earned value management earned value management system ... · 11/28/2018 · the purpose of this...
Post on 10-Jun-2020
0 Views
Preview:
TRANSCRIPT
-
What is EFCOG?
EFCOG does not: Engage in lobbying, Duplicate efforts of other groups, Exchange contractual, financial, or legal information, Take independent positions on DOE
policy, Require standardization of member positions; EFCOG does: Promote safe work practices, Promote, coordinate, and facilitate performance improvement
exchanges among DOE contractors, Establish and maintain effective networks for addressing key DOE complex-wide issues, Sponsor working groups and workshops to
ex-change management and technical information, Seek to reduce costs and improve efficiency, Establish liaisons with other organizations to minimize duplication of
efforts, Interface with DOE to ensure that EFCOG’s mission remains in alignment with DOE objectives, Recommend productivity enhancements
Earned Value Management Earned Value Management Earned Value Management Earned Value Management System System System System
Best PracticeBest PracticeBest PracticeBest Practice (EVMSBP)(EVMSBP)(EVMSBP)(EVMSBP)
BACKGROUND:
Within the Department of Energy (DOE) Office of Project Management (PM) and EFCOG earned value management
system (EVMS) arena there has been significant energy and resource spent to right size earned value implementation
guidance for its users and overseers regarding initial and ongoing compliance with the industry’s EVMS standard EIA-
748. While the collaborative PM/EFCOG effort experienced expansion and contraction, most agree the current guidance
represented by this Best Practice strikes a balance between ideal and sustainable compliance implementation.
This best practice guidance incorporates knowledge from the notable key documents identified below:
• DOE O 413.3B Program and Project Management for the Acquisition of Capital Assets
• EIA-748-C Earned Value Management Systems
• NDIA IPMD EVMS Intent Guide
• NDIA IPMD IBR Guide
• NDIA IPMD Surveillance Guide
• NDIA IPMD EVMS Acceptance Guide
• NDIA IPMD EVMS Application Guide
• NDIA IPMD Planning and Scheduling Excellence Guide (PASEG)
• NDIA IPMD EVMS Guideline Scalability Guide
• GAO-16-89G – Schedule Assessment Guide
• GAO-09-3SP – GAO Cost Estimating and Assessment Guide
PURPOSE:
The purpose of this EFCOG Best Practice is to assist earned value professionals with the implementation, operation, and
self-governance of their earned value management system or needs. The guidance contained in this document can be
used in its full depth and breadth, piecemeal as needed, or completely ignored, at the sole discretion of the user. EFCOG
encourages its member companies to customize this guidance information to fit their specific needs. There is no explicit
or implicit EFCOG authority requiring the use of this best practice, other than within PM for its compliance reviews
(consistent with the DOE-PM-SOP-04-2018 statement, “RELEASABILITY. LIMITED. This SOP is approved for internal use
only”).
Constructive comments or recommended improvements to the narrative or compliance tests are always welcome and
should be submitted to Tony Spillman, Project Controls Vice-Chair/Earned Value Task Team Leader, via email at
Anthony_W_Spillman@rl.gov.
This document will reside on the EFCOG Webpage at http://efcog.org/project-delivery/project-controls-
subgroup/earned-value-management-task-team/
-
Office of Project Management (PM)
Earned Value Management Systems
Compliance Review
Standard Operating Procedure
(ECRSOP)
Issued by
Office of Project Management (PM)
Project Controls Division
DOE-PM-SOP-04-2018
November 28, 2018
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
ii
1. PURPOSE. The White House Office of Management and Budget (OMB) requires federal agencies to implement an Earned Value Management System (EVMS) compliant with the Electronic Industries
Alliance Standard 748 (EIA-748), current version or other as required by contract, on major capital
acquisitions due to their importance to the agency mission. The Department of Energy (DOE)
implements this requirement through DOE O 413.3B, Program and Project Management for the
Acquisition of Capital Assets, which requires the Office of Project Management (PM) to establish,
maintain and execute a documented EVMS compliance assessment process. This Office of Project
Management (PM) EVMS Compliance Review Standard Operating Procedure (ECRSOP) serves as a
primary reference for PM’s determination of compliance. This Standard Operating Procedure (SOP)
provides guidance for PM staff and PM support contractors performing EVMS compliance reviews in
accordance with established thresholds in DOE O 413.3B to ensure full compliance with Federal
Acquisition Regulations (FAR) and OMB compliance requirements. Utilization of this SOP by PM
staff and support contractors will ensure consistent assessment of compliance and evaluation of the
implementation of a contractor’s EVMS while minimizing the need and duration for onsite reviews.
2. APPLICABILITY. This SOP applies only to PM personnel and PM-led or initiated review teams responsible for the determination of EVMS compliance of applicable projects and contractors subject
to DOE O 413.3B.
3. RELEASABILITY. LIMITED. This SOP is approved for internal use only.
4. SUPERSEDES. This SOP supersedes the ECRSOP dated September 11, 2018.
5. EFFECTIVE DATE. This SOP is effective immediately.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
iii
TABLE OF CONTENTS
1. POLICY AND AUTHORITY ......................................................................................................... 6
1.1 Federal Regulations ..................................................................................................................... 6
1.2 DOE O 413.3B EVMS Compliance Requirements ...................................................................... 6
1.2.1 EVMS Credentialing ................................................................................................................ 6
1.2.2 EVMS Certification Thresholds ............................................................................................... 7
1.2.3 EVMS Surveillance Thresholds ............................................................................................... 7
1.2.4 Integrating the EVMS Compliance Process with PM Led External Independent Reviews (EIR)
and Independent Cost Estimates (ICE)/Independent Cost Reviews (ICR) ............................................... 7
1.3 EVMS References ....................................................................................................................... 8
2 EVMS COMPLIANCE OVERVIEW ............................................................................................. 9
2.1 Objective ..................................................................................................................................... 9
2.2 Types of EVMS Compliance Review .......................................................................................... 9
2.3 Compliance Assessment Guidance and Tools ............................................................................ 10
2.4 Non-Compliances ...................................................................................................................... 11
2.4.1 Documenting Non-Compliances. ........................................................................................... 11
2.4.2 Material Impact ......................................................................................................................... 12
2.4.3 Documenting CARs/DRs ....................................................................................................... 15
2.5 Continuous Improvement Opportunity (CIO) ............................................................................ 17
3 EVMS COMPLIANCE REVIEW ROLES AND RESPONSIBILITIES ....................................... 18
3.1 Primary EVMS Compliance Review Team Roles ...................................................................... 18
3.1.1 PM-30 Project Controls ......................................................................................................... 18
3.1.2 The EVMS Compliance Review Team................................................................................... 19
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
iv
3.2 Supporting EVMS Compliance Review Team Roles ................................................................. 21
3.2.1 PM-1 Office of Project Management...................................................................................... 21
3.2.2 PM-30 Project Controls ......................................................................................................... 21
3.2.3 PM-20 Project Assessment .................................................................................................... 21
3.2.4 Project Management Support Office (PMSO) ........................................................................ 22
3.2.5 Federal Project Director (FPD) .............................................................................................. 22
3.2.6 Contracting Officer (CO) ....................................................................................................... 22
3.2.7 Contractor .............................................................................................................................. 23
4 EVMS COMPLIANCE PROCESS ............................................................................................... 24
4.1 EVMS Compliance Process Phases and Steps ........................................................................... 24
4.1.1 Need Determination Phase ..................................................................................................... 25
4.1.2 Initial Visit (IV) Phase ........................................................................................................... 27
4.1.3 Data Analysis Phase............................................................................................................... 29
4.1.4 Readiness Assessment (RA) Phase ......................................................................................... 31
4.1.5 On-Site EVMS Preparation Phase .......................................................................................... 33
4.1.6 Post Review and Closeout Phase ............................................................................................ 42
4.2 Changes to Approved EVM System Descriptions and Supporting Procedures ........................... 44
5 EVMS CORRECTIVE ACTION MANAGEMENT PLAN (CAMP) PROCESS .......................... 46
5.1 CAMP Content .......................................................................................................................... 46
APPENDIX A: PM EVMS COMPLIANCE ASSESSMENT GUIDANCE .......................................... 54
APPENDIX B: REFERENCES AND RESOURCES ........................................................................... 55
APPENDIX C: ACRONYM LIST ....................................................................................................... 56
APPENDIX D: PM EVMS COMPLIANCE REVIEW TEAM TOOLKIT ........................................... 60
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
v
APPENDIX E: DEFINITIONS AND SOURCES ................................................................................ 62
APPENDIX F: PM COMPLIANCE REVIEW DATA CALLS ............................................................ 76
LIST OF TABLES
Table 1. EVMS Compliance Process Phases ........................................................................................ 25
Table 2. Need Determination Phase ..................................................................................................... 25
Table 3. Initial Visit Phase ................................................................................................................... 27
Table 4. Data Analysis Phase ............................................................................................................... 29
Table 5. Readiness Assessment Phase .................................................................................................. 31
Table 6. On-Site EVMS Preparation and Review Phase ....................................................................... 33
Table 7. Post Review and Closeout Phase ............................................................................................ 42
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
6
1. POLICY AND AUTHORITY
This Office of Project Management (PM) Earned Value Management System (EVMS)
Compliance Review Standard Operating Procedure (ECRSOP) serves as a primary reference for PM in the determination of EVMS compliance. The purpose of this PM SOP is to provide
standardized and repeatable processes based on a common understanding of EVMS
compliance techniques, methods and practices. All information contained here provides
detailed processes for PM to implement the requirements in DOE Order (O) 413.3B,
consistent with guidance provided in DOE Guide (G) 413.3-10A, Earned Value Management
System. The Electronic Industries Alliance Standard 748, current version or other as required
by contract (EIA-748) establishes 32 EVMS guidelines.
