Familiarity
% part % cumul
36
Most responders indicated to be familiar with 4D BIM workflows. Indeed, around 85%
indicated to be up to 80% with this methodology. Only 12.5% of the recipients indicated not to
be familiar at all with 4D BIM (see Fig. 22).
Fig. 22. 4D BIM Familiarity in the AEC Industry
Correspondingly, participants have manifested the utility of 4D BIM for one or multiple
purposes (see Fig. 23).
Fig. 23. 4D BIM Usage in the AEC Industry
12.50%
87.50%
Non-familiar vs. familiar with 4D BIM
not at all familiar
familiar
6%
94%
Use of 4D BIM
No uses
One or more uses
37
Among the main 4D BIM uses, recipients responded that construction visualization
(63%) is the most useful benefit they retrieve from 4D BIM (see Fig. 24). Other relevant answers
highlight the use of this workflow for progress monitoring (45%), trades coordination (40%),
constructability analysis (38%) and owner communication (33%).
Fig. 24. 4D BIM Type of Use in the AEC Industry
Regarding the utility of 4D BIM during preconstruction and construction phases, most
recipients manifested they find 4D BIM somewhat useful in both scenarios. In general,
participants consider most useful 4D BIM during preconstruction than construction phase (see
Fig. 25)
45%
63%
38%
18%
33%
40%
13%
8%
18%
20%
33%
23%
5%
8%
Progress monitoring
Construction visualization
Constructability analysis
Construction safety
Schedule quality control
Coordination among trades
Field validation
AR / VR
Project controls
Digital management
Owner communication
I don't obtain any uses
Sales / marketing
Other
0% 10% 20% 30% 40% 50% 60% 70%
4D BIM Type of Use
38
Fig. 25. Perception 4D BIM utility during Pre-construction and Construction phases in the
AEC Industry
Regarding the challenges of performing 4D BIM, participants selected the omission of
various task procedures as the most challenging process to face within 4D BIM. Furthermore,
they indicated linkage between construction activities and 3D-objects represents highest
moderate challenge. Finally, responders highlighted the inconsistency of task names as the least
challenging part when performing workflows in 4D BIM (see Fig. 26).
18%
25%
35%
15%
8%
10%
25%
43%
10%
13%
Extr
emel
y
use
ful
Ver
y u
sefu
l
Som
ewh
at
use
ful
No
t so
use
ful
No
t at
all
use
ful
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
4D BIM Utility perception: Preconstruction vs. Construction
Preconstruction phase Construction phase
39
Fig. 26. Type and Level of 4D BIM Challenges in the AEC Industry
In addition, participants had the opportunity to define other challenges not addressed in
Fig. 26. As a summary of responses, Table 1. shows other less frequent challenges during 4D
BIM performance.
3%
0%
0%
0%
5%
5%
5%
8%
13%
33%
23%
18%
30%
20%
10%
23%
20%
23%
15%
13%
23%
25%
10%
18%
13%
15%
10%
Linking tasks with 3D Objects
Some 3D objects do not represent tasks
Some tasks do not represent 3D objects
Omission of various procedure tasks
Sequence is inappropriate
BIM-objects and tasks do not match
Insufficient level of granularity of BIM-based objects
System interoperability
Tasks names are inconsistent
0% 5% 10% 15% 20% 25% 30% 35%
4D BIM Challengues
Very challenging Moderate challenging Not at all challenging
40
Table 1. Summary of less frequent 4D BIM challenges
Item Challenge description
1 Flexibility for project duration, If it is a very long and large project, it’s hard to
foresee everything, so it might not be very efficient to put an effort in this
project in advance. But 4D BIM would be useless over the project if it doesn’t
meet any required quality.
2 Applicability to Bid-Build Public work, there is substantial effort required to
bring the project into 4D BIM. Design-Build and Engineering / Procurement /
Construction (EPC) are more integrated at the design phase to reduce this
barrier to entry.
3 Lack of detail and LOD, it needs an extreme level of precision in both BIM and
schedule for optimal utility (maybe that's what is meant by granularity)
4 Sequence arrangements, changing conditions in sequencing, manpower and
schedule make integrating the model extremely hard. For mega-jobs, in my
experience the model is only a visualization or measuring tool. Very hard to
have updated models of large scale that have the confidence of the whole staff.
Models frequently do not even have materials tied to the BIM due to lack of
transfer from design phase. 4D is much more useful to have material
information than schedule
5 Trades training, educating trades that are not familiar with 4D coordination
6 Trades applicability, Does all subcontractors use 4D?
7 Scheduling-friendly platform, Flexibility in changing WBS as job progresses to
system based
3.4 AEC Construction Scheduling & 4D BIM Improvement
Regarding the areas of improvement, the surveyed AEC experts indicated construction
scheduling requires a lot of improvements for trade coordination. 58% of the participants
selected this area as the most relevant area of improvement for scheduling workflows (Fig. 27).
In addition, they voted software interoperability as another relevant area of improvement for this
procedure.
41
Fig. 27. Areas of Improvement of Construction Scheduling in the AEC Industry
Meanwhile, responders considered 3D / scheduling coordination as the main area of
improvement within 4D BIM workflows. Additionally, special significance was given to areas of
improvement such as task linkage procedure, functionality, and accessibility (see Fig. 28). Other
responses referred to improvements within the binding relation of 4D BIM Technology
Information (TI) sources, and bandwidth accessibility.
45%
25%
35%
35%
33%
28%
58%
3%
Software interoperability
Sequencing
BIM-based formulation
Accessibility
Functionality
Portability
Trade coordination
Other
0% 10% 20% 30% 40% 50% 60% 70%
Construction Scheduling: Areas of Improvement
42
Fig. 28. Areas of Improvement of 4D BIM in the AEC Industry
Consequently, participants were asked to provide their opinions regarding their vision of
construction scheduling and 4D BIM for future developments. They manifested positive inputs
regarding the current utility of 4D BIM. Most importantly, they shared their perspectives
regarding a widespread and more functional platform across construction trades (see Table 2.)
33%
20%
38%
15%
30%
18%
28%
30%
10%
10%
Tasks linkage procedure
Interface with reality capture
3D / scheduling coordination
Visualization
Accessibility
Interoperability
Complexity
Functionality
Other
N/A
0% 5% 10% 15% 20% 25% 30% 35% 40%
4D BIM: Areas of Improvement
43
Table 2. Summary of vision of development in construction scheduling and 4D BIM
Item Challenge description
1 Functionality, helpful during preconstruction, hard to update during
construction. Useful to a large extent, reaches limits due to the need of
extremely accurate input.
2 Accessibility and shareability, easy to access, to update and to share. 4D is
extremely useful if all trades and subcontractors know how to do it. If it is only
used by the BIM Manager, can be a waste of time because the rest of the team
doesn't see the true value it adds.
3 Automated scheduling, BIM can develop an ideal schedule. In addition,
software packages should be able to create a better connection between the
schedule and model. Sequencing can be optimized.
4 Operability, if software is easy to use, implement, and share with other
members of the project team, it would be more feasible to use
5 Standardized, industry needs a standard to measure the progress of
construction. Otherwise it is a very subjective issue
6 Reliability, more reliable and largely compromised in refurbishment of existing
buildings. Additionally, the more it is proven the benefits of driving a project
through progress tracking and scheduling, the more company internal
standardization of schedules will occur across the industry.
7 Friendly interface, a 55-year-old superintendent should be able to put together
an excel 3-week schedule and pop it into the model. Furthermore, it should be
done easily. People in construction is not so detail-oriented
8 Granularity, getting granular with activity metrics and driving work through
KPI analysis
44
CHAPTER 4: CONSTRUCTION SCHEDULING DATA ANALYSIS
The status quo of construction planning & scheduling and 4D BIM has been stated. Lack
of master schedule / construction schedule updating is still one of the difficulties to overcome in
construction operation workflows. Similarly, the current perspectives of 4D BIM still rely on
construction visibility as the main use to leverage from its application. In other words, AEC
members still perceive a lack of reliability in the process of fully implementation of 4D BIM. As
indicated, this due to the complexity of its process in comparison with the benefits obtained.
Understanding this complexity will facilitate the dissemination of further research in the field.
Thus, this thesis intends to step out on understanding the complexity of construction scheduling
information.
In lieu to provide a comprehensive understanding towards the automation of 4D BIM,
this chapter provides a method to classify and standardize construction activities into BIM-based
construction scheduling data. Achieving such standardization required the use of object-based
classifiers like UniFormatTM. Thousands of annotations to classify construction scheduling data
were required. The methodology applied to achieve such standardization is described in the
following sections.
45
4.1 Construction Scheduling Data
In collaboration with the Real-Time and Automated Monitoring and Control (RAAMAC)
laboratory of the department of Civil and Environmental Engineering at the University of Illinois
at Urbana-Champaign we retrieve construction schedule information from ten different real
estate projects. These projects focused their operations in building, commercial and sport
facilities. The information was retrieved in “.csv” format. The source of schedule datasets has
been named as listed below (see Table 3.):
Table 3. Source of schedule datasets
Item Project
1 Clark
2 MSTR
3 Centene
4 DWP Master
5 Hill Farm
6 Mortenson
7 Saratoga
8 SandConcrete
9 WSHU
10 Stadium
The schedule information was structured into seven different column indexes. Each index
represented a category of information. The categories and their organization are listed below:
0 - Activity ID, contains the code of activity systematically generated by the scheduling software
utilized to formulate the construction schedule.
1 - Activity status, contains three different subcategories: Not started, In progress and Complete.
46
2 - WBS code, this category varies depending in the conventions utilize to code WBS. As
discussed in chapter 3, this could be established according to the existing or in-house standards.
3 - WBS name, again this varies depending on the standards used in the project.
4 - Activity name, as discussed in chapter 3, it is mainly assigned by the project manager or
superintendent. Practitioners do not use guides to name the activity tasks.
5 - Start, represents the as-planned o as-built start date of the activity tasks. This depends on
whether the construction schedule has been updated or not.
6 – Finish, established according to the as-planned or updated as-built finish date of the
construction activity.
The information contained in each of these categories represented by activity task is
considered construction scheduling data or scheduling data. In other words, each construction
activity is composed by a total of 7 datapoints of construction scheduling data. The scope of this
study is the analysis of the column index Activity Name.
The timeline for the analysis of the date has been approximately 6-months (June 2018 to
December 2018). Due to the large amount of data, it was necessary the creation of batches of
datasets. A total of two batches was created to organize and annotate classified data
progressively (see Table 5.) The batch No 1contained information retrieved from a total of 9
construction projects. This batch included a total of 15,066 construction activities (105,462
datapoints). Conversely, the data batch No 2 represented a single construction project containing
a total of 10,800 activity tasks (75,600 datapoints).
A sample of the construction scheduling in shown in Table 4.
47
Table 4. Sample of Typical of Construction Scheduling Data Retrieved
Activity
ID
Activity
Status WBS Code (*) WBS Name Activity Name (*) Start (*) Finish
MS1010 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
Design Assist Subcontract
Awards 30-Sep-14 05-Mar-15
MS1020 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting Schematic Design 03-Nov-14 05-Mar-15
MS2000 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting SD Package to Kaiser 05-Mar-15
MS2010 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting Design Development to 50% DD 06-Mar-15 15-May-15
MS2020 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
Design Development to 100%
DD 18-May-15 26-Jun-15
MS2080 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
Construction Document 1st
Backcheck 10-Aug-15 26-Aug-15
MS2100 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
C&S Package + Utilities 2nd
Backcheck 18-Nov-15 26-Nov-15
MS2110 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
C&S Package + Utilities 2nd
Backcheck
Corrections/Resubmittal 19-Feb-16 19-Feb-16
MS2130 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting Pull Building Permit 21-Apr-16
MS2030 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
Design Development City
Submittal 29-Jun-15 09-Jul-15
MS2040 Completed
150885-
MSTR.1.15.1
Building Design &
Permitting
Design Development City
Submittal – Revised Conference
Center 10-Jul-15 23-Jul-15
(…)
A total of 25886 construction scheduling data were collected, retrieved and analyzed.
48
Table 5. Construction Scheduling Data batches
Item Data
Batch
No
Construction
Projects
No Activity
Tasks
1 1 9 15066
2 2 1 10800
Total activity tasks 25866
Preliminary, the scheduling data was distributed according to the amount of activity tasks
contained. The result of this distribution is described in Table 6. As seen, the organization of the
data shows ~58% of data distributed in batch No 1, and ~42% in batch No 2. Since all
construction projects have different scopes, it is relevant to keep the heterogeneity of the datasets
in order to avoid skewed results regarding the source of data. Although the annotations were
performed according to data batches, the analysis was conducted to the overall data classified.
Table 6. Distribution of Construction Scheduling by Source
Number Data
Batch
Construction
Schedule
No
Data Act.
Data
%
1 1 Clark 686 2.7%
2 1 MSTR 1963 7.6%
3 1 Centene 1587 6.1%
4 1 DWP Master 3993 15.4%
5 1 Hill Farm 846 3.3%
6 1 Mortenson 782 3.0%
7 1 Saratoga 83 0.3%
8 1 SandConcrete 201 0.8%
9 1 WSHU 4925 19.0%
10 2 Stadium 10800 41.8% Total 25866
For more detail, distribution of data by course can be observed in Fig. 29.
49
Fig. 29. Construction Scheduling Data distributed by source
50
4.2 UniFormatTM Data Classification
The standards utilized in this analysis correspond to CSI® UniFormatTM. BIM-based
elements are represented through Industry Foundation Classes (IFC) and these have relationship
with the object-driven elements provided by UniFormatTM standards. For the purpose of this
study, construction scheduling data will be classified according to such standards.
The classification process will be broken into five different UniFormatTM levels. Each
level increases the level of detail according to the specificity of the construction schedule. A total
of seven categories have been established in the first level as follows:
L1, 1 Building sitework, includes all site-related and civil work construction activities,
L1, 2 Equipment & Furnishing, contemplates all tasks for temporal equipment and furnishing to
be incorporated in the jobsite,
L1, 3 Interior, includes all construction tasks to perform interior work. Finishes are included
within this category,
L1, 4 Services, entails the classification of MEPF-related tasks and installation of permanent
equipment,
L1, 5 Shell, includes structural, roofing, cladding and envelop work mainly
L1, 6 Special construction and demolition, entails the classification of specialty construction and
all-related demolition work, and
L1, 7 Substructures, contemplates tasks aimed to the construction of foundation elements.
A total of 458 UniFormatTM standards has been annotated. The detail of the classifiers is
presented below (see Table 7.):
51
Table 7. UniFormatTM Element Class List
Item UniFormatTM Element Class
1 Building Sitework
1.1 Other Site Construction
1.1.1 Service and Pedestrian Tunnels
1.1.1.1 Pedestrian Tunnels
1.2 Site Electrical Utilities
1.2.1 Electrical Distribution
1.2.1.1 Overhead Power Distribution
1.2.1.2 Substations
1.2.1.3 Underground Power Distribution
1.2.2 Other Site Electrical Utilities
1.2.2.1 Site Emergency Power Generation
1.2.3 Site Communication and Security
1.2.4 Site Lighting
1.2.4.1 Site Fixtures & Transformers
1.2.4.2 Site Lighting Poles
1.2.4.3 Wiring Conduits & Ductbanks
1.3 Site Improvement
1.3.1 Landscaping
1.3.1.1 Fine Grading & Soil Preparation
1.3.1.2 Irrigation Systems
1.3.1.3 Other Landscape Features
1.3.1.4 Planters
1.3.1.5 Planting
1.3.1.6 Seeding & Sodding
1.3.2 Parking Lots
1.3.2.1 Curbs Gutters & Drains
1.3.2.2 Guardrails & Barriers
1.3.2.3 Painted Lines & Markings
1.3.2.4 Parking Lot Bases & Sub-Bases
1.3.2.5 Parking Lot Paving & Surfacing
1.3.2.6 Signage
1.3.3 Pedestrian Paving
1.3.3.1 Brick & Tile Plazas
1.3.3.2 Exterior Steps & Ramps
1.3.3.3 Pedestrian Bridges
1.3.3.4 Sidewalks
1.3.4 Roadways
1.3.4.1 Curbs Gutters & Drains
1.3.4.2 Curbs, Gutters & Drains
1.3.4.3 Guardrails & Barriers
1.3.4.4 Painted Lines & Markings
52
Table 7. (cont.)
