The accreditation of the largest infrastructural project in Netherlands, the MV2 project, with the PRINCE2 Maturity
Model
Drs. R. Moret
Copyright Expecto 2005 2
Content• Introduction
• Background of the MV2 project
• Implementing the PRINCE2 methodology Unfreeze-Change-Freeze
• The PRINCE2 accreditation
• The assessment process
• The results
• Feedback and evaluation
Copyright Expecto 2005 3
Port of Rotterdam, 2005
Harbour area: 10,500 ha Direct employment: 60,000Rented: 4,500 ha Total employment: 315,000Shipments 300 mln tonnes Share GNP: 1.5%
Copyright Expecto 2005 4
Port of Rotterdam N.V.
CEO
CCO CFO COO HarbourMaster
Project-directorMV2
StafdirectorHRM
InternalAccountants
Service
Corporate Affairs
(AJBZ, CS, CC)
= Directors Board of the Harbourcompany
Copyright Expecto 2005 5
Project Mainport development Rotterdam
750 ha Nature and
Recreation area
Social and
Infrastructure projects
CompensationLand reclamation
Beach BrouwersdamMarine reserve
Dunes Delfland
Maasvlakte 2
Copyright Expecto 2005 6
The Project Maasvlakte 2
With Maasvlakte 2,
Rotterdam is creating a new, advanced top location at the heart of the European market. The new port and industrial area will comprise 1000 hectares net of industrial sites
Copyright Expecto 2005 7
PMV2: organisation and advisory structure
Projectdirectie
Omgeving & CommunicatieProjectbureau
ConditiesExploitatie & Inrichting Realisatie
Tenderboard i.o.
Adviesgroep duurzame
ontwikkeling
Gebruikers -klankbord
AvA
RvC
CEO
CCO, CFO, COO
Projectboard
Projectmanagement
Stakeholders & CommunicationProject office
Environmental affairsBusiness Development Port development & Construction
Tenderboard i.o.Tender Board
Adviesgroep duurzame
ontwikkeling
SustainableDevelopment
Advisory Group
Gebruikers -klankbord
User group
advisory body
AvA
RvC
CEO
CCO, CFO, COO
Project Board
Audit/ Advisory Committee
Copyright Expecto 2005 8
Maasvlakte 2
• Characteristics:The entrance to Maasvlakte 2 by the Yangtze harbour of 600 meters wide
• Industrial site 1000 ha– Containers: 600 ha– Distribution: 170 ha– Chemical: 210 ha– Else: 20 ha
• Project cost: 2,9 milliard euro
Copyright Expecto 2005 10
The MV2 project and the environment
• The MV2 project is one of the largest infrastructural projects in the Netherlands
• In the Netherlands a lot of discussion about large infrastructural projects
• The public opinion about large infrastructural projects is negative because of the increasing costs
• The government is watching large infrastructural projects very closely
• The project has the ambition to set a ‘best practice’ for large infrastructural projects
Copyright Expecto 2005 11
Reasons for the MV2 project for using PRINCE2• The project is primarily Business Case driven
• The duration of the project is approximately 10 years, there wasa need for product based planning
• A need for an standard method that is widely accepted in projects
• For the project organisation it was important to have an independent review about directing and controlling the project
Copyright Expecto 2005 12
Unfreeze-Change-Freeze approach• There was a short time frame for introducing PRINCE2 based
working in the project organisation
• There was the need for a project plan (PID) at the end of September 2004
• No time for large trainings programme's and a long implementation stage; the work was already started
• To introduce PRINCE2 in the organisation the Lewin (1951) approach was used
• Main focus: start with PRINCE2 and coaching on the job
Copyright Expecto 2005 14
Approach during the Change Period
• Initiating a Project as a learning stage for the implementation
• Short introduction in the methodology with Quick Reference Card and presentations for the project team
• ‘Learning on the job’, direct coaching during work
• Acceptance of PRINCE2 project based working measured with the projectivity check
• Working to a Project Initiation Document with organisation
Copyright Expecto 2005 15
Tailoring PRINCE2 for the MV2 Organisation• The use of PRINCE2 is tailored for the MV2 project, the use of
the Project Board, the MP process
• The PRINCE2 reports where tailored for the MV2 project
• The most important process is the Business Case developmentProject
Mandate/Project Proposal
Project Brief /
Feasibiltiy StudyPID
Post-ProjectReview Plan
Project Issues End Stage
Report
BusinessCase
Reasons for the Project Outline Business Case Enhanced and approvedBusiness Case
Expected benefits Reviewed Business Case Updated Business Case
Copyright Expecto 2005 16
Aims and objectives of the Accreditation• How PRINCE2 is used in the MV2 project and what is the
maturity level of the project management organisation?
