dsa inspectors arcadia usd arcadia hs · 2014. 4. 29. · dsa 155 project inspector semi-monthly...
Post on 16-Oct-2020
2 Views
Preview:
TRANSCRIPT
DSA Inspectors
Arcadia USD
Arcadia HSCampus Enrichment
Inspection ReportMar 2014
ArchitectLPA Architect
DSA Application No. A03-111889
33 Narcissa Drive, Rancho Palos Verdes, CA 90275 | (626) 786-4331 | Info@KnowlandInc.com
Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA.
PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2)
STATUS OF CONSTRUCTION WORK:
Bldg B Electrical and plumbing rough in has begun
Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing
Bldg K (Gym) - Storefront windows have been installed(Notice of non-compliance issued for not having
deferred approval prior to install)
Bldg U UG Electrical has begun, framing of the soffits is ongoing
Site-work site utilities are ongoing, Main walkway canopy north half is complete
OUTSTANDING DEVIATION NOTICES: (List “Notice Numbers” used on forms DSA 154.)
Notice issued for storefront window system being installed without approval from DSA on the deferred approval
RESOLVED DEVIATION NOTICES: (List the “Notice Numbers” used on forms DSA 154.)
None.
School District/Owner: Arcadia Unified School District DSA File #: 19 - H32
Project Name/School: Arcadia High School – Campus Enrichment DSA App. #: 03 - 111889
From: Building #(s)
(As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site)
Kenneth Burr
DSA Project Inspector Certification #: Cert 5654, Class 1
Report #: 41 Page 1 of 2 Date of Report: 3/17/2014 DSA 152 Card #(s):
N/A
(List above all building numbers and inspection card numbers for which this report applies.)
REPORTING PERIOD DATES
From: 3/1/14 To: 3/15/14
Construction project is estimated to be 73 % complete at this time.
DSA 155
PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13
Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
Report #: 41 Page 2 of 2 Date of Report: 3/17/2014 DSA App. #: 03 - 111889
PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1)
QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.)
None
PROBLEMS OR NON-COMPLYING CONDITIONS:
(List any problems or non-complying conditions and how they were resolved.)
[1] All Addenda are approved
[2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13.
INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.)
None.
OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.) .
Weekly Owner/Architect/Contractor meetings. Owner’s Rep and Architect in attendance.
Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project:
DSA OAKLAND
oakfielddoc@dgs.ca.gov
DSA SACRAMENTO
sacfielddoc@dgs.ca.gov
DSA LOS ANGELES
lafielddoc@dgs.ca.gov
DSA SAN DIEGO
sdfielddoc@dgs.ca.gov
Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA.
PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2)
STATUS OF CONSTRUCTION WORK:
Bldg B Electrical and plumbing rough in has begun
Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing
Bldg K (Gym) - Storefront windows have been installed(Notice of non-compliance issued for not having
deferred approval prior to install)
Bldg U UG Electrical has begun, framing of the soffits is ongoing
Site-work site utilities are ongoing, Main walkway canopy north half is complete
OUTSTANDING DEVIATION NOTICES: (List “Notice Numbers” used on forms DSA 154.)
Notice issued for storefront window system being installed without approval from DSA on the deferred approval
RESOLVED DEVIATION NOTICES: (List the “Notice Numbers” used on forms DSA 154.)
None.
School District/Owner: Arcadia Unified School District DSA File #: 19 - H32
Project Name/School: Arcadia High School – Campus Enrichment DSA App. #: 03 - 111889
From: Building #(s)
(As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site)
Kenneth Burr
DSA Project Inspector Certification #: Cert 5654, Class 1
Report #: 42 Page 1 of 2 Date of Report: 4/1/2014 DSA 152 Card #(s):
N/A
(List above all building numbers and inspection card numbers for which this report applies.)
REPORTING PERIOD DATES
From: 3/15/14 To: 3/31/14
Construction project is estimated to be 75 % complete at this time.
