FY2021 COVID-19 FINANCIAL IMPACTS AS OF JULY 31, 2020
PRESENTED BY:Gary Gold
Interim Chief Financial Officer (CFO) & Assistant TreasurerAugust 31, 2020
In fo rmat iona l Upda te
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
3
2
DISCLAIMERWe continue to work through the unprecedented global, national,state, and local implications of COVID-19. Our current financialprojections were prepared in-light of COVID-19 for preliminaryinformational discussion purposes only. We are all early in thisperiod of COVID-19 implications, and as such, these financialprojections are preliminary and subject to change at any time inthe future. Please be assured that we worked hard to thoughtfullythink through our financial analysis. This said, since there istremendous uncertainty across the current economic and financiallandscapes, the actual results for this fiscal year could be lower,comparable, or higher than what we are projecting at this time.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
4
3
OBJECTIVES & TAKEAWAYS
• FINANCIAL RESULTS FORECAST• HIGHLIGHT FINANCIAL PERFORMANCE &
METRICS
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
5
4
AGENDA
• NET INCOME YTD• ELECTRIC SALES• NET INCOME FORECAST• FLOW OF FUNDS• KEY FINANCIAL METRICS• ACTIONS & NEXT STEPS
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
6
5
NET INCOME JULY 2020 YTD ACTUAL PERFORMANCE
Highlights: Net operating revenue – Driven
by lower sales due to COVID-19, offset by warmer weather.
O&M – Favorable due to hiring freeze and achieved budget mitigations.
Interest & debt-related –Reflects actuals from refinancing transactions and delay of GASB implementation regarding capitalized interest.
($ in millions)
Description
Revenue available for nonfuel expensesElectric $ 1,269.9 $ 1,198.1 $ (71.8) Gas 73.9 67.5 (6.4) Total operating revenue 1,343.8 1,265.6 (78.2)
Less:Electric fuel, distribution gas & regulatory 507.8 433.5 74.3 Payments to the City of San Antonio 163.2 162.5 0.7 Net operating revenue 672.8 669.6 (3.2)
Nonoperating revenue 10.8 14.2 3.4 Total revenue available for nonfuel expenses 683.6 683.8 0.2
Nonfuel expensesOperation & maintenance 356.7 340.1 16.6 Depreciation, amortization & decommissioning 219.6 214.6 5.0 Interest & debt-related 117.8 95.4 22.4 Total nonfuel expenses 694.1 650.1 44.0
Net Income (Loss) $ (10.5) $ 33.7 $ 44.2
FY2021
Budget ActualsVariance:Favorable
(Unfavorable)
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
7
Customer Sector Usage% of
Total Load% Impact onTotal Usage
Residential 9.5% 46.7% 4.4%
Churches & Services ‐9.3% 7.9% ‐0.7%
Manufacturing ‐1.4% 3.9% ‐0.1%
Retail ‐4.1% 5.2% ‐0.2%
Educational Services ‐9.1% 4.0% ‐0.4%
Hotel & Food Services ‐16.3% 4.9% ‐0.8%
Other** ‐5.0% 27.4% ‐1.3%
Total System 100.0% 0.9%
ELECTRIC SALES BY CUSTOMER SEGMENT- JULY 2020*
6
**Other sector includes other commercial sectors, food & wood product manufacturing, municipals, lighting, etc.
*Billed July actual performance to budget.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
8
7
NET INCOME POTENTIAL EFFECTS OF COVID-19
Assumptions: Operating Revenue - Retail Electric Sales estimated to be
4.7% lower. Assumes $28M of Bad Debt; $20M
higher than budget; 50% greater than the recession level of 2008.
Wholesale Revenue Net Fuel reduced from budget to $44M for the Medium Impact scenario. Lower market prices driven by assumed reduced ERCOT-wide demand & higher wind volumes.
Reflects actuals through July.
Interest & debt-related – Reflects actuals from refinancing savings & delay of GASB implementation regarding capitalized interest.
O&M – Reflects identified cost savings & reduction to labor associated with unfilled positions.
($ in millions)
Revenue available for nonfuel expensesElectric $ 2,522.1 $ 2,306.9 $ (215.2) $ 2,269.6 $ (252.5) Gas 183.0 158.3 (24.7) 158.3 (24.7) Total operating revenue 2,705.1 2,465.2 (239.9) 2,427.9 (277.2)
Less:Electric fuel, distribution gas & regulatory 995.1 896.2 98.9 887.0 108.1 Payments to the City of San Antonio 365.3 335.9 29.4 326.1 39.2 Net operating revenue 1,344.7 1,233.1 (111.6) 1,214.8 (129.9)
Nonoperating revenue 71.2 70.1 (1.1) 43.1 (28.1) Total net revenue available for nonfuel expenses 1,415.9 1,303.2 (112.7) 1,257.9 (158.0)
Nonfuel expensesOperation & maintenance 712.8 664.8 48.0 669.8 43.0 Depreciation, amortization & decommissioning 457.1 454.3 2.8 454.3 2.8 Interest & debt-related 242.1 212.5 29.6 212.5 29.6 Total nonfuel expenses 1,412.0 1,331.6 80.4 1,336.6 75.4
Net Income (Loss) $ 3.9 $ (28.4) $ (32.3) $ (78.7) $ (82.6)
COVID-19Medium Impact
Budget
FY2021
COVID-19High
Impact
Variance:Favorable
(Unfavorable)
Variance:Favorable
(Unfavorable)
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
9
-$34.0
+$7.5 +$0.8 +$2.7
-$4.0
-$1.4
-$60.0
-$50.0
-$40.0
-$30.0
-$20.0
-$10.0
$0.0
PreviousForecast
Net RetailRevenue
Net WholesaleRevenue
OtherRevenues
Depreciation &Amortization
Debt‐RelatedExpenses
COVID‐19MediumImpact
($ in millions)
NET INCOMEPOTENTIAL EFFECTS OF COVID-19MEDIUM IMPACT: PREVIOUS TO CURRENT FORECAST
8
Updated for
actuals thru July
Delay of GASB implementation
regarding capitalized
interest & Finance Plan savings
Performance lower due to higher wind volumes and softer market prices in July.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
10
9
FLOW OF FUNDSPOTENTIAL EFFECTS OF COVID-19
Assumptions: Operating Revenue - Retail Electric Sales estimated to be
4.7% lower. Assumes $28M of Bad Debt; $20M
higher than budget; 50% greater than the recession level of 2008.
Wholesale Revenue Net Fuel reduced from budget to $44M for the Medium Impact scenario. Lower market prices driven by assumed reduced ERCOT-wide demand & higher wind volumes.
Reflects actuals through July.
Interest & debt-related – Reflectsactuals from refinancing savings.
O&M – Reflects identified cost savings & reduction to labor associated with unfilled positions.
Capital – Reflects identified cost mitigations.
($ in millions)
Revenues, net of unbilled $ 2,758.2 $ 2,511.2 $ (247.0) $ 2,445.3 $ (312.9) Less: city payment (CP) per flow of funds 365.3 335.9 29.4 326.1 39.2
Revenues, net of unbilled & CP 2,392.9 2,175.3 (217.6) 2,119.2 (273.7) Less: fuel & regulatory expense 995.1 896.2 98.9 887.0 108.1 Revenues, net fuel & regulatory 1,397.8 1,279.1 (118.7) 1,232.2 (165.6)
Operation & maintenance 714.4 669.0 45.4 674.0 40.4 Debt service 425.9 406.1 19.8 406.1 19.8 Total expenses 1,140.3 1,075.1 65.2 1,080.1 60.2
6% Gross Revenue to R&R 165.5 150.7 (14.8) 146.7 (18.8) Remaining to R&R 92.0 53.3 (38.7) 5.4 (86.6) Total R&R fund additions $ 257.5 $ 204.0 (53.5) $ 152.1 (105.4)
Total capital expenditures $ 625.8 $ 581.1 44.7 $ 581.1 44.7
FY2021
BudgetCOVID-19Medium Impact
COVID-19High
Impact
Variance:Favorable
(Unfavorable)
Variance:Favorable
(Unfavorable)
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
11
KEY FINANCIAL METRICS, PART 1POTENTIAL EFFECTS OF COVID-19
1 Aligned to Credit Ratings Agency Guidance
ADSC & DCOH degraded resulting from COVID-19 Could signal a monitor from Credit Ratings AgencyLegend
Outside of Credit Ratings Agency GuidanceOn Target with Credit Ratings Agency Guidance
10
Metric FY2020Actuals Budget
Accountability Plans
Threshold
COVID-19 Medium Impact
COVID-19 High
Impact
Adjusted Debt Service Coverage (ADSC)
1.94 1.60 1.501 1.50 1.37
Days Cash on Hand (DCOH) 225 161 1501 167 157
• Management will work to implement additional mitigations to improve financial performance
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
12
Metric FY2020Actuals Budget
Accountability Plans
Threshold
COVID-19 Medium Impact
COVID-19 High
Impact
Debt Capitalization (DC)
59.9% 61.7% 61.7%1 60.5% 60.8%
KEY FINANCIAL METRICS, PART 2POTENTIAL EFFECTS OF COVID-19
1 Aligned to the Financial Gate Protocol Set by the Board of Trustees11
LegendOn Target with Credit Ratings Agency Guidance
• Management will work to implement additional mitigations to improve financial performance
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
13
12
ONGOING ACTIONS• Continue to monitor COVID-19 landscape• Analyze actual sales results to better understand
demand patterns• Monitor accounts receivable & bad debt, providing
customers with information on assistance programs• Focus on cash flows to ensure liquidity• Prioritize ongoing spend to identify additional cost
reductions & cash savings• Scan for emerging risks• Continue to provide monthly updates
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
14
Thank You
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
15
COST SAVINGS: SWEETWATER 3 WIND FARM REPOWER
PRESENTED BY:
Kevin PolloInterim VP
Energy Supply & Market Operations
August 31, 2020
In fo rmat iona l Update
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
16
OBJECTIVES & TAKEAWAYS
2
• HIGHLIGHT CUSTOMER BENEFITS FROM WIND REPOWERING & CONTRACT NEGOTIATION
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
17
AGENDA
3
• BACKGROUND
• STRATEGIES
• SAVINGS SUMMARY
• ONGOING FOCUS
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
18
4
BACKGROUND• We were contacted last year by the owner/operator of the
Sweetwater 3 Wind Farm to seek our agreement to repower the turbines
• Repowering consists of replacing blades & turbines with more efficient technology such as longer, lighter blades & higher capacity turbines
• Owner/operators are incentivized to repower to leverage advancing technology and due to the federal Production Tax Credit (PTC)
Benefits of repowering include increased output, improved reliability, & lower cost.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
19
5
SAVINGS STRATEGYCONTRACT AMENDMENT
We successfully negotiated a contract amendment that will give us lower cost power without changing the original contract length.