• An independent accreditation of the PRINCE2 maturity level on the Project:
–verified by the APM-Group –based on the OGC’s Project Management Maturity Model as the Standard
• Confirming PRINCE2 is correctly used and that its implementation has been successful?
• Recommendations for further developing the use of PRINCE2 on the Project and increasing the maturity level of the organisation?
Copyright Expecto 2005 17
Method used - The PRINCE2 Maturity Model• Purpose of the PRINCE2 Maturity Model
–To enable organisations to gauge, by assessment, their maturity in the use of PRINCE2–Provides a focus for improvement–Provides verified evidence of maturity
• How the model is used–Determined by PRINCE2 Registered Consultants–Verified independently by the APM Group–Will be offered for Accreditation by UKAS
Copyright Expecto 2005 18
PRINCE2 Maturity model
• Maturity is measured on 16 ‘Key process Area’s
• Four levels– 0 No identified use of PRINCE2– 1 Initial use of PRINCE2– 2 PRINCE2 is used correctly in individual projects in basic
level– 3 PRINCE2 is tailored for the organisation and developed
over al the projects in the organisation
Copyright Expecto 2005 19
PRINCE2 Maturity Model Key Process Area’s• Describes a part of the PRINCE2 method with the minimal
scores per level
• Key process Area’s (16)Project Definition ControlsDirecting a Project Management of RiskInitiating a Project Training in PRINCE2Controlling a Stage/Managing Stage Boundaries Business CaseChange and Configuration Mngt OrganisationClosing a Project Organisational FocusPlans and Planning Tailoring PRINCE2Quality and Quality assurance Integrated Management
Copyright Expecto 2005 20
Assessment process
What is the starting situation and what are omissions?
Interviews, documentation research and review of the daily practice
Analysing, Maturity Level research, follow on recommendations
Report with recommendations Letter of Accreditation
Copyright Expecto 2005 21
Pre Assementscore MV2
Onderdeel Status Datum status
Directing a Project 27-10-04
Initiating a Project 27-10-04
Controlling a Stage 27-10-04
Closing a Project 27-10-04
Business Case 27-10-04
Organisation 27-10-04
Onderdeel Status Datum status
Plans / Planning 27-10-04
Management of Risk 27-10-04
Controls 27-10-04
Quality 27-10-04
Configuration Management and Change Control
27-10-04
Quality Assurance 27-10-04
Project Definition 27-10-04
Status Kleurcode
Volledig ingericht
Ingericht maar nog verbeterpunten
Nog in ontwikkeling
Nog niet voldoende aanwezig
Copyright Expecto 2005 23
Audit group
The following people were audited by the interview questionnaire
Dhr. H. Smits in the role of Business Executive MV2Dhr. R. Paul in the role of Project director MV2Dhr. E. Kemperman in the role of van Head of Project office MV2Dhr. R. van der Plas in the role of Project manager RealisationDhr. T. Vellinga in the role of Project manager ConditionDhr. F. Maasson in the role of Project manager Exploitation Dhr. A. Doe in the role of Project manager Enviroment
and Communication Dhr. T. Stam in the role of Risk ManagerAdd. Dhr. K. Krikke in the role of Senior Planner
Copyright Expecto 2005 24
Review group
The following persons were interviewed for control purposes
Dhr. A. Smit Configuration ManagerDhr. G. Piazza Finance and ControlMw. N. Koolwijk-Claassen Finance and ControlDhr. K. Krikke PlanningDhr. T. Stam Risk ManagerMw. C. Versteegh Direction Secretary
Copyright Expecto 2005 25
