Experience Sharing and Lessons Learnt regarding Environmental & Social

Management Framework (ESMF) Implementation in

2013-14

2

Presented ByPresented By

Mr. Shafaqat Hussain Mr. Shafaqat Hussain DO RoadsDO Roads

CDG RawalpindiCDG Rawalpindi

Contents

• About Environmental and Social Management Framework (ESMF)

• Environmental and Social Categorization of Schemes

• Environmental and Social Management Plans (ESMP)

• Case study of ESMP preparation

• Scenario before ESMF Introduction at CDG

• ESMF Present Scenario

• Issues faced by CDG

• Conclusion3

Environmental and Social Management Framework (ESMF)

• ESMF has been prepared under the project “Punjab Cities Governance Improvement Project (PCGIP).

• ESMF serves as a guiding document to address the environmental and social issues during projects implementation.

• ESMF ensure that schemes to be designed and implemented by the Government are environmentally sound, socially acceptable and comply with the national regulatory and WB policy frameworks.

4

Environmental Categorization of schemes

E – 1 Schemes wherein major

environmental impacts are foreseen

EIA/IEE*

E - 2Schemes that are expected

to have only moderate environmental impacts

ESMPs**

E - 3schemes with negligible environmental impacts

no further assessment required

*Environmental Impact Assessment (EIA). Initial Environmental Examination (IEE)**Environmental & Social Management Plans (ESMPs)

Social Categorization of schemes

S – 1 schemes that will impact more

than 40 households, and are expected to have significant

negative social consequencesRAP *

S - 2Schemes that will impact less than 40 households and are expected to have significant

social consequences affecting local inhabitants

RAP*

S - 3schemes expected to have no

significant social consequences affecting local inhabitants

* Resettlement Action Plan (RAP)** Social Assessment Report (SAR)

Environment & Social Management Plans (ESMPs)

• For each scheme with E2 category, The Environmental and Social Management Plan (ESMP) is prepared according to the World Bank Policy Guidelines; environmental and social laws; and policies of Government of Punjab (GoPb).

• ESMPs will be used to identify and mitigate the environmental and social impacts that may emerge during implementation of schemes.

7

ESMPs of CDG Schemes 2013-14

ESMPs have been prepared of following 14 schemes of CDG:

1.REPAIR / IMPROVEMENT OF ROAD AWAN TOWN TO DARGAH TAHIRI NASEERABAD I/C DRAIN 2.REPAIR / IMPROVEMENT OF STREETS IN DHOKE GANGAL & DEFENCE COLONY3.REPAIR / IMPROVEMENT OF STREETS IN BANK COLONY DHAMIAL ROAD 4.REPAIR / IMPROVEMENT OF STREETS (LANE NO. 7) NEAR QADIR MOTORS 5.REPAIR / IMPROVEMENT OF STREET OPPOSITE DIVA CNG ADYALA ROAD6.REPAIR & IMPROVEMENT OF DHOKE MUSTAQEEM ROAD I/C DRAIN 7.REPAIR & IMPROVEMENT OF ROAD FROM SADIQ ABAD CHOWK TO PUMPAN WALA CHOWK

8

ESMPs of CDG Schemes 2013-14

8. REPAIR / IMPROVEMENT OF ROAD FROM SUZUKI STAND (KHANNA ROAD) TO JEHAZ GROUND

9. REPAIR / IMPROVEMENT OF ROAD FROM CHATRI CHOWK TO DHOKE HAFIZ CHOWK

10. REPAIR / IMPROVEMENT OF STREET I/C DRAIN FROM TAYYAB CNG CHOWK ON MAIN HIGH COURT ROAD TO AWAN CHOWK

11. REPAIR / IMPROVEMENT OF DEFENCE ROAD I/C REPAIR OF DRAIN FROM JAVAID STREET TO GATE C-BLOCK

12. REPAIR / IMPROVEMENT OF ROAD FROM KHANNA PULL TO GAIAN WALA CHOWK VIA CHUNGI NO. 8 (ALLAH WALA CHOWK) I/C NULLAH

13. REPAIR & IMPROVEMENT OF ALLAH ABAD SCHOOL ROAD UPTO IJP ROAD I/C BOTH SIDE DRAIN

14. REPAIR / IMPROVEMENT OF STREETS IN KHOKHAR ABAD, JAMSHED COLONY, ANWAR COLONY & PROFESSOR COLONY

9

CASESTUDY

ESMP OF REPAIR & IMPROVEMENT OF DHOKE

MUSTAQEEM ROAD I/C DRAIN

10

SCHEME INFORMATION• Length 1 KM• Total Cost: 10.727 Million

11

ENVIRONMENTAL AND SOCIAL SCREENING OF SCHEME

• Site visit of Team including officials from departments of Works & Services, Environment, Social and CPU-The Urban Unit

• Environment and social screening form filling

• Public consultation

• Finding:

Environmental category: E2 (ESMP prepared)

Social category: S3 (no further assessment required)

12

Experience during Screening

• Public was informed about the project/scheme through meetings

• Their comments / views / suggestions taken regarding the scheme

• People has shown positive attitude towards scheme and suggested to do more improvement in other areas too

• Some people enquired about work duration and suggested to complete the project soon in order to avoid hindrance in traffic flow and pedestrians walking

13

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

PREPARATION

• ESMP prepared by the Environment and Social Safeguards Specialist.

• The ESMP include details of the works to be carried out under the scheme, the site-specific environmental and social information, site-specific and scheme-specific mitigation measures, ESMP cost estimation and monitoring plan.

• The ESMP approved by Environment Protection Department, Punjab

14

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

• Environmental and social impacts, their mitigation measures and monitoring plan provided in the ESMP regarding the following parameters:

Air quality and Dust emissions

Noise

Waste management

Health and safety of workers and community

Traffic control

Disturbance to community etc.

15

ESMP IMPLEMENTATION COST

16

17

ESMP IMPLEMENTATION

• The ESMP cost included in the scheme implementation cost.

• The ESMP included in the bidding documents.

• Training of Contractors conducted regarding ESMP compliance

• Contractor's guideline for environmental and social management prepared by the Urban Unit distributed among the contractors

18

ESMP MONITORING

• Site visits of Team including officials from departments of Works & Services, Environment, Social and CPU-The Urban Unit

• Environment and social checklist

• Testing of environmental parameters through EPA certified laboratory

• On site training of labour and contractor

• Public consultation

• Photographic record

• Monitoring report preparation

19

EXPERIENCE DURING MONITORING

• Most of the people were happy for improvement of roads. They cooperated with the workers.

• Some people complained regarding inconvenience and suggested to complete work early.

• People of nearby areas gave their views to improve their streets also.

• Labour were reluctant to wear PPE’s. They were provided training and benefits of wearing PPEs.

• Contractors complaints regarding non cooperation of some residents. People were made satisfied through meetings and discussions.

20

SCENARIO BEFORE ESMF INTRODUCTION AT CDG

• No environmental and social screening of schemes carried out

• Cost of environmental and social management was not included in the schemes implementation cost

• No preparation of environmental and social management plans

• No environmental and social monitoring of schemes during execution

• Contractors were unaware about the environmental and social management

• No implementation of local Environmental laws and regulations (PEPA 1997, EIA/IEE Regulations 2000)

21

ESMF PRESENT SCENARIO

• Environmental and social screening is being carried out at scheme identification stage

• Cost of environmental and social management is being included in the schemes implementation cost

• Environmental and social management and monitoring plans are being prepared and implemented

• Contractors are being trained for environmental and social management

• Public consultation is being carried out at each step of scheme execution