We remain committed to renewable energy sources through our Flexible Path.
Annual Savings
Remaining Years
Total Savings
$1.4M 5 $7M
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
20
6
SAVINGS STRATEGYBENEFITS
The $7 million in savings will be passed on to our customers, helping keep bills affordable.
Customer Affordability is one of our Guiding Pillars.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
21
7
SUMMARY
• We are committed to keeping our energy affordable & will continue our efforts to be a trusted energy advisor for our customers & community.
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
22
8
OUR GUIDING PILLARS &FOUNDATION
Identifying savings supports our Financially Responsible foundation & Customer Affordability pillar.
SecurityCustomer
AffordabilityReliability
EnvironmentalResponsibility Resiliency Safety
FINANCIALLYRESPONSIBLE
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
23
Thank You
August 31, 2020 Board Meeting - UPDATE ON CHAIR’S PRIORITIES
24
Draft for review and approval at the August 31, 2020 meeting
CPS ENERGY MINUTES OF REGULAR MEETING OF THE BOARD OF TRUSTEES
HELD ON JULY 27, 2020
The Regular Meeting of the Board of Trustees of CPS Energy for the month of July was held on Monday, July 27, 2020, by telephone conference in order to advance the public health goal of limiting face-to-face meetings (also called “social distancing”) to slow the spread of the Coronavirus (COVID-19). There was no in-person public access to the meeting. Chair John Steen called the meeting to order at 1:00 p.m. Present via phone were Board members: Mr. John Steen, Chair Dr. Willis Mackey, Vice Chair Mr. Ed Kelley Ms. Janie Gonzalez Mayor Ron Nirenberg
Also present via phone were: Ms. Paula Gold-Williams, President & CEO Dr. Cris Eugster, Chief Operating Officer Ms. Carolyn Shellman, Chief Legal Officer & General Counsel and Board Secretary Mr. Fred Bonewell, Chief Security, Safety & Gas Solutions Officer Ms. Vivian Bouet, Chief Information Officer Mr. Frank Almaraz, Chief Administrative & Business Development Officer Mr. Rudy Garza, Interim Chief Customer Engagement Officer CPS Energy Staff Members City of San Antonio officials Interested Citizens I. ROLL CALL OF BOARD MEMBERS Ms. Shellman called the roll and confirmed the presence of a quorum. II. SAFETY MESSAGE The Board meeting began with a safety message delivered by Mayor Nirenberg and Ms. Gold-Williams. Mayor Nirenberg noted that hospitalizations in Bexar County due to COVID-19 are leveling off, but we remain under an order limiting large indoor gatherings and requiring face coverings. He asked the public for patience and compliance. He commented on the recent dialogue which has focused on how schools can safely reopen for Fall 2020 classes. Ms. Gold-Williams thanked Mayor Nirenberg and Judge Nelson Wolff for their diligence in keeping our community safe, especially since our employees perform an essential service for the community. She noted that as of July 23, 2020, 67 CPS Energy employees have tested positive for the COVID-19 virus, and 251
August 31, 2020 Board Meeting - CONSENT AGENDA
25
Draft for review and approval at the August 31, 2020 meeting
are quarantined because of possible exposure. To date, there have not been any employee deaths and there are currently no employee hospitalizations due to COVID-19. CPS Energy employees continue practicing physical distancing and wearing face coverings. Chair Steen thanked Mayor Nirenberg and Ms. Gold-Williams for their leadership during this challenging time. III. INVOCATION An invocation was delivered by Ms. Melissa Sorola, Interim Senior Director, Corporate Communications, Marketing & Smart City Outreach. IV. PUBLIC COMMENT Chair Steen announced that public comments would be taken and outlined the guidelines for making public comment. The following people made comments:
1. Mr. Rey Chavez, President & CEO of the San Antonio Manufacturer’s Association (SAMA), stated that SAMA opposes the creation of the Rate Advisory Committee (RAC) because the Citizens Advisory Committee has been an efficient and effective liaison between the public and CPS Energy.
2. Ms. Henrietta LaGrange spoke about her concerns with the poles and wires around her home and requested that someone call her to discuss.
3. Mr. John Agather spoke against the creation of the RAC, commenting that it is being proposed for political expediency and will result in unnecessary bureaucracy.
4. Mr. Richard Perez, President & CEO of the San Antonio Chamber of Commerce, stated that this challenging time is not right for the creation of the RAC and that efforts to advance it should be postponed.
5. Dr. Meredith McGuire, Sierra Club, noted her interest in the FlexPOWER Bundle and asked CPS Energy to implement the next iteration of Save for Tomorrow Energy Plan (STEP). She also expressed concern about the impacts of the COVID-19 pandemic and urged rehabilitative programs.
V. CEO REPORT Ms. Gold-Williams provided context for several agenda items, including the FlexPOWER Bundle update. She highlighted the global request for information (RFI) being issued today. Ms. Gold-Williams reminded the Board that we have been looking for ways to partner with the San Antonio Water System (SAWS) to leverage our buying power. Currently, there is a potential opportunity to partner with them on a project which, if successfully advanced by SAWS, we may broach with the Board in August. Notably, the City of San Antonio (City) has encouraged this type of collaboration which creates economic, service and operational benefits. Ms. Gold-Williams noted that there are a host of tariffs, such as the Resiliency Tariff, Electric Vehicle (EV) Tariff, Wholesale Distribution Services Tariff, and On-Site Solar Tariff that we plan to discuss with the Board. The Line Extension Policy, which needs to be updated, will also be discussed at a future meeting.
August 31, 2020 Board Meeting - CONSENT AGENDA
26
Draft for review and approval at the August 31, 2020 meeting
Ms. Gold-Williams thanked Trustee Gonzalez for participating in a recent virtual program for our interns who are unable to partake in an in-person internship this summer due to the pandemic. Regarding the RAC, we continue to take input and are working internally on proposed options to present to the Board. In conclusion, she listed recent awards earned by CPS Energy, including Peak Load Management’s Thought Leadership for Public Engagement award and Escalent’s Most Trusted Brand award, which we have received for five consecutive years. VI. ADDITIONAL UPDATES A. FY2021 COVID-19 Financial Impact, Cont. Mr. Gary Gold, Vice President, Corporate Services & Assistant Treasurer, presented the FY2021 COVID-19 Financial Impact. This update includes actual results through June 30, 2020, and projections for the remainder of the fiscal year. Because of the uncertainty related to the full impact of COVID-19, these projections were noted to be preliminary and subject to change. Mr. Gold explained that for the fiscal year through June 30, 2020, the Company budgeted a net loss of $3.2 million. However, the actual year-to-date net income amount is $25.8 million, a favorable variance of $29 million. The favorability is driven by lower operations and maintenance (O&M) expense, as well as lower interest and debt-related expenses. Turning to June electric sales by customer segment, commercial and industrial customers used less power than projected. Residential customers, on the other hand, increased their usage. Overall, total system sales are approximately 3.7 percent below budget. Regarding the potential effects of COVID-19 on net income for FY2021, a net loss of $34.0 million is projected, assuming a Medium Impact scenario. A High Impact scenario is projected to result in a net loss of $63.2 million. These projections are based on assumptions that retail electric sales will be 5.4 percent lower than projected, wholesale revenues will be lower than budget and bad debt levels will be higher. Turning to the Flow of Funds, Mr. Gold stated that Total Repair and Replacement (R&R) Fund additions for the year were budgeted to be $257.5 million. Considering the effects of COVID-19, R&R Fund additions in a Medium Impact scenario are projected to be $201.1 million, slightly lower from the June projections. A High Impact scenario is projected to result in R&R Fund additions of $170.5 million. Mr. Gold highlighted that actual capital expenditures year-to-date are $44.7 million under budget, reflecting cost mitigations. Turning to the key financial metrics, the forecasted Adjusted Debt Service Coverage (ADSC) is 1.49x for the Medium Impact scenario, lower than the June projection of 1.50x, and slightly below the accountability plan threshold of 1.50x. In the High Impact scenario, ADSC is projected to be 1.42x. Days Cash on Hand (DCOH) for the Medium Impact scenario is projected at 166, better than the accountability plan’s threshold of 150. In the High Impact scenario, DCOH is projected to be 161. The Debt Capitalization (DC) ratio is projected to
August 31, 2020 Board Meeting - CONSENT AGENDA
27
Draft for review and approval at the August 31, 2020 meeting
be 60.5 percent for the Medium Impact scenario and 60.7 percent for the High Impact scenario, both favorable to the accountability plan threshold of 61.7 percent. We continue to monitor the pandemic and take the following steps to minimize its impact:
- Analyze actual sales results to better understand demand patterns - Monitor accounts receivable and bad debt, providing customers with information on assistance
programs - Focus on cash flows to ensure liquidity - Prioritize ongoing spend to identify additional cost reductions and cash savings - Scan for emerging risks - Continue to provide monthly updates
Dr. Mackey complimented Mr. Gold on doing an outstanding job, particularly under difficult circumstances. B. Moving forward with the FlexPOWER Bundle Dr. Eugster provided an overview of CPS Energy’s next step regarding the FlexPOWER Bundle, which is to issue an all-source RFI to identify transformative and innovative solutions to power our community. He recapped the Flexible Path strategy, transitioning from traditional power plants to more generation sources that include traditional sources plus renewables, energy storage, smart grid technology and energy efficiency. The FlexPOWER Bundle is the future of the Flexible Path strategy, providing more zero-emission power generation sources to our customers. The Flexible Path strategy is grounded in our Strategic Pillars, with particular focus on Environmental Responsibility. Dr. Eugster recapped the milestones achieved to get where we are today, including the retirement of the Deely coal power plant in 2018, the FlexPOWER Bundle launch and the public input session in 2019. Most recently, we issued a request for proposals (RFP) for a consultant to assist with the FlexPOWER Bundle. Our next step is the issuance of an RFI that will support and shape the FlexPOWER Bundle RFP later this year. Over 30 percent of CPS Energy’s capacity comes from plants that are over 40 years old. Dr. Eugster explained that the FlexPOWER Bundle is intended to replace and supplement these aging power plants with new low-to-zero emission technologies. The FlexPOWER Bundle seeks to add up to 900 MWs of solar, 50 MWs of energy storage and an all-source firming capacity to our generation portfolio. It is a meaningful step towards the City’s Climate Action and Adaptation Plan, which the Board supported through a resolution adopted in August 2019. The approach for the all-source RFI is to “think globally and apply locally” so that we can get valuable and innovative solutions for our customers. This approach will also raise our global visibility, identify global and local players, reveal market conditions and help us to understand COVID-19 impacts as we move towards issuing the RFP. Audio messages announcing the FlexPOWER Bundle RFI recorded by Mayor Nirenberg and Ms. Gold-Williams were played at this time.
