Project Vicinity MapProject Vicinity Map

22

The ProblemsThe Problems

33

The ProblemsThe Problems

Headcut

44

The ProblemsThe Problems

Fish Passage

55

The ProblemsThe Problems

Lack of Quality Pool Habitat

66

The ProblemsThe Problems

High Sediment Input

77

The ProblemsThe Problems

Lack of Large Woody Debris

88

The ProblemsThe Problems

Lack of Riparian Vegetation

99

Project GoalsProject Goals

1010

Project GoalsProject Goals

Headcut StabilizationStabilize Irrigation Diversion FacilityStabilize Channel MorphologyImprove Fish PassagePrevent Stream Bank ErosionVegetate Riparian Zone

1111

Project DescriptionProject Description

1212

Project DescriptionProject Description

Cooperate with landowners to vegetate riparian zones, improving diversity and function, providing shade and preventing stream bank erosion.

1313

Project DescriptionProject Description

Replace the pushup irrigation diversion and stabilize the headcut structure to improve adult and juvenile salmon, steelhead and bull trout passage.

1414

Project DescriptionProject Description

Place root wads, anchored logs, J-hooks and W-weirs to provide safe migration corridors by reducing channel gradient, prevent channel migration, and provide stream bank erosion protection thereby reducing sedimentation.

1515

Project DescriptionProject Description

Educate landowners on management practices that will enhance riparian zones.

1616

Project DescriptionProject Description

Pursue Phase II - Next mile downstream to the Island City Bridge

1717

Plate 1Plate 1

1818

Plate 2Plate 2

1919

Plate 3Plate 3

2020

Plate 4Plate 4

2121

Future Without ProjectFuture Without Project

Headcut Could Break Free Resulting in the Following:

2222

Future Without ProjectFuture Without Project

Severe Headward Channel Downcutting Loss of Channel Complexity Continued Riparian Habitat Degradation Loss of Spruce Street Bridge Massive Sediment Movement and Entrapment (gravel bars)

2323

FundingFunding

2424

FundingFunding

Feasibility Study, Environmantal Assessment and Specifications (up to August 2001) $250,000

Phase I Construction $3,264,320 U.S. Army Corps of Engineers share -$2,448,240 BPA Request (25% of total) $816,080

2525