Offshore Energy InsuranceGard AS Arendal
Offshore Energy Insurance - What is so special?
What are the main differences between marine and energy insurance?
4
• Drilling into unknown underground conditions (Wildcats)o High pressureso Uncertainty when pressured zones are reached
• High Risk Operations – release of hydrocarbons
• Resourceful Assureds
• Insured objects are stationary whilst operating
• Tailor made items and parts with long lead time
• High values and significant retention/deductible levels
• ”Tailor made” insurance policies – manuscript wordings
• Low frequency but large and complex losses
• Limited case law and market practice
Contents• Who needs it and why?• What triggers cover?• Main considerations for pricing• How are losses calculated?• Important practical claims handling considerations
Who needs it and why
Who needs it and why
Two categories of clients:•Oil Company: Can be either an operator or a co-venturer.
o An operator owns a license from the state to develop a field and extract the oil and/or gas. A co-venturerer pays a share of the expenses, but also receive a share of the revenue
•Contractoro Chartered in by the operator for a specific tasko Most Mobile Offshore Units (MOUs) are owned by various contractors. MOUs include:
Drilling rigs, accomodation units, and FPSOs.
The nature of the risks and structure of insurances for an oil company and a contractor differs – Still placed in the same insurance markets
7
8
Oil Companies
9
Contractors
Phases in the oil and gas industry
10
• Exploration & Production (Offshore)o Upstream activities (prospecting, exploration, development and
extracting/production)
o Midstream activities (transport from offshore field to marine terminal/ refinery/petrochemical plant/gas processing & transmission)
• Refining & Marketing (Onshore)o Downstream activities (refining, petrochemical, processing,
marketing & distribution)
Kermac 16 – First “offshore” well
11
As at 20.08.2016
12
Split between oil & gas companies and contractors
By premium volumes, as at 20.08.2016
13
Gard Energy lead – oil & gas companies and contractors
Who needs it and whyExploration and Drilling
Jack-up Drilling Rigs – On Seabed
16
Who needs it and whyProduction
Development Concepts
19
• Stationary platformso Steel jacketso Concrete - Gravity Base Structures
• Floating platformso Tension Leg Platform (TLP)o Floating Production Unit/System
(FPU/FPS)o Floating Production Storage and
Offloading Unit (FPSO)o Floating Storage Offloading Unit
(FSO) o SPAR platform
Fixed Platform
20
Troll Condeep
21
FPSO units – Floating Production Storage Offloading
22
Floating Production Units in operation
23http://www.marinelink.com/news/manufacturers-opportunity381817
Location and Water Depth of Planned Floating Production Projects
24
http://www.marinelink.com/news/manufacturers-opportunity381817
What triggers coverContractor’s hull insurance policy
The insurance needs of MOU owners – Operating units
26
• Hull & Machinery incl. Collision liability and Sue & Labour• Total Loss Insurance - Hull Interest incl. Collision liability
- Freight Interest• Loss of Hire (excl. Total Loss)
• Contingent Operator’s Extra Expense
• War & Terrorist
• Protection & Indemnity Insurance• Comprehensive General Liability Insurance
The insurance needs of MOU owners – Operating units
27
• Hull & Machinery incl. Collision liability and Sue & Labour• Total Loss Insurance - Hull Interest
» Freight Interest• Loss of Hire (excl. Total Loss)
Insuring Agreements:
• London Master Rig Drilling Contract / London Market Offshore Mobile Unit Form
• American Institute Hull Clauses• Nordic Marine Insurance Plan 2013 version 2016
Nordic Marine Insurance Plan 2013
28
• Part One: General Rules
• Part Two: Hull Insurance
• Part Three: Other Insurance for Ocean- Going vessels
• Part Four: Other Insuranceso Fishing Vesselso MOU
o Builders Risk
Hull & Machinery incl. Collision liability and Sue & Labour
29
• All Risk Policy• Assessed Sum Insured
• 3 sums insured availableo For Physical repairso For Collision liabilityo For Measures to minimize loss (Sue
& Labour)
• Ch. 18 reflects the general principles of the Plan
Chapter 18 Particularities
30
• No cover for loss resulting from using MOU for drilling relief well
• Additional Safety Regulation: o Wells have to be equipped with Blow-Out
preventers
• Sue and labour limited to USD 500,000,000
• Collission liability limited to USD 500,000,000, or 50% of sum insured whatever is higher
What triggers coverContractor’s P&I insurance policy
P&I for Mobile Offshore Units
• Liabilities relating to any unit carrying out oil and gas drilling or production operations are not allowed entry in the International Group
• Gard has responded by establishing a separate cover based on specialised conditions for MOUs
32
Knock for Knock
33
Knock for knockLiability regime
• Liability: Each party to be solely liable for illness, injury and death of its personnel and for loss of or damage to its property (and for subcontractors’ personnel and property), pollution from its own property, removal of wreck of its own property, and their own consequential losses.