1.1 Federal Regulations The White House Office of Management and Budget (OMB) requires federal agencies to
implement an Earned Value Management System on Capital Acquisitions (Reference (f)).
As defined in the OMB Circular A-11, Part 7, Capital Programming Guide, major acquisitions
are capital assets that require special management attention because of their importance to the
agency mission.
1.2 DOE O 413.3B EVMS Compliance Requirements DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets,
states that prior to Critical Decision (CD)-2, the contractor is responsible to employ and
maintain an EVMS compliant with EIA-748, or as required contractually (DOE O 413.3B,
Appendix A, Section A-11). DOE O 413.3B, Appendix C, Section 8, further defines DOE’s
policy for EVMS compliance relative to project threshold values.
1.2.1 EVMS Credentialing Certification refers to the confirmation of certain characteristics of a contractor’s EVMS. The
EVMS credentialing is the process of obtaining, verifying, and assessing the qualifications of
a contractor to implement an integrated project management methodology and holistic
management and control system for measuring project performance and progress in an
objective manner. Verification of a contractor EVMS ensures the data and information
produced by the management and control system is current, accurate, complete, auditable,
repeatable, and compliant for determining a project’s status. This process tests a contractor’s
EVMS for "compliance" with the guidelines of the EIA-748.
PM will recognize a contractor’s EVMS certification indefinitely so long as the system
remains active at the specified location where the certification applies and continues to meet
the intent of EIA-748 EVMS Guideline criteria and the contractor remains the same.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
7
1.2.2 EVMS Certification Thresholds The certification process assesses the capability of the system to provide an objective measure
of cost and schedule progress and the effective use of the system by the contractor. Elements
of the EVMS (i.e., the design as reflected by policies, procedures, and processes; and the
implementation as reflected by reports and other documents) are evaluated individually and
as a whole to ensure that they meet the intent of EIA-748.
• Project TPC of $100M or greater: Prior to CD-3, PM must conduct an EVMS compliance review to certify that the contractor’s EVMS is compliant with the EIA-
748, or as defined and required by the contract.
• Project TPC below $100M: The Order requires that the contractor employ an EVMS compliant with the EIA-748 prior to CD-2. There is no formal determination or
‘certification’ designation by PM that the contractor’s EVMS is compliant with the
EIA-748. However, on an exception basis, or at the request of the Project
Management Support Office (PMSO), PM may assess EVMS compliance to identify
and document system deficiencies and any areas of non-compliance.
1.2.3 EVMS Surveillance Thresholds The purpose of surveillance is to ensure that a contractor's certified EVMS remains in full compliance with the EIA-748, or as required by the contract, on all applicable projects. EVMS
surveillance may include an assessment against some or all of the 32 EIA-748 EVMS Guidelines.
• Project TPC of $100M or greater: For contracts where there are applicable projects having a TPC of $100M or greater, PM-30 will conduct risk-based, data-driven
surveillance during the performance of the contract, during contract extensions, or as
requested by the Federal Project Director (FPD), the Program, or the Project
Management Executive (PME). The data-driven approach looks to efficiently test the
reliability of core management processes from initial implementation through project
and contract execution thereby reducing the risk of system failure. This approach may
include remotely testing contractor EVMS data, thus eliminating the need and costs
for multiple interviews and assessments. The extent of the EVMS surveillance will
be tailored as appropriate based on current conditions.
• Projects TPC below $100M: PM may, on an exception basis, or at the request of the PMSO, conduct EVMS compliance reviews to identify and document system
deficiencies and any areas of non-compliance.
1.2.4 Integrating the EVMS Compliance Process with PM Led External Independent Reviews (EIR) and Independent Cost Estimates (ICE)/Independent Cost Reviews (ICR)
The evaluation of the efficient implementation of the EVMS as part of other PM-led reviews
(e.g., EIRs, ICEs, and ICRs) is to assess whether the contractor has placed an adequate level
of emphasis on the principles and importance of earned value management. These
assessments are not intended to be a formal EVMS compliance review, but rather a validation
of the executability of the Performance Baseline (PB) and Performance Measurement
Baseline (PMB). It also ensures management strategies are in place emphasizing the full use
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
8
of the EVMS including, but not limited to, thorough upfront planning, scheduling, and
budgeting, change control, risk management, funding requirements, portfolio analysis,
performance-based acquisition management, and stewardship and accountability to achieving
desired outcomes (e.g. performance goals) at specific dates (e.g. time goal) for a specific
amount of resources (e.g. cost goal). System issues found during the course of these
assessments should be documented and further examined following the EVMS compliance
process described in this PM SOP. With regard to EVMS and the PB and PMB, the EIR and
ICE/ICR assessments should determine whether the contractor emphasizes the importance of
Earned Value Management (EVM) as a viable project management methodology to plan and
control work, and to confirm that the contractor has followed its compliant EVM System
Description and associated processes.
1.3 EVMS References This document provides detailed guidance based on recognized leading sources for
establishing, employing, and maintaining a compliant EVMS as referenced in the EIA-748
and DOE O 413.3B, including DOE G 413.3-10A, EVMS Guide, the EIA-748 EVMS
Standard, multiple National Defense and Industry Association (NDIA) Integrated Program
Management Division (IPMD) Guides including the EVMS Intent Guide, EVMS
Surveillance Guide, EVMS Acceptance Guide, EVMS Application Guide, EVMS Scalability
Guide, and the Planning and Scheduling Excellence Guide (PASEG), the Government
Accountability Office (GAO) Cost Estimating & Assessment Guide, and the GAO Schedule
Assessment Guide.
Given that the details contained in these numerous resources have been distilled and
coordinated to reflect a comprehensive and holistic EVMS compliance framework based on
DOE’s project management governance and contracting approaches as well as the type of
work DOE performs and manner in which it is performed, users of this Appendix should be
careful to not take discrete elements or statements in one reference document that may
appear on the surface to be contradictory, out of context to or misconstrued with the whole
of this Appendix. In short, use of singular guidance by itself outside the PM ECRSOP –
Appendix A: Compliance Assessment Guidance (CAG) should not be construed as EVMS
compliant by PM. Thus, this synthesized and uniform approach to evaluate the performance
of a contractor’s EVMS in the manner described herein ensures fairness and consistency of
EVMS compliance proceedings by PM in performance of its responsibilities.
