SELECTION,WORKING
AND SAFETY ASPECTS
OF CONSTRUCTION EQUIPMENT,LIFTING TACKLES
& SAFE LIFTING
-
8/12/2019 Heavy Lift Presentation
2/46
Rev.-02 2
CONSTRUCTION EQUIPMENT &
SAFETY
With modernized construction techniques in placenow a days, construction equipment forms an integralpart of any construction activity.There will be very littledoubt to the fact that progress of any constructionactivity, largely depends on the extent of mobilizationand utilization of construction equipment.
Ultimately safe and successful execution of a
construction involves safe usage of construction eqpt.Needless to mention, that the safety factor becomemore predominant when the construction equipmentare being used in a operation plant
-
8/12/2019 Heavy Lift Presentation
3/46
Rev.-02 3
TYPES OF CONSTRUCTION EQUIPMENT
Broadly, the construction equipment can be classified asbelow: -
Material Handling Equipment
Various types of Hydraulic & Crawlers Cranes,
Hydra ,Forklifts, and hoists, etc.
Transport Equipment
Axles, SPMT, Trailers,Pick-up vans,Trucks,Tippers,etc.
Earthmoving Equipment:
Exacavator, Loaders, Graders, Rollers,Compactors, etc.
-
8/12/2019 Heavy Lift Presentation
4/46
-
8/12/2019 Heavy Lift Presentation
5/46
Rev.-02 5
SELECTION OF CONSTRUCTION EQUIPMENT
Proper selection of construction eqpt. for a
particular job is the key factor which determines thesafety and progress of any job that involves use ofconstruction equipment.
Following factors,in general,governs selection of
construction equipment -
Type of job to be carried out.
Quantum of job.
Availability of equipment.
Rate of Output desired from the eqpt.
-
8/12/2019 Heavy Lift Presentation
6/46
Rev.-02 6
Time duration of requirement.Site conditionSoil condition, obstructions etc
Size of eqpt.With respect any restriction in the site
Maneuverability requirement
Environmental factorsAtmospheric conditions likeRain,wind etc.
Other material/tools/tackles/accessories to be used inconjunction.
SELECTION OF CONSTRUCTION EQUIPMENT
-
8/12/2019 Heavy Lift Presentation
7/46
Rev.-02 7
Selection of Construction EquipmentBroad Parameters for Selection (of some main category) Equipment for a perticular job
Type of Equipment Factors that govern selection
Cranes & material handling >Net Weight to be handled/lifted(Hydraulic/Crawler Cranes of >Size of the load to be liftedvarious capacities & sizes, Hydra etc) >Radius of Operation
>Height of Placement>Quantum of job>Site conditions - Ground bearing capability, approach available, existingOut put desired in terms of quantity & time>Activities involved in operation (travel with load, swing etc)>Lifting tackles being us ed>Environmental factors like wheather condition, wind speed etc
>Availib ility (use of available eqpt)>Cost factor
Transport Equipment >Type of Material to be transported(Trailers, Pick Up Vans, >Weight & size of material to be transportedTippers, Trucks etc) >Transporting Distance
>Means for Loading & unloading- Type & size of eqpt used>Quantum of job>Out put desired in terms of quantity & time>Speicial conditions des ired such as self unloading, tipping etc>Availib ility (use of available eqpt)>Site conditions>Cost factor
Earthmoving Equipement >Type of job to be carried out (function desired from the equipment)
Excavators, Graders, >Quantum of job
Rollers, Loaders etc) >Out put desired in terms of quantity & time
>Site Conditions es p. condition of soil>Availib ility (use of available eqpt)>Type & size of Hauling Eqpt (tranporting dumpers etc)>Cost factor
Concreting Equipment Concrete Producing >Quality & type of concrete desired ( Batching Plant, Mixing Plant etc) >Quantum of job
>Out put desired in terms of quantity & time>Space availability & other site conditions>Availibility of raw material, power supply & other resources>Cost factor
Concrete Transporting >Quantity to be handled
(Transit Mixers etc) >Distance between Place of concreting & batching plant>Out put desired>Cost factor
Concrete Placing>Out put desired (Concrete Pump, Boom Placers etc) >Height of Placement>Availabi lity of power supply>Maneuverability required>Cost factor
Air Compressors >Output CFM requirement>Output Pressure Requirement>Availabi lity of power supply>Cost factor
Welding Equipment >Materail to be welded (Welding Rectifier, Generator etc) >Welding process to be used
>Electrodes to be used>Availabi lity of power supply>Out put requirement>Availib ility (use of available eqpt)
-
8/12/2019 Heavy Lift Presentation
8/46
Rev.-02 8
WORKING AND SAFETY ASPECTS OF
CONSTRUCTION EQUIPMENTSafe using of Const. Eqpt (Some Guidelines) :-
Properly select the construction eqpt. Any wrongselection can result in serious economical & safetyimplications. Consult concerned experts as applicable.