Item UniFormatTM Element Class
1.3.4.5 Roadway Bases & Sub-Bases
1.3.4.6 Roadway Paving & Surfacing
1.3.4.7 Signage
1.3.5 Site Development
1.3.5.1 Fences & Gates
1.3.5.2 Fountains Pools & Watercourses
1.3.5.3 Fountains, Pools & Watercourses
1.3.5.4 Other Site Development
1.3.5.5 Playing Fields
1.3.5.6 Retaining Walls
1.3.5.7 Signage
1.3.5.8 Site Furnishings
1.3.5.9 Terracing & Perimeter Walls
1.3.6 Site Mechanical Utilities
1.3.6.1 Cooling Distribution
1.3.6.1.1 Chilled Water Piping
1.3.6.1.2 Cooling Towers on Site
1.3.6.1.3 Wells for Cooling/Heating
1.3.6.2 Fuel Distribution
1.3.6.2.1 Fuel Piping
1.3.6.2.2 Fuel Storage Tanks
1.3.6.3 Heating Distribution
1.3.6.3.1 Pumping Stations
1.3.6.4 Other Site Mechanical Utilities
1.3.6.5 Sanitary Sewer
1.3.6.5.1 Sewage Piping
1.3.6.6 Storm Sewer
1.3.6.6.1 Ditches & Culverts
1.3.6.6.2 Headwalls & Catch Basins
1.3.6.6.3 Retention Ponds
1.3.6.6.4 Storm Sewer Piping
1.3.6.7 Water Supply
1.3.6.7.1 Fire Protection Distribution & Storage
1.3.7 Site Preparation
1.3.7.1 Hazardous Waste Remediation
1.3.7.1.1 Other Hazardous Waste Remediation
1.3.7.1.2 Removal of Contaminated Soil
1.3.7.1.3 Soil Restoration & Treatment
1.3.7.2 Site Clearing
1.3.7.3 Site Demolition and Relocations
1.3.7.3.1 Building Demolition
1.3.7.3.2 Demolition of Site Components
1.3.7.3.3 Relocation of Buildings
1.3.7.3.4 Utilities Relocation
53
Table 7. (cont.)
Item UniFormatTM Element Class
1.3.7.4 Site Earthwork
1.3.7.4.1 Borrow Fill
1.3.7.4.2 Site Grading Excavation & Disposal
1.3.7.4.3 Site Shoring
1.3.7.4.4 Soil Stabilization & Treatment
1.3.7.4.5 Utilities Trenching
2 Equipment & Furnishings
2.1 Equipment
2.1.1 Commercial Equipment
2.1.1.1 Office Equipment
2.1.1.2 Security & Vault Equipment
2.1.1.2.1 Security Equipment
2.1.2 Institutional Equipment
2.1.2.1 Audio-visual Equipment
2.1.2.2 Medical Equipment
2.1.2.2.1 X-ray Equipment
2.1.2.3 Other Institutional Equipment
2.1.2.4 Theater & Stage Equipment
2.1.3 Other Equipment
2.1.3.1 Food Service Equipment
2.1.3.1.1 Food Service - Appliances & Equipment
2.1.3.1.2 Food Service - Cabinets & Countertops
2.1.3.2 Maintenance Equipment
2.1.3.3 Other Equipment
2.1.3.4 Solid Waste Handling Equipment
2.1.3.5 Window Washing Equipment
2.1.4 Vehicular Equipment
2.1.4.1 Loading Dock Equipment
2.1.4.1.1 loading dock equipment
2.1.4.2 Parking Control Equipment
2.1.5 Wall Finishes
2.1.5.1 Wall Finishes
2.1.5.1.1 Wall Finishes - Paint
2.2 Furnishings
2.2.1 Fixed Furnishings
2.2.1.1 Fixed Casework
2.2.1.2 Window Treatments
2.2.1.2.1 Window Treatments - Blinds
2.2.2 Moveable Furnishings
2.2.2.1 Furniture & Accessories
2.2.2.2 Movable Multiple Seating
3 Interiors
3.1 Interior Construction
54
Table 7. (cont.)
Item UniFormatTM Element Class
3.1.1 Fittings
3.1.1.1 Bath & Toilet Accessories
3.1.1.1.1 Bath & Toilet Accessories - Commercial
3.1.1.2 Fabricated Cabinets & Counters
3.1.1.2.1 Cabinets
3.1.1.3 Fabricated Compartments & Cubicles
3.1.1.3.1 Toilet Partitions
3.1.1.4 Identifying/Visual Aid Specialties
3.1.1.4.1 Chalkboards & Whiteboards
3.1.1.4.2 Signs
3.1.1.5 Internal Traffic Protection Aids
3.1.1.5.1 Turnstiles
3.1.1.6 Storage Specialties
3.1.1.6.1 Lockers
3.1.2 Interior Doors
3.1.2.1 Interior Door Frames
3.1.2.1.1 Interior Door Frames - Metal
3.1.2.1.2 Interior Door Frames - Wood
3.1.2.2 Interior Door Hardware
3.1.2.2.1 Door Hardware
3.1.2.3 Interior Door Wall Opening Elements
3.1.2.4 Interior Doors
3.1.2.4.1 Interior Doors - Wood
3.1.2.5 Interior Doors with Frames
3.1.3 Partitions
3.1.3.1 Fixed Partitions
3.1.3.1.1 Ext. Wall - CMU
3.1.3.1.2 Partition Components - Drywall
3.1.3.1.3 Partition Components - Metal Framing
3.1.3.1.4 Partition Components - Wood Framing
3.1.3.1.5 Partitions - CMU
3.1.3.1.6 Partitions - Drywall w/ Metal Stud
3.1.3.1.7 Partitions - Drywall w/ Wood Stud
3.1.3.1.8 Partitions - Glass Block
3.1.3.1.9 Partitions - Stone Veneer w/ Stud
3.1.3.1.10 Partitions - Tile
3.1.3.2 Interior Windows & Storefronts
3.1.3.2.1 Interior Glazed Openings
3.1.3.3 Retractable Partitions
3.1.3.3.1 Partitions - Folding
3.2 Interior Finishes
3.2.1 Ceiling Finishes
3.2.1.1 Applied Ceiling Finishes
3.2.1.1.1 Ceiling Finishes - Coatings
55
Table 7. (cont.)
Item UniFormatTM Element Class
3.2.1.1.2 Ceiling Finishes - Coverings
3.2.1.1.3 Ceiling Finishes - Paint
3.2.1.1.4 Ceiling Finishes - Paneling
3.2.1.1.5 Ceiling Finishes - Tile
3.2.1.2 Drywall & Plaster Ceiling Components
3.2.1.2.1 Ceiling Components - Drywall
3.2.1.3 Other Ceiling Finishes
3.2.1.4 Suspended Ceilings
3.2.1.4.1 Suspended Ceilings - Acoustical
3.2.1.4.2 Suspended Ceilings - Gypsum Board
3.2.2 Floor Finishes
3.2.2.1 Access Pedestal Flooring
3.2.2.2 Bases Curbs & Trim
3.2.2.2.1 Base - Vinyl & Rubber
3.2.2.3 Bases, Curbs & Trim
3.2.2.4 Floor Toppings & Coatings
3.2.2.5 Flooring
3.2.2.5.1 Flooring - Other
3.2.2.5.2 Flooring - Terrazzo
3.2.2.5.3 Flooring - Tile
3.2.2.5.4 Flooring - Wood
3.2.2.6 Hardeners & Sealers
3.2.2.7 Traffic Membranes
3.2.3 Wall Finishes
3.2.3.1 Column Finishes
3.2.3.2 Wall Finishes
3.2.3.2.1 Wall Finishes - Coverings
3.2.3.2.2 Wall Finishes - Paint
3.2.3.2.3 Wall Finishes - Paneling
3.2.3.2.4 Wall Finishes - Tile
3.3 Stairs
3.3.1 Stair Construction
3.3.1.1 Regular Stairs
3.3.1.1.1 Stairs - CIP
3.3.1.1.2 Stairs - Precast
3.3.1.1.3 Stairs - Steel
3.3.1.1.4 stairs - wood
3.3.1.2 Stair Handrails/Balustrades
3.3.2 Stair Finishes
3.3.2.1 Stair Handrail & Balustrade Finishes
4 Services
4.1 Conveying
4.1.1 Elevators and Lifts
4.1.1.1 Freight Elevators
56
Table 7. (cont.)
Item UniFormatTM Element Class
4.1.1.1.1 Elevators - Freight
4.1.1.2 Passenger Elevators
4.1.1.2.1 Elevators - Hydraulic
4.1.2 Escalators and Moving Walks
4.1.2.1 Moving Walks
4.1.2.1.1 Moving Walks
4.1.3 Other Conveying Systems
4.1.3.1 Hoists & Cranes
4.2 Electrical
4.2.1 Communications and Security
4.2.1.1 Data Networking
4.2.1.2 Fire Alarm Systems
4.2.4.3 Intercommunication & Paging Systems
4.2.4.4 Security & Detection Systems
4.2.4.5 Telephone Systems
4.2.2 Electrical Service/Distribution
4.2.2.1 High Tension Service & Distribution
4.2.2.2 Low Tension Service & Distribution
4.2.3 Lighting and Branch Wiring
4.2.3.1 Branch Wiring & Devices
4.2.3.1.1 Receptacles - Floor
4.2.3.1.2 Receptacles - Wall
4.2.3.2 Lighting Equipment
4.2.4 Other Electrical Systems
4.2.4.1 Floor Raceway Systems
4.2.4.2 General Construction Items (Elect.)
4.2.4.3 Grounding Systems
4.2.4.4 Misc. Other Electrical Systems
4.3 Fire Protection
4.3.1 Fire Protection Specialties
4.3.1.1 Fire Extinguisher Cabinets
4.3.1.2 Other Fire Protection Specialties
4.3.2 Other Fire Protection Systems
4.3.2.1 Clean Agent System
4.3.2.2 Hood & Duct Fire Protection
4.3.2.3 Misc. Other Fire Protection Systems
4.3.3 Sprinklers
4.3.3.1 Sprinkler Water Supply
4.3.3.2 Wet Sprinkler Systems
4.3.4 Standpipes
4.3.4.1 Pumping Equipment
4.4 HVAC
4.4.1 Controls & Instrumentation
4.4.1.1 Building Automation Systems
57
Table 7. (cont.)
Item UniFormatTM Element Class
4.4.1.2 Energy Monitoring & Control
4.4.1.3 Exhaust & Ventilating Systems
4.4.1.4 Heating Generating Systems
4.4.1.5 Heating/Cooling Air Handling Units
4.4.2 Cooling Generating Systems
4.4.2.1 Direct Expansion Systems
4.4.2.2 Other Cooling System Components
4.4.3 Distribution Systems
4.4.3.1 Exhaust Ventilation Systems
4.4.4 Energy Supply
4.4.4.1 Hot Water Supply System
4.4.5 Heat Generating Systems
4.4.5.1 Boilers
4.4.5.2 Insulation
4.4.6 Other HVAC Systems/Equip
4.4.6.1 General Construction Items (HVAC)
4.4.6.2 Misc. Other HVAC Systems & Equipment
4.4.7 Systems Testing & Balancing
4.4.7.1 Air System Testing & Balancing
4.4.7.2 HVAC Commissioning
4.4.7.3 Other System Testing & Balancing
4.4.7.4 Piping System Testing & Balancing
4.4.8 Terminal & Package Units
4.5 Plumbing
4.5.1 Domestic Water Distribution
4.5.1.1 Cold Water Service
4.5.1.2 Hot Water Service
4.5.2 Other Plumbing Systems
4.5.2.1 Gas Distribution
4.5.2.2 Misc. Other Plumbing Systems
4.5.2.3 Piping & Fittings
4.5.3 Plumbing Fixtures
4.5.3.1 Lavatories
4.5.3.1.1 Lavatories - Single
4.5.3.2 Showers
4.5.3.2.1 Showers
4.5.3.3 Sinks
4.5.3.4 Water Closets
4.5.3.4.1 Water Closets - Single
4.5.4 Rain Water Drainage
4.5.4.1 Pipe Insulation
4.5.4.2 Roof Drains
4.5.5 Sanitary Waste
4.5.5.1 Floor Drains
58
Table 7. (cont.)
Item UniFormatTM Element Class
4.5.5.2 Pipe Insulation
4.5.5.3 Waste Piping
5 Shell
5.1 Exterior Enclosure
5.1.1 Exterior Doors
5.1.1.1 Door Wall Opening Elements
5.1.1.2 Glazed Doors & Entrances
5.1.1.2.1 Exterior Glazed Doors - Aluminum
5.1.1.3 Other Exterior Doors
5.1.1.4 Overhead Doors & Roll-up Grilles
5.1.1.4.1 Overhead Doors
5.1.1.5 Revolving Doors
5.1.2 Exterior Walls
5.1.2.1 Balcony Walls & Handrails
5.1.2.2 Exterior Louvers Screens & Fencing
5.1.2.3 Exterior Louvers, Screens & Fencing
5.1.2.4 Exterior Soffits
5.1.2.5 Exterior Wall Construction
5.1.2.5.1 Ext. Wall - CIP
5.1.2.5.2 Ext. Wall - CMU
5.1.2.5.3 Ext. Wall - Metal Siding Panels
5.1.2.5.4 Ext. Wall - Precast
5.1.2.5.5 Ext. Wall - Stone Veneer w/ Stud
5.1.2.5.6 Ext. Wall - Wood Stud w/ Stucco
5.1.2.6 Parapets
5.1.2.7 Standard Slab on Grade
5.1.3 Exterior Windows
5.1.3.1 Curtain Walls
5.1.3.1.1 Curtain Walls - Framing
5.1.3.1.2 Curtain Walls - Panels
5.1.3.2 Exterior Windows
5.1.3.2.1 Curtain Walls
5.1.3.3 Storefronts
5.1.3.4 Windows
5.1.3.4.1 Windows - Aluminum
5.2 Roofing
5.2.1 Roof Coverings
5.2.1.1 Gutters & Downspouts
5.2.1.2 Roof Eaves & Soffits
5.2.1.3 Roof Finishes
5.2.1.3.1 Roofing - Built-up
5.2.1.3.2 roofing - formed metal
5.2.1.3.3 Roofing - Preformed Metal
5.2.1.3.4 Roofing - Shingle & Tile
59
Table 7. (cont.)
