Subject: DES – Arlington Metro Station Improvements
1
FY 2017 Proposed Work Session Follow-Up
April 10, 2016 The information below is in response to a request made by Mr. Vihstadt on a summary of current Arlington Metro station improvements.
I-1
Arlington County’s
Current Metro Station Capital Projects
(Project cost estimates shown are subject to review and
update as part of the proposed CIP for FY2017-FY2026.)
I-1
Metro Access Improvements Program
• WMATA’s CIP priorities focus on safety and state of good
repair
• County leads station access improvements to: – Ensure timely completion of projects
– Support increasing density around transit stations
– Improve continuous street-level access to Metrorail stations
– Ensure access points are compatible with communities’ urban design
• Project objectives:1. Improve ADA access and provide elevator redundancy
2. Improve emergency egress
3. Increase access/egress capacity at high ridership stations
4. Upgrade street level elevator exteriors
2I-1
• Project Scope:
• Improve ADA access and provide elevator
redundancy
• Design and construct second elevator near
existing west side escalator entrance
• Upgrade exterior of existing elevator
• Schedule:
• Completed Feasibility Study – 2010
• Completed PE – 2013
• Design – FY16 to FY17
• Construction – FY18 to FY19
• Working Est.: $5.1M (FY15-24 CIP)*
– Funding: $4.9M Fed/State Grants; $0.2M Local
– Fully funded, but aging federal and state grants
*Subject to review as part of proposed CIP for FY17-FY26. 3
Intersection of Hayes and 12th Streets
Existing ElevatorNew Elevator
Pentagon City Metro Station Second Elevator
I-1
4
Ballston-MU Metro Station West Entrance
• Project Scope:
• Design and construct full entrance at N.
Fairfax & N. Vermont
• New escalators and elevators from street
to tunnel and from mezzanine to platform
• New mezzanine over train platform
• Schedule:
• Completed PE – 2006
• Design – FY17 to FY19
• Construction – FY19 to FY22
• Working Est.: $89.9M (FY15-24 CIP)*
– Funding: NTVA Regional, State, Local and
Developer Contributions – Design phase funded;
construction not fully funded
*Subject to review as part of proposed CIP for FY17-FY26.
I-1
5
• Project Scope:
• Design and construct two ADA accessible
elevators to Metro station from street level in
front of 2200 Clarendon Blvd.
• Replace existing elevator, provide improved
service, and elevator redundancy
• Schedule:
• Completed Feasibility Study and Concept
Plan – 2014
• Design – FY17 to FY18
• Construction – FY18 to FY20
• Working Est.: $16.6M (FY15-24 CIP)*
– Funding: State, Local and Developer
Contributions – Design phase funded;
construction not fully funded*Subject to review as part of proposed CIP for FY17-FY26.
Court House Metro Station Second Elevator
I-1
6
• Project scope:
• Full second entrance located on Crystal Drive at
18th Street South
• Preliminary cost estimate: $68M*
• Some local and state funding identified; mostly
regional
• Potential to seek federal grant
• Milestones:
• Spring 2014 - feasibility and alternatives study
completed
• Winter/spring 2016 - finalize location and
concept design and update cost estimate
• TBD - design/construction
• Negotiating with WMATA to lead project and
include in WMATA CIP
*Subject to review as part of proposed CIP for FY17-FY26.