Use the eqpt. in the way, it is supposed to be used.
Check for valid safety inspection certificate, otherentry passes & manuals and charts of the eqpt. beforeactually using it.
Check for general condition of eqptvisual check onits tyres, reverse horn, lights, brakes, any leakage etc.
-
8/12/2019 Heavy Lift Presentation
9/46
Rev.-02 9
Before putting the eqpt into actual use, check for the vitalparameters such as Capacity, size and other parameters.
Before starting the operation,carefully check the site conditionsuch as ground condition, restriction from existing structures,restriction from operation requirement, etc.
Check for the environmental factor like weather conditions,wind speed etc.
Allow only authorized and competent personnel
Do not experiment. Consult concerned persons.
Carefully assess the risks associated with the job.
Use proper methods, tools and accessories.Ensure Continuous supervision.
Adhere to safety rules and regulation of the plant
Feedback & reporting.
Safe using of Const. Eqpt (Some Guidelines)
-
8/12/2019 Heavy Lift Presentation
10/46
Rev.-02 10
LIFTING TACKLESThe lifting tackles are the equipment used to connect
a load to the lifting machine or appliance.The most commonly used lifting tackles are :
Wire Rope Slings
Fibre Rope & Slings
Chain Sling.
Shackles ( Bow type & D type)
The other tackles includes-
Wire ropes, hook and eye bolts, Hook chuck etc.
Lifting lugs, spreader beam etc.
Generallyall the lifting tackles are identified by theirSWL(Safe Working Load).Further they can be classified
based upon their type, material, nos., and lengths etc.
-
8/12/2019 Heavy Lift Presentation
11/46
Rev.-02 11
SAFE USE OF LIFTING TACKLES
Select proper Lifting tackles.
Ensure SWL of tackle before use.
Ensure tag & test certificate of the Tackle.
Visually inspect the tackle before use- Check for anydistortion,cut,dent,abrasion,wear,corrosion broken wires incase of wire rope & slings any other visual damage.
Do not overload any Lifting Tackle.
Do not exceed the safe slinging angles.
Use proper lifting appliances & procedures.Load
-
8/12/2019 Heavy Lift Presentation
12/46
Rev.-02 12
Keep the slings/shackles away from heat ,fumes,
chemicals & exhaust gases.
Avoid using the sling/ ropes against sharp edges. Ifnecessary, use proper packing or padding.
Never drag the rope & slings on dirt or road.
Do not subject the slings to shock load.
The wire rope slings should be kept properly lubricated toprevent rust.
Follow proper method of securing the dead end whenwire rope is used for lifting.
Do not twist/knot the chain sling.
SAFE USE OF LIFTING TACKLES
-
8/12/2019 Heavy Lift Presentation
13/46
Rev.-02 13
Never replace shackles pin with a bolt.
Never use Pin Type Shackle without cotter pin
Do not tie slings, guy ropes to the operating facilities suchpipe line, hydrant, instrument and electrical posts andscaffolding pipes.
Use more than 2 slings with chain blocks to balance a pipe
spool with bends and any load with irregular shapes. Balancethe load at ground before lifting.
Tighten the slings before lifting.
DShackle Loading
SAFE USE OF LIFTING TACKLES
0.7 @45 deg.
0.5 @ 90 deg
1
-
8/12/2019 Heavy Lift Presentation
14/46
Rev.-02 14
Method
ofloading
Direct
loade
d
Choke hitch Basket Hitch
Round
load
Rectangular
load
Round load Other than Round load
Included
Angle- - - 0 60 90 120 0 60 90 120
Loading
Factors1 0.75 0.5 2 1.73 1.41 1 1 0.87 0.71 0.5
SAFE WORKING LOADS UNDER GENERAL USE OF SINGLE-PART
SINGLE-LEG SLINGS WITH 1570 GRADE WIRE AND FIBRE CORE
WITH FERRULE SECURED EYES
-
8/12/2019 Heavy Lift Presentation
15/46
Rev.-02 15
-
8/12/2019 Heavy Lift Presentation
16/46
Rev.-02 16
-
8/12/2019 Heavy Lift Presentation
17/46
Rev.-02 17
-
8/12/2019 Heavy Lift Presentation
18/46
Rev.-02 18
SELECTION & SAFE USE OF CRANES
Properly select the crane. Select the one, which best suitsthe requirements.