August 31, 2020 Board Meeting - CONSENT AGENDA
28
Draft for review and approval at the August 31, 2020 meeting
In conclusion, Dr. Eugster noted that, barring any issues, the RFI would be issued today. In response to an inquiry by Trustee Kelley, Dr. Eugster stated that the 500 MWs of all-source capacity must be available at all times to firm up intermittent renewable sources. Initially, we contemplated that the firming capacity would be natural gas, but in response to feedback, we are open to other sources that meet the defined operating characteristics needed to serve our customers. Trustee Kelley asked about a scenario in which pricing of the firming capacity is significantly less than that of the solar component. Dr. Eugster replied that the RFI is intended to bring some clarity to the economics and environmental aspects of certain sources. For example, the cost of solar has recently dropped significantly, but it is not constant. The RFI will help us understand how solar can work with storage and other firming capacity before we issue the RFP. Trustee Kelley commented that utility assets are long-lived. He asked how our generation portfolio ratio of plants older than 40 years compares with our historical ratio and asked whether the ratio was inordinate. Dr. Eugster stated that assets 40 years and older tend to experience reliability issues and require more maintenance. Plants are typically retired in the 40 to 55-year timeframe and, from an accounting perspective, plants older than 55 years are considered “end of life.” Utilities consider many factors when determining when to retire a plant. We are fortunate to have some flexibility around how we want to replace our aging assets. Trustee Kelley concluded his comments by emphasizing the “all-source” component of the FlexPOWER Bundle and cautioned against an overreliance on renewable energy, recognizing that this has been an issue for some municipal utilities. Dr. Eugster agreed, stating that we will be looking closely at many factors, including the operating characteristics of resources that are available to us. VII. APPROVAL OF CONSENT ITEMS: On motion duly made by Dr. Mackey, seconded by Trustee Kelley, and upon affirmative vote by all members present, the following items on the Consent Agenda were unanimously approved. Approval of Minutes
Minutes of the Regular Board Meeting held on June 29, 2020, were approved as submitted. Approval of Payment to the City of San Antonio for June 2020
The New Series Bond Ordinance that took effect February 1, 1997, provides for a total cash payment to the City of San Antonio (City) in an amount not to exceed 14% of gross revenue as calculated pursuant to such Ordinance, less the value of other services provided to the City, with the percentage (within the 14% limitation) to be determined by the governing body of the City. The cash transfer to the City for the month of June 2020 is based on actual gross revenue per the New Series Bond Ordinance of $215,516,163.02, less applicable exclusions. The revenue for the month of June 2020 is calculated as follows:
August 31, 2020 Board Meeting - CONSENT AGENDA
29
Draft for review and approval at the August 31, 2020 meeting
Gross revenue per CPS Energy financial statements
Electric revenue $227,156,673.67
Gas revenue 9,101,499.16
Interest and other income 2,578,470.44
Gross revenue per CPS Energy financial statements 238,836,643.27
Excluded revenue
School and hospital revenue per City Ordinance 55022 (5,780,309.52)
LVG revenue per City Ordinance 100709 0.00
Fuel cost component of off-system nonfirm
energy sales per City Ordinance 61794
and revenue for wholesale special contracts (7,653,485.23)
Noncash and other income, GASB 31
investment market value change, miscellaneous
Interest income, gas billing adjustment and unbilled
revenue (9,886,685.50)
Total excluded revenue (23,320,480.25)
Gross revenue per New Series Bond Ordinance subject to
14% payment to the City $215,516,163.02
City payment per Bond Ordinance for June 2020
based upon June 2020 revenue $30,172,262.82
City payment per memorandum of understanding (MOU) regarding wholesale special contracts 519,011.68
Wholesale Special Contract Annual True Up 751,228.87
City Payment reduction per gas customer billing adjustment MOU (12,500.00)
City payment per Bond Ordinance plus adjustments for
memorandums of understanding 31,430,003.37 A
Utility services provided to the City for June 2020 (2,400,721.98)
Net amount to be paid from June 2020 revenue to
the City in July 2020 $29,029,281.39
Comparison of City payment per Bond Ordinance (plus adjustments for memorandums of understanding) vs. Budget before deduction for utility services provided to the City:
(Dollars in thousands)
June 2020 Actual Budget Variance
Current Month* A $31,430 $32,921 ($1,491) -4.5%
Year-to-Date* $124,959 $132,536 ($7,577) -5.7%
* This amount does not include any additional funding authorized by the Board of Trustees.
Approval of the following resolution is requested:
"BE IT RESOLVED by the CPS Energy Board of Trustees that payment to the City of San Antonio in the amount of $29,029,281.39, representing 14% of applicable system gross revenues for the month of June
August 31, 2020 Board Meeting - CONSENT AGENDA
30
Draft for review and approval at the August 31, 2020 meeting
2020, such payment being net of City utility services ($2,400,721.98), is hereby approved.” The Board ratifies that June 2020 revenue was sufficient to recover $18,046,652.38 in funds that were advanced to the City in prior fiscal months. The remaining amount to be recovered from future months’ revenues for fiscal year 2021 is $40,541,644.00. VIII. COMMITTEE REPORTS Audit & Finance (A&F) Committee Meeting Dr. Mackey stated that a report of the A&F meeting which took place on July 8, 2020, was posted with the public notice of this meeting and will be attached (as Attachment “A”) to the meeting minutes. Employee Benefits Oversight Committee (EBOC) Meeting Dr. Mackey stated that a report of the EBOC meeting which took place on July 8, 2020, was posted with the public notice of this meeting and will be attached (as Attachment “B”) to the meeting minutes. A&F & EBOC Aligned Risk Sub-Committee Meeting Dr. Mackey stated that a report of the A& and EBOC Aligned Risk Sub-Committee meeting which took place on July 8, 2020, was posted with the public notice of this meeting and will be attached (as Attachment “C”) to the meeting minutes. IX. NEW PRODUCT: GREEN TARIFF Mr. Chad Hoopingarner, Senior Director, Strategic Pricing & Cost Recovery, presented the Green Tariff for Board approval. He reminded the Board that the Tariff was presented during the June 2020 Board meeting and, because of questions and requests for additional information, further discussion was occurring today. The Tariff provides several strategic benefits. It meets customer needs by providing flexible options available in other markets. The Tariff also creates optionality for our Flexible Path while contributing to the fixed cost of our existing generation fleet. Finally, the Tariff design maintains revenue and improves our recovery of fixed costs. Mr. Hoopingarner recapped CPS Energy’s efforts since 2017 to develop and finalize the design of the proposed Tariff. He highlighted our objective in crafting the Tariff - designing a pricing structure that fairly recovers the cost of infrastructure through fixed charges, not volumetric charges, while also improving renewable energy access. Mr. Hoopingarner explained that about 56 percent of the current cost to serve commercial customers is variable. The remaining 46 percent comprises fixed costs, such as the cost of infrastructure and operating & maintenance costs. However, our current commercial rate structures deliver about 72 percent of revenue from the variable, volumetric elements of the bill, and only 28 percent from fixed elements, resulting in a difference between fixed costs and recoveries through the fixed recovery elements on the bill. The Green Tariff fixes that problem by decreasing the variable components and increasing the fixed components of the
August 31, 2020 Board Meeting - CONSENT AGENDA
31
Draft for review and approval at the August 31, 2020 meeting
rate. Notably, the Tariff produces the same amount of revenue as the current commercial rates and maintains the same amount of CPS Energy’s general fund transfer to the City. In response to Board feedback about the Tariff received during the June 2020 Board meeting, CPS Energy will carefully monitor the efficacy of the Tariff and provide quarterly updates to the Board during Board committee meetings and annually during the July Board meeting. Additionally, the Tariff has been modified to restrict additional participation if unintended consequences are identified. Relative to other new product offerings, we will undertake increased Board engagement as the products are being developed and before Board approval is requested. Mr. Hoopingarner requested Board approval of the Green Tariff. Responding to Chair Steen’s concerns, Mr. Hoopingarner and Ms. Gold-Williams stated that all Trustees, including Mayor Nirenberg at his convenience, will receive updates on the Tariff. Trustee Kelley commented that he was not comfortable voting for the Tariff during the June Board meeting because he did not have enough information about it, having previously discussed only general terms about it. The improvements made as a result of Board feedback address his concerns. Finally, Trustee Kelley stressed the value of work sessions to prepare the Board on emerging tariffs before they are presented for Board approval. Chair Steen concurred. Mayor Nirenberg commented in favor of the Green Tariff. On motion duly made by Mayor Nirenberg, seconded by Trustee Gonzalez, and upon affirmative vote by all members present, the Green Tariff was unanimously approved. X. OUR BRAND JOURNEY Mr. Rudy Garza, Interim Chief Customer Engagement Officer, provided an overview of CPS Energy’s brand and logo. He defined the basic concepts and discussed the evolution of each, noting that, when properly aligned, a company’s logo should fit on a well-designed brand. So, periodically considering a logo refresh is appropriate. CPS Energy’s brand – taking care of our customers – is presently very strong. Our current logo was introduced 15 years ago, in 2005. Our brand has been tested through customer feedback, including surveys and focus groups. Since 2016, we have strengthened our brand and have improved service satisfaction by 3 percent, or 26 points. Mr. Garza noted the Cogent/Escalent awards CPS Energy has earned since 2015, indicating a positive brand trend. Trustee Gonzalez, Ms. Gold-Williams and Mr. Garza discussed some pros and cons of rebranding and changing our logo. Trustee Gonzalez noted that during these challenging times, updating the logo may not carry the same priority as other initiatives, such as the FlexPOWER Bundle or rate affordability. She offered specific feedback on the current logo’s design. Ms. Gold-Williams thanked her for her input and agreed to continued discussion if there is Board interest to continue exploring rebranding and updating the logo.