This PM ECRSOP now incorporates applicable elements of the PM EVMS Corrective Action
Standard Operating Procedure (ECASOP) which previously served as a primary reference for
PM to document non-compliances and continuous improvement opportunities issued as part
of the EVMS compliance review process in addition to the assessment, tracking, and closure
of contractor system deficiencies during the corrective action process, hereafter referred to as
the Corrective Action Management Plan (CAMP). As a result, the PM ECASOP has been
cancelled.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
9
2 EVMS COMPLIANCE OVERVIEW
2.1 Objective The primary objective of the PM EVMS compliance process is to determine (1) if descriptive
processes and practices are compliant with the EIA-748, (2) if descriptive documents
containing contractor policies and procedures are used in the actual execution of work, (3)
how performance data and information are generated by the system, (4) how those data and
information are used in the management of the project, and (5) managers’ knowledge of their
EVMS roles and responsibilities. Positive results of the PM EVMS compliance process
ensure the Government can rely on the data produced by the EVMS for the objective
determination of project status. It is important that the PM-30 leadership be an active
participant in the EVMS compliance process to ensure the timeliness of the assessment, the
consistency in the application of required standard operating procedures, including the
interpretation of the 32 EIA-748 EVMS Guidelines and the determination of compliance
considering past precedents. Cost and schedule performance data should be derived from the
same system used to manage the project and determined to satisfy EIA-748 requirements.
2.2 Types of EVMS Compliance Review PM EVMS compliance assessments are conducted on a contractor’s EVMS at various times,
based on contractual requirements, the life cycle of the capital asset project, and/or
implementation concerns. The type of the EVMS compliance review conducted depends on
the situation that initiated the assessment. The four types of EVMS Compliance Reviews are:
• Certification Review (CR). A formal review to determine that a contractor’s EVMS, on all applicable DOE projects, is in full compliance with EIA-748, or as required by
the contract, and in accordance with the applicable contract clause FAR 52.234-4,
Earned Value Management System, or other applicable contract requirement
necessitating the contractor to use an EVMS that has been determined by the
Cognizant Federal Agency (CFA) to be compliant with EIA-748. (Source: DOE O
413.3B and DOE APM Glossary of Terms Handbook, 9/30/2014)
• Implementation Review (IR). A special type of surveillance performed in lieu of a Certification Review when EVMS compliance is required. This type of review
extends the certification of a contractor's previously certified system to another
facility, or from one project to another project after a prolonged period of system non-
use, or from one certifying entity to another when the certified system has been
significantly changed. (Source: DOE O 413.3B and DOE APM Glossary of Terms
Handbook, 9/30/2014)
• Review for Cause (RFC). A review of specific elements of a contractor’s EVMS that have displayed a lack of applied discipline in the actual execution of work or
deemed at risk of no longer meeting the requirements of the EIA-748. This type of
review is used to determine whether a contractor’s EVMS certification should be
withdrawn. (Source: DOE APM Glossary of Terms Handbook, 9/30/2014)
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
10
• Surveillance Review (SR). The process of continuously reviewing a contractor's EVMS on all applicable projects necessitating the use an EVMS that has been
determined to be compliant with EIA-748. (Source: DOE O 413.3B)
2.3 Compliance Assessment Guidance and Tools A uniform approach to evaluate the oversight of a contractor’s EVMS in the manner as
described above helps to safeguard the fairness and transparency of the EVMS compliance
assessment process. Making the correct interpretation of the 32 EIA-748 EVMS Guidelines,
and the determination of compliance considering past precedents can make the difference
between creating an authentic connection to a necessary management principle, or the
implementation of an unwarranted, burdensome, and costly routine.
Appendix A of this PM SOP contains:
• PM Compliance Assessment Guidance o Serves to facilitate the standard definition and consistent application of each of
the 32 EIA-748 EVMS Guidelines.
o Addresses the purpose and management value of each EIA-748 guideline, the impact of noncompliance, attributes, and a discussion of compliance
characteristics.
• PM EVMS Compliance Review Checklist (CRC) o Used to assess a contractor’s descriptive documents containing EVMS policies
and procedures that are used in the actual execution of work. A contractor’s
written policies and processes should be documented in an EVM System
Description and may be further supported by guides and aids that are maintained
under the contractor’s formal configuration control process.
• PM Guideline Attributes and Tests o Used to assess the contractor’s implementation of their EVM System Description.
To the extent possible, tests have been developed with identification of typical
acceptable outcomes and thresholds. Breached thresholds flag potential issues for
evaluation through further analysis, interviews, and/or discussions via automated
tests or manual artifact traces. Specific test thresholds were either based on expert
judgment and collaborated during development and initial utilization of the tests
in a compliance review environment or taken directly from established DoD
precedent. These thresholds will be reassessed on a periodic basis (no less than
yearly) with EFCOG and other DOE stakeholders to reconfirm their relevance and
reliability.
These documents are used at several points in this PM SOP. They are not considered
standalone documents but rather tools to support the Compliance Review.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
11
2.4 Non-Compliances The Compliance Review Team will assess and report EVMS compliance utilizing the six
management areas of the EIA-748 EVMS Guidelines: (1) Organization; (2) Planning,
Scheduling, and Budgeting; (3) Analysis and Management Reports; (4) Revisions and Data
Maintenance; (5) Accounting Considerations; and (6) Indirect Cost Management, by
considering the adequacy of ten core management processes associated with the integrated
project management approach. These include 1. Organizing, 2. Planning and Scheduling, 3.
Budgeting and Work Authorization, 4. Material Management, 5. Subcontract Management,
6. Analysis and Managerial Reporting, 7. Change Control, 8. Accounting Considerations, 9.
Indirect Cost Management, and 10. Risk Management). The determination of EIA-748
compliance for a core management process is accomplished by assessing associated data and
information over a specified time period to determine how well a specified management
process meets a set of capability limits or thresholds. The EVMS Compliance Review Team’s
primary objective in the EVMS compliance process is to formulate a determination of a
contractor’s EVMS compliance by identifying EIA-748 deficiencies through data analysis
and discussions.
The EVMS compliance assessment may determine a contractor’s written EVMS process, the
implementation of the written EVMS process during project execution, or both do not comply
with EIA-748. A process non-compliance exists when the EVM System Description and
supporting procedures do not adequately address EIA-748 compliance requirements. An
EVMS deficiency and implementation non-compliance exists when either a properly
designed process is not operating or being implemented as intended, or the person performing
the process does not possess the necessary authority or qualifications to effectively execute
the process. When a process is insufficiently defined and results in an implementation non-
compliance, the resulting non-compliance determination will address both process and
implementation aspects. The severity of an EVMS non-compliance determination can range
from an inconsequential concern to a material weakness in meeting EIA-748 compliance
requirements.
2.4.1 Documenting Non-Compliances.
The Corrective Action Request (CAR) and Discrepancy Report (DR) are used to document
EIA-748 non-compliances. The use, characteristics, and impact of each type of EIA-748 non-
compliance are listed below:
• Corrective Action Request (CAR) o Used to document material discrepancies. o Characteristics of materiality include high dollar or high-risk impact and/or
recurring and pervasive across control accounts, projects, and/or contracts.
o Impact could significantly influence performance measurement, currency, accuracy, completeness, repeatability, and auditability of the data.
• Discrepancy Report (DRs) o Used to document non-material discrepancies.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
12
o Characteristics include low dollar, minimal risk non-compliances that require minor clarifications to processes, errors or oversights, and non-systemic, isolated,
infrequent, and nonrecurring issues.
o Impact has not significantly influenced performance measurement, but may if left uncorrected.
Appendix A is utilized by PM-30 to assist in the identification of attributes and tests that
substantiate EIA-748 compliance for all 32 EVMS Guidelines. The assessment of an EIA-
748 EVMS Guideline may have multiple CARs and DRs written against it as guidelines often
have multiple attributes being assessed. For example, the assessment of EIA-748 EVMS
Guideline 6 covers several attributes for a complete, realistic, and comprehensive project
schedule. Each attribute has multiple tests. Although multiple draft non-compliances may be
documented citing failed tests, the EVMS Compliance Process/Area Team Lead and Review
Chief, in consultation with the Review Director, will combine the non-compliances into either
a single CAR or DR, per attribute, with all relevant supporting documentation/artifacts
attached. Consequently, the most CARs/DRs possible would then equal the total number of
the attributes (see Appendix A). The nature of the non-compliance and impact(s) are further
explained in the CAR and/or DR. The material impact can then be based on the combination
of non-compliances for a particular attribute.