DSA 155
PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13
Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
Report #: 42 Page 2 of 2 Date of Report: 4/1/2014 DSA App. #: 03 - 111889
PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1)
QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.)
None
PROBLEMS OR NON-COMPLYING CONDITIONS:
(List any problems or non-complying conditions and how they were resolved.)
[1] All Addenda are approved
[2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13.
INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.)
None.
OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.) .
Weekly Owner/Architect/Contractor meetings. Owner’s Rep and Architect in attendance.
Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project:
DSA OAKLAND
oakfielddoc@dgs.ca.gov
DSA SACRAMENTO
sacfielddoc@dgs.ca.gov
DSA LOS ANGELES
lafielddoc@dgs.ca.gov
DSA SAN DIEGO
sdfielddoc@dgs.ca.gov
Week ofWeek of March 07, 2014
Top right Area drain connection to storm drainnTop left Roof joist cut during a previous upgrade in need of repairBottom right trenching for waste line in building U restroomsBottom left old swamp coolers discovered during demo in the caferteria
Arcadia High SchoolWeek of March 14, 2014
Top Right Storm drain south of building BTop Left Concrete walkway removed at the libraryBottom Right Concrete placement in B for shear wallBottom Left Grounding at building B doghouse
Arcadia High SchoolWeek of March 21, 2014
Top Right Ceiling demo in the cafeteriaTop Left waste lines roughed in at library restroomsBottom right Rebar and concrete placement at covered walkwayBottom Left Termite damage at column in the caferteria
Arcadia High SchoolWeek of March 28, 2014
Top Right Wall framing in the libraryTop Left Floor boxes roughed inBottom Right Footing for counter supports in the libraryBottom Left restroom in the library waste lines
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/3/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo sawcutting trenches and removing concrete inside of building U and soft demo in the Cafeteria
4 Electrical roughing in conduits in building B and trenching in U for floor boxes
2 Framers framing soffits and wall lay-out
2 Landscapers maintenance of completed phases
3 Plumbing digging trenches for waste in building U
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/4/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo saw cutting trenches and removing concrete inside of building U and soft demo in the Cafeteria
4 Electrical roughing in conduits in building B and trenching in U for floor boxes
2 Framers framing soffits and wall framing
3 Plumbing digging trenches for waste in building U
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/5/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
8 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing
3 Plumbing roughing waste for waste in building U restrooms
3 Utilities installing storm drain under the canopy
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/6/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
7 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing
3 Plumbing roughing waste for waste in building U restrooms
3 Utilities installing storm drain under the canopy and recompacting the trench
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/7/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
5 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing
3 Plumbing roughing waste for waste in building U restrooms
3 Utilities installing storm drain between buildings B and C
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/10/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing
3 Plumbing roughing waste for waste in building U restrooms
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/11/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing and backing in walls at building B
3 Plumbing roughing waste for waste in building U restrooms
2 fencing installing ornamental fencing around the electrical enclosure
3 Graders grading for landscape and curbs at building O
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/12/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing and backing in walls at building B
3 Plumbing roughing waste for waste in building U restrooms
3 Graders grading for landscape and curbs at building O
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/13/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing and backing in walls at building B
3 Plumbing backfilling waste in building U restrooms
2 Concrete saw cutting walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/14/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing the roofing materials at building U and abatement in the Cafeteria
4 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
4 Framers framing soffits and wall framing and framing shear wall at building B
3 Concrete saw cutting walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/17/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in trenches at U for floor boxes
5 Framers framing soffits and wall framing and framing shear wall at building B
3 Concrete demoing walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/18/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in the walls at U
5 Framers framing soffits and walls in building U
3 Concrete demoing walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/19/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in the walls at U
5 Framers framing soffits and walls in building U
3 Concrete demoing walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/20/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in the walls at U
5 Framers framing soffits and walls in building U
3 Concrete demoing walkway at B for demo
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/21/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in the walls at U
5 Framers framing soffits and walls in building U
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
None
Knowland Construction
33 Narcissa Dr. Palos Verdes, CA. 90275
KNOWLAND CONSTRUCTION SERVICES
Daily Report
Kenneth Burr Phone: (951) 258-5174 DSA Project Inspector Email: ken.burr@sbcglobal.net Class 1 #5654
Date: 3/24/2014
Project: Arcadia High School Arcadia USD Campus Enrichment A03-111889 Architect: LPA Architects Testing Laboratory: Ninyo and Moore General Contractor: McCarthy WORK COMPLETE
8 Demo removing materials from building P cafeteria
8 Electrical roughing in conduits in building B and conduits in the walls at U
5 Framers framing soffits and walls in building U
SPECIAL INSPECTIONS
None DEVIATIONS:
None REMARKS
Walked with Dan Alberico to explain what is being done while he is covering me while im on vacation.
KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daily Report
Daniel Alberico Phone: none
DSA #4269 Fax: none
Cell: (818) 402-7163
Email: Danielalberico@att.net
March 25, 2014 Overcast, 65
Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32
180 Campus Dr, Arcadia, Ca 91007
Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Murry company Plumbers at the library building hanging roof drains.
RFI-299, CCD-17, CO-0, ASI-1 SPECIAL INSPECTION: none
MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site toady for Ken Burr who is on vacation until April 2, 2014
KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daily Report
Daniel Alberico Phone: none
DSA #4269 Fax: none
Cell: (818) 402-7163
Email: Danielalberico@att.net
March 26, 2014 clear, 65
Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32
180 Campus Dr, Arcadia, Ca 91007
Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Rebar installers at the slab infill cuts with rebar placement at the bathrooms. 2-Murry company Plumbers at the library building hanging roof drains. SPECIAL INSPECTION: none
MEETINGS: none DEVIATIONS: none REMARKS: none
KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daily Report
Daniel Alberico Phone: none
DSA #4269 Fax: none
Cell: (818) 402-7163
Email: Danielalberico@att.net
March 27, 2014 clear, 65
Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32
180 Campus Dr, Arcadia, Ca 91007
Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Rebar installers at the slab infill cuts with rebar placement at the bathrooms. 2-Murry company Plumbers at the library building hanging roof drains. SPECIAL INSPECTION: none
MEETINGS: none DEVIATIONS: none REMARKS: IOR Dan Alberico signed off on infill concrete slab rebar with corrections at building U. Sign-off of in wall electrical and framing at building B-OK to insulate.
KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daily Report
Daniel Alberico Phone: none
DSA #4269 Fax: none
Cell: (818) 402-7163
Email: Danielalberico@att.net
March 28, 2014 Clear, 75
Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32
180 Campus Dr, Arcadia, Ca 91007
Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at the snack bar building 2-Murry company Plumbers at the library building on pour watch. (7) Concrete workers on slab slot-cut infill at library. (1) Boom pump operator placing concrete.
SPECIAL INSPECTION: (2) Nino and Moore concrete inspector at batch plant, and on site. MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site tody for Ken Burr who is on vacation until April 2, 2014
KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daily Report
Daniel Alberico Phone: none
DSA #4269 Fax: none
Cell: (818) 402-7163
Email: Danielalberico@att.net
March 31, 2014 Clear, 75
Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32
180 Campus Dr, Arcadia, Ca 91007
Architect: LPA Architects Construction Manager: McCarthy Building Companies Testing Laboratory: Nino and Moore General Contractor: McCarthy Building Companies WORK COMPLETED: 7-Carpenters on framing crew at the library. 2- Miller Demolition workers at building P on demolition of kitchen walls and investigation of drain lines. 2-Murry company Plumbers at the library building on pour watch.
SPECIAL INSPECTION: (2) Nino and Moore concrete inspector at batch plant, and on site. MEETINGS: none DEVIATIONS: none REMARKS: IOR Daniel Alberico on site tody for Ken Burr who is on vacation until April 2, 2014