Introduction of Program Expedition
MND USFK Base Relocation Office
USFK Base Relocation ProgramUSFK Base Relocation Program
2
3
CONTENTS
❑ OVERVIEW
❑ EXPEDITION STATUS
❑ YRP PROGRAM STATUS
❑ DIRECTION OF EXPEDITION
❑ CURRENT TASKS
❑ CLOSING REMARKS
Relocate through consolidating Relocate through consolidating scattered USFK bases across scattered USFK bases across The Republic of KoreaThe Republic of Korea
Efficient use of returned Efficient use of returned sites following base sites following base
relocationrelocation
Stronger ROK USAlliance
EnsureStable
ConditionFor stationed
USFK
ConceptConceptUSFK Base Relocation
ProgramBalanced
development of
National Land
Construct Future-Construct Future-Oriented Security Oriented Security
AllianceAlliance
SUMMARY
❑ Background
5
EXPEDITION PROGRESS
Yongsan base relocation ROK US agreement (MOA/MOU)
JUN 1990 ROKᆞ US summit agreement of early relocation of Yongsan Base
MAY 2003
Agreement on the Relocation of USFK (UA/IA), Ratification of LPP revised agreement by ROK National Assembly and enactment of special legislation to support Pyeongtaek city.
DEC 2004
Completion of purchase of relocation site In Pyeongtaek JAN 2006
Selection of Program Management Consortium(PMC):Kunwon-CH2M HILL JUN 2007
Contribution-Concession Project treaty signed and groundbreaking ceremony at Pyeongtaek relocation siteNOV 2007
Establishment of MURO(MND USFK Base Relocation Office)JUL 2006
ROK and US approval of Master Plan (MP)JAN 2008
5
Start Land development and infrastructure constructionDEC 2008
Elementary ㆍ High School Groundbreaking CeremonySEP 2011
7
7
RailheadIndian
Head HQ
Warehouse FacilitiesGolf
Course
SchoolFacilities
Small UnitTraining Area
Anseong Stream
Vehicle Maintenance Facility
※ Square Area : 14.65M ㎡ (Existing: 4.98M ㎡ New: 9.67M ㎡ )
DaeChu-Ri
WelfareFacilities
HousingFacilities
KORCOM
EUSA HQExistingUSAG
Humphreys
DowntownArea
❑ Master Plan(MP)
▪ Program Characteristics : Determine Facility Requirements(DD1391)
through ROK US agreement under DoD standards, in-kind payment
principle.
▪ Design : Basic Design (30%)- US(US Contractor) , Detailed Design (70%)-ROK (ROK
Contractor)
* Exception : Special facilities constructed by ROK after 100% US design,
SCIF facilities designed and constructed 100% by US
▪ Facility Construction : ROK (ROK construction company)
MethodMethod
▪ Progress of entire program: Plan 29.8% / Execution 28.8% (on schedule)
- Land Development and Utility Infrastructure (Complete by 2013) : 50.4 %
- Exterior access road, electricity·gas ·water and sewer Line ·railroad construction
(Complete by 2013) : 69.6%
▪ Determination of Relocation Facility Requirements : 48 out of 57 projects completed
(84%)
▪ Basic Design : 31 out of 57 projects completed (54%), and 5 projects including
Elementary School and High school under construction
* Construction Award/Start from 2011, scheduled to complete construction in 2015 and
complete relocation in 2016
StatusStatus
YRP CONSTRUCTION PROGRAM STATUS (1/7)
9
CAT TotalBefore2010
2011 2012 2013 2014 2015 Remarks
FacilityRequirements
(DD1391)ROK US Approval
57 40 8 7 1 1 ·
USLead
Completion of Criteria
Package(CP)57 13 18 22 3 2 ·
Detailed Design and
Technical Proposal Bid
57 5 7 38 5 1 1
ROKLead
Start Construction
57 3 2 6 29 15 2
YRP CONSTRUCTION PROGRAM STATUS (2/7)
※ Projects scheduled to start construction in 2012 (6 projects) :
Hospital/Dental Facility(JUL), SPARTAN(SEP), Family Housing(SEP), EUSA Barracks(SEP),
Child Development Center(DEC)
❑ Status of design and construction
❑ Pyeongtaek Land Development Construction: Current Progress 50.4% (Scheduled to complete in 2013)
ROK Construction :49.2% progress
(Hanjin, Daewoo, GS E&C)
Existing USAG Humphreys
US Construction : 49% progress
(Seohee, SK E&C)
YRP CONSTRUCTION PROGRAM STATUS (3/7)
③ Move soil & landfill④ Road & pipeline construction
11
② Soft grounding construction① Demolish existing buildings and elimination of surface soil
YRP CONSTRUCTION PROGRAM STATUS (4/7)YRP CONSTRUCTION PROGRAM STATUS (4/7) ❍ Process procedures : Elimination of surface soil → soft grounding → landfill
→ pipeline and road construction
❍ Elevation of landfill : 1.2 ~ 2.4m (13M m3), Construction Cost :
Appr. \830B
12