August 31, 2020 Board Meeting - CONSENT AGENDA
32
Draft for review and approval at the August 31, 2020 meeting
XI. BRAND SENTIMENT Mr. Garza introduced Ms. Mary Repole of Epiphany Research & Marketing, Inc. to provide the results of recent brand sentiment focus group research. The research, conducted in September 2019, sought to explore the strength of CPS Energy’s brand; gather reaction to the company’s visual and verbal brand identity; determine the attributes and perceptions that customers associate with brand personality; and gain an understanding of perceived consistency of selected communication efforts, content relevance, and delivery effectiveness. The focus groups were demographically and socio-economically diverse and included small and medium commercial customers. Regarding visual and verbal brand identity, the research indicated that participants recognized CPS Energy’s logo, acronym and name, and liked the logo. Spanish-speaking participants were less aware of what “CPS” stood for, and all participants noted some confusion with Child Protective Services. CPS Energy’s brand image is driven by field employees and the company’s practices of helping customers manage energy and lower cost. Our evolution towards renewable energy and giving back to the community also affects brand perceptions. The commercial customer group was the least positive and was not aware of programs tailored for them. Ms. Repole noted that most customers view CPS Energy as innovative and trustworthy and compared our “innovation and trustworthy” scores to those of other local companies and utilities. She stated that CPS Energy is currently more positively perceived than in the past. Overall, CPS Energy’s brand is positively viewed, but its strength is limited by customers’ lack of critical information about its role in the community, including our financial contribution to the City. Ms. Repole suggested strengthening the connection between the positive perception of field employees with the brand. Focus group participants were overwhelmingly impressed with Ms. Gold-Williams’ demeanor and found her to be the living embodiment of a progressive, innovative company. They were surprised and appreciative of her ethnicity and gender. Customers stated they want to know more about CPS Energy, including its plans for the future, and would like more communication in a method of their choosing. In contrast to past sentiments, they asked for more advertisements and streaming content on social media. Commercial customers stated that an account manager would be the best way to interact with them. Mr. Garza noted that since the research was conducted in 2019, CPS Energy has implemented many of the suggestions made by the participants, including television commercials, social media events, print ads, outbound customer calls, and account management for small and medium businesses. At Chair Steen’s request, Ms. Repole provided a brief background of her company, Epiphany, highlighting that it is a local business. Mayor Nirenberg commented that while a discussion about our brand may seem superficial at this time, it is meaningful as it contemplates what the next era of the company, including energy production, will look like. So, the conversation is welcomed, though we must remain judicious about the time and resources put into it. Chair Steen stated that this topic grew out a conversation with Ms. Gold-Williams prior to the COVID-19 pandemic. He noted that our logo has evolved over the years and it should not be static. Although the focus
August 31, 2020 Board Meeting - CONSENT AGENDA
33
Draft for review and approval at the August 31, 2020 meeting
groups indicated that we are a trusted brand, he opined that our logo looks old-fashioned and is not reflective of the innovative company that we strive to be. He acknowledged that there is a cost factor to updating the logo and that other initiatives have a higher priority at this time. He questioned whether any special efforts with small business customers are necessary given their responses in the focus group research. Trustee Gonzalez responded that small businesses want tools for effective decision-making and ways to leverage CPS Energy’s existing and future products and services. Regarding brand sentiment, she noted that customers want action regardless of the logo. We should understand the diversity and literacy levels, including digital literacy, of our community and provide different programs and services around communication. Cultural marketing should be part of our strategy. Mr. Garza agreed that there are many opportunities across differing customer segments, including small business, Spanish-speaking and elderly customers, and we are working to improve in those areas. Ms. Gold-Williams confirmed that she and Chair Steen discussed this topic before the pandemic. She acknowledged that we currently have a good brand foundation and, whether or not our logo is refreshed, the real value is in anything that helps our customers. We strive to remain self-critical for the benefit of our customers and community. Ms. Gold-Williams thanked the Board for their feedback and commented that while there is a need to control costs, we want to keep this topic on the Board’s agenda, so we will provide options tied to costs soon. XII. EXECUTIVE SESSION At approximately 3:30 p.m., Chair Steen announced that the required notice had been posted and that the Trustees, with only necessary parties in attendance, would convene into Executive Session, pursuant to the provisions of Chapter 551 of the Texas Government Code, for discussion of the following posted items:
• Attorney-Client Matters (§551.071)
• Competitive Matters (§551.086)
The Board reconvened in open session at 5:02 p.m. Ms. Shellman reported that only Attorney-Client Matters and Competitive Matters, and no others, were discussed and no votes were taken in Executive Session. XIII. ADJOURNMENT There being no further business to come before the Board and upon a motion duly made by Trustee Kelley and seconded by Trustee Gonzalez and upon an affirmative vote by all members present, the meeting was unanimously adjourned at 5:03 p.m. by Chair Steen. _____________________________ Carolyn E. Shellman Secretary of the Board
August 31, 2020 Board Meeting - CONSENT AGENDA
34
CPS Energy Board of Trustees Meeting August 31, 2020
Approval of Payment to the City of San Antonio for July 2020 The New Series Bond Ordinance that took effect February 1, 1997 provides for a total cash payment to the City of San Antonio (City) in an amount not to exceed 14% of gross revenue as calculated pursuant to such Ordinance, less the value of other services provided to the City, with the percentage (within the 14% limitation) to be determined by the governing body of the City. The cash transfer to the City for the month of July 2020 is based on actual gross revenue per the New Series Bond Ordinance of $266,169,432.17, less applicable exclusions. The revenue for the month of July 2020 is calculated as follows: Gross revenue per CPS Energy financial statements
Electric revenue $277,986,032.08 Gas revenue 9,044,021.16 Interest and other income 2,013,667.16 Gross revenue per CPS Energy financial statements 289,043,720.40
Excluded revenue
School and hospital revenue per City Ordinance 55022 (6,547,721.82)
LVG revenue per City Ordinance 100709 0.00 Fuel cost component of off-system nonfirm
energy sales per City Ordinance 61794
and revenue for wholesale special contracts (9,378,569.06)
Noncash and other income, GASB 31
investment market value change, miscellaneous
Interest income, gas billing adjustment and unbilled
revenue (6,947,997.35)
Total excluded revenue (22,874,288.23) Gross revenue per New Series Bond Ordinance subject to
14% payment to the City $266,169,432.17
City payment per Bond Ordinance for July 2020
based upon July 2020 revenue $37,263,720.50
City payment per memorandum of understanding (MOU) regarding wholesale special contracts 311,231.14
Wholesale Special Contract Annual True Up 0.00 City Payment reduction per gas customer billing adjustment MOU (12,500.00) City payment per Bond Ordinance plus adjustments for
memorandums of understanding 37,562,451.64 A Utility services provided to the City for July 2020 (2,605,907.17) Net amount to be paid from July 2020 revenue to
the City in August 2020 $34,956,544.47
August 31, 2020 Board Meeting - CONSENT AGENDA
35
CPS Energy Board of Trustees Meeting August 31, 2020
Comparison of City payment per Bond Ordinance (plus adjustments for memorandums of understanding)
vs. Budget before deduction for utility services provided to the City:
(Dollars in thousands) July 2020 Actual Budget Variance
Current Month* A $37,562 $40,782 ($3,220) -7.9%
Year-to-Date* $162,521 $173,318 ($10,797) -6.2% * This amount does not include any additional funding authorized by the Board of Trustees.
Approval of the following resolution is requested:
"BE IT RESOLVED by the CPS Energy Board of Trustees that payment to the City of San Antonio in the amount of $34,956,544.47, representing 14% of applicable system gross revenues for the month of July 2020, such payment being net of City utility services ($2,605,907.17), is hereby approved.” The Board ratifies that July 2020 revenue was sufficient to recover $40,541,644.00 in funds that were advanced to the City in prior fiscal months.
August 31, 2020 Board Meeting - CONSENT AGENDA
36
Executive Summary
Appointment of Treasurer & Assistant Treasurers For the CPS Energy Board of Trustees
Prepared By: Treasury 8/12/2020 Page 1 of 2
BACKGROUND:
Gary Gold was recently promoted to Interim Chief Financial Officer (CFO) to oversee CPS Energy’s financial functions.
There are currently three Assistant Treasurers:
• Gary Gold
• Shannon R. Albert • Maricela Benavides
With Gary Gold’s promotion to Interim CFO, we are recommending the following
appointments to help further facilitate effective and timely financial transaction coverage.
1. The appointment of Gary Gold as Treasurer effective September 1, 2020.
2. The appointment of Cory Kuchinsky as an Assistant Treasurer
effective September 1, 2020.
Gary Gold is the Interim CFO at CPS Energy. Gary joined CPS Energy in 2005 and has served in a variety of
positions, most recently as Vice President of Corporate Services & Assistant Treasurer. Gary is a Certified Public
Accountant (CPA) with over 30 years in the energy industry. He holds a BBA with an emphasis in Accounting
from the University of Texas at San Antonio.
Cory Kuchinsky is the Interim Vice President of Strategic Pricing & Enterprise Risk Management and Solutions. Cory
joined CPS Energy in 2006 and has served in several
positions, including as the Senior Director of Grid Transformation Management. Prior to joining CPS Energy,
Cory worked for Ernst & Young. He has over eight years as an adjunct instructor teaching numerous university level
accounting courses at several local institutions. Cory is a CPA and holds a Bachelor of Science in Business
Administration and a Master of Science in Accounting from
Trinity University in San Antonio.
August 31, 2020 Board Meeting - REGULAR AGENDA
37
Executive Summary
Appointment of Treasurer & Assistant Treasurers For the CPS Energy Board of Trustees
Prepared By: Treasury 8/12/2020 Page 2 of 2
3. The appointment of Julie Johnson as an Assistant Treasurer effective
September 1, 2020.
ACTION REQUIRED:
• Board approval of Appointment of Treasurer and two new Assistant Treasurers
(for a total of four Assistant Treasurers) • Should you have any questions or need any additional information, please
contact Shannon R. Albert at 210-353-3818 (office) or 210-319-0250 (cell) or
Gary Gold at 210-353-2523 (office) or 210-414-8311 (cell).
CONTENTS:
Board Resolution: Approving Appointment of Treasurer and Assistant
Treasurers
Julie Johnson is the Sr. Director, Treasury & Finance. Julie has been with CPS Energy for over 25 years and
has served in numerous roles within Financial Services,
most recently as the Sr. Director & Controller. Julie earned both a BBA with a concentration in Accounting
and an MBA from the University of Texas at San
Antonio. Julie is also a CPA.
August 31, 2020 Board Meeting - REGULAR AGENDA
38
RESOLUTION APPROVING APPOINTMENT OF TREASURER AND ASSISTANT TREASURERS FOR THE CPS ENERGY BOARD OF TRUSTEES
WHEREAS, the CPS Energy Board of Trustees is required to designate and authorize specific officers and staff to conduct financial transactions on behalf of CPS Energy; and
WHEREAS, effective August 1, 2020, CPS Energy appointed Gary Gold to serve as the Interim Chief Financial Officer (CFO), to oversee all of CPS Energy's financial functions; and
WHEREAS, in his new role as Interim CFO, Mr. Gold will assume responsibility for managing and directing the financial transactions that require Board of Trustees approval and will be providing support to the Board related to these financial matters; and
WHEREAS, Mr. Gold was most recently and currently serves as an Assistant
Treasurer, and
WHEREAS, the role of Board Treasurer has been vacant since the departure of the prior CFO on July 31, 2020; and
WHEREAS, the Board previously appointed Shannon R. Albert, who now serves as Interim Vice President - Accounting and Maricela Benavides, who now serves as Sr. Director, Financial Systems & Strategic Projects to serve as Assistant Treasurers to the Board; and
WHEREAS, one Treasurer and four Assistant Treasurers will facilitate more
effective and timely financial transaction coverage, and the below named individuals have broad experience in financial matters;
NOW, THEREFORE, BE IT RESOLVED that the CPS Energy Board of Trustees hereby approves the appointment of Gary Gold as Treasurer as well as Cory Kuchinsky and Julie Johnson as additional Assistant Treasurers to the Board of Trustees, effective September 1, 2020.
