Gillentown Trailhead Access Control Project. Images are before the Yamaha Grant. Grant was provided to the SSRT for Access Control. Contractors Discussing Project. Brooks Welding and C.E. Concrete December 2012 Met to discuss Project . Breaking Ground January 8, 2013. - PowerPoint PPT Presentation

TRANSCRIPT

Gillentown Trailhead Access Control Project

Images are before the Yamaha Grant

Grant was provided to the SSRT for Access Control

Contractors Discussing Project

Brooks Welding and C.E. Concrete December 2012Met to discuss Project

Breaking Ground January 8, 2013

Funded partially by Yamaha and

Snow Shoe Rails to Trails.

Concrete Bollards Installed

Fence Post Installation by R&R Fencing

Started Jaunary 23, 2013

Installation of Rail Fencing by Brooks Welding

Family Owned and Operated company Brooks Welding installation of the railing was flawless. Installation Date: 03-19-2013

Continuation of Rail and Gate Installation

Installation Completed 5-2-2013

Painting of Fence

Painting provided by community service volunteers

Special Thanks Centre County Probation Office

Project Completed 05-29-2013