2.4.2 Material Impact
An assessment of Materiality considers how an EIA-748 non–compliance impacts the ability
of the contractor’s EVMS to produce current, accurate, complete, auditable, repeatable, and
compliant information needed for project management and making decisions. Materiality
addresses both process (the written word) and implementation (the act of doing) deficiencies.
Similar EIA-748 non-compliances may be pervasive yet have a combined minor magnitude
while a single EIA-748 non-compliance can be of high magnitude yet a single occurrence.
When documenting the materiality impact of EVMS non-compliances in the CAR or DR, the
EVMS Compliance Review Team must clearly document the impacts through EVMS data
and information, including instances of cost reporting errors, EAC miscalculations, erroneous
critical path determinations, and inaccurate performance measurement. The EVMS
Compliance Review Team should document each deficiency’s impact to the ability of the
government and contractor to:
• Know the project status in terms of scope, schedule, and budget baseline plan;
• Forecast the project’s schedule and cost;
• Take corrective action to address root cause issues driving scope, schedule, and budget impact and bring project back into alignment with baseline plan; and
• Make informed decisions such as to re-baseline to new budget and/or schedule targets in an Over Target Baseline (OTB) and/or Over Target Schedule (OTS) or changing
scope requirements.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
13
Discrepancies considered systemic or demonstrate a systemic nature based on the frequency
of occurrence or recurrence and pervasiveness across programs, contracts, and/or control
accounts may also support an assessment of material impact. Materiality and systemic
deficiencies are evidenced through EVMS data analyses. Control Account Manager (CAM)
interviews are used as a tool to further explore the potential concern(s) and substantiate any
basis for a CAR and/or DR. Therefore, it is critical that a representative sample from the data
analyses is further investigated to support the pervasiveness of the issue(s). Pervasiveness
and magnitude must be considered and explained by the EVMS Compliance Review Team
as part of developing a CAR and/or DR.
• Pervasiveness Considerations o Is this systemic, across the project, instead of an isolated noncompliance? o Is there a number of similar non-compliances observed? o Do repeat findings from prior reviews indicate pervasiveness? o Are there a percentage of control accounts (CAs), CAMs, or projects that have the
same non-compliances (only effective when all CAs are assessed)?
o Do scheduling metrics, calculated by percentage of Work Packages (WPs) or activities, indicate pervasiveness?
• Magnitude Considerations o What is the impact of data credibility for use in managerial assessment and
decision making
o What is the absolute dollar value impact (including potential impact to annual funding and performance baseline breaches)?
o What is the risk impact associated with the non-compliance (low dollar yet critical item vice high dollar yet non-critical item)?
o What is the magnitude of the impact, which may be calculated as a percentage of dollar value impact of non-compliance to the total PMB; cost or schedule impacts
at an attribute level, or as summed to a GL level; or risk measurement based on
impact of non-compliances to scope, cost, and schedule.
Impact. Material impact is a matter of professional judgment influenced by the perception
of the needs of a reasonable person who relies on the performance measurement reports and
financial statements. Materiality judgments are made in light of surrounding circumstances
and involve both quantitative and qualitative considerations, including the number of
discrepancies observed, the associated absolute dollar value impact, the importance of item(s)
to the accomplishment of contract requirements, and the potential impact on government
funding.
Risk Factors. Risk factors influence the possibility that a deficiency, or a combination of
deficiencies, will result in a misstatement. The factors include, but are not limited to, the
following:
• The nature of the financial or performance measurements, disclosures, and assertions involved;
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
14
• The susceptibility of the related statement to loss or fraud;
• The subjectivity, complexity, or extent of judgment required to determine the amount involved;
• The interaction or relationship of the control with other controls, including whether they are interdependent or redundant;
• The interaction of the deficiencies; and
• The possible future consequences of the deficiency.
Deficiency Evaluation. The evaluation of whether an EIA-748 deficiency presents a
reasonable possibility of a misstatement can be made without quantifying the probability of
occurrence as a specific percentage or range. Multiple EIA-748 deficiencies that affect the
same financial or performance measurement statement account balance or disclosure increase
the likelihood of a misstatement and may in combination constitute a material weakness, even
though such deficiencies may individually be less severe. Therefore, the EVMS Compliance
Review Chief should determine whether individual EIA-748 deficiencies individually or
collectively result in a material weakness. Factors that affect the magnitude of a misstatement
that could result from one or more EIA-748 deficiencies include, but are not limited to, the
following:
• The financial statement amounts or total of transactions exposed to the deficiency; and
• The volume of activity in the account balance or class of transactions exposed to the deficiency that has occurred in the current period or that is expected in future periods.
Impact Evaluation. In evaluating the magnitude of the potential misstatement, the
maximum amount that an account balance or total of transactions can be overstated is
generally the recorded amount, while understatements could be larger. In addition, in many
cases, the probability of a small misstatement will be greater than the probability of a large
misstatement. The EVMS Compliance Review Chief should evaluate the effect of
compensating issues when determining whether an EIA-748 deficiency or combination of
deficiencies is a material weakness. To have a mitigating effect, the compensating issue
should be identified using a level of precision that would prevent or detect a misstatement
that could be material. Indicators of a material weakness in a contractor’s internal control
over performance and financial reporting include:
• Restatement of previously issued financial statements to reflect the correction of a material misstatement;
• Identification by the auditor of a material misstatement of financial statements in the current period in circumstances that indicate that the misstatement would not have
been detected by the company's internal control over financial reporting; and
• Ineffective oversight of the company's external financial reporting and internal control over financial reporting by the company's audit committee.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
15
Severity Evaluation. When evaluating the severity of a deficiency or a combination of
deficiencies, the EVMS Compliance Review Chief should determine the level of detail and
degree of assurance that would satisfy prudent officials in the conduct of their own affairs
and provide reasonable assurance that transactions are recorded as necessary to permit the
preparation of performance measurement and financial statements in conformity with
generally accepted EVMS practices and principles. If however the EVMS Compliance
Review Chief determines that a deficiency or a combination of deficiencies would prevent
prudent officials in the conduct of their official affairs from concluding that they have
reasonable assurance that transactions are recorded as necessary to permit the preparation of
performance measurement or financial statements in conformity with generally accepted
EVMS practices and principles, then the EVMS Compliance Review Chief should treat the
deficiency or combination of deficiencies as a material weakness. The EVMS Compliance
Review Chief should both qualify and quantify the effect and impact that his or her adverse
opinion has on the financial and/or performance measurement statements.
Material Computations. Material deficiencies computed for consideration in the EVMS
compliance process should be limited to only those anomalies/errors as defined by the
attributes and tests that indicate substantiate EIA-748 compliance for all 32 EVMS of the
Guidelines (see Appendix A). The EVMS Compliance Review Chief will identify a
representative sample population of the EIA-748 EVMS guidelines or processes being
evaluated.
2.4.3 Documenting CARs/DRs
After the CAR/DR author makes an initial determination of the materiality of the findings
resulting from the review of the contractor’s EVMS description, data analysis, artifact
traces and/or on-site interviews and chooses a CAR or DR, the author documents the
CAR/DR on the EVMS CAR/DR/CIO Template (Appendix D). The fields, selections,
and narrative guidance is provided:
(1) Review Information The review information includes the following:
• Contractors Name
• Site Office Name
• Contractor’s Location
• Type of Review: Certification, Implementation, Review for Cause, Surveillance
• Dates of Review
• PMSO
• Organization Leading the Review: PM-30
• Process Area: Choose one of the following: Organization, Planning, Scheduling, Budgeting, Accounting Considerations, Analysis and
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
16
Management Reports, Revisions and Data Maintenance, or Indirect
Considerations
• Contractor EVM System Description and Revision Number
• EVM System Description Dated: Date of contactor’s latest revision
• Date of Preparation: Date CAR/DR/CIO was initiated
• Review Director
• Date Sent to Contractor
• Requested Contractor Response Date
(2) CAR/DR/CIO Information
The CAR/DR/CIO Information required includes the following:
• CAR, DR, or CIO: Select one
• CAR/DR Type: Choices include Process, Implementation or Process and Implementation
• Guideline: One guideline per CAR/DR/CIO.
• Subject Title: A short subject title that describes (a) the specific issue of the failure for CARs and DRs, or (b) the nature of the CIO.