The following documentation was formally reviewed (1)Project Management products- Project Initiation Document Customer Approved Version- Team plans Project Approved Version- Plan for the Project office Project Approved Version- Business Case Customer Approved Version- Letter introducing the Project board
Copyright Expecto 2005 26
The following documentation is formally reviewed (2)Planning products- Master planning Customer Approved Version- Product Break down structures Customer Approved Version
- Product Flow Diagram Customer Approved Version- Product Description Project Approved Version
Copyright Expecto 2005 27
The following documentation is formally reviewed (3)Procedures- Procedure Issue Management Project Approved Version- Procedure Quality Review Project Approved Version- Procedure Change Management Project Approved Version- Procedure Configuration Management Project Approved Version
Other plans- Quality Plan Project Approved Version- Risk Management Plan Project Approved Version- Finance and control Process Project Approved Version
Copyright Expecto 2005 28
Assess interviews and documentation review
Interviewlist
Documentationreview
Level 3
Minimal Score values
Level 2 Minimal Scorevalues
Level 1Minimal Score
values
Level 3
Miniimal Score value
Scored valuesLevel 2
on Key Process Area X
Individual scores
Scores from the documentation review
Scoreper Key process
Area(16)
16 Key Process Areas
Scores
Maturity Level XXAll scored on 16 Key process Areas
LowestScoreSet thelevel
Lowest individualscore setsThe level
RccomendationsFor groowwth
Copyright Expecto 2005 29
Findings from the accreditation (1)
Organisational Questions
0
10
20
30
40
50
60
70
80
90
100
Project D
efinition
Initiating aP
roject
Closing aP
roject
Organisation
TailoringP
RIN
CE
2
IntegratedM
anagement
Key proces
Sco
re
Highest scoreLowest ScoreMaturity level 2Maturity level 3
Note: the scores are not the real scores
Copyright Expecto 2005 30
Findings from the accreditation (2)
Project Questions
0
10
20
30
40
50
60
70
80
90
100
Project D
efinition
Initiating aP
roject
Closing aP
roject
Organisation
Controls
Plans and
Planning
TailoringP
RIN
CE
2
IntegratedM
anagement
Key process
Sco
re
Highest ScoreLowest ScoreMaturity level 2Maturity level 3
Note: the scores are not the real scores
Copyright Expecto 2005 31
Recommended Maturity Level
The Project Maasvlakte 2is at
PRINCE2 Maturity Level 2
But note:• The recommendation is based on the current situation of the project• To hold or develop the present Maturity level will require constant focus
on the use of PRINCE2. The whole project team must have a proper knowledge and understanding of PRINCE2
• There needs to be a full commitment that PRINCE2 will be used effectively in the execution phase of the project
Copyright Expecto 2005 32
Summary
The MV2 project has a good level 2 maturity
• A major development in the last three months
• For maintaining the level the recommendations must be followed on
• The project organisation has set up effectively and the use of PRINCE2 is tailored for the project organisation
Copyright Expecto 2005 34
Conclusion
• The use of PRINCE2 gives structure to the processes in the MV2 project
• The accreditation gives confidence to the stakeholders and then public opinion that the project is effectively setup and controlled during initiation
• The accreditation was important to show to the government that the project is controlled during the initiation stage
• The accreditation helped the project organisation to focus on using PRINCE2 effectively in the project