PMO Construction(55%) : ExteriorPMO Construction(55%) : Interior Ceiling Construction in progress
Elementary and Highshool Construction (7%) : Ground Floor
Installation of Concrete Wall)
Elementary and Highshool Construction(7%) : Ground Floor
Installation of Concrete Wall
YRP CONSTRUCTION PROGRAM STATUS (5/7)YRP CONSTRUCTION PROGRAM STATUS (5/7)
13
❑ Exterior Infrastructure Construction
WaterGAS
Railroad
Electricity
Sookseong Station
Pyeongtaek Station
Naeri Maeul Access Road
City plan road
Sewage Process Plant
Hamjeongri Road
Road 10
Road 12
Naeri Road
CPX Road
Dodoori Road Dodoo Construction Road
Dongchangri Road
YRP CONSTRUCTION PROGRAM STATUS (6/7)YRP CONSTRUCTION PROGRAM STATUS (6/7)
Sub-Station Construction (90%)
Road Construction(7 of 10 roads complete)
YRP 건설사업 추진 현황 (7/7)
Railroad connection Construction (1.5Km)
14Construction within Garrison
15
2015 Complete Construction, 2016 Complete Relocation
(OCT 2010 SCM Agreement)
2015 Complete Construction, 2016 Complete Relocation
(OCT 2010 SCM Agreement)
② Early completion
of Land
Development and
Utility
Infrastructure
③ Apply
technical
proposal bid
method for
procurement
① Ensure
connection
between CP
Design and
Detail Design
④ Cost reduction
through using
localized
materials
“Adequate program expedition
through reduced program duration and appropriate
costs” (ROK US Joint Program Management Perspective)
GoalGoal
MethodMethod
DIRECTION OF PROGRAM EXPEDITION (1/4)
① Master Plan(MP): ROK US Agreement
☞ Facility size and layout per ROK
US responsibility
⇒
② Facility Requirement
(DD1391) : ROK US Agreement
☞ Use, number of personnel, square area, cost
⇒
③ Criteria Package (CP): US prepared
☞ Appr. 30% designed
Approved by SOFA Joint
Committee, JAN 200848 among 57 agreed
31 among 48
complete
⇒
④ Detailed Design: ROK prepared
☞ Appr. 70% designed⇒
⑤ Facility Construction
: ROK Construction⇒ ⑥Facility Turn-over
9 among 31 complete5 among 9 awarded
Final Verification (US FED)
Ⅰ. Ensure connection between CP design and detail design
ROK US facility agreement procedure (E-MOU)
Joint effort for facility requirements of remaining facility and early
completion of CP
DIRECTION OF PROGRAM EXPEDITION (2/4)
ROK US LDUI cost share(SEP 2007) : ROK 55%, US 45%
ROK US LDUI progress : 50.4% / Completion scheduled in late 2013
Improvement of quality of life and welfare of USFK through relocating Downtown area ⇒ Necessity of US swing space plan and early completion of design change
ROK US Joint T/F for on-site interface management, share information and maintain cooperation
Ⅱ. Early Completion of Land Development and Utility
Infrastructure (LDUI) Construction
DIRECTION OF PROGRAM EXPEDITION (3/4)
Humphreys utlities Completion plan
Conduct design review at 60, 90, 100% under supervision ROK US DCAs and PMC (E-MOU)
Technical Proposal bid method includes construction management, shortening of duration, cost reduction, high quality construction at 30~100% design completion phase
Ⅲ. Applying technical proposal bid method for procurement
General Facility ⇒ Criteria
Package(US)Detaied
Design(ROK) + Construction(ROK)
Special Facility ⇒ Detailed Design(US) Construction(
ROK)
CPTP(Criteria Package Technical Proposal)
DDTP(Detailed Design Technical proposal)
DIRECTION OF PROGRAM EXPEDITION (3/3)
USFK facility is constructed based on DoD facility standards, usage of local material was low ※ Apply US standards such as UL,
ANSI, ASTM etc
Method for easier O&M and reduction of maintenance costs after the completion of YRP/LPP program
243 among 302 domestic materials localized : 73.4%
Ⅳ. Cost reduction through using local material
DIRECTION OF PROGRAM EXPEDITION (4/4)
Establishing concrete plan regarding relocation of PMO in May, 2012(Seoul→Pyeongtaek) and site control (Operate on-site situation room)
Focus on design and construction management of 10 main projects including US KORCOM, EUSA HQ
On-site interface management for land development and utility infrastructure
Management of main infrastructure for site access including Road & Railroad, and completion schedule
Effort for ROK US joint design VE and localization of materials
CURRENT TASKS
22
CLOSING REMARKS
● Based on strong ROK US Alliance
● Program completion within target year
● Build the best US Base in the world