Item UniFormatTM Element Class
5.2.1.3.5 Roofing - Single Ply Membrane
5.2.1.4 Roof Flashing & Trim
5.2.1.4.1 Base Flashing
5.2.1.4.2 Roof Flashing
5.2.1.5 Roof Insulation & Fill
5.2.1.5.1 Roof Insulation - Rigid
5.2.1.6 Traffic Toppings & Paving Membranes
5.3 Superstructure
5.3.1 Floor Construction
5.3.1.1 Fireproofing - Floor Construction
5.3.1.1.1 Steel Beam Fireproofing
5.3.1.2 Floor Raceway Systems
5.3.1.3 Upper Floor Framing - Horizontal Elements
5.3.1.3.1 Beams - CIP
5.3.1.3.2 Beams - Precast
5.3.1.3.3 Beams - Steel
5.3.1.3.4 Deck - Metal
5.3.1.3.5 Planks - Precast
5.3.1.3.6 upper floor framing - horizontal elements
5.3.1.4 Upper Floor Framing - Systems
5.3.1.4.1 CIP Beam & Slab - Two Way
5.3.1.4.2 CIP Slabs - Flat Plate
5.3.1.4.3 Composite Beam & Slab
5.3.1.4.4 Composite Beam Deck & Slab
5.3.1.4.5 Composite Beam, Deck & Slab
5.3.1.4.6 Steel Beams w/ Steel Joists
5.3.1.4.7 Steel Girders w/ Steel Beams
5.3.1.4.8 W Shape Composite Deck & Slab
5.3.1.5 Upper Floor Framing - Vertical Elements
5.3.1.5.1 Bearing Walls - Block
5.3.1.5.2 Bearing Walls - CIP
5.3.1.5.3 Columns - CIP
5.3.1.5.4 Columns - Precast
5.3.1.5.5 Columns - Steel
5.3.2 Roof Construction
5.3.2.1 Canopies
5.3.2.2 Fireproofing - Roof Construction
5.3.2.2.1 Steel Beam Fireproofing
5.3.2.3 Flat Roof Framing - Horizontal Elements
5.3.2.3.1 Beams - Steel
5.3.2.3.2 Deck - Metal
5.3.2.3.3 Joists - Steel
5.3.2.4 Flat Roof Framing - Systems
5.3.2.4.1 CIP Slabs - Flat Plate
60
Table 7. (cont.)
Item UniFormatTM Element Class
5.3.2.4.2 Composite Beam, Deck & Slab
5.3.2.5 Flat Roof Framing - Vertical Elements
5.3.2.5.1 Bearing Walls - Block
6 Special Construction & Demolition
6.1 Selective Building Demolition
6.1.1 Building Elements Demolition
6.1.1.1 Building Exterior Demolition
6.1.1.2 Building Interior Demolition
6.2 Special Construction
6.2.1 Special Construction Systems
6.2.1.1 Special Security Systems
6.2.2 Special Controls & Instrumentation
6.2.2.1 Building Automation Systems
6.2.2.2 Other Special Control& Instrumentation
6.2.3 Special Facilities
6.2.3.1 Aquatic Facilities
6.2.3.2 Liquid & Gas Storage Tanks
6.2.3.3 Other Special Facilities
6.2.4 Special Structures
6.2.4.1 Other Special Structures
7 Substructure
7.1 Basement Construction
7.1.1 basement construction
7.1.1.1 basement construction
7.1.1.1.1 basement construction
7.1.2 Basement Excavation
7.1.2.1 Excavation for Basements
7.1.2.1.1 Basement Excavation & Backfill
7.1.2.2 Shoring
7.1.2.2.1 Shoring
7.1.2.3 Structural Backfill & Compaction
7.1.3 Basement Walls
7.1.3.1 Basement Wall Construction
7.1.3.1.1 Basement Walls - CIP
7.1.3.2 Moisture Protection
7.1.3.2.1 Foundation Dam proofing
7.2 Foundations
7.2.1 Slab on Grade
7.2.1.1 Pits & Bases
7.2.1.2 Standard Slab on Grade
7.2.1.2.1 SOG - Reinforced
7.2.1.2.2 SOG - Unreinforced
7.2.1.3 structural slab on grade
61
Table 7. (cont.)
Item UniFormatTM Element Class
7.2.1.3.1 structural slab on grade
7.2.1.4 Under-Slab Drainage
7.2.1.5 Under-Slab Insulation
7.2.1.5.1 Sub drainage Piping
7.2.2 Special Foundations
7.2.2.1 Caissons
7.2.2.2 Dewatering
7.2.2.3 Grade Beams
7.2.2.3.1 Grade Beams - CIP
7.2.2.4 Other Special Foundation Conditions
7.2.2.5 Pile Foundations
7.2.2.5.1 Piles - CIP
7.2.2.6 Pressure Injected Grouting
7.2.2.7 Raft Foundations
7.2.3 Standard Foundations
7.2.3.1 Footings & Pile Caps
7.2.3.1.1 Strip Footings
7.2.3.2 Foundation Walls
7.2.3.2.1 Foundation Walls - CIP
7.2.3.3 Perimeter Drainage
7.2.3.3.1 Footing Drains
7.2.3.3.2 Footings & Pile Caps
62
4.3 Data Analysis
The intent of this methodology is the analysis of BIM-based construction scheduling
data. For the scope of this study, BIM-based construction scheduling data analyze is the result of
two types of information: construction scheduling data and object-driven standards (see Fig. 30).
The combination of both variables provides a framework of object-driven tasks that can
leveraged through data analytics and IFC ontologies towards the generation of predictive and
automated BIM-based schedules. Training this data can provide substantial development in big
data analytics and 4D BIM.
Fig. 30. Definition of BIM-based construction scheduling data
The methodology utilized to analyze the data entails the completion of three different
procedures: 1) data collection, 2) data characterization, and 3) BIM-based data (see Fig. 31).
Each of these stages requires the compliance of different tasks. Data collection contemplates the
Construction Scheduling
Data
Object-driven UniFormatTM
Standard Classification
BIM-based Construction Scheduling
Data
63
retrieval of schedule information and data structures processes to organize it; Data
characterization entails the annotation of classified data according to established standards, in
our case, UniFormatTM standard classification; and BIM-based data which includes the
validation of the classified data through peer review and the analysis of frequencies of BIM-
based data. Upon completion of this workflow, BIM-based data is presented to be trained for
data analytics purposes.
Fig. 31. Construction Scheduling Data Analysis workflow
Special emphasis is required for data characterization procedure. The annotation of
classified data required a specific retrofit workflow. This depends on the level of detail or
granularity of the retrieved construction schedules. In other words, while non-BIM-based activity
tasks were not contemplated in the annotation process, BIM-based activity tasks were fully
adapted to the highest level of detail according to their granularity (see. Fig. 32).
BIM-based DataData
Characterization Data Collection
Construction Schedule retrieval
Data Annotations
Validation
Analysis
64
Fig. 32. Construction Scheduling Data Annotations process.
Data
AnnotationsData Structures
BIM-driven classification
YesBIM-based
dataValidation Analysis
No
Object-driven standards
(UniFormatTM)
65
Similarly, the process of data validation required peer review to establish error-prone
annotations. This procedure included:
1) filtered annotation review, errors were reduced by applying filters to select the annotated
UniFormatTM classes. By executing this action, inconsistencies in annotations where found and
solved,
2) selection of inconsistent data, inconsistencies within the annotations were found. These were
isolated and corrected. Some of these inconsistencies relied in the lack of granularity provided by
scheduling data. Scenarios like multiple types of activity tasks for a single classifier, or, multiple
classifiers for a single activity tasks were selected and modified,
3) modification of scheduling data annotations, all inconsistencies due to errors in annotation, or
lack of granularity of the information were modified and updated. Once this step was completed,
data was ready to be analyzed.
A typical sample of the annotations performed is shown in Table 8. As observed, in one
hand activity tasks with lack of granularity such as “in wall electric RI 3rd lift-w tower-level 04-
utility room” were classified as object-driven activities for level 2: “D50 Electrical”. On the
other hand, activity tasks like “layout CMU-w tower-level 04-utility room” included enough
level of detail to be classified as level 5: “B2010140 Ext. Wall CMU” in the UniFormatTM
category. Difficulties with several types of non-standardized abbreviations count as one the
challenges during the performance of data annotation.
66
Table 8. Sample of Annotation process for UniFormatTM standard classification
Construction Scheduling Data UniFormatTM Classification for Construction Scheduling Data
LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 LEVEL 5
Activ.
ID Activ.
Status WBS Code
(*) WBS
Name Activity Name
(*)
Start
(*)
Finish No Descript. No Descript. No Descript. No Descript. No Descript.
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
IN WALL ELECTRIC RI 3RD
LIFT-W TOWER-LEVEL 04-
UTILITY ROOM
25-
Sep-
17
27-
Sep-
17 D Services D50 Electrical
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
SET DOOR FRAMES 3RD
LIFT-W TOWER-LEVEL 04-
UTILITY ROOM
25-
Sep-
17
27-
Sep-
17 B Shell B20
Exterior
Enclosure B2030
Exterior
Doors B2030500
Door Wall
Opening
Elements
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
IN WALL PLUMBING RI
3RD LIFT-W TOWER-LEVEL
04-UTILITY ROOM
25-
Sep-
17
27-
Sep-
17 D Services D20 Plumbing
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
SET EMBEDS 3RD LIFT-W
TOWER-LEVEL 04-UTILITY
ROOM
25-
Sep-
17
27-
Sep-
17 B Shell B10 Superstructure B1010
Floor
Construction
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
INSTALL REBAR 3RD LIFT-
W TOWER-LEVEL 04-
UTILITY ROOM
25-
Sep-
17
27-
Sep-
17 B Shell B10 Superstructure B1010
Floor
Construction B1010200
Upper Floor
Framing -
Vertical
Elements
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
GROUT 3RD LIFT-W
TOWER-LEVEL 04-UTILITY
ROOM
28-
Sep-
17
28-
Sep-
17 B Shell B10 Superstructure B1010
Floor
Construction
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
LAYOUT CMU-W TOWER-
LEVEL 04-UTILITY ROOM
11-
Sep-
17
12-
Sep-
17 B Shell B20
Exterior
Enclosure B2010
Exterior
Walls B2010100
Exterior Wall
Construction B2010140
Ext. Wall
- CMU
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
LAYUP CMU 1ST LIFT-W
TOWER-LEVEL 04-UTILITY
ROOM
13-
Sep-
17
15-
Sep-
17 B Shell B20
Exterior
Enclosure B2010
Exterior
Walls B2010100
Exterior Wall
Construction B2010140
Ext. Wall
- CMU
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
IN WALL ELECTRIC RI 1ST
LIFT-W TOWER-LEVEL 04-
UTILITY ROOM
13-
Sep-
17
15-
Sep-
17 D Services D50 Electrical
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
SET DOOR FRAMES-W
TOWER-LEVEL 04-UTILITY
ROOM
13-
Sep-
17
15-
Sep-
17 B Shell B20
Exterior
Enclosure B2030
Exterior
Doors B2030500
Door Wall
Opening
Elements
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
IN WALL PLUMBING RI 1ST
LIFT-W TOWER-LEVEL 04-
UTILITY ROOM
13-
Sep-
17
15-
Sep-
17 D Services D20 Plumbing
Not
Started 113438MSTR.CN.P111.11.3.2.4.5
Utility
Room-
Level 04
IN WALL ELECTRIC RI 2ND
LIFT-W TOWER-LEVEL 04-
UTILITY ROOM
19-
Sep-
17
21-
Sep-
17 D Services D50 Electrical
67
CHAPTER 5: RESULTS AND DISCUSSION
5.1 Results
A total of 25,866 construction activities precedent from ten different construction projects
have been analyzed. A total of 77% of scheduling data was classified as BIM-based (see Fig.
33). The non-object-driven activity tasks presented a lack of granularity and object-oriented
representation.
Fig. 33. BIM-based Construction Scheduling Data
In the analysis of BIM-based classification by level and by source (see Fig. 34), results
show consistency in the granularity of scheduling data for level 1 through 4. In other words,
among the BIM-based data, construction activities by different source present consistent level of
detail up to level of classification 4. In addition, results indicate variability of consistency in
level 5 by source. Only one data source achieved high level of detail at the highest level of
77%
23%
BIM-based Construction Scheduling Data Classification
Object-driven activity
Non object-driven activity
68
standard classification. In terms of individual analysis by data source, 3 out 10 (30%) datasets
presented more than 90% of BIM-based tasks whereas other sources kept BIM-based
elements near to the total average indicated in Fig. 33.
Fig. 34. Uniformat Level Classification for Construction Scheduling Data by source
In general, scheduling data presents different levels of BIM-based tasks for different
levels of detail. The higher level of detail, the lower BIM-driven relationship. Among the total of
data, levels of classification 1 and 2 presented the highest rates of BIM-based activity tasks
frequency. Indeed, these levels show consistent granularity for UniFormatTM standard
classification (see Fig. 35). Special emphasis requires the frequency achieved in level 5 of
classification. Only 19% of BIM-driven data presents high level of detail during the
classification process.
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%C
lark
MS
TR
Cen
tene
DW
P M
aste
r
Hil
l F
arm
Mort
ense
n
Sar
ato
ga
San
dC
oncr
ete
WS
HU
Sta
diu
m
% D
istr
ibuti
on
Data source
Uniformat Classified Levels by data source
LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 LEVEL 5
69
Fig. 35. Distribution of BIM-based Construction Scheduling Data by UniFormatTM Level
Classification
By levels of BIM-based standardization, the frequency of activity tasks also showed
remarkable results. In Level 1, a total of 19,823 construction activities have been annotated and
analyzed. Results show that most BIM-based construction scheduling data (39.62%) is
related to services (see Fig. 36). This category entails the highest number of BIM-based tasks
during construction. In other words, construction activities such as MEPF are more BIM-based
oriented in comparison with other activity tasks. Categories like shell and interiors also count
with significant quantity of BIM-based tasks. On the other hand, as reasonably expected,
categories such as special construction and demolition count with the least number of BIM-
based tasks (0.38%).
77% 75%
66%
56%
19%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 LEVEL 5
Data distribution per Uniformat Classified Level
70
Fig. 36. Distribution of BIM-based Construction Scheduling Data by UniFormatTM
Categories - Level 1
Similarly, a total of 19,339 object-driven activities have been annotated and analyzed for
Level 2. The activity tasks have been classified into 22 object-driven categories. BIM-based
tasks related to Electrical, Exterior envelop, HVAC, Interior Construction, interior finishes,
Plumbing and Superstructures show the highest frequency for object-based classification
in Level 2 (see Fig. 37).
