WCCUSD Bond ProgramConstruction Update

Edward Downer Elementary School Playfield RenovationStatus Update

10/14/14

Construction Manager: Gabriel Fortich (SGI)

Inspector of Record: Man Wah Cheng

Architect of Record: BCA Architects

General Contractor: Maggiora & Ghilotti, Inc.

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Team

Fine grading to commence 10/20/14 -11/24/14

Sod Installation to commence on 10/27/14 – 10/31/14

Irrigation booster pump 11/6/14 – 11/13/14

Field complete 11/15/14

Edward Downer Elementary SchoolPlayfield Renovation

PROJECT SUMMARY

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Summary

Project Duration: 180 (Calendar

Days)

Notice To Proceed Date: May 19, 2014

Completion Date: Nov 15, 2014

Percent Complete: 90%

Base Contract Amount: $563,226.00

Change Order to date: .1%

Edward Downer Elementary SchoolPlayfield Renovation

Project

General Information

Edward Downer Elementary SchoolPlayfield Renovation

Project

Graded Site

Edward Downer Elementary SchoolPlayfield Renovation

Project

Landscape Planting