August 31, 2020 Board Meeting - REGULAR AGENDA
39
EXECUTIVE SUMMARY
New Products / Tariffs
Resiliency and WDS
August 31, 2020 Board of Trustees Meeting
Prepared By: Strategic Pricing Page 1 of 4 08/31/2020
ACTION REQUIRED:
As discussed and previewed at the August 17, 2020, Board of Trustees Special Meeting, we will next request your approval on two tariffs:
1. Resiliency Service 2. Wholesale Distribution Service (WDS)
CONTENTS: To be responsive to the questions and comments we received at the August 17,
2020, Board of Trustees Special Meeting we have prepared this Executive
Summary and have attached a PowerPoint document that will be presented to the Board at its upcoming August 31, 2020, Regular Meeting. The points of the
Executive Summary are as follows: • Resiliency Service:
o While all the questions for this tariff were answered in the Special Meeting, in the next section of this document, we will provide basic background
information for your convenience. • WDS:
o Most of your previous questions related to this tariff. ▪ Accordingly, this Executive Summary is more focused on this updated
tariff ▪ A White Paper is attached that dives deeply into the advance battery
technology aspect of the service
EXECUTIVE SUMMARY:
Resiliency Service: This product applies to back-up power systems on customer premises. It does not relate to our generating assets. Third parties make an
investment in generators that our customers can use when they have an unplanned outage.
This occurs for example when a retail customer services unexpectedly go offline
because a vehicle hit a pole and knocked down our distribution lines down. Another example of this is a storm. The back-up system can be used by the customer until
we can reconnect the customer to the grid.
August 31, 2020 Board Meeting - REGULAR AGENDA
40
EXECUTIVE SUMMARY
New Products / Tariffs
Resiliency and WDS
August 31, 2020 Board of Trustees Meeting
Prepared By: Strategic Pricing Page 2 of 4 08/31/2020
While we are paid a fee by the third-party to broker their power transactions, we
have no obligation to take their power. We also are not exposed to market timing. We only move the power at the price they have contracted in the wholesale market.
While currently not necessary, in the long-term we could also consider purchasing
the excess power from the generators, when and if that could be helpful to us. This increases our portfolio of potential energy supply resources.
WDS: For years, we have been required by law to let new customers use our
distribution grid to access the Electric Reliability Council of Texas (ERCOT) wholesale market.
Historically for us, existing customers on this tariff have not had their own power
generation resources. They have been our customers for years. While we
originally treated them as retail customers, based upon their changing preference, they are now considered wholesale customers. They currently are not delving into
batteries. Their connections are fairly basic and accordingly they will stay on the original tier of the tariff.
Our new proposal modernizes the existing WDS tariff to enable positive benefits to
the community and ensure full cost recovery of distribution infrastructure. New customers located in San Antonio bring strategic benefits to our community.
Importantly, since batteries can be charged with and can discharge power, we are not supplying them energy from our energy resources.
This proposal is not a general rate increase, and it only impacts new battery storage
customers. Our 2 existing WDS customers will not be impacted by this change.
How others can use our distribution assets.
Anytime someone wants to use our distribution assets, we can charge them for
that use. While our existing rate has served its purpose over the years, because of the changes in technology, the tariff needed updating.
A new kind of customer is coming, along with energy storage technology, that also
wants to use our distribution assets. However, unlike our existing customers, they only want to utilize our distribution assets. They will buy power from the wholesale
market to charge their battery and then sell that stored power back to the wholesale market during advantageous times. Other than auxiliary load, they are
not asking that any retail power to charge the battery be supplied by us.
August 31, 2020 Board Meeting - REGULAR AGENDA
41
EXECUTIVE SUMMARY
New Products / Tariffs
Resiliency and WDS
August 31, 2020 Board of Trustees Meeting
Prepared By: Strategic Pricing Page 3 of 4 08/31/2020
Connecting to our distribution assets is allowed by ERCOT so long as they pay us
for the use of our distribution assets. Since they will use our distribution grid in different ways through connections at different points, the existing WDS tariff,
which is a “one size fits all” tool, cannot be used to fairly & appropriately recover distribution system costs from all types of customers. Therefore, since these new
types of customers will be coming to market across ERCOT and we must allow access, it is prudent for us to update our pricing. With our revised pricing and new
customers arriving, this will provide for additional revenue and is a benefit to our system. With the revised pricing, we do not lose money on the use of our assets.
To modernize, with our existing 2 customers, we are going to migrate the cost
recovery for the use of our distribution assets to their existing wholesale contracts. Since we are their energy supplier in addition to providing distribution service, this
is a more effective means to recover related costs. Thereby, these existing
relationships will be effectively unchanged.
Prospectively, the revised WDS tariff will now be structured with more precise tiered pricing and include recovery for upfront costs that would be necessary for
interconnection to our distribution assets. These new customers will only be charged for the use of our distribution assets, as they will buy and sell power from
the ERCOT wholesale market. Should they ever decide they want to change and buy power from us, we can always be ready to serve.
We are required to provide open ERCOT market access through our
distribution system upon request.
This requirement is a function of our state’s efforts to create a healthy, vibrant energy market in Texas. Regulations from the Public Utility Regulatory Act (PURA),
the Public Utility Commission of Texas (PUCT) and ERCOT require utilities, like CPS
Energy, to provide open access to the transmission & distribution systems for generators & wholesale providers. Generators and wholesale providers are
required to pay utilities for the use of their distribution systems through PUCT-approved tariffs.
While providing open access is a requirement, having these battery
storage operators locate in San Antonio provides strategic benefits to CPS Energy and the community.
These battery storage operators can locate anywhere they want within the ERCOT
market. However, having them locate in our community has strategic benefits.
August 31, 2020 Board Meeting - REGULAR AGENDA
42
EXECUTIVE SUMMARY
New Products / Tariffs
Resiliency and WDS
August 31, 2020 Board of Trustees Meeting
Prepared By: Strategic Pricing Page 4 of 4 08/31/2020
These customers will contribute additional revenue and city payment in exchange for providing access to our distribution system (enabled by the Wholesale
Distribution Service tariff). There is also a potential for revenue from other wholesale market services (e.g., scheduling services).
These systems provide increased reliability by mitigating outages when deployed
in our service area. This could lead to the development of new resiliency service offerings in the future.
This is an evolution of an existing tariff. It is not a general rate increase,
and it does not impact customers broadly.
We have an existing Wholesale Distribution Service tariff (Rider E14) that is over
20 years old. It has a single price of $0.50/KW of contracted interconnection to our distribution infrastructure. If no changes are made to the current tariff, these
new customers will pay the current rate. By stratifying the rate into three tiers, we have more appropriate price points to assess to the new customers.
This change is not a rate increase in the traditional sense that would apply to most
or all customers. Our 2 existing full service wholesale customers on the current tariff will not be impacted by this change. We will migrate their charges for using
our distribution assets into our existing wholesale contracts. Only new battery storage operators will be impacted by the proposed changes. In fact, because
these batteries will utilize existing assets in many cases, their incremental revenue contributes to keeping rates low for other customer classes over time.
The key take-aways from our WDS tariff modernization effort are:
• Customers use our distribution assets in different ways, and the WDS tariff
is being modernized to recover costs accordingly. New customers will be coming across ERCOT & utilities are required to connect these customers
• This provides for an additional revenue opportunity • There are strategic, tangible benefits to us that will be realized in the future
– (e.g. revenue, resiliency, etc.) • This is not a rate increase – the proposal has a narrow focus to these new
types of customers
We look forward to discussing this topic with you further at our Board of Trustees on August 31, 2020. Thank you!
August 31, 2020 Board Meeting - REGULAR AGENDA
43
NEW PRODUCTS:WHOLESALE DISTRIBUTION SERVICE
& RESILIENCY SERVICEPRESENTED BY:
Cory KuchinskyInterim V.P., Strategic Pricing & Enterprise Risk Management
& Solutions
August 31, 2020
Approva l Reques ted
August 31, 2020 Board Meeting - REGULAR AGENDA
44
OBJECTIVES & TAKEAWAYS
2
• REVIEW OUR ALIGNED PRODUCT ROADMAP• ALIGN WITH COMMUNITY GOALS WHILE
MAINTAINING FINANCIAL STABILITY
o PROVIDE OVERVIEW OF UPDATED WHOLESALE DISTRIBUTION SERVICE (WDS) PRODUCT & PROPOSED RESILIENCY SERVICE PRODUCT
• REQUEST FOR APPROVAL
August 31, 2020 Board Meeting - REGULAR AGENDA
45
AGENDA
3
• ALIGNED ROADMAP• WDS OVERVIEW• RESILIENCY SERVICE OVERVIEW• REQUEST FOR APPROVAL
August 31, 2020 Board Meeting - REGULAR AGENDA
46
Q2 Q3 Q4
4
Environmental Responsibility
Resiliency
Reliability
Green Tariff On-site Solar
EV Pilots
Wholesale Distribution
ServiceLine Extension
Resiliency Service
PRODUCT ROADMAP FOR FY2021
Alig
ned
with
Gui
ding
Pill
ars
Pilot Programs(Under New Service
Options Tariff)
Rooted in Financial Stability
APPROVEDAPPROVED
INFORMEDINFORMED
August 31, 2020 Board Meeting - REGULAR AGENDA
47
5
OBSERVING EVOLUTIONThe “greening of the grid” is driving noticeable innovation…
…and customers are finding new ways to use & interact with the grid.
Yesterday’s Grid Today’s Grid• 2-way power flows
• Distributed resources
• Battery storage
August 31, 2020 Board Meeting - REGULAR AGENDA
48
6
ENABLING NEW OPPORTUNITIES
Generators
TransmissionGrid
Battery operators will use our system differently than our retail energy customers. Updating our WDS product unlocks new
revenue streams & has operational benefits for all customers.
DistributionGrid
PUCT rules & ERCOT protocols are designed to create a healthy, efficient energy market. These rules stipulate:
We are the sole retail energy provider in our market. Bills recover the cost of generation, transmission & distribution infrastructure, as well as the cost of energy.
1
2 We must allow battery operators to use our distribution grid to access the wholesale market. Bills recover the cost of distribution infrastructure.
Retail Energy Customer
Battery Operator
Wholesale Energy Market
Wholesale Energy Market
August 31, 2020 Board Meeting - REGULAR AGENDA
49
Our modernized tariff delivers value, aligns with community goals & protects our community’s electric infrastructure investment.
7
STRATEGIC BENEFITS
• ENABLES new technologies that support intermittent renewable resources on the grid
• ENHANCES resiliency & reliability of ERCOT & our system
• PROVIDES new revenue streams & recovers cost of infrastructure
Wholesale Distribution
Service
August 31, 2020 Board Meeting - REGULAR AGENDA
50
The WDS tariff recovers costs based on how much of our distribution system the customer uses.