5.29%3.22%
23.14%
39.62%
23.89%
0.38%
4.47%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
Bu
ild
ing
Sit
ewo
rk
Equ
ipm
ent
& F
urn
ishin
gs
Inte
rio
rs
Ser
vic
es
Shel
l
Spec
ial
Con
stru
ctio
n &
Dem
oli
tio
n
Sub
stru
ctu
re
FR
EQ
UE
NC
Y %
UNIFORMAT ELEMENT CLASSIFICATION - LEVEL 1
UniFormatTM Classification Data Frequency - Level 1
71
Fig. 37. Distribution of BIM-based Construction Scheduling Data by UniFormatTM Categories - Level 2
0.93%
2.00%
12.46%
1.58%
8.91%
3.37% 3.66%
1.73%
13.73%
11.17%11.58%
0.01%
6.55%
0.41%0.06%
1.15%
2.11%
0.74%1.40%
0.33%0.97%
15.16%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
Bas
emen
t C
on
stru
ctio
n
Co
nv
eyin
g
Ele
ctri
cal
Equ
ipm
ent
Exte
rio
r E
ncl
osu
re
Fir
e P
rote
ctio
n
Fou
nd
atio
ns
Furn
ishin
gs
HV
AC
Inte
rio
r C
on
stru
ctio
n
Inte
rio
r F
inis
hes
Oth
er S
ite
Con
stru
ctio
n
Plu
mb
ing
Ro
ofi
ng
Sel
ecti
ve
Buil
din
g D
emoli
tion
Sit
e E
lect
rica
l U
tili
ties
Sit
e Im
pro
vem
ent
Sit
e M
echan
ical
Uti
liti
es
Sit
e P
rep
arat
ion
Spec
ial
Con
stru
ctio
n
Sta
irs
Sup
erst
ruct
ure
FR
EQ
UE
NC
Y %
UNIFORMAT ELEMENT CLASSIFICATION - LEVEL 2
UniFormatTM Classification Data Frequency - Level 2
72
Regarding Level 3, a total of 17,081 BIM-based activity tasks were classified. This data
was broken down into 76 UniFormatTM categories. The analysis of BIM-based scheduling data at
Level 3 shows Floor Construction (15.88%) and HVAC systems / equipment (11.38%) are
the activity tasks with highest object-driven frequency in a medium level of detail (see Fig.
38). In addition, significant number of frequencies was observed in BIM-based tasks for wall
finishes, plumbing fixtures, partitions, other electrical systems, lighting and branch, interior
doors, floor finishes, exterior walls, communications and safety, and ceiling finishes.
Conversely than Level 3, classification of BIM-based tasks at Level 4 show the largest
amount of object-driven UniFormatTM categories represented in the datasets (Fig. 39). A
total of 222 categories were utilized to classify 14,523 datapoints. The activity tasks with the
highest BIM-driven frequency were General construction items – HVAC (13.36%); Fixed
partitions (7.97%); Upper floor framing – vertical elements (6.14%); Upper floor framing
systems (5.78%); Exterior wall construction (5.69%); and Upper floor framing – horizontal
elements (2.55%).
Finally, the analysis of Level 5 shows a lack of granularity of the detail in BIM-based
construction activities (see Fig. 40). Only 4,892 reached the highest level of detail of the
standards utilized. This data was classified into 113 UniFormatTM categories, which is around
50% of the diversity shown in Level 4. The BIM-based tasks with the highest level of detail
were Wall finishes – paint (9.53%), Partition components – drywall (7.69%), Bearing walls
(6.15%), Exterior wall – CMU (5.91%), and Steel girders w/steel beams (4.19%).
73
Fig. 38. Distribution of BIM-based Construction Scheduling Data by UniFormatTM Categories - Level 3
3.85%3.39%
6.77%
2.49%
15.88%
3.06% 2.97%2.65%
3.90%
11.38%
7.34%
3.54%
4.77%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
bas
emen
t co
nst
ruct
ion
Bas
emen
t E
xca
vat
ion
Bas
emen
t W
alls
Bu
ild
ing
Ele
men
ts D
emoli
tion
Cei
ling
Fin
ishes
Co
mm
erci
al E
quip
men
t
Co
mm
unic
atio
ns
and
Sec
uri
ty
Co
ntr
ols
& I
nst
rum
enta
tio
n
Co
oli
ng
Dis
trib
uti
on
Co
oli
ng
Gen
erat
ing
Sy
stem
s
Dis
trib
uti
on S
yst
ems
Do
mes
tic
Wat
er D
istr
ibu
tion
Ele
ctri
cal
Dis
trib
uti
on
Ele
ctri
cal
Ser
vic
e/D
istr
ibu
tio
n
Ele
vat
ors
an
d L
ifts
Ener
gy
Su
pp
ly
Esc
alat
ors
an
d M
ov
ing W
alk
s
Exte
rio
r D
oo
rs
Exte
rio
r W
all
s
Exte
rio
r W
indo
ws
Fir
e P
rote
ctio
n S
pec
ialt
ies
Fit
tin
gs
Fix
ed F
urn
ish
ing
s
Flo
or
Co
nst
ruct
ion
Flo
or
Fin
ish
es
Fuel
Dis
trib
uti
on
Haz
ard
ou
s W
ast
e R
emed
iati
on
Hea
t G
ener
atin
g S
yst
ems
Hea
tin
g D
istr
ibu
tion
Inst
itu
tio
nal
Eq
uip
men
t
Inte
rio
r D
oo
rs
Lan
dsc
apin
g
Lig
hti
ng a
nd B
ran
ch W
irin
g
Mov
eab
le F
urn
ish
ing
s
Oth
er C
on
vey
ing
Sy
stem
s
Oth
er E
lect
rica
l S
yst
ems
Oth
er E
quip
men
t
Oth
er F
ire
Pro
tect
ion S
yst
ems
Oth
er H
VA
C S
yst
ems/
Eq
uip
Oth
er P
lum
bin
g S
yst
ems
Oth
er S
ite
Ele
ctri
cal
Uti
liti
es
Oth
er S
ite
Mec
han
ical
Uti
liti
es
Par
kin
g L
ots
Par
titi
ons
Ped
estr
ian P
avin
g
Plu
mb
ing
Fix
ture
s
Rai
n W
ate
r D
rain
age
Ro
adw
ays
Ro
of
Con
stru
ctio
n
Ro
of
Cov
erin
gs
San
itar
y S
ewer
San
itar
y W
aste
Ser
vic
e an
d P
edes
tria
n T
un
nel
s
Sit
e C
lear
ing
Sit
e C
om
mun
icat
ion
and
Sec
uri
ty
Sit
e D
emo
liti
on a
nd R
elo
cati
on
s
Sit
e D
evel
op
men
t
Sit
e E
art
hw
ork
Sit
e L
ighti
ng
Sla
b o
n G
rad
e
Spec
ial
Con
stru
ctio
n S
yst
ems
Spec
ial
Con
tro
ls &
Inst
rum
enta
tion
Spec
ial
Fac
ilit
ies
Spec
ial
Fo
un
dat
ions
Spec
ial
Str
uct
ure
s
Spri
nkle
rs
Sta
ir C
onst
ruct
ion
Sta
ir F
inis
hes
Sta
nd
ard
Fo
un
dat
ions
Sta
nd
pip
es
Sto
rm S
ewer
Syst
ems
Tes
ting
& B
alan
cing
Ter
min
al &
Pac
kag
e U
nit
s
Veh
icu
lar
Eq
uip
men
t
Wal
l F
inis
hes
Wat
er S
up
ply
FR
EQ
UE
NC
Y %
UNIFORMAT ELEMENT CLASSIFICATION - LEVEL 3
UniFormatTM Classification Data Frequency - Level 3
74
Fig. 39. Distribution of BIM-based Construction Scheduling Data by UniFormatTM Categories - Level 4
Exterior Wall Construction, 5.69%
Fixed Partitions, 7.97%
General Construction Items (Elect.), 4.19%
General Construction Items (HVAC), 13.36%
Upper Floor Framing - Horizontal Elements, 2.55%
Upper Floor Framing - Systems, 5.78%
Upper Floor Framing - Vertical Elements, 6.14%
Wall Finishes, 5.58%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
Acc
ess
Ped
esta
l F
loo
rin
g
Ap
pli
ed C
eili
ng
Fin
ish
es
Au
dio
-vis
ual
Eq
uip
men
t
bas
emen
t co
nst
ruct
ion
Bas
es C
urb
s &
Tri
m
Bat
h &
To
ilet
Acc
esso
ries
Bo
rro
w F
ill
Bri
ck &
Til
e P
laza
s
Bu
ild
ing
Dem
oli
tio
n
Buil
din
g I
nte
rio
r D
emo
liti
on
Cai
sso
ns
Ch
ille
d W
ater
Pip
ing
Co
ld W
ater
Ser
vic
e
Co
oli
ng
To
wer
s o
n S
ite
Cu
rbs,
Gu
tter
s &
Dra
ins
Dat
a N
etw
ork
ing
Dew
ater
ing
Dit
ches
& C
ulv
erts
Dry
wal
l &
Pla
ster
Cei
lin
g C
om
po
nen
ts
Exca
vat
ion
fo
r B
asem
ents
Exhau
st V
enti
lati
on
Sy
stem
s
Exte
rior
Lou
ver
s, S
cree
ns
& F
enci
ng
Ex
teri
or
Ste
ps
& R
amp
s
Ex
teri
or
Win
do
ws
Fab
rica
ted C
om
par
tmen
ts &
Cu
bic
les
Fin
e G
rad
ing
& S
oil
Pre
par
atio
n
Fir
e E
xti
ng
uis
her
Cab
inet
s
Fir
epro
ofi
ng
- F
loo
r C
on
stru
ctio
n
Fix
ed C
asew
ork
Fla
t R
oo
f F
ram
ing -
Ho
rizo
nta
l E
lem
ents
Fla
t R
oo
f F
ram
ing
- V
erti
cal
Ele
men
ts
Flo
or
Rac
eway
Sy
stem
s
Flo
ori
ng
Fo
oti
ng
s &
Pil
e C
aps
Fo
unta
ins
Po
ols
& W
ater
cou
rses
Fre
igh
t E
lev
ato
rs
Fu
el S
tora
ge
Tan
ks
Gas
Dis
trib
uti
on
Gen
eral
Const
ruct
ion
Ite
ms
(HV
AC
)
Gra
de
Bea
ms
Gro
un
din
g S
yst
ems
Gu
tter
s &
Do
wn
spo
uts
Hea
dw
alls
& C
atch
Bas
ins
Hea
ting
/Cooli
ng
Air
Han
dli
ng
Un
its
Ho
ists
& C
ran
es
Ho
t W
ater
Ser
vic
e
HV
AC
Co
mm
issi
on
ing
Insu
lati
on
Inte
rio
r D
oo
r F
ram
es
Inte
rior
Door
Wal
l O
pen
ing
Ele
men
ts
Inte
rio
r D
oo
rs w
ith
Fra
mes
Inte
rnal
Tra
ffic
Pro
tect
ion
Aid
s
Lav
ato
ries
Liq
uid
& G
as S
tora
ge
Tan
ks
Low
Ten
sion S
erv
ice
& D
istr
ibu
tio
n
Med
ical
Eq
uip
men
t
Mis
c. O
ther
Fir
e P
rote
ctio
n S
yst
ems
Mis
c. O
ther
Plu
mb
ing
Sy
stem
s
Mov
able
Mu
ltip
le S
eati
ng
Off
ice
Eq
uip
men
t
Oth
er C
oo
lin
g S
yst
em C
om
po
nen
ts
Oth
er E
xte
rio
r D
oo
rs
Oth
er H
azar
do
us
Was
te R
emed
iati
on
Oth
er L
and
scap
e F
eatu
res
Oth
er S
pec
ial
Co
ntr
ol&
In
stru
men
tati
on
Oth
er S
pec
ial
Fo
un
dat
ion
Co
nd
itio
ns
Oth
er S
yst
em T
esti
ng
& B
alan
cin
g
Over
hea
d P
ow
er D
istr
ibu
tio
n
Par
apet
s
Par
kin
g L
ot
Bas
es &
Su
b-B
ases
Pas
sen
ger
Ele
vat
ors
Ped
estr
ian
Tu
nn
els
Pil
e F
ou
nd
atio
ns
Pip
ing
& F
itti
ng
s
Pit
s &
Bas
es
Pla
nti
ng
Pre
ssu
re I
nje
cted
Gro
uti
ng
Pu
mp
ing
Sta
tio
ns
Reg
ula
r S
tair
s
Rem
ov
al o
f C
on
tam
inat
ed S
oil
Ret
enti
on
Po
nd
s
Rev
olv
ing
Do
ors
Road
way
Pav
ing
& S
urf
acin
g
Ro
of
Eav
es &
So
ffit
s
Ro
of
Fla
shin
g &
Tri
m
Sec
uri
ty &
Det
ecti
on
Sy
stem
s
See
din
g &
So
dd
ing
Sh
ori
ng
Sid
ewal
ks
Sin
ks
Sit
e F
ixtu
res
& T
ran
sfo
rmer
s
Sit
e G
radin
g E
xca
vat
ion
& D
isp
osa
l
Sit
e S
ho
rin
g
So
il S
tab
iliz
atio
n &
Tre
atm
ent
Sp
ecia
l S
ecu
rity
Sy
stem
s
Sta
ir H
andra
il &
Bal
ust
rad
e F
inis
hes
Sta
nd
ard
Sla
b o
n G
rad
e
Sto
refr
on
ts
Str
uct
ura
l B
ack
fill
& C
om
pac
tio
n
Su
bst
atio
ns
Tel
eph
on
e S
yst
ems
Thea
ter
& S
tag
e E
qu
ipm
ent
Tra
ffic
Topp
ings
& P
avin
g M
emb
ran
es
Un
der
-Sla
b D
rain
age
Upper
Flo
or
Fra
min
g -
Ho
rizo
nta
l E
lem
ents
Upper
Flo
or
Fra
min
g -
Ver
tica
l E
lem
ents
Uti
liti
es T
ren
chin
g
Was
te P
ipin
g
Wel
ls f
or
Co
oli
ng
/Hea
tin
g
Win
do
w T
reat
men
ts
Win
do
ws
FR
EQ
UE
NC
Y %
UNIFORMAT ELEMENT CLASSIFICATION - LEVEL 4
UniFormatTM Classification Data Frequency - Level 4
75
Fig. 40. Distribution of BIM-based Construction Scheduling Data by UniFormatTM Categories - Level 5
Bearing Walls - CIP, 6.15%
2.15% 2.06%
2.58%
3.15%
2.49%2.39%
3.86%
Ext. Wall - CMU, 5.91%
2.00%
Partition Components - Drywall, 7.69%
2.39% 2.31%2.47%
Steel Girders w/ Steel Beams, 4.19%
Wall Finishes - Paint, 9.53%
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
8.00%
9.00%
10.00%
Bas
e -
Vin
yl
& R
ub
ber
Bas
e F
lash
ing
bas
emen
t co
nst
ruct
ion
Bas
emen
t E
xca
vat
ion
& B
ack
fill
Bas
emen
t W
alls
- C
IP
Bat
h &
To
ilet
Acc
esso
ries
- C
om
mer
cial
Bea
ms
- C
IP
Bea
ms
- P
reca
st
Bea
ms
- S
teel
Bea
rin
g W
alls
- B
lock
Bea
rin
g W
alls
- C
IP
Cab
inet
s
Cei
lin
g C
om
po
nen
ts -
Dry
wal
l
Cei
lin
g F
inis
hes
- C
oat
ing
s
Cei
lin
g F
inis
hes
- C
ov
erin
gs
Cei
lin
g F
inis
hes
- P
ain
t
Cei
lin
g F
inis
hes
- P
anel
ing
Cei
lin
g F
inis
hes
- T
ile
Ch
alk
bo
ard
s &
Wh
iteb
oar
ds
CIP
Bea
m &
Sla
b -
Tw
o W
ay
CIP
Sla
bs
- F
lat
Pla
te
Co
lum
ns
- C
IP
Co
lum
ns
- P
reca
st
Co
lum
ns
- S
teel
Co
mp
osi
te B
eam
& S
lab
Co
mp
osi
te B
eam
Dec
k &
Sla
b
Co
mp
osi
te B
eam
, D
eck
& S
lab
Cu
rtai
n W
alls
Cu
rtai
n W
alls
- F
ram
ing
Cu
rtai
n W
alls
- P
anel
s
Dec
k -
Met
al
Do
or
Har
dw
are
Ele
vat
ors
- F
reig
ht
Ele
vat
ors
- H
yd
rau
lic
Ex
t. W
all
- C
IP
Ex
t. W
all
- C
MU
Ex
t. W
all
- M
etal
Sid
ing
Pan
els
Ex
t. W
all
- P
reca
st
Ex
t. W
all
- S
ton
e V
enee
r w
/ S
tud
Ex
t. W
all
- W
oo
d S
tud
w/
Stu
cco
Ex
teri
or
Gla
zed
Do
ors
- A
lum
inu
m
Flo
ori
ng
- O
ther
Flo
ori
ng
- T
erra
zzo
Flo
ori
ng
- T
ile
Flo
ori
ng
- W
oo
d
Fo
od
Ser
vic
e -
Ap
pli
ance
s &
Eq
uip
men
t
Fo
od
Ser
vic
e -
Cab
inet
s &
Co
un
tert
op
s
Fo
oti
ng
Dra
ins
Fo
oti
ng
s &
Pil
e C
aps
Fo
un
dat
ion
Dam
pp
roo
fin
g
Fo
un
dat
ion
Wal
ls -
CIP
Gra
de
Bea
ms
- C
IP
Inte
rio
r D
oo
r F
ram
es -
Met
al
Inte
rio
r D
oo
r F
ram
es -
Wo
od
Inte
rio
r D
oo
rs -
Wo
od
Inte
rio
r G
laze
d O
pen
ing
s
Jois
ts -
Ste
el
Lav
ato
ries
- S
ing
le
load
ing
do
ck e
qu
ipm
ent
Lo
cker
s
Mo
vin
g W
alk
s
Ov
erh
ead
Do
ors
Par
titi
on
Co
mp
on
ents
- D
ryw
all
Par
titi
on
Co
mp
on
ents
- M
etal
Fra
min
g
Par
titi
on
Co
mp
on
ents
- W
oo
d F
ram
ing
Par
titi
on
s -
CM
U
Par
titi
on
s -
Dry
wal
l w
/ M
etal
Stu
d
Par
titi
on
s -
Dry
wal
l w
/ W
oo
d S
tud
Par
titi
on
s -
Fo
ldin
g
Par
titi
on
s -
Gla
ss B
lock
Par
titi
on
s -
Sto
ne
Ven
eer
w/
Stu
d
Par
titi
on
s -
Til
e
Pil
es -
CIP
Pla
nk
s -
Pre
cast
Rec
epta
cles
- F
loo
r
Rec
epta
cles
- W
all
Ro
of
Fla
shin
g
Ro
of
Insu
lati
on
- R
igid
Ro
ofi
ng
- B
uil
t-u
p
roo
fin
g -
fo
rmed
met
al
Ro
ofi
ng
- P
refo
rmed
Met
al
Ro
ofi
ng
- S
hin
gle
& T
ile
Ro
ofi
ng
- S
ing
le P
ly M
emb
ran
e
Sec
uri
ty E
qu
ipm
ent
Sh
ori
ng
Sh
ow
ers
Sig
ns
SO
G -
Rei
nfo
rced
SO
G -
Un
rein
forc
ed
Sta
irs
- C
IP
Sta
irs
- P
reca
st
Sta
irs
- S
teel
stai
rs -
wo
od
Ste
el B
eam
Fir
epro
ofi
ng
Ste
el B
eam
s w
/ S
teel
Jo
ists
Ste
el G
ird
ers
w/
Ste
el B
eam
s
Str
ip F
oo
tin
gs
stru
ctu
ral
slab
on
gra
de
Su
bd
rain
age
Pip
ing
Su
spen
ded
Cei
lin
gs
- A
cou
stic
al
Su
spen
ded
Cei
lin
gs
- G
yp
sum
Bo
ard
To
ilet
Par
titi
on
s
Tu
rnst
iles
upp
er f
loo
r fr
amin
g -
ho
rizo
nta
l el
emen
ts
W S
hap
e C
om
po
site
Dec
k &
Sla
b
Wal
l F
inis
hes
- C
ov
erin
gs
Wal
l F
inis
hes
- P
ain
t
Wal
l F
inis
hes
- P
anel
ing
Wal
l F
inis
hes
- T
ile
Wat
er C
lose
ts -
Sin
gle
Win
do
w T
reat
men
ts -
Bli
nd
s
Win
do
ws
- A
lum
inu
m
X-r
ay E
qu
ipm
ent
FR
EQ
UE
NC
Y %
UNIFORMAT ELEMENT CLASSIFICATION - LEVEL 5
UniFormatTM Classification Data Frequency - Level 5
76
5.2 Discussion
The results of this research provide a better understanding of the current practices in
construction planning and scheduling and 4D BIM in the AEC industry. The analysis performed
indicates that 77% of construction activities are BIM-based. Regardless the level of involvement
in 4D BIM, scheduling data shows extraordinary possibilities to standardize this data into object-
driven tasks, which creates possibilities to connect such tasks with IFC ontologies in the future.