• Indemnity: The indemnitor shall indemnify and hold harmless the indemnitee from the indemnitor’s liability under knock-for-knock
• Waiver of recourse: Each party (and its insurers) shall waive its rights of recourse against the other party to the extent of its liability under knock-for-knock
34
Knock-for-knock division of liability
35
Offshore contracts
Main contract
Main contrac
tCompany Contractor
Other contract
Other Contractor
Other Contractor
1st tier sub-
contract Sub-
contractorSub-
contractor
2nd tier sub-
contract
Sub-contractor
1st tier sub-
contract Sub-
contractorSub-
contractor
2nd tier sub-
contractSub-
contractorSub-
contractor
3nd tier sub-
contractSub-
contractor
Company Group Contractor GroupCo- venturer
COMPANY liable for its Group’s personnel and property
CONTRACTOR liable for its Group’s personnel and property
Offshore contractsDivision of liability for what?
• Personnel• Property• Pollution• Removal of wreck• Consequential losses• Third parties (negligence, not knock for knock)
36
Insurance premium contractor rigGard Explorer
37
Gard Explorer – semi submersible delivered to Agder Drilling fromKorean yard 15 May 2015:
Estimated market value when delivered USD 600,000,000Hull and Machinery: USD 480,000,000 – 0.6%Hull Interest: USD 120,000,000 – 0.3%Deductible USD 2.5m, Brokerage 7.5%
Loss of Hire:60/180/180:Dayrate USD 440,000. Total sum insured USD 79,200,000 -1,4%Brokerage - 7.5%
Gard MOU P&I: Limit USD 250m. Fixed Premium USD 270,000.Deductible USD 10,000 Direct business, no brokerage
The Energy Insurance Market
38
• 1966 - London Master Drilling Rig Contract Rate 9,75%
• 1973 – Norwegian Oil Risk Pool Rate 5,75%
What triggers cover Contractor’s - Claims
West Vanguard
40
Petromar V
41
Gryphon A – Loss of Mooring
42
Petrojarl Banff FPSO
43
Damaged risers / anchor chain corrosion
44
Anchor chain damage
45
Perro Negro 6 – Loss of stability
46
Cidade de São Mateus
47
What triggers coverOil Company’s insurance policy
E&P – ”package” policies
49
• Physical damage to offshore installations
• Business Interruption• Cost of Well Control• Seepage & Pollution• Cost of Redrilling• Third Party Liabilities• Offshore Terrorism• Deliberate well firing
Business Interruption / Loss of Production Income
50
• Is there a loss, when the oil is still underground?
• Cover based on Agreed Value basis or Indemnity basis: o Agreed Value= Value of Oil x
Expected Production
• Contingent BI cover
Cost of Well Control
51
• Blowout = Unintended and uncontrolled flow of oil
• Uncontrolledo When the well is flowing above ground/water and the flow cannot
be stopped by BOP / increasing mud pressure / diversion into production
• Covero For materials and services of specialists necessary to get control of
the well
• Exclusion: No cover for loss in production capacity, loss of reservoir
Relief Well plan
52
Well Redrill / Well Restoration
53
• Additional cover to Well Control Costs
• Well out of control triggers insurance cover
• Insurance covers replacement to the same depth as the original well and to the same reservoir.
• Limits of cover
E&P – ”package” policies
54
• Physical damage to offshore installations
• Business Interruption• Cost of Well Control• Seepage & Pollution• Cost of Redrilling• Third Party Liabilities• Offshore Terrorism• Deliberate well firing
Main Considerations for pricing
55
Arendal Oil Company:Gard Explorer is chartered from Agder Drilling, but Arendal Oil Company is the Operator with a 30% interest in the well. Purchase of Operators Extra Expense cover (OEE) – includes Cost of Well Control, Seepage & Pollution, Cost of redrilling
Premium:0-10,000 feet: USD 18,07 per foot10,000-17,500 feet: USD 27,10 per foot17,500 – 20,000 feet: USD 40,66 per footDeductible USD 2m. Limit USD 150m. Brokerage 7.5%
Third party liabilityLimit USD 100mRate at 0,05% of limit. Deductibe USD 500,000 Brokerage. 7.5%
What triggers cover?Oil Company claims
Alexander L. Kielland – mechanical failure
57
Sleipner ”A” - GBS collapse
58
Troll A - Motor failure
59
Seawater ingress
60
Blowout : Ekofisk Bravo
61
Explosion and fire on Piper “A”
62
Elgin Platform Gas leak - North Sea
63
Eugene Island Platforms - hurricane
64
Eugene Island 330 S & C Platforms post Rita
65
Typhoon TLP
66
Claims
Energy claims (Offshore)
68
• Drilling operationso Well blow-outs with or without fire/explosiono Collapse of drilling hole/seabed (cratering)o Collision against drilling rig/platform
• Production operationso Gas leakage with explosion/fireo Hurricane/weather damages o Mechanical failure/overload/fatigue fractureo Pipeline breakageo Excessive corrosion damage (Sulphur Reducing Bacteria)o Anchor or fishing equipment damage on pipelines/subseao Business interruption as a consequence of damage on other installation
Phases of claims handling
1. Emergency response phase2. Reinstatement phase 3. Adjustment phase4. Payment of claim
69
1. Emergency response phase
70
2. Reinstatement phase
71
• Starting point: Same condition as prior to the accident• New for old?