8
HOW THE PRODUCT WORKSGeneration Transmission Distribution Service
Primary Voltage Service:
Extended Primary Voltage Service:
Secondary Voltage Service:
$0.50/KW
$1.21/KW
$1.78/KW
A
A
B
B
C
C
A tiered rate accommodates various
connection points.
Wholesale Distribution
Service
August 31, 2020 Board Meeting - REGULAR AGENDA
51
• WDS monthly bill covers the cost of distribution infrastructure
• In addition, we will coordinate battery charge and discharge timing with ERCOT on behalf of the customer (i.e., “scheduling”)
9
FINANCIAL ASSESSMENT
Note: Cost of Service consists of O&M, A&G, debt service, internal funds and city payment
$12.1k $12.1k
COST TO SERVE PI LOT BI LL
Wholesale Distribution Service Monthly Bill Sample
By locating in San Antonio, battery operators will incrementally contribute to the cost of distribution assets and will also
generate other revenue for wholesale scheduling services.
Cost to Serve Customer Bill
10MW Battery x $1.21/KW
August 31, 2020 Board Meeting - REGULAR AGENDA
52
10
DELIVERING DEPENDABILITY
• Commercial customers want a solution for dependable power during critical weather events
• For a monthly fee, we will provide access to onsite generation
• Pilot was launched in mid-2019 & we are ready to finalize the rate for broader customer use Ice/Snow
Hurricane
High Winds
Flooding
Resiliency Service
Our new Resiliency Service offering is an excellent fit for large businesses that require continuous operations.
August 31, 2020 Board Meeting - REGULAR AGENDA
53
11
• Builds & maintains facilities to interconnect generators
• Revenue:o Resiliency Service fee from retail
energy customero Share of proceeds for brokering
3rd Party’s wholesale market access
• Builds & maintains back-up generators at customer sites
• Wholesale market revenue
• Pays monthly Resiliency Service fee ($1.04/kW)
• Receives enhanced reliability
3rd Party Solution Provider
Large Retail Customer
HOW THE PRODUCT WORKS
Resiliency Service
In exchange for a monthly Resiliency Service fee, the customer is guaranteed to experience minimal disruption of service.
August 31, 2020 Board Meeting - REGULAR AGENDA
54
• The Resiliency Service fee is designed to recover the cost of:
o Infrastructure & system costs
o Operations & maintenance expenses
o Energy from back-up generation
• We expect to see additional revenue from our share of the 3rd Party’s wholesale market revenue
12
FINANCIAL ASSESSMENT
$1,040 $1,040
COST TO SERVE PI LOT BI LL
Resiliency Service Fee Monthly Bill Sample
The Resiliency Service rate is designed to cover the fixed cost of interconnecting with our distribution grid
Cost to Serve Customer Bill
1MW Resiliency Service x
$1.04/KW
August 31, 2020 Board Meeting - REGULAR AGENDA
55
13
RECAP
• Our industry is changing as customer expectations & technologies evolve
• We are committed to providing product options & flexibility to our customers
• New products align with community goals & maintain financial responsibility
• The proposed products support & align with our Guiding Pillars
August 31, 2020 Board Meeting - REGULAR AGENDA
56
14
We respectfully request the Board of Trustees’ approval of:
• The updated Wholesale Distribution Service Tariff• The new Resiliency Service Tariff following our
successful pilot
REQUEST FOR APPROVAL
August 31, 2020 Board Meeting - REGULAR AGENDA
57
Thank You
August 31, 2020 Board Meeting - REGULAR AGENDA
58
Appendix
August 31, 2020 Board Meeting - REGULAR AGENDA
59
17
OUR GUIDING PILLARS &FOUNDATION
Our product & rates strategy is supported by our Guiding Pillars.
SecurityCustomer
AffordabilityReliabilityEnvironmentalResponsibility Resiliency Safety
FINANCIALLYRESPONSIBLE
August 31, 2020 Board Meeting - REGULAR AGENDA
60
18
GLOSSARY
Acronym or Word Definition
kW A kilowatt (kW) is 1,000 watts of instantaneous power.
Pilot A program with very strict operational guidelines including that allows for data collection
Tariff A pricing structure or policy that governs how a utility provides services & generates revenue from those services
August 31, 2020 Board Meeting - REGULAR AGENDA
61
1 August 2020
Wholesale Distribution Battery Energy Storage Executive Summary This whitepaper is intended to provide context and explain why wholesale
distribution battery storage is being deployed across the Electric Reliability
Council of Texas (ERCOT) and how distribution service providers can recover
cost through a Wholesale Distribution Service (WDS) rate.
CPS Energy is a leader in renewable energy and supports the integration of
new technologies to support the grid. Energy storage, and specifically
batteries, are key to our future as our utility and industry move toward a more
distributed energy system. The thoughtful addition of more renewables and
new technologies also aligns with our strategic Flexible Path that will
transform our generation fleet to lower and non-emitting resources.
Energy storage is unique in that it provides power (generation) and consumes
power (places a “load” on our circuits). We therefore need to be thoughtful in
how to integrate this technology to ensure the reliability and security of our
grid. This technology continues to accelerate at a greater pace in the ERCOT
market. This paper will focus on one type of storage technology, battery
energy storage, and highlight the multiple factors that are contributing to the
increased use of batteries. This paper will also highlight key strategic benefits
of battery energy storage to CPS Energy and the community. Key points to
consider:
• Wind and solar capacity in Texas have grown at an incredible rate; the
intermittency of these resources creates challenges requiring ERCOT to
encourage storage integration in the market
• Battery storage technology has become much cheaper and more
capable in recent years (and this trend will continue), making batteries
a potential solution for renewable intermittency (e.g., smoothing, solar
shifting, firming)
• Regulations from the Public Utility Regulatory Act (PURA), the Public
Utility Commission of Texas (PUCT) and ERCOT require utilities, like CPS
Energy, to provide open access to the transmission and distribution
systems for generators and wholesale providers. Generators and
wholesale providers are required to pay utilities for the use of their
distribution systems through published wheeling tariffs, while
transmission costs are recovered through a separate mechanism called
Transmission Cost of Service (TCOS).
• CPS Energy is updating and modernizing our Wholesale Distribution
Service tariff to recover the use of our assets as we continue to look for
August 31, 2020 Board Meeting - REGULAR AGENDA
62
2 August 2020
opportunities to develop value-added services. An ERCOT meter at the
battery site will track the power dispersed and consumed by the battery.
• Our Wholesale Distribution Service tariff is not a new service, as CPS
Energy has provided service under this tariff to existing wholesale
customers. We are updating this tariff to reflect the current cost of
providing this service.
• The ERCOT market uses the Ancillary Services (AS) market to mitigate
the risks caused by intermittency; for example, they buy “operational
reserves” that can rapidly provide energy/power to the grid when the
wind suddenly stops blowing or the sun stops shining.
• There are strategic benefits of having battery energy storage located in
our community, including:
o Revenue from providing access to our distribution system
(enabled by the Wholesale Distribution Service tariff), as well as
the potential for revenue from other wholesale market services
(e.g., scheduling)
o Future value-added services as more systems are deployed.
o Increase in reliability by mitigating outages when the systems are
deployed in our service area, which could lead to development of
new resiliency service offerings.
Overview of Battery Energy Storage Batteries have been developed over a long period of time, but their usage
grew to a greater degree during the 20th century. Their development and use
have since grown exponentially during the early part of the 21st century with
the increase of renewable energy production and the adoption of electric
vehicles.
The battery was first invented in the 1800’s but it was in 1908, with the
invention of the Edison Alkaline cell, that batteries began to be used in
industry. We now see batteries used in all aspects of life, including an increase
in the use of storage in the power industry. Due to the widescale use across
multiple industries, battery applications continue to grow.
August 31, 2020 Board Meeting - REGULAR AGENDA
63
3 August 2020
The growth in the electric vehicle (EV) market has driven more research and
innovation in the battery space. Infrastructure to design, build and mass
produce the battery components and units themselves has been constructed,
making batteries more available than ever before. Batteries have now been
built into Battery Energy Storage Systems (BESS) that can store and deliver
hundreds of megawatts over hours.
Battery Types There are varied types of battery chemistries in use (I.e. lead-acid, nickel
based and sodium-based) today but the one most commonly used in the
energy market is the Lithium-ion battery. This chemistry accounts for more
than 90% of the batteries currently deployed in the energy market. The reason
why Lithium-ion batteries are so commonly used is due to their high-cycle
efficiency, fast response times, and high energy density.
Battery Operational Capabilities The benefits and challenges posed by
renewable generation have been well
documented. Batteries have low to zero
total emissions which is great for the
environment. The major challenge with
renewable generators is that they are not
completely controllable (i.e. they only
produce power when the sun is shining, or
the wind is blowing). At times the
intermittent nature of renewables can be
constant throughout production periods, at times producing at the maximum
capacity (referred to as “nameplate capacity”) or zero, all in the matter of
seconds. By combining BESS with solar, it is possible to turn intermittent
solar into a uniform and consistent generator by providing power when solar
production is reduced (e.g. cloud over solar park) and absorbing power spikes
(e.g. clouds pass). This smoothing of the generation curve provides a more
stable power source and reliable distribution grid, solving the challenges of
integrating solar.
August 31, 2020 Board Meeting - REGULAR AGENDA
64
4 August 2020
Solar shifting uses the BESS to charge using solar energy during the solar
peak and discharge the solar energy during peak hours or when electricity
prices are significantly higher. Solar is unable to provide constant operating
capacity (e.g. exactly 10 MW for 6 hours), thus the solar needs firming
(dependable operating capacity) via battery energy storage. This enables the
total system (solar and storage) to provide consistent energy to the grid.
Benefits to a utility include avoided cost of ancillary service procurement or
deferred cost of building peaking units.
BESS units can play an important role in the concept of virtual power plants.
Virtual power plants connect different sources of renewable power production
and storage and can solve one of the major challenges to renewables: weather
dependency. These components are connected remotely utilizing software
systems to behave like a conventional power plant. BESS in these systems
charge when the renewable power is over-producing and can discharge when
they are underproducing to mirror the controllable generation of a
conventional power plant.
Battery Cost Battery cost has experienced a decline and is projected to continue declining
over the next decade. Between 2010-2018, the cost of Lithium-ion batteries
was reduced by approximately 85% to $176 per kilowatt-hour (kWh). This
cost reduction has made BESS attractive in the power industry to address
issues that face the power grid.
ERCOT Wholesale Market ERCOT has seen an increased capacity installation of wind and solar resources.
Since 2000, wind capacity increased from just over 100 MW to more than
24,000 MW. Also, as of June 2020, there is nearly 2,700 MW of installed utility-
scale solar capacity in ERCOT, with another 72,000 MW under study. This
demonstrates the potential for an uptick in renewable generation in
comparison to overall capacity, which is currently 82,000+ MW.