Participants surveyed be
Although results seem to be promising, several challenges were found when analyzing
scheduling data. The first challenge was the variability of the activity name designation. Through
the classification and annotation of scheduling data, different conventions to describe activity
tasks were found. Examples such as RI (rough-in), TO (trim-out), FRP (forming / rebar /
pouring), CW (curtain wall), etc. are some of the typical abbreviations found. We asked AEC
experts how these conventions are introduced in construction schedules and majority indicated it
is a decision of the project manager or superintendent. In addition, they manifested more than
50% of activity tasks use such conventions, and these are present in multiple scheduling
packages (MEPF, Structures, Architecture, etc.). Furthermore, most responders (60%) indicated
the lack of standard guides to create WBS. Apparently, there is a lack of standardization in the
process of naming activities that makes construction scheduling data very complex to understand
and analyze. Therefore, scheduling data needs to be classified through common object-driven
standards in order to provide opportunities for data analytics for the automation of 4D BIM.
The second challenge was the lack of granularity in construction scheduling data.
Although lot of construction activities were analyzed (around 25,866), few of them contained a
high level of BIM-based detail (19%). According to the survey conducted, multiple explanations
77
could be given to understand such shortage like the use of in-house standards, lack of WBS
guides, low frequency in the use of the master schedule and its at the jobsite, etc. Regardless the
reasons of detail scarcity, the process of classifying certain activity tasks became troublesome.
Two typical cases required troubleshooting: “one to many”, and “many to one”. The case of
“One to many”, where one activity task classified into more than one UniFormatTM categories.
For instance, the activity task: “Prime & paint-w tower – level 03 – entrance corridor”, due to
the lack of detail, classified into two different categories at Level 05: C3010110 Wall Finishes –
Paint, and C3030110 Ceiling Finishes – Paint. Because of the uncertainty generated, activities
like this were categorized with a lower level of detail (Level 2 - C30 Interior finishes) in order to
avoid classification errors. The case “many to one” where multiple construction activities
required a higher level of specificity than Level 5. For instance, the tasks: “CMU install Main
Entrance (15.5 corridor) (a)” and “CMU install – elevator lobby” can be classified at Level 5 as
B2010140 Ext. Wall – CMU. Although both tasks fit in the same category, a higher level of
specificity is required to identify specific attributes like type of CMU material.
The last challenge is associated with the cumbersome validation process. Due to the large
amount of data, continuous validation process was required to acquire a high level of consistency
in the data. Typical examples of same activity tasks classified into two different UniFormatTM
categories was as trend during the validation process. Introducing NLP algorithms to automate
the validation process represents one of the next steps to in the analysis of BIM-based
construction analysis data towards 4D BIM automation.
78
CHAPTER 6: CONCLUSION & FUTURE WORK
The study provided a comprehensive understanding of current practices in construction
planning & scheduling and 4D BIM in the AEC industry. Although future work is still required
to achieve autonomous workflows for the creation and updating of construction schedules in 4D
BIM, the results of the analysis of data utilized for such purpose have been presented and
described. Consequently, some of the relevant conclusions and future research opportunities in
this field are addressed in this chapter.
6.1 Conclusions
The survey conducted and the analysis of construction scheduling data towards the
automation of 4D BIM have set the foundation for future development. Some of the import ant
findings of this process are indicated below.
1. Construction planning and scheduling in the AEC industry is still an empirical
practice. 63% of industry members utilize in-house standards to create and
execute construction schedules. Moreover, this practice has become a process
where guides to classify and organize construction activities is no longer a
common practice. In fact, 60% of the surveyed participants indicated they do not
utilize guides to create WBS. As a result, different conventions have been
adopted to organize and name activity tasks. Results show that up to 75% of
construction practitioners use their own conventions when performing
construction scheduling. They indicate project managers and constructor
superintendents are responsible for such incorporation. In addition, they define
79
MEPF as the most empirical field with incorporated conventions, followed by
Structures and Architecture.
2. Mostly, master schedules or construction schedules are updated on a monthly
basis. 53% of participants confirmed such trend. Although majority of
practitioners indicate a frequent use of construction schedule during construction
phase, only 3% of them manifest to update the master schedule in less than a
weekly basis. This is a problem in the practice of construction planning and
scheduling, especially when AEC professionals: a) do not fully embrace the use
of 4D BIM to perform schedule quality control – only 18% of practitioners
confirmed their use for this purpose – replacing this opportunity for traditional
face-to-face meetings with different trades of the construction project – 73% of
participants referred it as the most common technique for schedule quality
control; and b) identify updating construction/baseline schedule as the main
approach to track construction project progress (68% confirmed the use of this
technique as main to for tracking progress).
3. Most of the AEC members are familiar with 4D BIM workflows. The study
shows than 87.5% of professionals involved in construction activities are familiar
with tasks and challenges to perform 4D BIM. Practitioners define construction
visualization, progress monitoring, and coordination among trades as the main
usages leveraged from 4D BIM. Furthermore, they indicate that such workflow is
primarily somewhat useful during preconstruction than construction. Explanation
80
regarding this perception lies on the challenges inherited within 4D BIM
workflows. The study reveals that omission of various tasks procedures is the
most challenging difficulty practitioners face in 4D BIM. Also, it identifies
linkage of construction activities with BIM-objects and inconsistency of task
naming as the most important moderate challenges.
4. Trade coordination has been identified as the primary common area of
improvement in construction planning & scheduling and 4D BIM. Software
interoperability has been considered as the second biggest challenge to overcome
in construction planning and scheduling workflows. Similarly, task linkage
procedure has been identified as the main secondary area of improvement in 4D
BIM.
5. Standardization of construction activities into 4D BIM-based workflows is
feasible. The study reveals that majority of construction activities can be
classified as BIM-based scheduling data. Indeed, it shows that 77% of real
activity tasks are object-oriented. In a high level, services contain the highest
frequency amongst all BIM-based tasks analyzed. This trend is followed by
categories such as interiors and shell (structures, cladding, envelope, etc.). For
this reason, tasks related to activities like electrical, exterior envelop, HVAC,
interior construction, interior finishes, plumbing and superstructures occupy the
highest hierarchy of frequency in the analysis of construction scheduling data.
like
81
6. There is a shortage of detail in construction scheduling data. The analysis
performed indicates that only 19% of BIM-based scheduling data reaches a high
level of detail. In terms of UniFormatTM classification, while a range of 56-76%
of BIM-based construction activities can reach the levels of detail 1 through 4,
only 19% of tasks can achieve a level of detail 5.
7. There is a possibility to develop further research in the field to investigate more
specific relationships between construction scheduling data and 4D BIM
workflows. This research can be conducted to provide a more specific analysis of
construction activities according to the type of construction industry
(commercial, buildings, healthcare, heavy civil, etc.). In addition, BIM-based
scheduling data can be leveraged for data analytics purposes. In fact, intelligent
models can utilize this standardized data to learn the process of classification of
construction activities within BIM environments, and eventually, to automate the
procedure of creation and updating of construction schedules in 4D BIM.
82
6.2 Future Work
The method developed represents an opportunity for future applications and research.
First, the analysis of construction scheduling data could be leveraged through NLP
algorithms to increase the efficiency and accuracy of the results. Also, the analysis could be
applied to more construction scheduling data and could be broken down into specific type of
construction: buildings, commercial, healthcare, education, etc. This analysis will help with more
specific understanding of scheduling data diversified by the type of industry.
Second, BIM-based construction scheduling data can be tested in data analytics and
machine learning algorithms. Prototypes to predict construction schedules based on the
interaction of BIM-based scheduling data and IFC object-driven elements is very feasible with
the classified scheduling data. Future research in this field can optimize the process of
classifying and annotating information that lately can be retrofit intelligent models and,
eventually, can create automated schedules in 4D BIM environments.
Finally, the results show acceptable relationship between construction activities and BIM.
This relationship can be optimized by classifying scheduling data with different standards
(MasterFormat®, OmniClass®, etc) or in-house parameters. Eventually, the fully automation of
4D BIM in the AEC industry will be possible as long as the workflows in construction planning
and scheduling are standardized. This standardization must be studied with more detail.
83
REFERENCES
Abath, M., De Sourza, I., Sampario, R., & Pinto, J. (2018). 4D BIM Building Information
Modeling: A systematic mapping study. 35th International Symposium on Automation
and Robotics in Construction.
Alizadehsalehi, S., & Yitmen, I. (2019). Automated construction progress monitoring:
Technologies Adoption for Benchmarking Project Performance Control. Arabian Journal
For Science & Engineering, 44(5), 4993-5008. doi:https://doi.org/10.1007/s13369-018-
3669-1
Antwi-Afari, M. F., Li, H., Pärn, E. A., & Edwards, D. J. (2018). Critical success factors for
implementing building information modelling (BIM): A longitudinal review. Automation
In Construction, 100-110. doi:https://doi.org/10.1016/j.autcon.2018.03.010
Baldwin, A., & Bordoli, D. (2014). Handbook for Construction Planning and Scheduling. Wiley
Blackwell. Pondicherry, India: Wiley Blackwell.
doi:https://doi.org/10.1002/9781118838167
Bernstein, H., Jones, S., & Russo, M. (2012). The business of BIM in North America: multi-year
trend analysis and user rating (2007-2012). McGraw-Hill Construction.
Bilal, M., Oyedele, L. O., Qadir, J., Munir, K., Ajayi, S. O., Akinade, O. O., . . . Pasha, M.
(2016). Big Data in the construction industry: A review of present status, opportunities,
and future trends. Advanced Engieering Informatics, 30(3), 500-521.
doi:https://doi.org/10.1016/j.aei.2016.07.001
Borges, M. L., Cavalcanti de Souza, I., Melo, R. S., & Giesta, J. P. (2018). 4D building
information modeling: A systematic mapping study. ISARC 2018 - 35th International
Symposium on Automation and Robotics In Construction and International AEC/FM
84
Hackathon: The Future of Building Things. Retrieved from
http://search.ebscohost.com/login.aspx?direct=true&db=edselc&AN=edselc.2-52.0-
85053921711&site=eds-live&scope=site
Boton, C. (2018). Supporting constructability analysis meetings with Immersive Virtual Reality-
based collaborative BIM 4D simulation. Automation In Construction, 96, 1-15.
doi:https://doi.org/10.1016/j.autcon.2018.08.020
Burguer, R. (2019, February 03). How the construction industry is using big data. Retrieved
from The balance small business: https://www.thebalancesmb.com/how-the-construction-
industry-is-using-big-data-845322
Chang, A. S.-T., & Tsai, Y.-W. (2003). Engineering Information Classification System. Journal
Of Construction Engineering & Management, 129(4), 454-460.
