e032004012gnv orange county solid waste management facility southern expansion site project
Post on 17-Jan-2016
216 Views
Preview:
TRANSCRIPT
E032004012GNV
Orange CountySolid Waste
Management Facility
Southern Expansion Site Project
E032004012GNV
Cell 9 65
acres
Cell 10 64
acres
Cell 11 77 acres
Cell 12 82 acres
Wet BorrowPit No.2
Wet BorrowPit No.1
Pond #8
Pond #6
Pond #5
Pond #7
Pond #9
Pond #10
New Access Road &
Entrance Area
Wetland Conservation Area (1592 Acres)Upland Conservation Area (447 Acres)
Permanently Impacted Wetlands (39.4 Acres)
Total Acreage - 288Total Capacity - 31.4 Million Cubic Yards
Permitted Site Plan
Permitted Site Plan
Cells 9 through 12 Will Provide County With 20 to 25 Years of Class I Disposal Capacity
Young Pine RoadN
E032004012GNV
AccessRoad
Cell 9 Site Plan
Cell 9 Site Plan
Cell 9
Employee Quarters
andOffice
ScaleHouse
TrailerStaging
Area
General Maintenance Building
TireRepairShop
PondNo. 5
OptionalBorrowArea
PondNo.6
Leachate
Storage
Tanks
N
AerialView
PointingSouth
E032004012GNV
April 17, 2003
E032004012GNV
July 24, 2003
E032004012GNV
Sept. 18, 2003
E032004012GNV
Oct. 24, 2003
E032004012GNV
Dec. 16, 2003
E032004012GNV
Feb. 19, 2004
E032004012GNV
Projected Schedule Projected Schedule
Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
2002 2003 2004 2005 2006TASK
BOC Action on Hubbard Contact
Contact Date
Final Environmental Permits Issued
Gopher Tortoise Re-location
Official Notice to Proceed
Phase 1 Substantial Completion (Cell 9 Operational)
Phase 2 Substantial Completion (Overall Site)
Final Completion
Prepare Partial Cert. of Construction Completion Report
FDEP Partial Cert. of Construction Completion
Prepare Final Cert. of Construction Completion Report
FDEP Final Cert. of Construction Completion Report
Floor Cell 9
Anticipated Fill Cell 7B/8
KEY:Milestone
Progress
Task
External Task
E032004012GNV
SummarySummary A New Scale House Will Be Used to Control
Access to Cells 9-12
Continue Using Existing Scale House for Activities on Existing 1,500-acre site
Start-Up of Cell 9 Will Require Concurrent
Operations in Cell 9, and Cell 7B/8
During the Filling of the Class I Cells 9-12, the Following Activities Will Remain At the 1,500-acre site
Class III Landfill
HHW Facility
Recycling Facility
Yard Waste Composting
Waste Tire Storage
Small Vehicle Drop-off
E032004012GNV
SummarySummary
Construction of Cell 9 is Proceeding on Time and on Budget
Changes to date result in slight decrease in contract
amount Contract Time has been increased 9 days because of
inclement weather
Construction Progress is approximately one month ahead
of schedule