• The CAR/DR/CIO Control Number: The control number and the file name are one in the same. The control number is coordinated with the person
responsible for maintaining the CAR/DR/CIO log during the Compliance
Review process, typically the Review Assistant. The control number and file
name convention follow these rules:
• CARs/DRs o Abbreviation of Contractor’s Name, e.g. ZZNL o Month and Year of review (MM/YY) o CAR or DR o Attribute Number o Sequence o Example: ZZNL0818_CAR_6A.1.
• CIOs: The naming convention for a CIO is sequential, e.g. ZZNL0818_CIO01, ZZNL0818_CIO02. (Add a leading zero for the first
nine.)
• System Description: Provide quotations from the contractor’s EVM System Description supporting the non-compliance. This information is mandatory for
CARs and DRs to document and support that the process is noncompliant, or
that the process is correct, however the implementation was faulty. For
process issues, a quote from the contractor’s EVM System Description
containing the non-compliant verbiage for each Attribute affected must be
included as evidence. For implementation issues, a quote will be included
from the EVM System Description describing the process not being properly
implemented, where applicable and/or available, as there may be gaps where
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
17
appropriate guidance is not provided within the contractor process documents.
If the EVM System Description does not address the attribute, then this would
be N/A. This field may or may not be applicable for a CIO.
• Attribute Discussion/Intent: Based on the attribute identified, this information can be found in the EVMS Compliance Assessment Guidance
(Appendix A) and must include exhibit(s) as evidence of the non-compliance
and to support the Review Director/Review Chief’s decision of materiality.
• Findings: Provide a detailed explanation, supported by exhibits. Exhibits are snapshots copied into the CAR/DR/CIO to clearly show the non-compliance
as identified from data analysis, artifact traces, and/or interviews. Exhibits
must provide self-explanatory screenshots of the problem, include a title
describing the exhibit, and an annotation of the area of interest by circles,
arrows, or any other indicator (typically Red in color, Pt. 3 Width) to assure
understanding of the non-compliance.
• Impact: The CAR/DR will contain an impact statement that addresses the affected EVMS guideline. Describe the impact the noncompliance has on the
accuracy, timeliness, and usefulness of the EVMS data for management
purposes. Refer to the EVMS Compliance Assessment Guidance (Appendix
A) for impact language that may be useful in writing this section.
• Prepared by: Include the first initial and last name of the author.
• Date the CAR/DR/CIO was written
• Reviewed by: Include the first initial and last name of the person reviewing the CAR/DR/CIO (usually the Review Director unless delegated to the
Review Chief).
• Reviewed date: Indicate the date the CAR/DR/CIO was approved by the Review Director.
• Out-brief Date: Indicate date of contractor out-brief by Review Director.
2.5 Continuous Improvement Opportunity (CIO) While reviewing a contractor’s EVMS, the EVMS Compliance Review Team may detect
areas for improvement. A listing of CIOs should be generated and used to identify and
document process improvement areas. CIOs share suggested best practices, lessons learned,
or other efficiency or effectiveness measures to streamline EVMS core management
processes. While CIOs do not require a written response from the contractor or approval by
the government review team, dialog is encouraged to share thoughts and plans pertaining to
the recommended suggestions.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
18
3 EVMS COMPLIANCE REVIEW ROLES AND RESPONSIBILITIES
An effective EVMS compliance assessment involves all stakeholders to include PM, PMSO,
FPD, CO, and the contractor, working in an integrated, transparent manner. The roles and
responsibilities of each participant vary based on the type, scope, and length of the review,
team assignments, composition of subject matter experts, and other factors that may arise
during the multi-month process. These must be considered when planning the EVMS
compliance review and forming the team.
Senior leadership sets a “tone from the top,” demonstrating strong support for the importance
of the EVMS compliance process (see page 1, Federal Regulations) to both the Department
and to industry as a mission priority. An important role of the senior leadership is to assist in
promoting a culture of EVMS compliance, and objective, fact-based decision making as the
preferred project management methodology. An EIA-748 compliant EVMS provides for the
generation of timely, reliable, and verifiable contractor performance and progress
information, permitting the government to evaluate the contractor's progress and assess the
likelihood of meeting project and contractual requirements for cost, schedule and technical
viability. The EVMS is, by federal regulation and contract, the project management tool of
choice on cost reimbursable contracts. EVM is a project management methodology that
effectively integrates the project scope of work with cost, schedule and performance elements
for optimum project planning and control. Its success depends on the reliability of the
contractor’s EVMS. EIA-748 describes the qualities and operating characteristics of a
compliant EVMS.
An undisciplined approach to project management in general, and the implementation of
EVMS specifically, ultimately jeopardizes the long-term stability of the project and
diminishes the purchasing power of the Department. An EIA-748 compliant EVMS is
necessary for Department stakeholders to rely on current, accurate, complete, auditable,
repeatable, and compliant performance measurement data and information intended for
effectively managing high cost contracts. Consequences may include:
• Managers unable to identify problems and take immediate corrective action; and
• Managers unable to assess the magnitude of problems.
3.1 Primary EVMS Compliance Review Team Roles
3.1.1 PM-30 Project Controls The mission of PM is to serve as the single voice for all matters involving EVMS compliance.
PM-30 develops and maintains all EVMS related policy and procedures, training, and making
final assessments of EIA-748 EVMS compliance for DOE capital asset projects.
Responsibilities include:
• Serves as EVMS Subject Matter Expert assisting employees and customers;
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
19
• Develops and maintains EVMS related procedures and templates;
• Serves as the lead for EVMS compliance review team activities;
• Develops and maintains a standardized data call to support EVMS reviews;
• Coordinates compliance processes with all stakeholders to avoid duplication of effort, minimize cost, and maximize communication;
• Plans and conducts EVMS Compliance Reviews in accordance with DOE O 413.3B requirements and as further defined in this PM SOP;
• Assesses contractor management of subcontractors in accordance with EVMS guidelines;
• Evaluates and provides formal concurrence on all contractor proposed alterations to the certified EVMS, including changes to documented processes and supporting
procedures;
• Monitors CAMP activities and verifies final closure; and
• Uploads all reports and supporting documentation to document management system in PARS.
3.1.2 The EVMS Compliance Review Team PM-30 organizes, plans, and leads EVMS compliance assessments using four standard review
formats, including the CR, IR, RFC, and SR all defined and discussed earlier in this PM SOP.
Note: Section 3, “Procedures” further discusses additional duties associated with each step
of the EVMS Compliance Process.
The key positions, roles and responsibilities of EVMS compliance reviews are as follows:
Review Director. The Review Director is a PM-30 senior representative responsible for
ultimate approval of EVMS findings and reports. The PM-30 Director typically fills this
position unless otherwise delegated. The Review Director assigns the Review Chief and
approves the selection of the Review Deputy and Review Assistant. The Review Director is
responsible for all decisions of EVMS noncompliance.
Review Chief. The Review Chief is responsible for the overall conduct of the assessment
and review and for leading the review team in the execution of its duties and responsibilities
before, during, and after the compliance review. A member of the PM-30 staff typically fills
this position. The Review Chief identifies and nominates the Review Deputy, Review
Assistant, and the Review Team to the Review Director for his or her approval.
Review Deputy. The Review Deputy supports the Review Chief and is responsible for the
operation of the Review Team and the EVMS compliance review process. This position is
typically filled by an EVMS SME on the PM-30 staff or obtained through contract support.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
20
Review Assistant. The Review Assistant assists the Review Chief in handling all
administrative details of the review including particularly document control. This position is
typically filled by an EVMS SME on PM-30 staff or obtained through contract support. One
of the most critical tasks for the Review Assistant is to maintain the CAR/DR/CIO log and
serve as the go between for all phases of CAR/DR/CIO development.