Chen, K., Lu, W., Peng, Y., Rowlinson, S., & Haung, G. (2015). Bridging BIM and buiding:
from a literature review to an integrated conceptual framework. Imnternational Journal
Of Project Management, 33(6), 1405-1416.
doi:https://doi.org/10.1016/j.ijproman.2015.03.006
Chen, L., & Luo, H. (2014). A BIM-based construction quality management model and its
applications. Automation In Construction, 46, 64-73.
doi:https://doi.org/10.1016/j.autcon.2014.05.009
Chen, W., Chen, K., Cheng, J. C., Gan, V. J., & Wang, Q. (2018). BIM-based framework for
automatic scheduling of facility maintenance work orders. Automation In Construction,
91, 15-30. doi:https://doi.org/10.1016/j.autcon.2018.03.007
85
Chengshuang, S., Qingpeng, M., & Yaowu, W. (2015). Study on BIM-based construction project
cost and schedule risk early warning. Journal Of Intelligent & Fuzzy Systems, 29(2), 469-
477. doi:https://doi.org/10.3233/IFS-141178
CSI. (2010). Uniformat: A Uniform Classification of Construction Systems and Assemblies.
Alexandria, VA 22314: The Construction Specification Institute.
Dimitrov, A., & Golparvar-Fard, M. (2014). Vision-based material recognition for automated
monitoring of construction progress and generating building information modeling from
unordered site image collections. Advanced Engineering Informatics, 28(1), 37-49.
doi:https://doi.org/10.1016/j.aei.2013.11.002
Ding, L., Li, K., Zhou, Y., & Love, P. E. (2017). An IFC-inspection process model for
infrastructure projects: Enabling real-time quality monitoring and control. Automation In
Construction, 84, 96-110. doi:https://doi.org/10.1016/j.autcon.2017.08.029
Ding, L., Zhou, Y., & Akinci, B. (2014). Building Information Modeling (BIM) application
framework: The process of expanding from 3D to computable nD. Automation In
Construction, 46, 82-93. doi:https://doi.org/10.1016/j.autcon.2014.04.009
Dong, N., Fischer, M., Haddad, Z., & Levitt, R. (2013). A method to automate look-ahead
schedule (LAS) generation for the finishing phase of construction projects. Automation In
Construction, 35, 157-173. doi:https://doi.org/10.1016/j.autcon.2013.05.023
Enshassi, A. A., Abuhamra, L., & Alkilani, S. (2018). Studying the benefits of building
information modeling (BIM) in architecture, engineering and construction (AEC)
industry in the Gaza strip. Jordan Journal Of Civil Engineering, 12(1), 87-98. Retrieved
from http://search.ebscohost.com/login.aspx?direct=true&db=edselc&AN=edselc.2-52.0-
85037715039&site=eds-live&scope=site
86
EU BIM. (2017). Handbook for the introduction of Building Information Modelling by the
European Public Sector - Strategic action for construction sector performance: driving
value, innovation and growth. EUBIM TaskGroup.
Faghihi, V., Reinschmidt, K. F., & Kang, J. H. (2016). Objective-driven and Pareto Front
analysis: Optimizing time, cost, and job-site movements. Automation In Construction, 69,
79-88. doi:https://doi.org/10.1016/j.autcon.2016.06.003
Gelisen, G., & Griffis, F. H. (2014). Automated productivtiy-based schedule animation:
Simulation-based approach to time-cost trade-off analysis. Journal Of Construction
Engineering & Management, 140(4), 1-10. doi:https://doi.org/10.1061/(ASCE)CO.1943-
7862.0000674
Ghaffarianhoseini, A., Tookey, J., Ghaffarianhoseini, A., Naismith, N., Azhar, S., Efimova, O.,
& Raahemifar, K. (2017). Building Information Modeling (BIM) uptake: clear benefits,
understanding its implementation, risks and challenges. Renewable and Sustainable
Energy Reviews, 75, 1046-1053. doi:https://doi.org/10.1016/j.rser.2016.11.083
Giel, B., Raja, R., & Issa, F. (2013). Return of Investment Analysis if Using Building
Information Modeling in Construction. Journal Of Computing in Civil Engineering,
27(5), 511-521. doi:https://doi.org/10.1061/(ASCE)CP.1943-5487.0000164
Gledson, B. J., & Greennwood, D. (2017). The adoption of 4D BIM in the UK construction
industry: An innovation diffusion approach. Engineering Construction And Architectural
Management, 950-967. doi:https://doi-org.proxy2.library.illinois.edu/10.1108/ECAM-03-
2016-0066
87
Goh, Y. M., & Ubeynarayana, C. U. (2017). Construction accident narrative classification: An
evaluation of text mining techniques. Accident Analysis and Prevention, 108, 122-130.
doi:https://doi.org/10.1016/j.aap.2017.08.026
Golparvar-Fard, M., Peña-Mora, F., & Savarese, S. (2011). Integrated Sequential As-Built and
As-Planned representation with D4 AR tools in supoort of decision-making tasks in the
AEC/FM industry. Journal Of Construction Enginering & Management, 137(12), 1099-
1116. doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0000371
Golparvar-Fard, M., Peña-Mora, F., & Savarese, S. (2015). Automated Progress Monitoring
Using Unordered Daily Construction Photographs and IFC-Based Building Information
Models. Journal Of Computing In Civil Engineering, 29(1), 1-19.
doi:https://doi.org/10.1061/(ASCE)CP.1943-5487.0000205
GSA. (2009). BIM Guide for 4D phasing. Washington, DC: U.S. General Services
Administration, Public Building Service. Retrieved from
https://www.gsa.gov/cdnstatic/BIM_Guide_Series_04_v1.pdf
Gwak, H., Son, S., Park, Y., & Lee, D. (2016). Exact time-cost tradeoff analysis in concurrency-
based scheduling. Journal Of Construction Engineering & Management, 1-13.
doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0001164
Habibi, S. (2017). The promise of BIM for improving building performance. Energy and
Buildings, 153, 525-548. doi:https://doi.org/10.1016/j.enbuild.2017.08.009
Hall, D. J. (2008). Divided by a common language. Retrieved from
http://search.ebscohost.com/login.aspx?direct=true&db=asn&AN=10266717
Hall, D., & Levitt, R. (2018). Which project integration strategies deliver High Performance
projects? Stanford University, CA: Center for Integrated Facility Engineering.
88
Hamid, M., Tolba, O., & El Antably, A. (2018). BIM semantics for digital fabrication: A
knowledge-based approach. Automation In Construction, 91, 62-82.
doi:https://doi.org/10.1016/j.autcon.2018.02.031
Hamledari, H., McCabe, B., Davari, S., & Shahi, A. (2017). Automated schedule and progress
updating of IFC-based 4D BIMs. Journal Of Computing in Civil Engineering, 31(4), 1-
16. doi:https://doi.org/10.1061/(ASCE)CP.1943-5487.0000660
Hamledari, H., McCabe, B., Davari, S., Shahi, A., Azar, E., & Flager, F. (2017). Evaluation of
Computer Vision-and 4D BIM-based Construction Progress Tracking on a UAV
Platform. Stanford University, CA: 6TH CSCE/ASCE/CRC International Construction
Specialty Conference.
Han, K. K., & Golparvar-Fard, M. (2017). Potential of big visual data and building information
modeling for construction performance analytics: An exploratory study. Automation In
Construction, 73, 184-198. doi:https://doi.org/10.1016/j.autcon.2016.11.004
Han, K. K., Cline, D., & Golparvar-Fard, M. (2015). Formalized knowledge of construction
sequencing for visual monitoring of work-in-progress via incomplete point clouds and
low-LoD 4D BIMs. Advanced Engineering Informatics, 29(4), 889-901.
doi:https://doi.org/10.1016/j.aei.2015.10.006
Hartmann, T., Gao, J., & Fischer, M. (2008). Areas of application for 3D and 4D on construction
projects. Journal of Construction Enginering & Management, 134(10), 776-785.
doi:10.1061/(ASCE)0733-9364(2008)134:10(776)
Honti, R., & Erdélyi, J. (2018). Possibilities of bim data exchange. International
Multidisciplinary Scientific GeoConference Surveying Geology and Mining Ecology
89
Management, SGEM, 18(2.2), 923-930.
doi:https://doi.org/10.5593/sgem2018/2.2/S09.117
Issa, R., & Ol bina, S. (2015). Building Information Modeling: Applications and Practices.
Reston, Virginia: American Society of Civil Engineers.
Issa, R., Flood, I., & O'Brien, W. (2005). 4D CAD and visualization in construction:
developments and applications. Abingdon, VA: Taylor & Francis.
Jang, S., & Lee, G. (2018). Process, productivity, and economic analyses of BIM–based multi-
trade prefabrication- A case study. Automation In Construction, 89, 86-98.
doi:https://doi.org/10.1016/j.autcon.2017.12.035
Kam, C., Senaratna, D., McKinney, B., Xiao, Y., & Song, M. (2016). The VDC Scorecard:
Formulation and Validation. Stanford University, CA: Center for Integrated Facility
Engineering.
Kensek, K. M., & Noble, D. (2014). Bulding Information Modeling - BIM in current and future
practice. Hoboken, New Yersey: Wiley & Sons.
Kifokeris, D., & Xenidis, Y. (2017). Constructability: Outline of Past, Present, and Future
Research. Journal of Construction Engineering & Management, 143(8), 1-13.
doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0001331
Koo, B., & Fischer, M. (2000). Feasibility study of 4D CAD in commercial construction.
Journal Of Construction Enginering & Management, 126(4), 251-260.
doi:https://doi.org/10.1061/(ASCE)0733-9364(2000)126:4(251)
Leite, F., Cho, Y., Behzadan, A., Lee, S., Choe, S., Fang, Y., . . . Hwang, S. (2016).
Visualization, Information Modeling, and Simulation: Grand Challenges in the
90
Construction Industry. Journal of Computing in Civil Engineering, 30(6), 1-16. doi:
10.1061/(ASCE)CP.1943-5487.0000604
Lin, J.-R., Hu, Z.-Z., Zhang, J.-P., & Yu, F.-Q. (2016). A Natural-Language-Based Approach to
Intelligent Data Retrieval and Representation for Cloud BIM. Computer-Aided Civil and
Infrastructure Engineering, 31(1), 18-33. doi:https://doi.org/10.1111/mice.12151
Liu, H., Al-Hussein, M., & Lu, M. (2015). BIM-based integrated approach for detailed
construction scheduling under resource constraints. Automation In Construction, 53, 29-
49. doi:https://doi.org/10.1016/j.autcon.2015.03.008
Liu, H., Singh, G., Lu, M., Al-Hussein, M., & Bouferguene, A. (2018). BIM-based automated
design and planning for boarding of light-frame residential buildings. Automation In
Construction, 89, 235-249. doi:https://doi.org/10.1016/j.autcon.2018.02.001
Lopez, R., Chong, H., Wang, X., & Graham, J. (2016). Technical review: analysis and appraisal
of Four-Dimensional building information modeling usability in construction and
engineering projects. Journal Of Construction Engineering & Management, 142(5), 1-6.
doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0001094
Ma, Z., & Liu, Z. (2018). Ontology-and freeware-based platform for rapid development of BIM
applications with reasoning support. Automation In Construction, 90, 1-8.
doi:https://doi.org/10.1016/j.autcon.2018.02.004
Maaz, Z. N., Bandi, S., & Amirudin, R. (2018). Big Data in the Construction Industry: Potential
Opportunities and Way Forward. urkish Online Journal of Design, Art &
Communication, 8, 1470-1480. doi:https://doi.org/10.7456/1080SSE/197
91
Marzouk, M., & Enaba, M. (2019). Text analytics to analyze and monitor construction project
contract and correspondence. Automation In Construction, 98, 265-274.
doi:https://doi.org/10.1016/j.autcon.2018.11.018
McKinsey Global Institute. (2017, February). Reinventing Contruction: A route to higher
productivity. Mckinsey & Company.
Migilinskas, D., Popov, V., Juocevicius, V., & Ustinovichius, L. (2013). The benefits, obstacles
and problems of practical bim implementation. Procedia Engineering, 57, 767-774.
doi:https://doi.org/10.1016/j.proeng.2013.04.097
Moon, H., Kim, H., Kamat, V. R., & Kang, L. (2015). BIM-based construction scheduling
method using optimization theory for reducing activity overlaps. Journal Of Computing
In Civil Engineerinf, 29(3), 1-16. doi:https://doi.org/10.1061/(ASCE)CP.1943-
5487.0000342
Navon, R., & Sacks, R. (2007). Assessing research issues in automated project performance
control (APPC). Automation In Constructin, 16(4), 474-484.
doi:https://doi.org/10.1016/j.autcon.2006.08.001
Peterson, F. (2015). A study of Input anf Output Field Quantification in Heavy Civil
Construction. Stanford, CA: Center for Integrate Facility Engineering.
Poh, C. Q., Ubeynarayana, C. U., & Goh, Y. M. (2018). Safety leading indicators for
construction sites: A machine learning approach. Automation In Construction, 93, 375-
386. doi:https://doi.org/10.1016/j.autcon.2018.03.022
Scaysbrook, S. J. (2016). How BIM can use Big City Data. Journal of Building Survey,
Appraisal & Valuation, 5(2), 144-156. Retrieved from
http://search.ebscohost.com/login.aspx?direct=true&db=asn&AN=120584316
92
Scroggins, M. (2018, 03 07). How BIM can enable construction scheduling in 4D. Retrieved
from Oracle Construction Ans Engineering Blog: http://blogs.oracle.com/
Sigalov, K., & König, M. (2017). Recognition of process patterns for BIM-based construction
schedules. Advanced Engineering Informatics, 33, 456-472.
doi:https://doi.org/10.1016/j.aei.2016.12.003
Succar, B. (2009). Building Information Modeling framework: A research and delivery
foundation for industry stakeholders. Automation In Construction, 18(3), 357-375.
doi:https://doi.org/10.1016/j.autcon.2008.10.003
Sun, C., Man, Q., & Wang, Y. (2015). Study on BIM-based construction project cost and
schedule risk earli warning. Journal Of Intelligence & Fuzzy Systems, 469-477.
doi:10.3233/IFS-141178
Sveikauskas, L., Rowe, S., Mildenberger, J. D., Price, J., & Young, A. (2018). Measuring
productivity growth in construction. Monthly Labor Review, 1-34. Retrieved from
http://search.ebscohost.com/login.aspx?direct=true&db=bsu&AN=128094529&site=eds-
live&scope=site
Sveikauskas, L., Rowe, S., Mildenberger, J., Price, J., & Young, A. (2016). Productivity Growth
In Construction. Jorunal OF Construction Engineering & Management, 142(10), 1-8.
doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0001138
The Economist. (2017, 08 17). Retrieved from The construction industry's productivity problem:
https://www.economist.com/leaders/2017/08/17/the-construction-industrys-productivity-
problem
Tixier, A. J.-P., Hallowell, M. R., Rajagopalan, B., & & Bowman, D. (2016). Automated content
analysis for construction safety: A natural language processing system to extract
93
precursors and outcomes from unstructured injury reports. Automation In Construction,
62, 45-56. doi:https://doi.org/10.1016/j.autcon.2015.11.001
Tixier, A. J.-P., Hallowell, M. R., Rajagopalan, B., & Bowman, D. (2016). Application of
machine learning to construction injury prediction. Automation In Construction, 62, 102-
114. doi:https://doi.org/10.1016/j.autcon.2016.05.016
Turkan, Y., Bosché, F., Haas, C. T., & Haas. (2013). Toward Automated Earned Value Tracking
Using 3D Imaging Tools. Journal Of Construction Engineering & Management, 139(4),
423-433. doi:https://doi.org/10.1061/(ASCE)CO.1943-7862.0000629
Volk, R., Stengel, J., & F., S. (2013). Building Information Modeling (BIM) for existing
buildings - Literature review and future needs. Automation In Construction, 38, 109-127.
doi:https://doi.org/10.1016/j.autcon.2013.10.023
Wang, W.-C., Weng, S.-W., Wang, S.-H., & Chen, C.-Y. (2014). Integrating bulding information
models with construction process simulations for project scheduling support. Automation
In Construction, 37, 68-80. doi:https://doi.org/10.1016/j.autcon.2013.10.009
Wei, G., Zhou, Z., Zhao, X., & Ying, Y. (2010). Design of building component library based on
IFC and PLIB standard. 2010 2nd International Conference on Computer Engineering
and Technology, Computer Engineering and Technology (ICCET), 2010 2nd
International Conference On, 4, 529-534.
doi:https://doi.org/10.1109/ICCET.2010.5485426
Weygant, R. S. (2011). BIM content development: standards, strategies and best practices.