Know the type and range of cranes & Its configurationsavailable.
Know your wt. of Load, Radius, & height of load setting.
Understand & interpret the load charts.
Look at the Ground & other site conditions.
Prefer crawler cranes for continuous lifts and tire cranes forfew lifts.
Prefer lattice boom crane to telescopic crane for holding
a heavy load for a long time.Be aware of and keep in mind, all surrounding areas,
hazards and obstructions.
Ensure on proper competency of all associated personnel.
-
8/12/2019 Heavy Lift Presentation
19/46
Rev.-02 19
-
8/12/2019 Heavy Lift Presentation
20/46
Rev.-02 20
-
8/12/2019 Heavy Lift Presentation
21/46
Rev.-02 21
Graph
-
8/12/2019 Heavy Lift Presentation
22/46
Rev.-02 22
Load
chart
-
8/12/2019 Heavy Lift Presentation
23/46
Rev.-02 23
Heavy Lift Plan &Execution
Any construction activity involves numerous lifting
operations, mainly with Cranes.Depending upon the nature of Lifting, Lifts can becategorized as Standard, Complex or Heavy Complex Lift.Further it can be in Hazardous or Non Hazardous area.
Any Lifting operation, is made up of two parts :
Planning Part
Actual Lifting Part.
A proper planning, followed by execution in accordancewith the planning, shall certainly ensure any Lifting as SafeLifting.
-
8/12/2019 Heavy Lift Presentation
24/46
Rev.-02 24
Planning of Safe Lifting Operation :
1. The load, its construction, and dimensions.
2. Details of C.G, lifting &tailing lugs & location of load.3. Plot plan with surrounding U/G& A/G details
4. Selection & position of of suitable Crane(s).
5. Calculation of capacity loading.6. Space availability for transportation of crane & load,
assembly/dismantling of cranes at site
7. Procedure for ground preparation. It gives items to beremoved, items to be strengthened, extend ofground preparation and methodology.
-
8/12/2019 Heavy Lift Presentation
25/46
Rev.-02 25
8. Identification of Hazards:
Existence of Hydrocarbon lines, emergencylines, emergency entry/exit, assembly point, U/Gcables, over head cables.
9. Selection of tools and tackles, & spreader beam
10. Preparation of lifting scheme with enabling workdetails.
11. Carry out the Risk assessment
The Environmental Condition: Weather condition,wind speed and other atmospheric conditions etc.
Selection Of Personnel: Skilled & experiencedpersonnel for rigging, slinging, signaling should onlybe deployed.
Planning of Safe Lifting Operation
-
8/12/2019 Heavy Lift Presentation
26/46
Rev.-02 26
Rigging Plan
-
8/12/2019 Heavy Lift Presentation
27/46
Rev.-02 27
Rigging
Elev.
-
8/12/2019 Heavy Lift Presentation
28/46
Rev.-02 28
CRANE RIGGING DATA
CRANECC2500 DETAILS
MAIN BOOM LENGTH (M) 66
RADIUS (M) 15COUNTER WEIGHT (MT) 140
CENTRAL BALLAST (MT) 30
CAPACITY (MT) 115
MAXIMUM LOAD (MT) 85
HOOK BLOCK WEIGHT (MT) 6.4
RIGGING ACCESSORIES (MT) 2.5
TOTAL LOAD (MT) 93.9
% OF CAPACITY LOADING 81.6
HOOK UP DETAILS
LIFTING CRANE
SWL 30 MT STEEL WIRE ROPE SLING 2 DIAx10m LONG-2 PARTS-2NOS.
SWL 25 MT DSHACKLE- 2NOS.
SWL 30 MT STEEL WIRE ROPE SLING 2 DIAx10m LONG-2 PARTS-1NO.
SWL 25 MT DSHACKLE-1NO.
TAILING CRANE
if i
-
8/12/2019 Heavy Lift Presentation
29/46
Rev.-02 29
1. Check before lifting :
Crane(s) in the correct configuration & positioned asplanned. Actual the radius & height.
Condition of cranes and tools & tackles.
Load details are same as considered in planning.
Ground is prepared or developed as per the requirement.
Proper Personnel - Riggers,signaller are deployed.
Risk assessment and other site condition are conducive.
Signaler should wear high visibility vest.