Process/Area Team Lead. Assigned by the Review Chief, the Process/Area Team Lead is
responsible for assessment and documentation of one or more of the six areas of the EIA-748
EVMS Guidelines as previously noted in Section 2.4, by considering the adequacy of the ten
core management processes associated with an integrated project management approach (i.e.,
organizing, planning and scheduling, budgeting and work authorization, material
management, subcontract management, analysis and managerial reporting, change control,
accounting considerations, indirect cost management, and risk management, or a combination
of both. This will be accomplished by conducting a process capability assessment to test the
ability of a core management process and practice to meet prescribed EIA-748 compliance
criteria. The final determination of EVMS compliance for a process capability is
accomplished by looking over a specified period time to determine how well a process meets
a set of specification limits. A person may be assigned to more than one Process/Area
pending the results of the data analysis and ultimate review scope. The Process/Area Team
Lead’s tasks begin at the data analysis step and continues through post review and closeout
step (see Table 3). Output documents include but are not limited to providing analysis results
of concerns to the respective Interview Team Leads, the Guideline Summary for area of
responsibility, and the associated CARs, DRs, and CIOs. The Process/Area Team Lead
assigns team members early in the data analysis step to ensure the team is involved, prepared,
and diligently executes their duties associated with the EVMS compliance process.
Interview Team Lead. Assigned by the Review Chief, the Interview Team Lead is
responsible for planning, scheduling, performance, and accurate reporting of the interviews
and discussions held with Control Account Managers (CAMs) and other contractor personnel.
Duties include understanding the concerns identified by the Process/Area Team Leads
pertinent to the Interview Team Lead’s interview assignments and preparing the interview
team members prior to making pre-review assignments for populating the Interview Findings
Form (IFF), reviewing team members’ work, and providing the Review Chief with completed
IFF, CARs, DRs, and CIO documentation upon completion of assigned interviews.
Review Team Members. Members are federal employees, contractor staff, and contracted
resources with EVMS compliance assessment experience responsible for performing detailed
evaluations of a contractor's EVMS within their assigned Area. Review Team members
typically serve cross-functional roles as both Process/Area and Interview Team members
supporting a(n) Process/Area analysis as well as conducting and documenting the interviews.
Assign a process/area team member to each interview when the IFF includes questions
relative to that process/area.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
21
The Review Director and Review Chief will consider team member credentials, working
knowledge, and practical EVMS implementation and use when assembling the team. EVMS
Review Team members may include Project Controls Analysts (PCA)/EVMS SMEs, and
direct contract support. Energy Facility Contractor’s Group (EFCOG) EVMS/PCA SMEs
may participate in reviews, subject to completion of a non-disclosure statement. All EVMS
Review Team members will be assigned specific responsibilities throughout the EVMS
compliance process. The Review Chief must approve contractor and government ‘observers’
(e.g. non-participating members) considering room accommodations and avoiding undo
pressures on the interviewee.
3.2 Supporting EVMS Compliance Review Team Roles An important aspect of a contractor’s EVMS continued compliance relies on the stakeholders,
i.e. senior leadership, project analysts, and designated EVMS compliance staff, to hold the
contractor accountable to performing defined roles and responsibilities. As part of an EVMS
self-governance plan (Ref. App. D, Self-Governance Review Checklist) and/or general
surveillance, each function should ‘check’ the performance of the other to make sure that the
EVMS is operating both effectively and efficiently. Note: Roles noted below of individuals
and organizations outside of PM are for discussion purposes only and do not constitute
direction. These are suggested roles to assist the PM team in conducting its EVMS
compliance mission.
3.2.1 PM-1 Office of Project Management PM-1 is the certifying authority for EVMS as well as the authority to decertify. Accordingly,
PM-1 provides the resources and budget for executing the EVMS compliance process as
described herein, and specifically for conducting EVMS Compliance Reviews, and is kept
current by briefings from the PM-20 and PM-30 staff relative to all matters relating to EVMS
compliance, policy, and training.
3.2.2 PM-30 Project Controls PM-30 serves as the EVMS compliance mission lead, responsible for development and
maintenance of EVMS compliance guides, training, and SOPs, and for leading EVMS
compliance assessments.
3.2.3 PM-20 Project Assessment The PM-20 Project Analyst is responsible for participating in the EVMS Compliance Review
process for assigned projects. Information provided by the Project Analyst includes in-depth
knowledge of the project scope, technical requirements, constraints, and specific concerns or
impacts of current and future project risks that will aid the EVMS Compliance Review team.
While conducting project level analysis, the PM-20 Project Analyst plays a key role in
providing an early warning of and assessing issues that may involve EVMS processes and
implementation. The PM-20 Project Analyst is responsible for coordinating with PM-30
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
22
EVMS SMEs, and for working collaboratively towards resolving data integrity issues which
may trigger a risk based, data-driven SR.
3.2.4 Project Management Support Office (PMSO) PMSO project level information is helpful in the EVMS Compliance Review process. A
PMSO EVMS SME is encouraged to participate as a team member in EVMS Compliance
Reviews and accept assignments offered by the Review Director and Review Chief.
3.2.5 Federal Project Director (FPD) The FPD prior to, during, and after the EVMS Compliance Review process can provide
insight into project level direction given to the contractor, past and planned baseline
modifications, and performance impacts. The review leadership involves the FPD in
collaborative discussions to ensure field or site office direction does not inadvertently
compromise EVMS compliance.
As stated in DOE Order 413.3B, the FPD ensures on capital asset projects with a TPC of
$50M or more the integration of current, accurate, complete, auditable, repeatable, and
compliant contractor performance data into the project's scheduling, accounting, and
performance measurement systems, to include PARS. DOE Order 413.3B Appendix A,
Table 2.3, Post CD-3, states the contractor must conduct an EVMS surveillance annually. The
FPD/IPT staff also shares in the responsibility to ensure annual EVMS surveillance is
conducted and the system remains compliant. The FPD provides the contractor’s internal
surveillance reports to the CO, PMSO, and PM.
FPD/IPT staff support EVMS reviews by:
• Communicating to PM-30 (the EVMS Compliance mission advocate) those actions and matters that could/may affect system compliance;
• Assisting in the resolution of problems cited in the review reports;
• Reviewing, evaluating, and analyzing performance reports and schedules,
• Communicating system and implementation concerns, and data integrity issues to the attention of PM-30; and
• Participating as members of the review team as requested.
3.2.6 Contracting Officer (CO) The CO is responsible for ensuring all applicable EVMS regulatory and contractual
requirements, FAR clauses, deliverables as listed in Attachment 1 of DOE O 413.3B, and
language relating to EVMS are included in contracts for capital asset projects with a TPC
greater than $50M. The CO also ensures that contractor performance is integrated with the
contract award fee determinations and other mechanisms to ensure pay for performance
including the assessment of EVMS health as supported by EVMS Compliance Reviews.
Methods such as establishing award fee on EVMS cost and schedule metrics has proven to
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
23
be flawed when it drives unintended behavior. It is incumbent upon the CO, PM, PMSO, and
FPD to work together to ensure government needs are met and understood, and that contractor
incentives are performance based.
Formal determination of compliance is provided to the CO by PM-1, and the CO notifies the
contractor of contractual compliance to the EVMS Certification requirement. At the
completion of all formal EVMS Compliance Reviews, PM will provide copies of reports to
the CO. Should a contractor fail to maintain their system, PM may determine a RFC is
necessary. Following a Surveillance Review or RFC, PM may withdraw EVMS certification.
The CO would then officially notify the contractor via letter and may pursue appropriate
contractual remedies.
3.2.7 Contractor The contractor is responsible for developing a compliant EVMS, implementing that system,
and maintaining EVMS compliance with EIA-748 as stated in DOE O 413.3B, Attachment
1. The contractor is also responsible for ensuring that its EVMS is implemented on a
consistent basis, is used effectively on all applicable projects, and EVMS clauses are flowed
down to subcontractors in accordance with the rules applied to itself as the prime contractor.
EIA-748 also states that the contractor is responsible for conducting surveillance of their
management systems to ensure continued implementation of an EVMS that meets the 32 EIA-
748 guidelines. DOE O 413.3B Attachment 1, Section 1 states that the contractor must
conduct EVMS surveillance annually. The contractor is required to provide documentation
of the EVMS surveillance results to the CO, PMSO, and PM-30.