Due to the variability of these two resources, ERCOT procures operational
reserves called Ancillary Services (AS), grid support functions (i.e. smoothing
August 31, 2020 Board Meeting - REGULAR AGENDA
65
5 August 2020
and firming), to ensure reserve capacity is available to address variability. AS
creates a market opportunity for not only generation resources but Distributed
Generation Resources (DGRs) that include battery energy storage. This
market encourages the increased installation of battery storage in Texas.
BESS units are ideal for AS because they can provide fast acting operating
capacity that helps balance the generation and load as well as frequency
regulation to the grid. Currently most of the storage units available in ERCOT
are being used for AS. As the deployment of these units continues to increase,
so will the efficiency of how the grid operates. Battery operators are
responding to energy market pricing signals and can monetize their
investment in several ways (e.g., buying and selling energy, AS). The BESS
units participating in the market are metered by ERCOT. They pay market
prices when charging, and they are paid market prices when discharging.
Their energy is metered separately from the utility’s energy requirements.
PURA requires open access to the ERCOT market on both the transmission and
distribution systems. The PUCT also mandated the real-time co-optimization
(RTC), which will create a real-time energy and AS market, to be implemented
by ERCOT. This market improvement will lead to increased opportunities for
storage to participate in the real-time AS market. The total battery project
size in the ERCOT interconnection queue as of November 2019 was 7,214 MW.
Almost 50% of these projects are hybrid projects (i.e. battery project co-
located with a solar project). Forty-two percent of the remaining 50% are
stand-alone battery projects. The ERCOT market rules and infrastructure
prove to be an enabler for future installations.
Effect of Market on CPS Energy Just as ERCOT has seen a growth of interconnection request, units requesting
to connect within the CPS Energy service territory has increased, as can be
seen in the figure below. As required by law, CPS Energy, as a Transmission
and Distribution Service Provider (TDSP), facilitates the interconnection of
both solar and BESS units on the grid. We recover the cost of the
interconnection based on established cost causation principles. We are
updating and modernizing our Wholesale Distribution Service tariff to realize
revenue from access to our distribution system.
August 31, 2020 Board Meeting - REGULAR AGENDA
66
6 August 2020
New potential revenues sources exist in the process of BESS units being
installed on the CPS Energy systems that can be evaluated. For example, CPS
Energy can serve as the Qualified Scheduling Entity (QSE) for the units,
connect their ancillary load as a retail customer and may be able to provide
backup services for the units. We continue to look for opportunities to partner
with the BESS operators.
CPS Energy also continues to advance our own generation portfolio by
incorporating renewable energy and now BESS. In the spring of 2019, CPS
Energy and the Southwest Research Institute partnered to build a BESS
located on the westside of San Antonio. The BESS can charge and discharge
up to 10 MW for an hour and was installed along with a 5 MW solar plant to
demonstrate the benefits of storage paired with renewables (i.e., hybrid
projects). The unit is also designed to provide AS in the ERCOT market.
In the FlexPOWER Bundle, CPS Energy will seek to pair renewable
generation (up to 900 MW of solar) with battery energy storage (50 MW),
realizing both the need and potential of the pairing.
Opportunities and Risks
Opportunities Risks Future value-added services as more
systems are deployed. Increase in
reliability by mitigating outages when
the systems are deployed in our service
Reliability of the grid can be
compromised based on operation
of the BESS units requiring CPS
Energy to perform detailed studies
August 31, 2020 Board Meeting - REGULAR AGENDA
67
7 August 2020
area, which could lead to development
of new resiliency service offerings.
New revenue opportunities such as
scheduling the battery provider’s bids
into the market.
Communication protocols can
pose cybersecurity risks
If sited properly, can provide a non-
wires alternative to transmission and
distribution needs on our system.
Rules from regulating agencies
can change requirements based
on equipment types and origins
Provides the ERCOT system additional
support as more renewables and
intermittent resources are added to the
grid.
Standards (i.e. electrical
connection, fire) being developed
due to BESS technology improving
capabilities
Provides local capacity on congested
parts of our system, helping to resolve
the congestion (overloading power
lines) and reduce congestion costs to
our customers.
ERCOT developing protocols that
will affect distribution connected
BESS
Future partnership opportunities as this
new technology continues to mature.
On the customer side, if the BESS is
installed behind the meter, the system
could help reduce peak demand and
even allow for micro-grid capabilities.
Conclusion CPS Energy is a leader in renewable energy and supports the integration of
new technologies to support the grid. We realize that energy storage, and
specifically batteries, are a key component of our Flexible Path as our utility
and industry move toward a more distributed energy system.
The increased deployment of renewables and other intermittent energy
sources continue to drive the need for wholesale battery storage on the
transmission and distribution system. The ERCOT region and CPS Energy
service territory anticipate increased applications of distribution-connected
battery storage.
CPS Energy is required by law to provide access to our distribution lines in
order to promote open access to the ERCOT market. We are modernizing our
Wholesale Distribution Service tariff to recover our cost, and we have
positioned ourselves to provide other value-added services that will generate
new revenue streams. CPS Energy will continue to pursue partnerships and
explore new business models that benefit the community and customers we
serve.
August 31, 2020 Board Meeting - REGULAR AGENDA
68
WHOLESALE DISTRIBUTION SERVICE - RIDER E14 DRAFT City Public Service Board of San Antonio Page 1 of 3
Revision Number: 1 Effective Date: TBD
CITY PUBLIC SERVICE BOARD OF SAN ANTONIO
______________________________________
RIDER E14 WHOLESALE DISTRIBUTION SERVICE
WDS
APPLICATION
City Public Service Board of San Antonio (CPS Energy) Wholesale Distribution Service (Rider E14, or WDS) is offered to Wholesale Distribution Service Customers who are eligible for and complete a formal request to purchase distribution level wholesale transmission services at CPS Energy’s standard distribution voltages and as defined in Public Utility Commission of Texas (Commission) Substantive Rules, Subchapter A, 25.5. CPS Energy will accommodate such request, provided that the Wholesale Distribution Service Customer executes a Service Agreement with CPS Energy for service and agrees to pay the WDS Charges as specified below. The distribution facilities utilized to connect the Wholesale Distribution Service Customer to the CPS Energy transmission system shall be planned and installed per standard CPS Energy engineering practices and in accordance with the current version of CPS Energy’s Electric Service Standards. Such interconnection distribution facilities may include but are not limited to the following: transformers, electric circuits, metering devices, system protection devices, and communications and control equipment. This rate schedule is not applicable to electric service offered by CPS Energy under any other rate schedule. Service offered under this rate schedule is available only to Wholesale Distribution Service Customers and is not available for retail service.
TYPE OF SERVICE
CPS Energy will provide service at one point of delivery and measured with one meter, using facilities rated at less than 60 kV, at 60 hertz, alternating current, and at one of the service levels defined below:
Primary Voltage Service — Substation-connected service supplied at standard primary voltage (13kV or 35kV) supplied by the substation transformer. This service is subject to available substation capacity determined by CPS Energy.
Extended Primary Voltage Service — Distribution-connected service supplied at standard primary voltage (13kV or 35kV) supplied by the substation transformer.
Secondary Voltage Service — Secondary-connected service supplied at standard voltages below 13kV.
August 31, 2020 Board Meeting - REGULAR AGENDA
69
WHOLESALE DISTRIBUTION SERVICE - RIDER E14 DRAFT City Public Service Board of San Antonio Page 2 of 3
Revision Number: 1 Effective Date: TBD
MONTHLY BILL
Grid Share
$13.00 Primary Voltage Service
$19.00 Extended Primary Service
$21.00 Secondary Voltage Service
Demand Charges
$0.50 Per kW for Primary Voltage Service
$1.21 Per kW for Extended Primary Voltage Service
$1.78 Per kW for Secondary Voltage Service
The demand charges shall be per kW of Contract Demand or Contract Capacity per month as specified in the Service Agreement. At termination of the Service Agreement for any reason, the Wholesale Distribution Service Customer shall also pay CPS Energy a sum equal to the estimated present worth of the unamortized original undepreciated cost (or book) value (if any) for all remaining distribution facilities plus removal costs for all remaining distribution facilities.
Wholesale Distribution Service Customer will also be billed for the following, if applicable: additional equipment required and related operation and maintenance expense, including metering devices; additional transformation services; monthly data services; operating and regulatory expenses caused by the operation of the Wholesale Distribution Service Customer's generation or energy storage assets; distribution system line losses; and transmission and market charges billed to CPS Energy for the Wholesale Distribution Service Customer's generation or energy storage assets. These billings and related payment due dates may be more frequent than monthly as agreed to within the Service Agreement.
LATE PAYMENT CHARGE
The Monthly Bill will be charged if payment is made within the period indicated on the bill. Bills not paid within this period will be charged an additional 2 percent times the Monthly Bill excluding the adjustment for fuel costs, garbage fees and sales taxes.
TERMS OF SERVICE
A customer requesting electric service under this rate schedule shall make the request in accordance with the Commission's Substantive Rules Applicable to Electric Service Providers and execute a Service Agreement with CPS Energy for wholesale distribution service.
Wheeling of power to other retail service locations connected to CPS Energy’s distribution system or within CPS Energy’s certificated service area is prohibited.
The Wholesale Distribution Service Customer shall be responsible for all costs of interconnecting with CPS Energy’s distribution system. If it is necessary to construct new or modify distribution or
August 31, 2020 Board Meeting - REGULAR AGENDA
70
WHOLESALE DISTRIBUTION SERVICE - RIDER E14 DRAFT City Public Service Board of San Antonio Page 3 of 3
Revision Number: 1 Effective Date: TBD
transmission facilities for interconnection, CPS Energy will construct new facilities, or alter existing facilities as necessary, and make the service available as soon as reasonably possible provided, however, that the Wholesale Distribution Service Customer pays a contribution in aid of construction in advance of CPS Energy's commencement of such construction or alteration.
CPS Energy shall estimate the cost for the construction or alteration based on CPS Energy's then-current material, labor and overhead costs, and the Wholesale Distribution Service Customer must agree in writing to pay such costs before construction or alteration commences. The actual cost is the total cost of all construction or alteration, as applicable, including not only the labor and materials used in constructing the new facilities or altering existing facilities, but also costs for planning, engineering, licensing, regulatory, permitting, right-of-way acquisition and clearing, overheads, interconnection studies, cyber-security and safety-standard testing, and all other costs directly attributable to such construction or alteration. All facilities constructed or altered by CPS Energy shall remain the property of CPS Energy.
Wholesale Distribution Service hereunder shall be subject to, and CPS Energy and the Customer will comply with, the regulatory and operational procedures established under Applicable Rules and ERCOT protocols.