• Repairs in the offshore sector:o more expensive o more lengthy
• Implications:o Loss of hireo Cancellation of contract
3. Adjustment phaseHow are losses calculated?
72
• Request for documentation
• Determining the coverage (Practical group work)
Practical group work FPSO – Heavy weather damage
73
Claims submittedRecoverable under NMIP 2013?
• Immediate salvage/loss mitigation FPSO: USD 15,000,000• Disconnection risers, umbilicals, mooring: USD 2,200,000• FPSO removal costs: USD 12,500,000• Cargo offloading costs: USD 465,000• ROV/Diver inspections FPSO/turret: USD 535,000• Subsea damage inspection campaign: USD 7,140,000• Seabed clean-up/restoration campaign: USD 22,500,000• Purchase of 10 risers: USD 100,000,000• Purchase of 2 umbilicals: USD 25,000,000• Purchase of mooring system (25% stronger): USD 22,500,000• Seabed assets repairs/replacements: USD 124,000,000• FPSO mooring reconnection: USD 7,500,000• Riser/umbilical tie-ins: USD 48,000,000• Project management: USD 23,000,000• Loss of Hire USD 324,000,000
74
4. Payment of claim
75
Important practical claims handling considerations
Practical claims handling
77
• Cooperation:o Assuredo Salvorso Surveyorso Loss adjusterso Lawyers
• Importance of a proactive approach
Case Study
Total Loss • §18-10 – Condemnation
– 80% of insurable value (Market value)– Equals H&M + HI insured values (Spec. Cond)
• §18-12 – Request for condemnation• No deductible applicable if Total Loss/Condemnation
• §18-13 – Removal of unit– Insurer’s demand without undue delay– Insurer to bear costs and assume liabilities
Insurers’ liability• Total Loss, incl. condemnation
– Pay sums insured - §4-1
• Interest on the Compensation - §5-4– One month after notice of the casualty– Rate of interest 4.42% p.a. – US$24,220 per day
• Costs of measures to avert or minimise loss - §4-7– Extraordinary and regarded as reasonable– Costs of particular measures taken - §4-12, second paragraph– Up to an amount equal to the sum insured - §4-18
Further clauses to consider• §18-1 Measures to avert a blow-out, etc.
• §18-1 Safety regulations– Utilization of blow-out preventer
• §5-19 Right of the insurer to take over the object insured– May be waived at the time of payment.
Insurers’ response to the condemnation claim
• Requested a more detailed breakdown of K-FELS estimate
• Matthews-Daniel asked to verify the estimates– Most items appeared adequate, some on the low side and some items missing– Mat-Dan total estimate US$ 240,290,000
• Gard, as claims leader, confirmed acceptance of the request to condemnation of West Atlas– Waived Insurers right to take over the the ownership of West Atlas
• Total Loss compensation paid on 15 December – Interest agreed and paid at a later date
• Notified claim for loss mitigation costs not yet submitted
Commitment and capacity – Gard Energy
93
• Underwriting energy risks since 1973• Sole insurer in Scandinavia providing extensive capacity• Working capacity USD 200 million
Pictures from www.oilrig-photos.com
Thank you
First Norwegian oil production
95
• Ocean Viking Built at Aker Yard, Oslo 1965 – 1967
• 9 June 1971 - J/U Gulftide at Ekofisk Field
1973: West Venture – NORP insurers
96
80% Gard Marine & Energy predecessors20% Norwegian Hull Club predecessors
First Gard P&I MOU entry
Finding - Marine Seismic survey
97http://www.youtube.com/watch?v=mK513qoYBac
Drilling
98
Risk Allocation in Offshore fields
99
• Starting point: Operator is responsible for the field on behalf of all JV licensees.
• Contractual allocation of liability with contractors and sub-contractors
• «Knock – for – Knock» is the ideal