Activities supporting the annual contractor surveillance can be spread throughout the year at
the contractor’s discretion; however, all 32 EIA-748 EVMS Guidelines must be evaluated at
least once during each year. When non-compliances are noted and corrective actions are
identified, it is incumbent upon the contractor to monitor implementation of the corrective
actions to ensure that the applied corrective actions have been successful. The contractor’s
EVMS surveillance should be conducted by a team independent of the contractor’s project
team, such as an internal audit group to avoid potential conflicts of interest. In accordance
with the EVMS certification letter from PM-1 through the CO, the contractor is also
responsible for notifying PM-30 through the CO in writing of any changes to their previously
accepted certified EVM System Description. EVMS improvements such as implementation
of corrective actions from internal surveillance, or the enhancement of a core management
process may trigger this reporting requirement.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
24
4 EVMS COMPLIANCE PROCESS
4.1 EVMS Compliance Process Phases and Steps
Each EVMS compliance phase is further defined by steps in the following subsections. The
structure of the following tables covers all steps required in an EVMS Certification Review
(CR) and those steps tailored to fit the other types of EVMS Compliance reviews (i.e., IR,
RFC, and SR). The duration of each phase and step of an EVMS compliance review will
vary depending on the size of the project, the maturity of the contractor’s EVMS, etc., with a
notional timeline established upon identifying the need to proceed with the assignment.
EVMS certification will take a minimum of between 12 and 15 months. This PM SOP is
designed to help the government and contractor navigate the EVMS Compliance Process.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
25
Table 1 provides a synopsis of the purpose for each Phase of the EVMS Compliance process.
Table 1. EVMS Compliance Process Phases Phase Purpose
1. Need Determination
Identify need and resources to conduct an EVMS Compliance Review
2. Initial Visit (IV)
A PM-30 visit to contractors requiring an initial EVMS certification credentials
to discuss the Certification Review (CR) process, set review expectations
among the stakeholders, and identify potential concerns with the contractor’s EVMS processes and procedures and areas of non-compliance already
observed.
3. Data Analysis (DA)
An initial assessment of the EVMS allowing the contractor to demonstrate the
operation of the system.
4. Readiness Assessment
(RA)
Determines the readiness of the contractor’s EVMS for continuation of the EVMS compliance process via data analysis results. This may include a
Readiness Assist visit.
5. On-Site Preparation and Review
Conduct final pre-visit assessments and preparations, proceed on-site to
commence the formal EVMS compliance review which concludes with a final exit brief to the contractor.
6. Post Review and Closeout
Documents the results of the contractor’s EVMS compliance review, issue
findings, monitors contractor Corrective Action Management Plan, and
conducts final closeout which includes a PM-1 memorandum to the CO.
Note: A check (√) means applicable, a dash (-) means not applicable.
4.1.1 Need Determination Phase As indicated by the chart below, each of the steps in the Need Determination Phase applied
to any type of EVMS Compliance review. The steps for this phase are explained in detail
following the table.
Table 2. Need Determination Phase
Phase Steps CR IR RFC SR
1. Need
Determination
1. Identify and Track EVMS-Applicable Projects
√ √ √ √
2. Determine Type of Review Needed √ √ √ √
3. Go/No Go Decision √ √ √ √
Step 1. Identify Projects Needing a Review. PM-20 will contact PM-30 to assist with the
identification of capital asset projects with EVMS compliance requirements. The PARS, as
the central repository for all capital asset projects, tracks the status of projects requiring a CR
via the CD status report. This report is monitored by PM-30 to identify both projects needing
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
26
a CR and those needing an IR based on specifics of the contractor and the EVMS of record
at the site.
PARS Performance Analytics reports, Analytics Summary Dashboard, Data Validity reports,
Schedule Health reports, and particularly the Baseline Volatility report under Trends, are
extremely helpful in identifying projects that may be experiencing compliance issues. These
reports should be reviewed by the assigned PM-20 Project Analyst, and PM-30 EVMS SME,
to identify if a risk-based, data-driven surveillance may be warranted.
For surveillance purposes, the PM-30 EVMS SME will, subject to available resources,
conduct initial data review (based on automated tests only) of all projects greater than $100M,
and greater than $50M upon request, provide a report that ranks projects and contractors
according to flagged test results. Based on the trends and concerns identified by the data
review, the EVMS SME may conduct a deeper investigation on particular projects beyond
the automated tests and perform manual tests involving additional artifacts. When the results
of the annual surveillance analysis determine that further action is not needed, the SME will
ensure the decision and supporting data is documented as an EVMS SR action for that
contractor and filed in the PARS document management system.
A post-certification compliance review can be requested by other enterprise stakeholders for
any number of reasons including the loss of confidence in reported EVMS data and
information. When a request for an SR or RFC comes from an outside stakeholder, e.g.,
PMSO, the PM-30 EVMS SME will meet with the stakeholder to discuss their concerns and
may perform the next level of analysis from the contractor’s EVMS data before moving
forward to Step 2.
Step 2. Determine Type of Review Needed. Based on the results from Step 1, the PM-30
Director meets with the PM-30 EVMS SME to determine the type and priority of EVMS
compliance review needed. The priority for a SR is normally a risk-based and data-driven
decision. EIR and ICE/ICR review requests will come directly to PM-30 from PM-20 for the
services of a PM-30 EVMS SME on an as needed basis.
Step 3. Go/No Go Decision. The PM-30 Director, or designee, will brief PM-1 prior to
proceeding with a CR, IR, RFC, and SR. PM will submit the results of the review to the
Program Office HCA/PMSO and CO concurrently.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
27
4.1.2 Initial Visit (IV) Phase This phase only applies to a Certification Review as indicated in the following table.
Table 3. Initial Visit Phase Phase Steps CR IR RFC SR
2. Initial Visit (IV) 4. Determine Need for IV √ - - -
5. Identify, Plan, and Schedule Team Resources, Coordinate Dates √
- - -
6. Issue Contractor Notification √ - - -
7. Conduct IV √ - - -
8. On-Site Certification Review Date Established
√ - - -
9. Document Visit √ - - -
Step 4. Determine Need for IV. An IV is a ‘meet and greet’ designed to assist a contractor
who is unfamiliar with the EVMS compliance process. The applicability is limited to initial
CRs and is not typically appropriate for a recertification following a decertification. The IV
provides an opportunity for early dialogue with the contractor on the CR process, sets review
expectations among the stakeholders, and identifies areas of noncompliance and potential
problems with the contractor’s EVMS processes and procedures. Typically, CAMs and other
managers are not interviewed during this visit.
Step 5. Identify, Plan, and Schedule Team Resources, Coordinate Dates. The Review
Director assigns a Review Chief, and together each determines the immediate needs for the
resources required to perform the IV. The IV is a small team, typically limited to the Review
Director, Review Chief, a Review Deputy, and key review team members if required. The
Review Director or Review Chief pre-coordinates with the contractor to establish a date for
the IV.
Step 6. Issue Contractor Notification. The Review Director sends an email notice to the
contractor advising the formal date for the IV, a copy of the proposed agenda, and a request
for the most current copy of the EVM System Description and supporting procedures. A
copy of the contract or project EVMS clause and related requirements will be requested along
with a brief discussion of expectations on the part of the contractor for this meeting.
This notification should also include suggestions for the contractor’s briefing, to include but
not limited to organizational structure, an overview of the project(s) where the EVMS is
implemented, progress made to date in terms of the EVM System Description and supporting
procedures, the development of training, and a demonstration of the contractor’s EVMS
integration and process flows. The contractor is encouraged to use a best practice
“storyboard” approach. The storyboard is a large stratified flow chart of the EVMS processes,
artifacts, and subsystems. Storyboards are extremely useful for contractors in designing their
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
28
EVMS by identifying handoffs and integration points between the various systems, toolsets,
processes, documents, artifacts, and functions.
The notification may also request a copy of the contractor’s cost and schedule files in a format
specified so that the PM-30 EVMS SME can prepare an analysis to share with the contractor
during the visit as non-attribution for the contractor’s awareness. No CARs or DRs are issued
at this early stage of the EVMS compliance process. The results are briefed by the Review
Chief (or designee) to the contractor in a power point presentation with bullets identifying
noteworthy areas of concern.
Step 7. Conduct Initial Visit (IV). The Review Chief along with the initial team members
arrive prepared by having reviewed the contractor’s proposed EVM System Description, any
associated procedures, the EVMS contract clause and related requirements, and results of the
cost and schedule data analysis. The Review Director will attend site or contractor visits at
his or her prerogative.
