DSA Inspectors

Arcadia USD

Arcadia HSCampus Enrichment

Inspection ReportMar 2014

ArchitectLPA Architect

DSA Application No. A03-111889

33 Narcissa Drive, Rancho Palos Verdes, CA 90275 | (626) 786-4331 | Info@KnowlandInc.com

Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA

This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA.

PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2)

STATUS OF CONSTRUCTION WORK:

Bldg B Electrical and plumbing rough in has begun

Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing

Bldg K (Gym) - Storefront windows have been installed(Notice of non-compliance issued for not having

deferred approval prior to install)

Bldg U UG Electrical has begun, framing of the soffits is ongoing

Site-work site utilities are ongoing, Main walkway canopy north half is complete

OUTSTANDING DEVIATION NOTICES: (List “Notice Numbers” used on forms DSA 154.)

Notice issued for storefront window system being installed without approval from DSA on the deferred approval

RESOLVED DEVIATION NOTICES: (List the “Notice Numbers” used on forms DSA 154.)

None.

School District/Owner: Arcadia Unified School District DSA File #: 19 - H32

Project Name/School: Arcadia High School – Campus Enrichment DSA App. #: 03 - 111889

From: Building #(s)

(As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site)

Kenneth Burr

DSA Project Inspector Certification #: Cert 5654, Class 1

Report #: 41 Page 1 of 2 Date of Report: 3/17/2014 DSA 152 Card #(s):

N/A

(List above all building numbers and inspection card numbers for which this report applies.)

REPORTING PERIOD DATES

From: 3/1/14 To: 3/15/14

Construction project is estimated to be 73 % complete at this time.

DSA 155

PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13

Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA

Report #: 41 Page 2 of 2 Date of Report: 3/17/2014 DSA App. #: 03 - 111889

PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1)

QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.)

None

PROBLEMS OR NON-COMPLYING CONDITIONS:

(List any problems or non-complying conditions and how they were resolved.)

[1] All Addenda are approved

[2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13.

INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.)

None.

OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.) .

Weekly Owner/Architect/Contractor meetings. Owner’s Rep and Architect in attendance.

Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project:

DSA OAKLAND

oakfielddoc@dgs.ca.gov

DSA SACRAMENTO

sacfielddoc@dgs.ca.gov

DSA LOS ANGELES

lafielddoc@dgs.ca.gov

DSA SAN DIEGO

sdfielddoc@dgs.ca.gov

Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA

This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA.

PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2)

STATUS OF CONSTRUCTION WORK:

Bldg B Electrical and plumbing rough in has begun

Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing

Bldg K (Gym) - Storefront windows have been installed(Notice of non-compliance issued for not having

deferred approval prior to install)

Bldg U UG Electrical has begun, framing of the soffits is ongoing

Site-work site utilities are ongoing, Main walkway canopy north half is complete

OUTSTANDING DEVIATION NOTICES: (List “Notice Numbers” used on forms DSA 154.)

Notice issued for storefront window system being installed without approval from DSA on the deferred approval

RESOLVED DEVIATION NOTICES: (List the “Notice Numbers” used on forms DSA 154.)

None.

School District/Owner: Arcadia Unified School District DSA File #: 19 - H32

Project Name/School: Arcadia High School – Campus Enrichment DSA App. #: 03 - 111889

From: Building #(s)

(As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site)

Kenneth Burr

DSA Project Inspector Certification #: Cert 5654, Class 1

Report #: 42 Page 1 of 2 Date of Report: 4/1/2014 DSA 152 Card #(s):

N/A

(List above all building numbers and inspection card numbers for which this report applies.)

REPORTING PERIOD DATES

From: 3/15/14 To: 3/31/14

Construction project is estimated to be 75 % complete at this time.

DSA 155

PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13

Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA

Report #: 42 Page 2 of 2 Date of Report: 4/1/2014 DSA App. #: 03 - 111889

PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1)

QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.)

None

PROBLEMS OR NON-COMPLYING CONDITIONS:

(List any problems or non-complying conditions and how they were resolved.)

[1] All Addenda are approved

[2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13.

INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.)

None.

OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.) .

Weekly Owner/Architect/Contractor meetings. Owner’s Rep and Architect in attendance.

Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project:

DSA OAKLAND

oakfielddoc@dgs.ca.gov

DSA SACRAMENTO

sacfielddoc@dgs.ca.gov

DSA LOS ANGELES

lafielddoc@dgs.ca.gov

DSA SAN DIEGO

sdfielddoc@dgs.ca.gov

Week ofWeek of March 07, 2014

Top right Area drain connection to storm drainnTop left Roof joist cut during a previous upgrade in need of repairBottom right trenching for waste line in building U restroomsBottom left old swamp coolers discovered during demo in the caferteria

Arcadia High SchoolWeek of March 14, 2014

Top Right Storm drain south of building BTop Left Concrete walkway removed at the libraryBottom Right Concrete placement in B for shear wallBottom Left Grounding at building B doghouse

Arcadia High SchoolWeek of March 21, 2014

Top Right Ceiling demo in the cafeteriaTop Left waste lines roughed in at library restroomsBottom right Rebar and concrete placement at covered walkwayBottom Left Termite damage at column in the caferteria

Arcadia High SchoolWeek of March 28, 2014

Top Right Wall framing in the libraryTop Left Floor boxes roughed inBottom Right Footing for counter supports in the libraryBottom Left restroom in the library waste lines

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/3/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo sawcutting trenches and removing concrete inside of building U and soft demo in the Cafeteria