Keep standby such as cutting set, welding machines,
transport, etc, as applicable to meet any emergency.
Lift Execution
-
8/12/2019 Heavy Lift Presentation
30/46
Rev.-02 30
Area is properly barricated.
Entry is restricted only to authorized persons
All required permits are taken2. Lifting operation
In accordance with planning made & methodstatement prepared, carry out the lift.
LIFTING OPERATION
-
8/12/2019 Heavy Lift Presentation
31/46
Rev.-02 31
General Safety Features Of Crane
1. Over Hoist Limit Switch :-
Gives alarm (and trips off further hoisting),in case of Hook Over Hoisting.
2. Boom Hoist Limit Switch (Crawler Cranes) :-
Generally a Shut Off valve which givesalarm in operators cabin (and cuts off further hoisting),when the boom has reached to a pre-set (maximum)angle during hoisting.
3. Overload Limit Switch :-Gives a warning (alarm), in case the
crane approaches Overload condition.
-
8/12/2019 Heavy Lift Presentation
32/46
Rev.-02 32
4 Safe Load Indicator (SLI) :-SLI, when fitted on crane, measures and displays following data
Radius of Load/hookBoom LengthBoom Angle
Actual Load Lifted by CraneRated Capacity (SWL)
SLI is also equipped to provide :-
A2B condition, indication & Tripping in case of Over Hoisting
Analog indication of Load Moment, in terms of Green (Safe
Zone), Yellow (Alert Zone) and Red (Danger & Cut Off zone)Indication, Alarm and Motion Cut Off, when an overloadcondition has reached.
General Safety Features Of Crane
-
8/12/2019 Heavy Lift Presentation
33/46
Rev.-02 33
If you over load the crane !
-
8/12/2019 Heavy Lift Presentation
34/46
Rev.-02 34
If you over load the crane !
-
8/12/2019 Heavy Lift Presentation
35/46
Rev.-02 35
Types of configuration available in mobile
cranes?
(a) Main boom
(b) Main boom with Super Lift
(c) Fixed Jib or Fly Jib(d) Fixed Jib with Super lift
(e) Luffing Jib
(f) Luffing Jib with Super Lift(g) Tower jib- Light load and better reach
M i B N l l d
-
8/12/2019 Heavy Lift Presentation
36/46
Rev.-02 36
Main Boom-Normal load
-
8/12/2019 Heavy Lift Presentation
37/46
Rev.-02 37
Main Boom with Super Lift-Heavy load
Fly or fixed Jib Better reach
-
8/12/2019 Heavy Lift Presentation
38/46
Rev.-02 38
Fly or fixed Jib- Better reach
L ffi Jib L h
-
8/12/2019 Heavy Lift Presentation
39/46
Rev.-02 39
Luffing Jib-Long reach
-
8/12/2019 Heavy Lift Presentation
40/46
Rev.-02 40
Luffing jib with Super lift- Heavy Load and long reach
-
8/12/2019 Heavy Lift Presentation
41/46
Rev.-02 41
RIGGING SCHEME OF PRIMARY
ABSORBER
PLAN VIEW
-
8/12/2019 Heavy Lift Presentation
42/46
Rev.-02 42
RIGGING SCHEME OF PRIMARY
ABSORBERELEVATION
-
8/12/2019 Heavy Lift Presentation
43/46
Rev.-02 43
REMOVAL SCHEME OF
DEPANTANIZERPLAN VIEW
-
8/12/2019 Heavy Lift Presentation
44/46
Rev.-02 44
REMOVAL SCHEME OF
DEPANTANIZER - ELEVATION
-
8/12/2019 Heavy Lift Presentation
45/46
Rev.-02 45
Practice the following!!! Do not keep pipe spool & structural Member on temporary
support. Make proper support and keep. Do not position crane and other machinery near to a temporary
or permanent U/G pits or trenches. Keep a distance equivalentto depth of pit from pit edge.
Do not position heavy crane and P&M on the water loggedarea. Dewater, dry and place.
Avoid positioning Crane and P&M on the U/G cable trenches.Not possible protect the cables with steel plates as applicable.
Level & compact the ground before placing the crane. Stdmats available with small cranes. Spread sand and steel platesfor heavy cranes movement and working.
Do not side load the crane boom & jibs. Do not place the crane on ground with slope.
When more than one cranes are working at one location, Keepsufficient space between the cranes.
Use ply woods under the crawler while marching crawler crane
on steel plates and concrete paving area.
-
8/12/2019 Heavy Lift Presentation