Land Grading involves the reshaping the
ground surface to planned grades as
determined as engineering survey,
evaluation, and layout. Land gradingprovides:
more suitable topography for buildings, facilities,
and other land uses
Helps to control surface runoff, soil erosion,
sedimentation during and after construction.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
3/39
Aesthetics
Geomorphic
Blends ecologically and visually with the character of
the existing natural landscape.
Architectonic
Creates uniform slope and forms usually are crisply
defined geometric shades.
Naturalistic
Most common type of grading, particularly in suburbanand rural settings. It is a stylized approach in which
abstract (or organic landforms are used) to present or
imitate landscape.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
4/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
5/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
6/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
7/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
8/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
9/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
10/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
11/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
12/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
13/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
14/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
15/39
Enclosure
Provides safety and protection such as restraining
children from running.
Containment
Protection
Privacy
Screening
It terminates the lines and eliminates undesirable
views.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
16/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
17/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
18/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
19/39
Enhancing topography
Proposed landforms, topography or grade
changes and design elements maybe constructed
or placed to emphasize, negate or have a little
impact on visual structure of the landscape.
Basic considerations:
Enhance
Compliment
Contrast Conflict particular landscape context
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
20/39
A cut is the
removal of a
portion of a sites
naturaltopography.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
21/39
Fill is the process
of blending
additional earth
into a sitesexisting
topography.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
22/39
A combination of
cut and fill.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
23/39
Grading that results in radical loss of
vegetation and or topsoil
Grading that interrupts the natural drainage
Grading that results in aesthetic degradationGrading on difficult slopes (excess of 25%), in
floodplains, estuaries, or bogs, or in other
environmentally unique conditions.
Grading in areas susceptible to naturaldisasters, such as mud slides or along
earthquake fault lines.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
24/39
Mulch
-Is a protective cover
placed over the soil,
to retain moisture,
reduce erosion,
suppress weed growth
and seed germination,
and provide nutrients
as they decay.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
25/39
Planting
Selected trees,
shrubs, and vines
(indigenouspreferred)
Plant roots and
detritus knit and
hold the surfacesoil layers.
Mortar bags
Treated bags filled
with dry sand-
cement mortar.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
26/39
Rubble
-Dumped or placedfragments of broken
stone.
-Rubble is broken
stone, of irregularsize, shape and
texture.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
27/39
Gabions
-boxes filled withsoil or sand-For erosion controlcaged riprap is used.-For dams orfoundationconstruction,cylindrical metalstructures are used.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
28/39
Rip-rap
- is rock or othermaterial used toarmour shorelines,streambeds, bridgeabutments, pilingsand other shorelinestructures againstscour, water or iceerosion.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
29/39
Cribbing
A laid-up crib at
interlocking used
metal or concrete
members filled with
rock ballast.
Footing
Pored concrete with
stone or ceramic
facing
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
30/39
Piling-Interlocking sectionsof steel or pre-castconcrete-a column of woodor steel or concrete
that is driven intothe ground toprovide support fora structure
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
31/39
Retaining wall
- Cast wall may be
left rough- with formboard or exposed
aggregate texture.
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
32/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
33/39
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
34/39
EMBANKMENT LANDSCAPE CURVE
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
35/39
GULLY SWALES
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
36/39
DITCH
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
37/39
MOUND KNOLL
-
8/3/2019 GRADING DESIGN and PROCESS( Piquero
38/39
Landscape curve is
used to blend cut
buttons and tops of
engineeredembankments. Such
naturalized slopes
are more stable and
more pleasing to theeye.
-