Hoboken, New Jersey: John Wiley & Sons, Inc.
94
Yalcinkaya, M., & Singh, V. (2015). Patterns and trends in Building Information Modeling
(BIM) research: A Latent Semantic Analysis. Automation In Construction, 68-80.
doi:https://doi.org/10.1016/j.autcon.2015.07.012
Yin, X., Liu, H., Chen, Y., & Al-Hussein, M. (2019). Building information modelling for off-site
construction: Review and future directions. Automation In Construction, 72-91.
doi:https://doi.org/10.1016/j.autcon.2019.01.010
Zhang, J., & El-Gohary, N. M. (2016). Integrating semantic NLP and logic reasoning into a
unified system for fully-automated code checking. Automation In Construction, 45-57.
doi:https://doi.org/10.1016/j.autcon.2016.08.027
Zhang, S., Teizer, J., Lee, J.-K., Eastman, C. M., & Venugopal, M. (2013). Building Information
Modeling (BIM) and Safety: Automatic Safety Checking of Construction Models and
Schedules. Automation In Construction, 29, 183-195. doi:Building Information Modeling
(BIM) and Safety: Automatic Safety Checking of Construction Models and Schedules
Zou, Y., Jones, S. W., & & Kiviniemi, A. (2017). Retrieving similar cases for construction
project risk management using Natural Language Processing techniques. Automation In
Construction, 80, 66-76. doi:https://doi.org/10.1016/j.autcon.2017.04.003
95
APPENDIX A: RESEARCH SURVEY
96
97
98
99
100
101
102
103
104
APPENDIX B: SURVEY RESULTS
105
Question 1 Question 2 Question 3 Question 4
When performing construction planning, do If Yes, can you upload the
you follow any standard convention to Do you have a guide to create a Work
Response No Timestamp Email Address document (.pdf, .doc, .xls,
organize/classify planning and estimating Breakdown Structure?
.jpg). to create the WBS?
construction activities?
1 5/22/2019 11:19:34 trrscld2@illinois.edu Masterformat, Uniformat
2 5/31/2019 17:53:08 lmo314@nyu.edu In-house standards
3 6/11/2019 12:06:10 jyooonk@gmail.com In-house standards No
4 6/26/2019 10:12:52 mkaiser621@gmail.com Masterformat, In-house standards Yes
5 6/26/2019 10:15:34 heerdave1@gmail.com In-house standards No
6 6/26/2019 10:15:54 s.taskan@cotterconsulting. In-house standards No
7 6/26/2019 10:20:12 sschung110@gmail.com I don't know Yes
8 6/26/2019 10:25:07 cronoj@gmail.com In-house standards No
9 6/26/2019 10:27:03 ehessenthaler@gfnet.com In-house standards Yes
10 6/26/2019 10:30:30 connievenegas24@gmail.c In-house standards No
11 6/26/2019 10:31:34 Drwallac@gmail.com In-house standards No
12 6/26/2019 10:33:08 ebenson2@illinois.edu Masterformat No
13 6/26/2019 10:38:02 jean.claude.saab@gmail.co In-house standards No
14 6/26/2019 10:42:44 bminot88@gmail.com In-house standards Yes https://drive.google.com/o
15 6/26/2019 10:58:21 jmeissner@arcomurray.com In-house standards No
16 6/26/2019 11:00:45 boseboppana94@gmail.co I don't know Yes
17 6/26/2019 11:06:51 dcjakh@gmail.com Masterformat No
18 6/26/2019 12:50:03 jscarosio1@gmail.com In-house standards No
19 6/26/2019 14:41:59 sjvmrb@mst.edu Masterformat, Uniformat Yes
20 6/26/2019 14:48:16 philrdzanek3@gmail.com Masterformat, Uniformat No
21 6/26/2019 15:20:12 stevejbauer@gmail.com Masterformat No
22 6/26/2019 15:53:05 gus.gvazquez@gmail.com In-house standards No
23 6/26/2019 21:31:26 gracieohs@gmail.com In-house standards Yes
24 6/27/2019 10:44:20 jcarroll34@aol.com In-house standards Yes
25 6/27/2019 13:37:11 alpkirmizioglu@gmail.com Masterformat, In-house standards No
26 6/27/2019 14:01:34 santiagonm@gmail.com In-house standards No
27 6/28/2019 10:32:08 juan.dnm@gmail.com Masterformat Yes
28 6/29/2019 10:53:42 isha.iitr@gmail.com I don't know Yes
29 6/29/2019 13:04:31 daniel.hill215@gmail.com In-house standards No
30 6/29/2019 14:48:02 holly.conrad@streamlineph In-house standards No
31 6/29/2019 19:11:39 k.mitsuteru1013@gmail.co We do not have standard in Japan, but I know No
32 6/29/2019 22:29:04 augustoyim@gmail.com In-house standards No
33 6/30/2019 19:47:56 kevin.hatcher@gmail.com Masterformat, Uniformat No
34 7/1/2019 11:18:09 mundewadi.adnan22@gma In-house standards Yes
35 7/1/2019 11:59:26 harsha1838@gmail.com In-house standards Yes
36 7/1/2019 14:48:22 khalid.wakil@hotmail.com Masterformat No
37 7/3/2019 14:51:15 menassa3@illinois.edu Masterformat Yes
38 7/5/2019 9:13:23 mpfranco88@gmail.com In-house standards Yes 39 7/5/2019 17:35:43 jj587300@gmail.com Masterformat, Uniformat No
40 7/7/2019 18:53:37 e5engineer@netzero.com In-house standards No
106
Question 5 Question 6 Question 7 Question 8
When working with construction schedules, regardless of the WBS structure, do you have
any specific convention to abbreviate/identify
some activities and their location? For
Which software, or in-house interface, When performing preconstruction, how instance, do you work with conventions to If yes / sometimes, how is this Response No do you use for scheduling construction do you conduct schedule quality abbreviate these tasks: a) Close shower walls convention incorporated within the activities? control? L1B3W - c1, which would mean: close shower construction schedule? walls, level 1, area B, west, cell1; or b) FRP
shaft D - CFE L1A2, which means
Form/Rebar/Pour shaft D, system CFE, level 1,
zone A2
1 Primavera P6 Contruction simulation Yes Conventions / abbreviations are widely k
2 Microsoft Project Direct design / construction coordination Sometimes It is used according to historical projects
3 All of above Contruction simulation, Site visits, Direct Sometimes Acoording to company's policy.
4 Primavera P6 Site visits, Virtual meetings with differen Sometimes Scheduler defines convention.
5 Primavera P6 Site visits, Virtual meetings with differen Yes Superintendent / PM defines convention
6 Primavera P6 Site visits, Face-to-face meeting or input No
7 Primavera P6 Site visits, Face-to-face meeting or input Yes combination of scheduler defined, superi
8 All of the above for different levels of sch Site visits, Face-to-face meeting or input Sometimes Varies based on Project, Owner requirem
9 Microsoft Excel Direct design / construction coordination Sometimes Conventions / abbreviations are widely k
10 Microsoft Project Site visits, Face-to-face meeting or input No
11 Primavera P6 Early involvement of different trades (des Sometimes Superintendent / PM defines convention
12 We use both Primavera P6 and Microsoft Face-to-face meeting or input from differ Sometimes Conventions / abbreviations are widely k
13 Primavera P6 Face-to-face meeting or input from differ No
14 Primavera P6 Site visits, Face-to-face meeting or input Yes It is used according to historical projects
15 Microsoft Project Site visits, Virtual meetings with differen Yes Superintendent / PM defines convention
16 Primavera P6 Face-to-face meeting or input from differ No
17 Primavera P6 Direct design / construction coordination No
18 Primavera P6 Site visits, Face-to-face meeting or input Yes Scheduler defines convention.
19 Primavera P6 Site visits, Virtual meetings with differen Sometimes Conventions / abbreviations are widely k
20 TouchPlan Site visits, Face-to-face meeting or input Yes Broken into digestible phases and "batch
21 Phoenix and Microsoft Project Site visits, Virtual meetings with differen Sometimes Scheduler defines convention.
22 Microsoft Project Contruction simulation, Site visits, Face-t Yes It is used according to historical projects
23 Primavera P6 Direct design / construction coordination Sometimes Acoording to company's policy.
24 Excel Spreadsheet combined w/BuildPro Site visits, Face-to-face meeting or input Yes Acoording to company's policy.
25 Primavera P6 Site visits, Early involvement of different No
26 Microsoft Project Face-to-face meeting or input from differ No none
27 Primavera P6 Contruction simulation, Virtual meetings Yes Its a mix of rules established by Project C
28 Smartsheet Virtual meetings with different trades, Ea Sometimes Superintendent / PM defines convention
29 Primavera P6 Site visits, Virtual meetings with differen No
30 IHMS Direct design / construction coordination Sometimes Acoording to company's policy.
31 Microsoft Excel Contruction simulation, Site visits, Face-t No
32 Microsoft Excel Direct design / construction coordination Yes Scheduler defines convention.
33 ASTA Powerproject Contruction simulation, Face-to-face mee Yes It is used according to historical projects
34 Microsoft Project Face-to-face meeting or input from differ Yes It is coordinated amongst trades during p
35 Primavera P6 Site visits, Virtual meetings with differen Sometimes Conventions / abbreviations are widely k
36 Touchplan Site visits, Face-to-face meeting or input Sometimes Superintendent / PM defines convention
37 Microsoft Project Site visits, Face-to-face meeting or input Sometimes
38 Microsoft Project Site visits, Virtual meetings with differen Sometimes Superintendent / PM defines convention 39 Primavera P6 Contruction simulation, Virtual meetings Yes Superintendent / PM defines convention 40 Microsoft Project Site visits, Face-to-face meeting or input No
107
Question 9 Question 10
Question 11 Question 12
Similarly, regarding the total number of During construction, how often do you
activities, how often do you find these What are the primary areas where these During preconstruction, how often do
Response No or the superintendent use look-ahead
conventions within a construction conventions are used to name activities? you use the Master Schedule?
Schedule?
schedule?
1 8 Architecture, Structures, Mechanical / El Sometimes Always
2 7 Architecture Sometimes Usually
3 8 Architecture, Structures, Mechanical / El Always Always
4 5 Mechanical / Electrical / Plumbing / Fire Always Always
5 10 Civil Sometimes Always
6 Usually Usually
7 8 Structures, Mechanical / Electrical / Plum Usually Usually
8 10 Architecture, Structures, Mechanical / El Sometimes Always
9 7 Civil Sometimes Always
10 2 Structures, Mechanical / Electrical / Plum Sometimes Sometimes
11 5 Structures, Mechanical / Electrical / Plum Usually Always
12 6 Architecture, Structures, Mechanical / El Always Always
13 Mechanical / Electrical / Plumbing / Fire Never Usually
14 9 Structures, Mechanical / Electrical / Plum Usually Usually
15 8 Structures, Mechanical / Electrical / Plum Always Always
16 Always Usually
17 1 Always Always
18 10 Architecture, Structures, Mechanical / El Never Always
19 7 Architecture, Mechanical / Electrical / Pl Always Always
20 10 Architecture, Structures Usually Always
21 5 Architecture, Structures, Mechanical / El Always Always
22 8 Architecture, Structures, Mechanical / El Usually Sometimes
23 8 Civil Always Usually
24 10 Residential Construction Always Always
25 1 Usually Usually
26 5 Civil Sometimes Usually
27 10 Structures, Mechanical / Electrical / Plum Always Always
28 5 Architecture, Mechanical / Electrical / Pl Always Always
29 6 Architecture, Structures, Mechanical / El Always Always
30 5 Mechanical / Electrical / Plumbing / Fire Rarely Usually
31 5 Always Always
32 8 Architecture, Civil Usually Usually
33 7 Structures, Mechanical / Electrical / Plum Always Always
34 7 Architecture, Structures Usually Usually
35 8 Architecture, Structures, Mechanical / El Usually Always
36 5 Architecture Always Always
37 4 Architecture, Structures Usually Always
38 3 Structures, Mechanical / Electrical / Plum Sometimes Sometimes 39 10 Mechanical / Electrical / Plumbing / Fire Usually Always 40 1 Never Usually
108
Question 13 Question 14 Question 15 Question 16
During construction, how often do you When executing a construction project,
What are the uses you leverage from 4D
Response No what method(s) do you apply to track How familiar are you with 4D BIM?
update the Master Schedule? BIM?
project progress?