TERMS AND CONDITIONS
The terms and conditions or the service are those stated in Commission Substantive Rules, Subchapter I, 25.191-25.203, CPS Energy Distributed Generation Manual and the Service Agreement.
August 31, 2020 Board Meeting - REGULAR AGENDA
71
Effective Date: TBD DRAFT Page 1 of 2
CPS Energy _______________________
RIDER E21
RESILIENCY SERVICE
APPLICATION
This Resiliency Service Rider (the “Rider”) is applicable to Customers for whom a separate contract or agreement (Service Agreement) between CPS Energy and the Customer exists for resiliency service, which is a redundant service to increase the reliability of electric retail service.
DEFINITIONS
Customer— a non-residential, CPS Energy electric retail customer Resiliency Mode — the state and time period during which power from a Resiliency Unit is redirected from grid operations to provide energy to the Customer’s connected load during an unforeseen outage of standard service Resiliency Unit— a natural gas generator, energy storage, or other energy technology unit capable of providing energy in Resiliency Mode; CPS Energy holds title to the energy from such unit, which is used to provide resiliency service to the Customer within the timeframes specified in the related Service Agreement ELIGIBILITY CRITERIA
This Rider is only applicable to customers that meet the minimum eligibility criteria. The proper application of the Rider shall be determined at CPS Energy’s sole discretion. A Customer must meet the following Minimum Requirements to be eligible for the Rider:
1. A CPS Energy Customer in good standing without any delinquent payments over the last 12 months; 2. Resiliency Unit(s) procured by CPS Energy or a third-party must be available at time of the request
for resiliency; and 3. Customer must meet financial criteria established by CPS Energy.
Resiliency service is complex and must be appropriately integrated into CPS Energy’s operations. In addition to the Minimum Requirements, CPS Energy will consider the following operational criteria in determining the applicability of the Rider to any prospective customer:
• Effective physical integration into CPS Energy’s existing electric generation, transmission, and distribution facilities;
• Effective integration into CPS Energy’s system operations and dispatching software and processes; • Generation diversity (type and physical location) consistent with generation resource planning; • Economic impact on CPS Energy’s generation fleet, and/or • Any other relevant generation or operational matters.
August 31, 2020 Board Meeting - REGULAR AGENDA
72
Effective Date: TBD DRAFT Page 2 of 2 MONTHLY BILL
Demand Charge $1.043 Per kW-AC of installed capacity
The Rider will be applied to the installed capacity of the Resiliency Unit(s) and included in the Customer’s monthly electric retail bill.
Additional Charges Prior to the start of construction, a standard capital contribution is required from Customer for each resiliency project. As specified in the Service Agreement, additional upfront capital contributions, monthly facilities charges, and/or monthly operations and maintenance charges may be required for
− Distribution system connection costs in excess of the standard amount included in the Rider, and/or − Customer support costs in excess of the standard amount included in the Rider, and/or − Resiliency Unit costs and equipment.
During Resiliency Mode, the standard applicable electric rate will be applied to energy provided to the Customer for a predetermined quantity of kWh as specified in the Service Agreement. Customer may incur additional charges for energy provided during Resiliency Mode that exceeds the predetermined number of kWh as specified in the Service Agreement.
Adjustments A bill adjustment shall be made as follows: plus or minus the proportionate part of the increase or decrease in taxes, required payments to governmental entities or for governmental or municipal purposes which may be hereafter assessed, imposed, or otherwise required and which are payable out of or are based upon CPS Energy electric system revenues.
The Monthly Bill amount for resiliency service shall consist of the demand charge stated above, plus any monthly adjustments or additional charges as may be specified in the Customer's Service Agreement.
LATE PAYMENT CHARGE
The Monthly Bill will be charged if payment is made within the period indicated on the bill. Bills not paid within this period will be charged an additional 2% times the Monthly Bill excluding the adjustment for fuel costs, garbage fees, and sales taxes.
TERMS AND CONDITIONS
Resiliency service shall be supplied for the length of time agreed to in the Service Agreement. Customer will execute a Service Agreement, subject to the applicable Rider, that may include additional terms and rates that ensure adequate capital, operations and maintenance, and fuel cost recoveries.
At all times during the delivery of resiliency service, the Customer shall remain solely served by CPS Energy. If the Resiliency Unit requires natural gas, it must be served exclusively by retail gas or transport service from CPS Energy.
Where applicable, resiliency service is subject to CPS Energy Customer Terms and Conditions Applying to Retail Utility Service (Terms and Conditions), as well as CPS Energy’s Electric Service Standards and Distributed Generation Manual (Technical Standards), as may be amended from time to time, which are incorporated herein by this reference as if set forth in full. In the event that the Terms and Conditions, Technical Standards, the terms of this Rider, and/or the Service Agreement conflict or are inconsistent with one another, the order precedence is as follows: (1) the Resiliency Service Rider, then (2) the Service Agreement, then (3) the Technical Standards, and then (4) the Terms and Conditions.
August 31, 2020 Board Meeting - REGULAR AGENDA
73
CPS ENERGY / SAWS AMI PARTNERSHIP
PRESENTED BY:
Jonathan R. Tijerina Sr. Director, Business & Economic Development
August 31, 2020
App rova l Reques ted
August 31, 2020 Board Meeting - REGULAR AGENDA
74
OBJECTIVES & TAKEWAYS
2
• REVIEW THE POTENTIAL PARTNERSHIP WITH SAWS FOR WATER AMI PROJECT AND SEEK SUPPORT FOR OUR PARTICIPATION
August 31, 2020 Board Meeting - REGULAR AGENDA
75
AGENDA
3
• GUIDING PILLARS• FLEXIBLE PATH• SAWS AMI PROJECT• DEAL STRUCTURE• NEXT STEPS• REQUEST FOR APPROVAL
August 31, 2020 Board Meeting - REGULAR AGENDA
76
4
OUR GUIDING PILLARS &FOUNDATION
The CPS Energy / SAWS AMI partnership leverages community assets to maximize customer benefits while enabling our
Smart City vision.
SecurityReliabilityEnvironmentalResponsibility Resiliency Safety
FINANCIALLYRESPONSIBLE
CustomerAffordability
August 31, 2020 Board Meeting - REGULAR AGENDA
77
August 31, 2020 Board Meeting - REGULAR AGENDA
78
CPS ENERGY / SAWS AMI PARTNERSHIP
Our strategic partnership with SAWS & Itron optimizes value to our community
• Expands the intelligence of the
SAWS water distribution system
• Promotes the means for better cost
management
• Improves information & services to
customers
The strategic partnership will leverage a community asset that brings value to our shared customer base that enables value and
new benefits.
San Antonio’s multipurpose network leveraged for water AMI, Intelligent Streetlights, & other Smart City applications
6
August 31, 2020 Board Meeting - REGULAR AGENDA
79
7
CPS ENERGY AS THE NAAS PROVIDER
This partnership expands our ability to maximize our investment for the betterment of the community.
500W
Communication Network
500W w / Water
Leak Sensor
CPS Energy
Electric meter
Gas
module
SAWS Owned
Equipment
CPS Energy
Owned Equipment
• We have created additional protocols for security.
• Will utilize the pilot to test and adjust the security architecture as needed.
Security Ring
Security Ring
August 31, 2020 Board Meeting - REGULAR AGENDA
80
8
DEAL STRUCTURE
Unique partnership that leverages our existing AMI network while providing SAWS with a proven, reliable & cost effective
water AMI solution.
Existing AMI contract:
- Electric Meters + Network
equipment + Field tools
- Network monitoring
We provide Network as a Service
(NaaS)
Itron provides Software as a Service
(SaaS), hardwareThis potential partnership presents an
opportunity to develop new
revenue streams.
August 31, 2020 Board Meeting - REGULAR AGENDA
81
9
NEXT STEPS
• Pending SAWS’ notification of selection, begin pilot phase of AMI Project
▪ SAWS Board Meeting, September 1, 2020▪ Begin rollout phase with our expanded partnership▪ Track & test performance of systems
• Keep our Board & key stakeholders up to date on pilot & full deployment efforts
August 31, 2020 Board Meeting - REGULAR AGENDA
82
10
REQUEST FOR APPROVAL
We respectfully request that the Board of Trustees approve a resolution in support of our involvement in CPS Energy / SAWS AMI Partnership
August 31, 2020 Board Meeting - REGULAR AGENDA
83
Thank You
August 31, 2020 Board Meeting - REGULAR AGENDA
84
Appendix
August 31, 2020 Board Meeting - REGULAR AGENDA
85
13
GLOSSARY / DEFINITIONS
Acronym or Word
DefinitionAcronym or Word
Definition
AMI Advanced Meter Infrastructure
NaaS Network as a service
SaaS Software as a service
August 31, 2020 Board Meeting - REGULAR AGENDA
86
RESOLUTION IN SUPPORT OF SAWS AUTOMATED METERING INFRASTRUCTURE PROJECT
WHEREAS, San Antonio Water System (“SAWS”) intends to pilot and
potentially implement an Advanced Metering Infrastructure (“AMI”) system for its customers (also referred to as the “SAWS AMI Project”);
WHEREAS, in 2019, SAWS released a request for proposals for vendors
to provide technology and services for the planning and implementation of advanced metering infrastructure to the SAWS customers; and
WHEREAS, CPS Energy, joined a third-party provider of its network
infrastructure (Itron), to submit a proposal to provide Network-as-a-Service (“NaaS”) to SAWS for the SAWS AMI Project. CPS Energy adds value to the SAWS AMI Project by providing an existing network that is reliable, proven,
secure and competitively priced; and
WHEREAS, SAWS, plans to pilot, refine and implement a fully effective AMI system, as determined at their sole discretion; and
WHEREAS, CPS Energy and the third party may be chosen for a city-
wide deployment of the AMI technology solution; and
WHEREAS, CPS Energy’s NaaS pricing model allows recovery of reasonable operation and maintenance costs while anticipating a variety of endpoints to be served on its network; and
WHEREAS, the NaaS fees are outside the scope of CPS Energy’s base
rates, and the transaction will be cost-neutral to all other customers served by CPS Energy; and
WHEREAS, CPS Energy will continually strive to be a strong steward of
the community’s energy utility assets while effectively balancing its following Guiding Pillars:
• Reliability;
• Customer Affordability; • Security; • Safety; • Environmental Responsibility; • Resiliency;
• Financial Responsibility; and
August 31, 2020 Board Meeting - REGULAR AGENDA
87
WHEREAS, CPS Energy’s participation in the SAWS AMI Project supports San Antonio & metropolitan citizens to better leverage infrastructure investment by both utilities and further enable future smart communities’
initiatives. NOW, THEREFORE, BE IT RESOLVED that after careful consideration, and in light of the foregoing, the CPS Energy Board of Trustees expresses its
support for CPS Energy’s participation in the SAWS AMI Project.
August 31, 2020 Board Meeting - REGULAR AGENDA
88
top related