The government in-brief is conducted by either the Review Director or the Review Chief (or
designee), and begins with the purpose for the IV, an introduction of the team members
assigned, and a presentation of the PM-30 EVMS compliance process, including the phases
and steps and data requirements that can be expected by the contractor. The Review Chief
(or designee) will discuss the specific areas reviewed and any areas of EVMS non-compliance
and/or potential concerns in order to facilitate early discussions towards resolution.
The contractor will then conduct a briefing, covering the areas identified in Step 6. The
Review Chief will need sufficient time during the visit to provide the cost and schedule data
analysis results and answer the contractor’s remaining questions regarding the EVMS
compliance process.
Step 8. On-Site Certification Review Dates Established. After the IV, the Review Chief
coordinates with the contractor to establish the timeframes for the remainder of the CR. The
Review Chief should explain to the contractor that these dates are dependent on the
contractor’s preparedness and progress made towards completing Phase 3, Data Analysis
(DA) and Phase 4, Readiness Assessment (RA). The on-site CR may be as soon as six months
following the IV, depending on the contractor’s ability to demonstrate the implementation of
a fully compliant EVMS. At the conclusion of this step, PM-30 and the contractor should
agree on an EVMS Compliance Review schedule.
Step 9. Document Visit. The Review Chief completes a trip report to document the IV,
including a list of attendees, copies of presentations, pertinent discussions, and any
agreements made for CR schedule. These documents are made part of the official CR files
and kept in the PARS document management system.
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
29
4.1.3 Data Analysis Phase
Table 4. Data Analysis Phase Phase Steps CR IR RFC SR
3. Data
Analysis
10. Identify, Plan, and Schedule Team Resources √ √ √ √
11. Issue Contractor Notification w/Standardized Data Call for: √ √ √ √
a. Data and Artifacts √ √ √ √
b. Contractor Independent Assessment and/or Past Surveillance √ √ √ √
c. EVM System Description and Supporting Procedures w/ Cross-Reference Checklist √ √ √ √
d. Contractor Demo of System via Webinar (as needed) √ √ √ √
12. Upon Receipt of Data, Assign Activities: √ √ √ √
a. Analyze Contractor Data & Artifacts √ √ √ √
b. Review Contractor Independent Assessment and/or Past Surveillance √ √ √ √
c. Review EVM System Description √ √ √ √
13. Document Results; Identify Concerns √ √ √ √
Step 10. Identify, Plan, and Schedule Team Resources. The Review Director together with
the Review Chief work with the PM-30 EVMS SME to determine the estimated review
timeframe based on urgency of need, budget, and resource availability. At this point, the PM-
30 EVMS SME analyzes the requested contractor EVMS data and reviews the contractor’s
EVM System Description.
Step 11. Issue Contractor Notification w/Standardized Data Call. When conducting a
CR, IR, RFC, or SR, the Review Chief composes the contractor notification memorandum
(see Appendix D) for PM-1 signature to the Program’s Head of Contracting Activity (HCA)
or CO as the formal notification to be sent the contractor. The notification should be sent to
the contractor no less than 60 calendar days (2 months) prior to the start of the on-site EVMS
compliance review. Receipt of all data requested must be delivered in its required formatting
and to PM-30 no less than 45 calendar days prior to the start of the review. The notification
memorandum specifies the EVMS Review type and data call. The Initial Standardized Data
Call (see Appendix F) consists of the request for the following:
• Data (cost and schedule files in the format specified to support automated and manual tests) and Artifacts as requested;
• Contractor independent assessment or past internal surveillance reports; and
• EVM System Description and supporting procedures maintained by the contractor’s configuration control process. If the contractor provides supporting procedures that
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
30
are not under configuration control, they will not be considered as part of the
contractor’s EVMS and will not be considered during the EVMS compliance process.
The notification will also explain where to publish the requested data, e.g., PARS, contractor
FTP site, or other electronic media, and the recommended folder structure for organizing the
data and information.
Step 12. Upon Receipt of Data, Assign Activities. A PM-30 EVMS SME is responsible for
conducting a data analysis following documented testing protocols, for both automated and
manual tests. The same PM-30 EVMS SME will also review the contractor’s independent
test results. Based on their analysis, the PM-30 EVMS SME may ask the Review Chief to
request additional documentation or artifacts to solidify their findings and concern(s).
The Review Chief may request a webinar at this point with the Process/Area Lead for the
contractor to demonstrate EVMS processes, procedures and toolsets to include the results of
the contractor’s CRC mapping of the EVM System Description to 32 EIA-748 EVMS
Guidelines to the Compliance Review Team.
a. Analyze Contractor Data and Artifacts. The Review Chief will assign a team
member(s) to analyze the contractor’s data using the automated tools and manual
templates defined in the Guideline Attributes and Tests Excel spreadsheet (see
Appendix A). The team should also review the PARS Data Validity reports, Schedule
Health reports, and particularly the Baseline Volatility report under Trends for the
same periods to identify areas of concern. A report will be provided to the Review
Director and Review Chief to document assumptions or context commentary, so the
compliance review team can properly interpret the results. Because this data is used
to determine issues of non-compliance and materiality, the order-of-magnitude
metrics must be included in the report that is provided to the compliance team (see
Step 31).
b. Review Contractor Independent Assessment and/or Past Surveillance. The
contractor’s independent assessment and/or past internal surveillances is reviewed
by the Process/Area Team Leads to assess completeness and compare with the
results found in Step 12a.
c. Review EVM System Description. The Review Chief and Process/Area Leads
review the contractor’s EVM System Description and supporting procedures for EIA-
748 compliance using the EVMS Compliance Review Checklist (CRC) found in
Appendix A. If the contractor has adopted self-governance, also review the EVM
System Description against the Self-Governance Review Checklist in Appendix D.
The reviewer should provide specific rationale for identified non-compliant text in the
contractor’s EVM System Description but should not provide recommend revised
language to the contractor as this could interfere with the contractor’s business
practices. The assessment must ensure the following in verifying adequacy and
-
PM EVMS COMPLIANCE REVIEW SOP
November 28, 2018
31
completeness of the contractor’s EVM System Description and any supporting
procedures maintained under the contractor’s configuration control process:
• Descriptions include the associated policies, procedures, and methods designed to satisfy the EIA-748;
• Descriptions are in the form and detail necessary to permit guideline evaluation for EIA-748 EVMS compliance; and
• Descriptions delineate roles & responsibilities of operating personnel, and internal authorizations and controls required.
Step 13. Document Results and Identify Concerns. The Process/Area Leads will document
the results of their review and identify any concerns that need further assessment. This
documentation will be provided to the Review Chief as soon as practicable. The Review Chief
will then coordinate with the Review Director for use in a determination to proceed to the
next step. Should non-compliance and material data validity issues be found, it may be
necessary for the Process/Area Leads to issue preliminary CARs and/or DRs prior to the RA
Step.
4.1.4 Readiness Assessment (RA) Phase The purpose of the RA is for a final determination to be made whether the contractor is ready
for the formal review, or if the contractor needs additional time to correct findings resulting
from the prior DA Phase. The RA may be conducted for CR, IR, and SRs. In the surveillance
mode, if the RA indicates serious EVMS non-compliance issues, the Review Director may
recommend to PM-1 that the SR be replaced by a RFC. The RA phase also allows for a
Readiness Assist Visit (RAV) to aid the contractor by explaining the current issues and to
further assess the contractor’s state of readiness for the formal EVMS review. RAVs are
conducted on an as needed basis as determined by the Review Director based on the indication
of the contractor’s readiness to date.
Table 5. Readiness Assessment Phase
Phase Steps CR IR RFC SR
4. Readiness Assessment
(RA)
14. Assess Contractor Readiness √ √ √ √
15. Conduct Readiness Assist Visit (RAV) (as needed) √ √ - √
16. Document Results √ √ √ √
17. Go/No Go Decision √ √ √ √
Step 14. Assess Contractor Readiness. The Review Director and Review Chief discuss the
results of DA Phase and, when applicable, the CAR/DR/CAMP status to determine contractor
readiness to proceed.
Step 15. Conduct Readiness Assist Visit (RAV) (if needed). A small team is sent on-site to
share the results of the data analysis, discuss any potential CARs and DRs issued r
top related