1 Earned Value Analysis (EVA), Look ahe 6 Construction visualization, Construction
2 Earned Value Analysis (EVA), "S" Curve 5 Construction visualization, Constructabil
3 Tri times an year Earned Value Analysis (EVA), "S" Curve 3 Progress monitoring, Construction visual
4 Bi-weekly FIeld input quantification, Look ahead sc 6 Progress monitoring, Construction visual
5 Monthly Tracking key milestones only, FIeld input 0 I don't obtain any uses
6 Monthly Tracking key milestones only 8 Progress monitoring, Construction visual
7 Monthly Tracking key milestones only, FIeld input 1 Progress monitoring, Construction visual
8 Monthly Earned Value Analysis (EVA), "S" Curve 5 I don't obtain any uses
9 Monthly Earned Value Analysis (EVA), Look ahe 1 I don't obtain any uses
10 Never Earned Value Analysis (EVA), Tracking 0 I don't obtain any uses
11 Monthly Look ahead schedules, Updating constru 0 I don't obtain any uses
12 Bi-weekly Tracking key milestones only, Look ahea 6 Progress monitoring, Construction visual
13 Bi-weekly FIeld input quantification, Updating cons 6 Progress monitoring, Construction visual
14 Monthly Earned Value Analysis (EVA), "S" Curve 7 Progress monitoring, Construction visual
15 Monthly Tracking key milestones only, FIeld input 2 Construction visualization, Schedule qua
16 Bi-weekly FIeld input quantification, Location-base 3 I don't obtain any uses
17 Monthly Earned Value Analysis (EVA) 3 Coordination among trades
18 Weekly Tracking key milestones only, Updating c 0 I don't obtain any uses
19 Bi-weekly Earned Value Analysis (EVA), "S" Curve 2 Construction visualization, Constructabil
20 Monthly Tracking key milestones only, Look ahea 0 Progress monitoring
21 Monthly Tracking key milestones only, FIeld input 5 Progress monitoring, Construction visual
22 Monthly "S" Curve, Tracking key milestones only, 10 Progress monitoring, Construction visual
23 Monthly FIeld input quantification 1 Constructability analysis, Coordination a
24 Weekly Tracking key milestones only, FIeld input 4 Not sure if our scheduling would be cons
25 Bi-weekly FIeld input quantification, Look ahead sc 8 Construction visualization, Owner comm
26 Weekly Look ahead schedules 5 Progress monitoring
27 Weekly Earned Value Analysis (EVA), FIeld inpu 10 Progress monitoring, Construction visual
28 Monthly Tracking key milestones only, FIeld input 9 Construction visualization
29 Monthly Look ahead schedules, Updating constru 7 Coordination among trades
30 Weekly Tracking key milestones only, Updating c 6 I don't obtain any uses
31 depends. if master schedule is well create Tracking key milestones only, FIeld input 8 Progress monitoring, Construction visual
32 Never Earned Value Analysis (EVA), "S" Curve 8 I don't obtain any uses
33 Monthly "S" Curve, FIeld input quantification, Lo 9 Construction visualization, Constructabil
34 Weekly Tracking key milestones only 2 Construction visualization, AR / VR, Dig
35 Monthly Tracking key milestones only, Look ahea 5 Progress monitoring, Construction visual
36 Twice a week Tracking key milestones only, Look ahea 8 Progress monitoring, Construction visual
37 Monthly Updating construction/baseline schedule 8 Progress monitoring, Construction visual
38 Monthly Excel workbook annotations, Updating c 10 Progress monitoring, Construction visual 39 Bi-weekly Earned Value Analysis (EVA), Reality ca 10 Progress monitoring, Construction visual 40 Monthly Tracking key milestones only, Look ahea 7 Construction visualization, sales
109
Question 17 Question 18 Question 19 Question 19
When performing 4D BIM, what are the When performing 4D BIM, what are the
During preconstruction, what is the During construction phase, what is the main challenges you face? (1 is "not at main challenges you face? (1 is "not at
Response No choice that best describes your choice that best describes your all challenging" and 5 is "very all challenging" and 5 is "very
perception regarding the functionality of perception regarding the functionality of challenging". If you are not familiar with challenging". If you are not familiar with
4D BIM? 4D BIM? 4D BIM, please select "N/A") [Linking 4D BIM, please select "N/A") [Some 3D
tasks with 3D Objects] objects do not represent tasks]
1 Somewhat useful Not at all useful 5 4
2 Extremely useful Not so useful 3 5
3 Somewhat useful Very useful 3 4
4 Extremely useful Somewhat useful 2 4
5 Not at all useful Not at all useful 3 3
6 Very useful Very useful 5 5
7 Somewhat useful Very useful N/A N/A
8 Not so useful Not so useful N/A N/A
9 Not at all useful Not at all useful N/A N/A
10 Not at all useful Not at all useful N/A N/A
11 Not so useful Somewhat useful N/A N/A
12 Somewhat useful Very useful N/A N/A
13 Very useful Very useful 3 2
14 Extremely useful Very useful 5 2
15 Somewhat useful Somewhat useful 3 3
16 Somewhat useful Somewhat useful N/A N/A
17 Somewhat useful Somewhat useful N/A N/A
18 Not so useful Not so useful N/A N/A
19 Not so useful Somewhat useful 3 3
20 Somewhat useful Somewhat useful N/A N/A
21 Somewhat useful Somewhat useful N/A N/A
22 Extremely useful Very useful 3 2
23 Not so useful Not at all useful 5 5
24 Somewhat useful Somewhat useful N/A N/A
25 Somewhat useful Not so useful 5 5
26 Somewhat useful Very useful 3 3
27 Very useful Somewhat useful 3 3
28 Very useful Somewhat useful 3 2
29 Not so useful Very useful 3 3
30 Very useful Extremely useful 3 5
31 Very useful Somewhat useful 5 3
32 Very useful Somewhat useful N/A N/A
33 Extremely useful Somewhat useful 4 4
34 Very useful Very useful N/A N/A
35 Extremely useful Somewhat useful N/A N/A
36 Very useful Extremely useful 2 4
37 Very useful Extremely useful 2 3
38 Somewhat useful Somewhat useful 1 3
39 Extremely useful Extremely useful 3 4
40 Somewhat useful Somewhat useful N/A N/A
110
Question 19 Question 19 Question 19 Question 19
When performing 4D BIM, what are the When performing 4D BIM, what are the When performing 4D BIM, what are the When performing 4D BIM, what are the
main challenges you face? (1 is "not at main challenges you face? (1 is "not at main challenges you face? (1 is "not at main challenges you face? (1 is "not at
Response No all challenging" and 5 is "very all challenging" and 5 is "very all challenging" and 5 is "very all challenging" and 5 is "very
challenging". If you are not familiar with challenging". If you are not familiar with challenging". If you are not familiar with challenging". If you are not familiar with
4D BIM, please select "N/A") [Some 4D BIM, please select "N/A") [Omission 4D BIM, please select "N/A") [Sequence 4D BIM, please select "N/A") [BIM-
tasks do not represent 3D objects] of various procedure tasks] is inappropriate] objects and tasks do not match]
1 3 5 4 5
2 5 5 4 2
3 3 5 5 5
4 4 3 1 2
5 3 3 3 3
6 5 5 4 4
7 N/A N/A N/A N/A
8 N/A N/A 5 N/A
9 N/A N/A N/A N/A
10 N/A N/A N/A N/A
11 N/A N/A N/A N/A
12 N/A N/A N/A N/A
13 5 5 3 4
14 5 4 3 4
15 4 5 2 3
16 N/A N/A N/A N/A
17 N/A N/A N/A N/A
18 N/A N/A N/A N/A
19 3 3 2 5
20 N/A N/A N/A N/A
21 N/A N/A N/A N/A
22 5 3 3 5
23 5 5 5 5
24 5 5 N/A N/A
25 5 4 1 5
26 3 3 3 3
27 2 3 3 4
28 2 3 4 1
29 3 3 3 3
30 5 5 3 5
31 3 3 2 4
32 N/A N/A N/A N/A
33 4 3 2 2
34 N/A N/A N/A N/A
35 N/A N/A N/A N/A
36 4 3 N/A 1
37 4 3 2 2
38 4 4 2 2
39 4 5 5 2
40 N/A N/A N/A N/A
111
Question 19 Question 19 Question 19 Question 20
When performing 4D BIM, what are the When performing 4D BIM, what are the When performing 4D BIM, what are the
main challenges you face? (1 is "not at main challenges you face? (1 is "not at main challenges you face? (1 is "not at
all challenging" and 5 is "very
all challenging" and 5 is "very all challenging" and 5 is "very Is there any other relevant challenge we
Response No
challenging". If you are not familiar with
challenging". If you are not familiar with challenging". If you are not familiar with did not address in the previous question?
4D BIM, please select "N/A") 4D BIM, please select "N/A") [System 4D BIM, please select "N/A") [Tasks
[Insufficient level of granularity of BIM-
based objects] interoperability] names are inconsistent]
1 4 5
2 4 3
3 3 5 3 Total duration of project. If it is a very lo
4 2 1 1
5 3 3 3 No
6 5 4 3
7 N/A N/A N/A Although I work as a scheduler, I have ne
8 5 5 N/A In Bid-Build Public work. There is substa
9 N/A N/A N/A
10 N/A N/A N/A
11 N/A N/A N/A
12 N/A N/A N/A
13 5 N/A 1 need an extreme level of precision in bot
14 1 2 1 Changing conditions in sequencing, man
15 4 5 4
16 N/A N/A N/A
17 N/A N/A N/A
18 N/A N/A N/A
19 3 5 4
20 N/A N/A N/A
21 N/A N/A N/A
22 3 3 5 educate trades that are not familiar with 4
23 5 5 5
24 N/A N/A N/A
25 4 3 4
26 3 3 3
27 4 2 1
28 4 2 3
29 3 3 3
30 5 5 5
31 2 3 4
32 N/A N/A N/A
33 2 2 3 no
34 N/A N/A N/A
35 N/A N/A N/A
36 3 3 1 No
37 3 3 4
38 3 1 2 Does all subcontractors use 4D? In Colo
39 1 1 3 flexibility in changing WBS as job progre
40 N/A N/A N/A
112
Question 21 Question 22 Question 23 Question 24
What aspects of construction scheduling What aspects of 4D BIM need
What is your vision regarding What is the type of business that best
Response No scheduling and project progress tracking
need improvement? improvement? in construction operations? describes your company's work?
1 BIM-based formulation 3D / scheduling coordination Academic / research
2 Functionality, Portability, Trade coordina 3D / scheduling coordination, Visualizati Really helpful during preconstruction, ha General contractor
3 Accessibility, Portability Accessibility, Interoperability Easy to access, to update and to share. General contractor
4 Software interoperability, BIM-based for 3D / scheduling coordination, Functional BIM can develop an ideal schedule General contractor
5 Accessibility, Functionality, Trade coordi 3D / scheduling coordination General contractor
6 Sequencing, BIM-based formulation, Fun Tasks linkage procedure, Interface with r Industry needs a standard to measure the Construction Management Agency
7 Software interoperability, BIM-based for Introducing the use of 4D BIM in the firs If software is easy to use, implement, and Program Management / Project Managem
8Software interoperability, Sequencing, BI Tasks linkage procedure, 3D / scheduling coordination, Interoperability, Complexit General contractor
9 Accessibility, Functionality Accessibility Consultant
10 Accessibility, Trade coordination N/A Construction Management Agency
11 Sequencing, Portability, Trade coordinati have never used General contractor
12 N/A not a scheduler so I do not know the N/A not a scheduler so I do not know the issues. General contractor
13 Functionality Accessibility, Complexity useful to a large extent, reaches limits du Design firm
14 Sequencing, Accessibility, Trade coordin Tasks linkage procedure, Functionality Using excel based short term schedules is General contractor
15 Software interoperability, Accessibility, F Interface with reality capture, Functionality General contractor
16 Software interoperability Complexity Construction Management Agency
17 Trade coordination 3D / scheduling coordination General contractor
18 Trade coordination Functionality General contractor
19 Software interoperability, Portability, Tra Complexity Construction Management Agency
20 Accessibility, Functionality, Portability, T N/A General contractor
21 Software interoperability, Accessibility, T Interface with reality capture, 3D / scheduling coordination, Interoperability, Comp General contractor
22 BIM-based formulation, Accessibility, Fu Tasks linkage procedure, 3D / scheduling software packages should be able to creat Subcontractor
23 Software interoperability, Functionality Functionality Public agency
24 Software interoperability I would need to better understand how 4DBIM could be utilized in residential cons Single and Multi-family Homebuilding/D
25 Software interoperability, BIM-based for Tasks linkage procedure, 3D / scheduling coordination, Visualization, Interoperabi General contractor
26 Sequencing Complexity General contractor
27 Software interoperability, Portability Tasks linkage procedure, Interface with r Scheduling and project progress tracking Technology/Construction
28 BIM-based formulation Tasks linkage procedure, Interface with reality capture, Use in TI scope General contractor
29 Software interoperability, Trade coordina Tasks linkage procedure, 3D / scheduling coordination, Functionality General contractor
30 Software interoperability, BIM-based for 3D / scheduling coordination, Visualization, Accessibility, Complexity DESIGN/BUILD HOMEBUILDER
31 Sequencing, BIM-based formulation, Tra Tasks linkage procedure, 3D / scheduling coordination, Complexity General contractor
32 Software interoperability, Portability Interface with reality capture, 3D / sched It should be done easily. People in constr Consultant
33 Accessibility Tasks linkage procedure, Interface with r Getting granular with activity metrics and General contractor
34 Software interoperability, BIM-based for Accessibility, Functionality General contractor
35 Software interoperability, Sequencing, BI Tasks linkage procedure, Interface with reality capture, 3D / scheduling coordinatio General contractor
36 Software interoperability, Sequencing, BI Visualization, Accessibility, Complexity They should all be connected in a more s General contractor
37 Software interoperability, BIM-based for Tasks linkage procedure, 3D / scheduling coordination Integrated Architecture/Design/Construct
38 Sequencing, Trade coordination Tasks linkage procedure 4D is extremely useful if all trades and su General contractor 39 Sequencing, Accessibility, Trade coordin Accessibility, bandwidth relates to access The more accuracy that can be shown wi Ge neral contractor 40 Accessibility, Trade coordination Accessibility updating completed tasks thru 4D BIM w Subcontractor
113
Question 25 Question 26 Question 27 Question 28
What type of industry does your What is your primary professional What best describes your job's role in How many years of experience do you
Response No have working in this position? (use only
company mainly focus operations in? background? your organization?
numbers)
1 Building Engineer Research 4
2 Building Engineer Construction Manager 4
3 Buildings, Heavy industrial, Heavy civil / Civil Engineer Project Engineer 8
4 Buildings Civil Engineer Project Engineer 2
5 Heavy civil / infrastructure Civil Engineer Project Engineer 3
6 Buildings Civil Engineer Project Engineer 1
7 Buildings, Heavy civil / infrastructure, A Civil Engineer Scheduler / Project Controls 6
8 Heavy industrial, Heavy civil / infrastruct Civil Engineer Project Manager 11
9 Heavy civil / infrastructure Civil Engineer Project Manager 5
10 Government facilities, Transportation Civil Engineer Project Manager 8
11 Buildings, Heavy industrial, Heavy civil / Civil Engineer Project Manager 4
12 Buildings, Commercial Civil Engineer Project Manager 3
13 Buildings, Government facilities, Engine Civil Engineer Project Manager 2
14 Heavy industrial, Heavy civil / infrastruct Civil Engineer Project Engineer 2
15 Buildings, Commercial Civil Engineer Owner 4
16 Heavy civil / infrastructure, Railroad Civil Engineer Project Engineer 1
17 Buildings, Mechanical / Electrical / Plum Civil Engineer Project Scheduler 1
18 Buildings, Heavy industrial, Heavy civil / Civil Engineer Superintendent 1
19 Buildings Civil Engineer Project Manager 10
20 Buildings, Facilities restauration / renova Civil Engineer Project Manager 6
21 Buildings, Commercial, Government faci Civil Engineer Project Manager 3
22 Buildings, Commercial, Facilities restaur Civil Engineer Project Manager 5
23 Heavy civil / infrastructure, Railroad, Go Civil Engineer Project Manager 10
24 Buildings, Subdivisions Civil Engineer President/Executive 20
25 Buildings Civil Engineer Executive Vice President, Construction 1
26 Commercial Civil Engineer Project Engineer 2
27 Buildings, Timber, Commercial, Facilitie Civil Engineer New Build R&D and Analyst 1
28 Buildings, Commercial, Government faci Architect VDC Engineer 3.5
29 Buildings Civil Engineer Project Manager 4
30 Buildings, Facilities restauration / renova Architect VDC Manager 2
31 Buildings, Heavy industrial, Heavy civil / Civil Engineer Project Manager 5
32 Buildings Civil Engineer Owner 1
33 Buildings, Commercial Civil Engineer Project Manager 14
34 Buildings Civil Engineer Site Engineer 2
35 Commercial Civil Engineer Project Manager 1
36 Buildings, Commercial, Facilities restaur Civil Engineer Project Engineer 2
37 Buildings, Heavy civil / infrastructure, M Civil Engineer VDC Engineer 0.5
38 Buildings, Commercial Civil Engineer VDC Manager 3 39 Buildings, Heavy industrial, Mechanical Architect VDC Manager 33 40 Buildings Civil Engineer General Manager 17
114
top related