4 Electrical roughing in conduits in building B and trenching in U for floor boxes

2 Framers framing soffits and wall lay-out

2 Landscapers maintenance of completed phases

3 Plumbing digging trenches for waste in building U

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/4/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo saw cutting trenches and removing concrete inside of building U and soft demo in the Cafeteria

4 Electrical roughing in conduits in building B and trenching in U for floor boxes

2 Framers framing soffits and wall framing

3 Plumbing digging trenches for waste in building U

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/5/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

8 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing

3 Plumbing roughing waste for waste in building U restrooms

3 Utilities installing storm drain under the canopy

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/6/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

7 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing

3 Plumbing roughing waste for waste in building U restrooms

3 Utilities installing storm drain under the canopy and recompacting the trench

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/7/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

5 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing

3 Plumbing roughing waste for waste in building U restrooms

3 Utilities installing storm drain between buildings B and C

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/10/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing

3 Plumbing roughing waste for waste in building U restrooms

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/11/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing and backing in walls at building B

3 Plumbing roughing waste for waste in building U restrooms

2 fencing installing ornamental fencing around the electrical enclosure

3 Graders grading for landscape and curbs at building O

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/12/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing and backing in walls at building B

3 Plumbing roughing waste for waste in building U restrooms

3 Graders grading for landscape and curbs at building O

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/13/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing and backing in walls at building B

3 Plumbing backfilling waste in building U restrooms

2 Concrete saw cutting walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/14/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing the roofing materials at building U and abatement in the Cafeteria

4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

4 Framers framing soffits and wall framing and framing shear wall at building B

3 Concrete saw cutting walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/17/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes

5 Framers framing soffits and wall framing and framing shear wall at building B

3 Concrete demoing walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/18/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in the walls at U

5 Framers framing soffits and walls in building U

3 Concrete demoing walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/19/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in the walls at U

5 Framers framing soffits and walls in building U

3 Concrete demoing walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/20/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in the walls at U

5 Framers framing soffits and walls in building U

3 Concrete demoing walkway at B for demo

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/21/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in the walls at U

5 Framers framing soffits and walls in building U

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

None

Knowland Construction

33 Narcissa Dr. Palos Verdes, CA. 90275

KNOWLAND CONSTRUCTION SERVICES

Daily Report

Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654

Date: 3/24/2014

Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE

8 Demo removing materials from building P cafeteria

8 Electrical roughing in conduits in building B and conduits in the walls at U

5 Framers framing soffits and walls in building U

SPECIAL INSPECTIONS

None DEVIATIONS:

None REMARKS

Walked with Dan Alberico to explain what is being done while he is covering me while im on vacation.

KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107

Campus Enrichment Project Daily Report

Daniel Alberico Phone: none

DSA #4269 Fax: none

Cell: (818) 402-7163

Email: Danielalberico@att.net

March 25, 2014 Overcast, 65

Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32

180 Campus Dr, Arcadia, Ca 91007

Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Murry company Plumbers at the library building hanging roof drains.

RFI-299, CCD-17, CO-0, ASI-1 SPECIAL INSPECTION: none

MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site toady for Ken Burr who is on vacation until April 2, 2014

KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107

Campus Enrichment Project Daily Report

Daniel Alberico Phone: none

DSA #4269 Fax: none

Cell: (818) 402-7163

Email: Danielalberico@att.net

March 26, 2014 clear, 65

Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32

180 Campus Dr, Arcadia, Ca 91007

Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Rebar installers at the slab infill cuts with rebar placement at the bathrooms. 2-Murry company Plumbers at the library building hanging roof drains. SPECIAL INSPECTION: none

MEETINGS: none DEVIATIONS: none REMARKS: none

KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107

Campus Enrichment Project Daily Report

Daniel Alberico Phone: none

DSA #4269 Fax: none

Cell: (818) 402-7163

Email: Danielalberico@att.net

March 27, 2014 clear, 65

Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32

180 Campus Dr, Arcadia, Ca 91007

Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Rebar installers at the slab infill cuts with rebar placement at the bathrooms. 2-Murry company Plumbers at the library building hanging roof drains. SPECIAL INSPECTION: none

MEETINGS: none DEVIATIONS: none REMARKS: IOR Dan Alberico signed off on infill concrete slab rebar with corrections at building U. Sign-off of in wall electrical and framing at building B-OK to insulate.

KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107

Campus Enrichment Project Daily Report

Daniel Alberico Phone: none

DSA #4269 Fax: none

Cell: (818) 402-7163

Email: Danielalberico@att.net

March 28, 2014 Clear, 75

Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32

180 Campus Dr, Arcadia, Ca 91007

Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Murry company Plumbers at the library building on pour watch. (7) Concrete workers on slab slot-cut infill at library. (1) Boom pump operator placing concrete.

SPECIAL INSPECTION: (2) Nino and Moore concrete inspector at batch plant, and on site. MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site tody for Ken Burr who is on vacation until April 2, 2014

KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107

Campus Enrichment Project Daily Report

Daniel Alberico Phone: none

DSA #4269 Fax: none

Cell: (818) 402-7163

Email: Danielalberico@att.net

March 31, 2014 Clear, 75

Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32

180 Campus Dr, Arcadia, Ca 91007

Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at building P on demolition of kitchen walls and investigation of drain lines. 2-Murry company Plumbers at the library building on pour watch.

SPECIAL INSPECTION: (2) Nino and Moore concrete inspector at batch plant, and on site. MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site tody for Ken Burr who is on vacation until April 2, 2014